Vous êtes sur la page 1sur 19

DFA Vs BCA The Arbitral Tribunal through Procedural Order

No. 11, granted BCA’s motion to admit, in the


Tickler: BOT, Amended increase in damages, premise that it would no longer present any
SC review discretionary, not matter of right, additional evidence to prove the bigger claim.
appeal to SC must be based on CA’s decision BCA opposed and passed a motion for partial
thus if SC cant hear cases directly appealing reconsideration, asking the Tribunal to allow it to
arbitration tribunal’s decision present further evidence, this request was granted
Form: Petition for certiorari under Rule 65 by the Tribunal through Proc. Oder No. 12 ,
between Department of Foreign Affairs and BCA accordingly modifying Proc Order 11 and
allowing BCA to present its evidence.
International Corporation appealing decision of
Arbitration Tribunal. DISMISSED. Through Proc. Order 12, DFA’s motion for
Facts: Through a Build-Operate- Translate reconsideration for Poc Order 11, thus filing this
petition under Rule 65, with prayer for issuance
(BOT) Agreement, DFA awarded the Machine
of a temporary restraining order and/or writ of
Readable Passport and Visa Project (MRP/V
preliminary injunction to annul Proc. Order Nos.
Project) to respondent BCA International
Corporation.In the course of its implementation, 11 and 12.
conflict arose and DFA sought to terminate the Citing Article 20 of the of the 1976 UNCITRAL
operation, which BCA opposed. The latter filed a Arbitration Rules, DFA contends that BCA’s
Request for Arbitration seeking the following motion to admit amended statement of claims
reliefs: a.) nullification of the notice of should have been denied as there a.) has been
termination of the DFA including DFA’s claim delay and prejudice to it, b.) fair and efficient
for damages, 2.) judgment confirming the notice administration of the proceedings should have
of default BCA issued to DFA and ordering the warranted its denial, and c.) the Arbitral Tribunal
latter for specific performance of its obligation did not have jurisdiction over the amended
under the agreement by approving the site of the claims.
Central Facility at the Star Mall Complex in Shaw
Boulevard, c.) ordering DFA to pay damages Article 20: AMENDMENTS TO THE CLAIM
estimated at 100 million pesos and d.) other just OR DEFENCE : During the course of the
relief. arbitral proceedings either party may amend or
supplement his claim or defence unless the
BCA then filed an Amended Statement of arbitral tribunal considers it inappropriate to
Claims in the event specific performance by allow such amendment having regard to the delay
petitioner was no longer possible, petitioner in making it or prejudice to the other party or any
prayed that the Arbitral Tribunal shall render other circumstances. However, a claim may not
judgment ordering petitioner to pay respondent be amended in such a manner that the amended
P1,648,611,531.00, representing the net income claim falls outside the scope of the arbitration
respondent is expected to earn under the clause or separate arbitration agreement.
Agreement, and P100,000,000.00 as exemplary,
temperate or nominal damages. DFA objected, Respondent avers that the Arbitration Tribunal
and BCA withdrew its statement, but later filed a had juriscition from the contractual consent of
new amended statement of claims increasing the the parties and that the Supreme Court has no
actual damages sought to P390,000,000.00, plus jurisdiction to intervene in a provate arbitration.
an additional P10,000,000.00 for exemplary,
temperate or nominal damages.
Issues: The issues to be resolved at the outset are only for serious and compelling reasons resulting
a.)n which laws apply to the arbitration in grave prejudice to the aggrieved party.
proceedings RA No. 876, 18 RA No. 9285 and
its IRR, and the Special ADR Rules and The following, while neither controlling nor fully
b.)whether the petition filed before the Court is measuring the court's discretion, indicate the
proper.NO. serious and compelling, and necessarily,
restrictive nature of the grounds that will warrant
Ruling: Tribunal had jurisdiction. The the exercise of the Supreme Court's discretionary
Agreement provides for the resolution of dispute powers, when the Court of Appeals:
between the parties in Section 19.02 thereof,
Under Article 33 of the UNCITRAL Arbitration a. Failed to apply the applicable standard or test
Rules governing the parties, "the arbitral tribunal for judicial review prescribed in these Special
shall apply the law designated by the parties as ADR Rules in arriving at its decision resulting in
applicable to the substance of the dispute." substantial prejudice to the aggrieved party;
"Failing such designation by the parties, the
b. Erred in upholding a final order or decision
arbitral tribunal shall apply the law determined by
despite the lack of jurisdiction of the court that
the conflict of laws rules which it considers rendered such final order or decision;
applicable." Established in this jurisdiction is the
rule that the law of the place where the contract is c. Failed to apply any provision, principle, policy
made governs, or lex loci contractus. As the or rule contained in these Special ADR Rules
parties did not designate the applicable law and resulting in substantial prejudice to the aggrieved
the Agreement was perfected in the Philippines, party; and d. Committed an error so egregious
our Arbitration laws, particularly, RA No. 876, 18 and harmful to a party as to amount to an
RA No. 9285 and its IRR, and the Special ADR undeniable excess of jurisdiction.
