JALNA DIVISION

J3 Wadigodri- Dhangerpimpari NH 753H Length= 30.39


Name of Contractor
M/s. State Construction Integrated Works & V. P. Sethi & Mehra
:
Milestone Amount in
TAFS Cost Rs.Cr. = 194.23 Awarded Cost in Cr. = 120.37 Date % Progress
(Days) Cr.
Date of LOA
28.03.2018 I (150) 26.11.2018 19% 23.65
Date of Agreement
16.05.2018 II (300) 25.04.2019 42.47% 51.12
Appointed Date
30.06.2018 III (455) 27.09.2019
Scheduled Completion Date 21.12.2019 IV (540) 21.12.2019
Authority's Engineer

Scope of work Targeted Length (Cumulative) Current status Expenditure


Sr. No. During
Upto July Upto March Upto March
Structures No Item Left Right 2018-19 Upto
2018 2019 2018
March2019
1 Major Bridge 0 Subgrade 20.39 22.39

2 Minor Bridge 11 GSB 20.39 22.39

3 Box Culvert 39 DLC 14.28 16.89

Pipe Culverts (7+29 at


4 36 PQC 14.28 15.39
juns)
5 Toll plaza 1 BT Overlay 0 0

6 Bridge cum Bandhara 0 11 Structures Completed Progress 0 7.49

MJB 0 0

MNB 6 1

Box 20 1

HPC 3 2

VUP 0 0

PUP/CUP 0 0
Bridge cum
Bandhara
Total 87

1 Mobilization of Contractor Nill

2 Tree Cutting Complete

3 LA Status LA process is in progress

4 Water Supply Estimates are received from concerned dept

5 Plans & Profiles Status Submit from EPC contractor

6 MSEB Estimates are awaited from MSEB


NA DIVISION
pimpari NH 753H Length= 30.39
s & V. P. Sethi & Mehra

Actual Exp till Progress in %


Date as per MPR

24.36 19%
52.65 42%

Expenditure in Cr.

Upto date Expdt. Demand for


(Cummulative) 2019-20

7.49 42
JALNA DIVISION
J4 Dhangerpimpari-Jalna-Mantha Chowk Length= 25.117 km
Name of Contractor
M/s. State Construction Integrated Works & V. P. Sethi & B. M.Danve
:
Milestone Amount in
TAFS Cost Rs.Cr. = 217.14 Awarded Cost in Cr. = 137.317 Date % Progress
(Days) Cr.
Date of LOA
28.03.2018 l (150) 26.11.2018 23.42% 32.16
Date of Agreement
13.05.2018 II (300) 25.04.2019 39.85% 54.72
Appointed Date
30.06.2018 III (455) 27.09.2019
Scheduled Completion Date 21.12.2019 IV (540) 21.12.2019
Authority's Engineer

Scope of work Targeted Length (Cumulative) Current status Expenditure


Sr. No. During
Upto July Upto March Upto March
Structures No Item Left Right 2018-19 Upto
2018 2019 2018
March2019
1 Major Bridge 0 Subgrade 16.41 19.87

2 Minor Bridge 11 GSB 16.41 19.87

3 Box Culvert 22 DLC 16.41 16.41

4 Pipe culvert 31 PQC 16.41 15.61

5 Toll plaza 1 BT Overlay 0 0

6 Bridge cum Bandhara 0 12 Structures Completed Progress 0 13.35

MJB 0 0

MNB 3 0

Box 11 2

HPC 2 1

VUP 0 0

PUP/CUP 0 0
Bridge cum
Bandhara
Total 65

1 Mobilization of Contractor Nill

2 Tree Cutting Proposal of tree cutting permission is submitted to forest dept NOC Under Progress

3 LA Status LA process is in progress

4 Water Supply Estimates are received from concerned dept

5 Plans & Profiles Status Submit from EPC contractor

6 MSEB Estimates are awaited from MSEB


NA DIVISION
a-Mantha Chowk Length= 25.117 km
s & V. P. Sethi & B. M.Danve

Actual Exp till Progress in %


Date as per MPR

33.13 23.42%
56.36 39.85%

Expenditure in Cr.

Upto date Expdt. Demand for


(Cummulative) 2019-20

13.35 100
pt NOC Under Progress