Académique Documents
Professionnel Documents
Culture Documents
WWW.OMNEX.COM
© 2014,Omnex, Inc.
325 E. Eisenhower Parkway, Suite 4
Ann Arbor, MI 48108
(734) 761-4940
Fourth Edition
August 2014
This publication is protected by Federal Copyright Law, with all rights reserved. No part of this
publication may be reproduced, stored in a retrieval system, translated, transcribed, or
transmitted, in any form, or by any means manual, electronic, electro-magnetic, mechanical,
chemical, optical, or otherwise, without prior explicit written permission from Omnex, Inc.
Agenda
• Setting The Stage – Why Lean ?
– MOST
• Practical exercises
WWW.OMNEX.COM
5
What is Lean?
50, 50, 20
• 50% increase in throughput
• The first four concepts reinforce each other and as the flow
velocity increases, it exposes more waste in the value
stream.
WWW.OMNEX.COM
The Seven Wastes
Examples
Inefficient layouts
Motion Lack of proximity of machines
Off-line resources
Operator waiting time
People Long setups and lead times
Idle Time
Making more than required to fulfill
a customer order
Overproduction Unused reports or schedules
Rework, Multiple reviews
Perform testing to materials that
were already tested
Operation
Product that doesn’t meet
Process specification; rejected material
Air shipments
Defects
Dissatisfied customers
Material not being used
Inventory Product in the warehouse
Pending reports
• Result:
– Reduced lead time (reduced cycle time)
– Improved customer response
– Flexibility
• Indirect Benefits:
– Greater output / productivity
– Reduced defects
22
Copyright © 2015 OMNEX Inc. All Rights Reserved
WWW.OMNEX.COM
5th Waste: Defects
• Defects have to be rectified
• Rectification costs money:
– Time
– Effort
– Materials
• Defects do not encourage customer satisfaction
• Defects in the field will lose customers
• What to look for:
– Rework
– Scrap Rates
– Process Metrics
– Errors in reports
– Data entry errors
– Claims
Copyright © 2015 OMNEX Inc. All Rights
23
Reserved
WWW.OMNEX.COM
3 Wastes
• Muri - Overburden
operations
12 TONS
X 3 = NO 3M’s
1 ton
X 6 = MUDA
(waste)
X 2 = MURI
(over burden)
Capacity MURA
: 4tons
(uneve
nness)
Value added
Value added has three dimensions:
Activities that do not add value to the process are called non-value
added activities. These activities :
Eliminated
Reduced
Simplified
Improvement Steps:
• Eliminate NVA activities
• Minimize motions/travel time/reaching
– Organize work to minimize distance traveled
• Simplify tasks
• Organize needed references, tools, and inputs
• Minimize redundant inspection/verification
• Organize around outcomes to avoid reformatting (work
should meet downstream need)
WWW.OMNEX.COM
Takt time
• Available time is total shift time minus meal and scheduled break times
• The question that needs to be answered before you layout your cell is:
• Can your existing machines perform at this pace?
• To answer this question you must determine the effective cycle time of each
machine.
Takt time
Takt sets the pace of production
- If Cell Takt Time is too long, longer than 120 seconds, the
increased number of work elements per operator can lead to
errors and defects. Better to add additional products to the
cell (if machine cycle times and equipment flexibility allows).
MOST
Maynard Operation Sequence Technique (MOST) is a predetermined
motion time system that is used primarily in industrial settings to set
the standard time in which a worker should perform a task.
All the motion element times are then added together and
any allowances are added, and the result is the standard time.
Takt time
Cycle time
Cycle time is the total time from the beginning to the end of your
process, as defined by you and your customer.
The minimum cycle time is equal to the longest task time and the
maximum cycle time is equal to the sum of the task times.
0.1 min 0.7 min 1.0 min 0.5 min 0.2 min
and the maximum cycle time is equal to the sum of the task times
i.e. 2.5 min.
TAKT
30 Sec.
34 S. 20 S. 28 S. 24 S. 16 S. 18 S. 29 S. 29 S.
10 S 15 S 35 S 20 S
Shear Turret Brake Weld
Copyright © 2015 OMNEX Inc. All Rights
50
WWW.OMNEX.COM Reserved
Operator Balance Charts / Line balancing
TAKT
60 Sec.
More
Waste
20 S 60 S 35 S 32 S 10 S 15 S 35 S 20 S
Shear Turret Brake Weld Shear Turret Brake Weld
TAKT
60 Sec.
37.5 S 37.5 S 60 S 15 S.
Work Elements
WWW.OMNEX.COM
Work Elements
• When you observe the work process closely you will notice
that each operator performs a series of discrete movements.
Those movements combine to make work elements.
– A work element is the smallest increment of work that could be performed by a
second operator.
– Thus, get one panel and place it in the fixture, would be a work element. Get
one panel would not.
Target
Work
Walk
Wait
Adjust
Load/Unload
Value
Reduction
Operator Work element Motion 1 2 3 4 5 6 7 8 9 10 Action Resp Target date
Time Study
WWW.OMNEX.COM
Cell Defined
A cell is a group of sequential operations organized so that
material is processed and transferred one-piece at-a-time
(continuous flow) or in very small batches (FIFO flow) that
are maintained throughout the sequence of operations.
Exercise 1
Given a precedence diagram
a b 1.0 min
0.1 min
c d e
Arrange the task into three workstations. Use cycle time of 1.0
min.
Calculate percentage of idle time and efficiency of the line.
0.1 min
c d e
Exercise 1
5) Compute the resulting percent idle time and efficiency of the system.
Exercise 3
5) Compute the resulting percent idle time and efficiency of the system.
Copyright © 2015 OMNEX Inc. All Rights
74
WWW.OMNEX.COM Reserved
THANK YOU
Info@Omnex.com
Any Questions?
WWW.OMNEX.COM