Rules apply. The IRR of RA No. 9285 provides
that "[t]he arbitral tribunal shall decide the The extent of court intervention in domestic
dispute in accordance with such law as is chosen arbitration is specifed in the IRR of RA No.
by the parties. In the absence of such agreement, 9285, thus:
Philippine law shall apply."
Art. 5.4. Extent of Court Intervention. In matters
Under the Special ADR Rules, review by the governed by this Chapter, no court shall
Supreme Court of an appeal by certiorari is not a intervene except in accordance with the Special
matter of right. ADR Rules.

The mere fact that the petitioner disagrees with Court intervention in the Special ADR Rules is
the Court of Appeals' determination of questions allowed through these remedies: (1) Specific
of fact, of law or both questions of fact and law, Court Relief, which includes Judicial Relief
shall not warrant the exercise of the Supreme Involving the Issue of Existence, Validity and
Court's discretionary power. The error imputed Enforceability of the Arbitral Agreement, Interim
to the Court of Appeals must be grounded upon Measures of Protection, Challenge to the
any of the prescribed grounds for review or be Appointment of Arbitrator, Termination of
closely analogous thereto. Mandate of Arbitrator, Assistance in Taking
Evidence, Confidentiality/Protective Orders,
RULE 19.36. Review Discretionary. — A review Confirmation, Correction or Vacation of Award
by the Supreme Court is not a matter of right, but in Domestic Arbitration, all to be filed with the
of sound judicial discretion, which will be granted RTC; (2) a motion for reconsideration may be
filed by a party with the RTC on the grounds arbitration proceedings
specified in Rule 19.1; (3) an appeal to the Court
of Appeals through a petition for review under
Rule 19.2 or through a special civil action for
certiorari under Rule 19.26; and (4) a petition for Heirs of Salas v Laperal Realty
certiorari with the Supreme Court from a
judgment or final order or resolution of the De Leon, Jr.
Court of Appeals, raising only questions of law.
Tickler: Only parties to original contract and
RULE 19.37. Filing of Petition with Supreme assignees are bound by arbitration clause, buyers
Court. — A party desiring to appeal by certiorari of land not assignees and are not bound
from a judgment or final order or resolution of
the Court of Appeals issued pursuant to these Form: Petition for review on certiorari of the
Special ADR Rules may file with the Supreme order of Regional Trial Court of Lipa City
Court a verified petition for review on certiorari. dismissing petitioners' complaint for rescission of
The petition shall raise only questions of law, several sale transactions involving land owned by
which must be distinctly set forth. It is clear that Augusto L. Salas, Jr., their predecessor-in-
an appeal by certiorari to the Supreme Court is interest, on the ground that they failed to first
from a judgment or final order or resolution of resort to arbitration. GRANTED
the Court of Appeals and only questions of law
Facts:
may be raised.
Salas, Jr. was the registered owner of a vast tract
Conclusion: , in this case, the appeal by certiorari
of land in Lipa City, Batangas spanning 1,484,354
is not from a final Order of the Court of Appeals
square meters. He entered into an Owner-
or the Regional Trial Court, but from an
Contractor Agreement with Laperal Realty
interlocutory order of the Arbitral Tribunal;
Corporation to provide complete (horizontal)
hence, the petition must be dismissed.
construction services on his land on May 15,
Case within the case 1987. Salas allowed respondent to exercise e
In another earlier case led by petitioner entitled general control, supervision and management of
Department of Foreign Affairs v. BCA the sale of his land, for cash or on installment
International Corporation, 22 docketed as G.R. basis through a Special Power of Attorney.
No. 210858, petitioner also raised as one of its
issues that the 1976 UNCITRAL Arbitration On June 10, 1989, Salas, Jr. left his home in the
Rules and the Rules of Court apply to the present morning for a business trip to Nueva Ecija. He
arbitration proceedings, not RA No. 9285 and never returned. After seven years, his wife
the Special ADR Rules. We ruled therein thus:
Teresita filed a petition for declaration of
Arbitration is deemed a special proceeding and
governed by the special provisions of RA 9285, presumptive death.
its IRR, and the Special ADR Rules. RA 9285 is
the general law applicable to all matters and Meantime, Laperal subdivided the land of Salas,
controversies to be resolved through alternative Jr. and sold subdivided portions thereof to
dispute resolution methods. While enacted only respondents Rockway Real Estate Corporation
in 2004, we held that RA 9285 applies to pending and South Ridge Village, Inc, spouses Dacillo,
arbitration proceedings since it is a procedural and to r Eduardo Vacuna, Florante de la Cruz
law, which has retroactive effect. Thus, contrary and Jesus Vicente Capalan.
to DFA's contention, RA 9285, its IRR, and the
Special ADR Rules are applicable to the present
On February 3, 1998, petitioners heirs of Salas as heirs of Salas, Jr., and respondent Laperal
filed in the Regional Trial Court of Lipa City a Realty are certainly bound by the Agreement.
Complaint for declaration of nullity of sale,
reconveyance, cancellation of contract, If respondent Laperal Realty had assigned its
accounting and damages against herein rights under the Agreement to a third party,
respondents. making the former, the assignor, and the latter,
the assignee, such assignee would also be bound
Laperal Realty filed a Motion to Dismiss on the by the arbitration provision since assignment
ground that petitioners failed to submit their involves such transfer of rights as to vest in the
grievance to arbitration as required under Article assignee the power to enforce them to the same
VI of the Agreement: extent as the assignor could have enforced them
against the debtor 18 or in this case, against the
“ARTICLE VI. ARBITRATION. All cases of heirs of the original party to the Agreement.
dispute between CONTRACTOR and
OWNER'S representative shall be referred to the However, respondents Rockway Real Estate
committee represented by: Corporation, South Ridge Village, Inc.,
Maharami Development Corporation, spouses
a. One representative of the OWNER; Abrajano, spouses Lava, Oscar Dacillo, Eduardo
b. One representative of the CONTRACTOR;
Vacuna, Florante de la Cruz and Jesus Vicente
c. One representative acceptable to both
OWNER and CONTRACTOR." Capellan are not assignees of the rights of
respondent Laperal Realty under the Agreement
to develop Salas, Jr.'s land and sell the same.
The trial court dismissed the heirs’ complaint for They are, rather, buyers of the land that
failure to comply with the Arbitration Clause. respondent Laperal Realty was given the authority
to develop and sell under the Agreement. As
Issues:
such, they are not "assigns" contemplated in Art.
Whether or not the dismissal of petitioners’ case 1311 of the New Civil Code which provides that
on the ground that it did not seek relief through "contracts take effect only between the parties,
arbitration is proper. NO their assigns and heirs".

Petitioners argue, thus: Petitioners are not exempted from complying


with the arbitration clause.
The petitioners' causes of action did not emanate
from the Owner Contractor Agreement They argue that rescission, being their cause of
action, falls under the exception clause in Sec. 2
The petitioners' causes of action for cancellation of Republic Act No. 876 which provides that
of contract and accounting are covered by the "such submission [to] or contract [of arbitration]
exception under the Arbitration Law. shall be valid, enforceable and irrevocable save,
upon such grounds as exist at law for the
Failure to arbitrate is not a ground for dismissal revocation of any contract".
Ruling: We grant the petition. The petitioners' contention is without merit. For
A submission to arbitration is a contract. As while rescission, as a general rule, is an arbitrable
such, the Agreement, containing the stipulation issue, they impleaded in the suit for rescission the
on arbitration, binds the parties thereto, as well as respondent lot buyers who are neither parties to
their assigns and heirs. But only they. Petitioners, the Agreement nor the latter's assigns or heirs.
Consequently, the right to arbitrate as provided in Tickler:
Article VI of the Agreement was never vested in
respondent lot buyers. Form: Appeal by certiorari under Rule 45 to
annul and set aside the decision of the Court of
Conclusion: Respondent Laperal Realty, as a Appeals dismissing the petition for certiorari filed
contracting party to the Agreement, has the right by petitioner to annul the two (2) orders issued by
to compel petitioners to first arbitrate before the Regional Trial Court of Makati in denying
seeking judicial relief. However, to split the petitioner's motion to dismiss and the second
proceedings into arbitration for respondent denying petitioner's motion for reconsideration
Laperal Realty and trial for the respondent lot thereof. DISMISSED.
buyers, or to hold trial in abeyance pending
arbitration between petitioners and respondent Facts: Victor Tancuan issued an HBSTC check
Laperal Realty, would in effect result in for P25,250,000.00 while Eugene Arriesgado
multiplicity of suits, duplicitous procedure and issued FEBTC checks for P8,600,000.00,
unnecessary delay. On the other hand, it would P8,500,000.00 and P8,100,000.00, respectively,
be in the interest of justice if the trial court hears the three checks amounting to P25,200,000.00.
the complaint against all herein respondents and Tancuan and Arriesgado exchanged each other's
adjudicates petitioners' rights as against theirs in a checks and deposited them with their respective
single and complete proceeding. banks for collection. Tancuan’s checks when
presented by FEBTC were dishonoured by
WHEREFORE, the instant petition is hereby HBSTC for insufficient funds.
GRANTED. The Order dated August 19, 1998
of Branch 85 of the Regional Trial Court of Lipa HBSTC sent Arriesgado's three (3) FEBTC
City is hereby NULLIFIED and SET ASIDE. checks through the Philippine Clearing House
Said court is hereby ordered to proceed with the Corporation (PCHC) to FEBTC but was
hearing of Civil Case No. 98-0047. returned as "Drawn Against Insufficient Funds.

Case within the case: HBSTC received the notice of dishonor but
In a catena of cases inspired by Justice Malcolm's refused to accept the checks and returned them
provocative dissent in Vega v. San Carlos Milling to FEBTC through the PCHC for the reason
Co. , this Court has recognized arbitration "Beyond Reglementary Period," implying that
agreements as valid, binding, enforceable and not HBSTC already treated the three (3) FEBTC
contrary to public policy so much so that when checks as cleared and allowed the proceeds
there obtains a written provision for arbitration
thereof to be withdrawn.
which is not complied with, the trial court should
suspend the proceedings and order the parties to
FEBTC demanded reimbursement for the
proceed to arbitration in accordance with the
terms of their agreement. Arbitration is the "wave returned checks and inquired from HBSTC
of the future" in dispute resolution. To brush whether it had permitted any withdrawal of funds
aside a contractual agreement calling for against the unfunded checks and if so, on what
arbitration in case of disagreement between date. HBSTC, however, refused to make any
parties would be a step backward reimbursement and to provide FEBTC with the
needed information.
Home Bankers Savings v CA Thus FEBTC submitted the dispute for
arbitration before the PCHC Arbitration
Buena, J.
Committee.
Pending the arbitration proceeding, FEBTC filed pending as obtains in this case stay the court
an action for sum of money and damages with action. A party to a pending arbitral proceeding
preliminary attachment against HBSTC, Robert may go to court to obtain conservatory reliefs in
Young, Victor Tancuan and Eugene Arriesgado connection with his cause of action although the
with the Regional Trial Court of Makati. disposal of that action on the merits cannot as yet
be obtained.
A motion to dismiss was filed by HBSTC
claiming that the complaint sought to enforce an Petitioner contends that
arbitral award which did not exist yet. The trial
court denied this motion and the subsequent one cannot file a complaint in court over a
motion for reconsideration. HBSTC filed a subject that is undergoing arbitration
petition for certiorari with the Court of Appeals Second, since arbitration is a special proceeding
contending that the trial court acted with grave by a clear provision of law, the civil suit filed
abuse of discretion amounting to lack of
below is, without a shadow of doubt, barred by
jurisdiction in denying its motion to dismiss. The
litis pendentia and should be dismissed de plano
CA dismissed the petition for lack of merit. The
insofar as HBSTC is concerned.
respondent court observed that "[i]n the
Complaint, FEBTC applied for the issuance of a Third, when arbitration is agreed upon and suit
writ of preliminary attachment over HBT's is filed without arbitration having been held and
[HBSTC] property" and citing Section 14 of terminated, the case that is filed should be
Republic Act No. 876, otherwise known as the dismissed.
Arbitration Law, maintained that "[n]ecessarily, it
has to reiterate its main cause of action for sum of Private respondent FEBTC, on the other hand,
money against HBT [HBSTC]," 13 and that "this contends that "the cause of action for collection
prayer for conservatory relief [writ of preliminary [of a sum of money] can coexist in the civil suit
attachment] satisfies the requirement of a cause and the arbitration [proceeding]" citing Section 7
of action which FEBTC may pursue in the courts of the Arbitration Law which provides for the stay
Hence, this present action of the civil action until an arbitration has been
had.
According to the respondent court, based in Sec
7 of the Arbritation Law, as seen in Issue: Whether or not private respondent which
jurisprudence, when there is a condition commenced an arbitration proceeding under the
requiring prior submiddion to arbitration before auspices of the Philippine Clearing House
institution of a court action, the action should not Corporation (pchc) may subsequently file a
be dismissed but suspended for arbitration. separate case in court over the same subject
HBSTC contended that this applies ontly in matter of arbitration despite the pendency of that
circumstances where a complaint is filed in court arbitration, simply to obtain the provisional
withour arbitration, and not like the case at bar remedy of attachment against the bank, the
where arbitration proceedings were initiated first adverse party in the arbitration proceeding." NO.
before filing filing a court action pending the
Ruling: We find no merit in the petition. Section
arbitration proceedings.
14 of Republic Act 876, otherwise known as the
Respondent court reasons that if the absence of a Arbitration Law, allows any party to the
prior arbitration may stay court action, so too and arbitration proceeding to petition the court to
with more reason, should an arbitration already take measures to safeguard and/or conserve any
matter which is the subject of the dispute in relief directly from the courts. In the case at bar,
arbitration, thus. undeniably, private respondent has initiated
arbitration proceedings as required by the PCHC
Petitioner's exposition of the foregoing provision rules and regulations, and pending arbitration has
deserves scant consideration. Section 14 simply sought relief from the trial court for measures to
grants an arbitrator the power to issue subpoena safeguard and/or conserve the subject of the
dispute under arbitration, as sanctioned by
and subpoena duces tecum at any time before
Section 14 of the Arbitration Law, and otherwise
rendering the award. The exercise of such power not shown to be contrary to the PCHC rules and
is without prejudice to the right of a party to ;le a regulations.
petition in court to safeguard any matter which is
the subject of the dispute in arbitration. In the
case at bar, private respondent ;led an action for a Case within the case: Puromines
sum of money with prayer for a writ of "In any case, whether the liability of respondent
should be based on the sales contract or that of
preliminary attachment. Undoubtedly, such
the bill of lading, the parties are nevertheless
action involved the same subject matter as that in obligated to respect the arbitration provisions on
arbitration, i.e., the sum of P25,200,000.00 which the sales contract and/or bill of lading. Petitioner
was allegedly deprived from private respondent in being a signatory and party to the sales contract
what is known in banking as a "kiting scheme." cannot escape from his obligation under the
However, the civil action was not a simple case of arbitration clause as stated therein." In
a money claim since private respondent has Puromines, we found the arbitration clause stated
in the sales contract to be valid and applicable,
included a prayer for a writ of preliminary thus, we ruled that the parties, being signatories to
attachment, which is sanctioned by Section 14 of the sales contract, are obligated to respect the
the Arbitration Law. arbitration provisions on the contract and cannot
escape from such obligation by ;ling an action for
At this point, we emphasize that arbitration, as an breach of contract in court without resorting ;rst
alternative method of dispute resolution, is to arbitration, as agreed upon by the parties.
encouraged by this Court. Aside from unclogging
judicial dockets, it also hastens solutions
especially of commercial disputes. The Court
looks with favor upon such amicable arrangement LM Power Engineering Corp v Capitol Industrial
and will only interfere with great reluctance to Construction Groups
anticipate or nullify the action of the arbitrator.
Panganiban, J.
Case within the case: Not applicable. In
Associated Bank, we aIrmed the dismissal of the Tickler:
third-party complaint ;led by Associated Bank
against Philippine Commercial International Form: Review on Certiorari under Rule 45
Bank, Far East Bank & Trust Company, Security seeking to annul CA’s decision requiring parties
Bank and Trust Company and Citytrust Banking to present their dispute in arbitration.
Corporation for lack of jurisdiction, it being
DISMISSED.
shown that the said parties were bound by the
Clearing House Rules and Regulations on
Facts:
Arbitration of the Philippine Clearing House
Corporation. Simply put, participants in the Petitioner LM Power Engineering Corporation
regional clearing operations of the Philippine
Clearing House Corporation cannot bypass the and Respondent Capitol Industrial Construction
arbitration process laid out by the body and seek Groups Inc. entered into a "Subcontract
Agreement" involving electrical work at the Third Ruling:
Port of Zamboanga. , Respondent took over
some of the work contracted to petitioner. 6 Arbitration necessary
Allegedly, the latter had failed to finish it because We side with respondent. The instant case
of its inability to procure materials. After involves technical discrepancies that are better left
completing its task under the contract, petitioner
to an arbitral body that has expertise in those
billed respondent for P6,711,813.90. 8
areas. In any event, the inclusion of an arbitration
Contesting the accuracy of the amount of clause in a contract does not ipso facto divest the
advances and billable accomplishments listed by courts of jurisdiction to pass upon the findings of
the former, the latter refused to pay. Respondent
arbitral bodies, because the awards are still
also took refuge in the termination clause of the
judicially reviewable under certain conditions.
Agreement. 9 That clause allowed it to set off the
cost of the work that petitioner had failed to In the case before us, the Subcontract has the
undertake — due to termination or takeover — following arbitral clause: ".The Parties hereto
against the amount it owed the latter. agree that any dispute or conflict as regards to
interpretation and implementation of this
LM filed with the RTC of Makati a complaint for Agreement which cannot be settled between
collection of the alleged balance. Instead of
[respondent] and [petitioner] amicably shall be
submitting an Answer, respondent filed a Motion
settled by means of arbitration . . ."
to Dismiss, alleging that the Complaint was
premature, because there was no prior recourse Clearly, the resolution of the dispute between the
to arbitration.The RTC denied the Motion on parties herein requires a referral to the provisions
the ground that the dispute did not involve the of their Agreement. Within the scope of the
interpretation or the implementation of the arbitration clause are discrepancies as to the
Agreement and was, therefore, not covered by amount of advances and billable
the arbitral clause. After trial on the merits, the accomplishments, the application of the provision
RTC 14 ruled that the take-over of some work on termination, and the consequent set-off of
items by respondent was not equivalent to a expenses.
termination, but a mere modi@cation, of the
Subcontract. The issue as to the correct amount of petitioner's
advances and billable accomplishments involves
Issues: a.) Whether or not there exist[s] a an evaluation of the manner in which the parties
controversy/dispute that requires prior recourse completed the work, the extent to which they did
to voluntary arbitration; YES it, and the expenses each of them incurred in
connection therewith. Arbitrators also need to
b.) In the affirmative, whether or not the look into the computation of foreign and local
requirements provided in Article III [1] of CIAC costs of materials, foreign and local advances,
Arbitration Rules regarding request for arbitration
retention fees and letters of credit, and taxes and
ha[ve] been complied with, (According to
duties as set forth in the Agreement.
petitioner, assuming arguendo that the dispute is
arbitrable, the failure to @le a formal request for Being an inexpensive, speedy and amicable
arbitration with the Construction Industry method of settling disputes, arbitration — along
Arbitration Commission (CIAC) precluded the with mediation, conciliation and negotiation — is
latter from acquiring jurisdiction over the encouraged by the Supreme Court. Aside from
question) NO unclogging judicial dockets, arbitration also
hastens the resolution of disputes, especially of Since petitioner has already filed a Complaint
the commercial kind. It is thus regarded as the with the RTC without prior recourse to
"wave of the future" in international civil and arbitration, the proper procedure to enable the
commercial disputes. Brushing aside a CIAC to decide on the dispute is to request the
contractual agreement calling for arbitration stay or suspension of such action, as provided
between the parties would be a step backward. under RA 876 [the Arbitration Law].

Consistent with the above-mentioned policy of


encouraging alternative dispute resolution
methods, courts should liberally construe Case within the case: China Chang Jiang Energy
Corp v Rosal:
arbitration clauses. Provided such clause is
"Under the present Rules of Procedure, for a
susceptible of an interpretation that covers the particular construction contract to fall within the
asserted dispute, an order to arbitrate should be jurisdiction of CIAC, it is merely required that
granted. Any doubt should be resolved in favor the parties agree to submit the same to voluntary
of arbitration arbitration Unlike in the original version of
Section 1, as applied in the Tesco case, the law as
Failure to file formal request does not preclude it now stands does not provide that the parties
the tribunal from acquiring jurisdiction. should agree to submit disputes arising from their
agreement speci@cally to the CIAC for the latter
Section 1 of Article II of the o l d Rules of to acquire jurisdiction over the same. Rather, it is
Procedure Governing Construction Arbitration plain and clear that as long as the parties agree to
indeed required the submission of a request for submit to voluntary arbitration, regardless of what
forum they may choose, their agreement will fall
arbitration, as follows: "SECTION 1.Submission
within the jurisdiction of the CIAC, such that,
to Arbitration — Any party to a construction even if they speci@cally choose another forum,
contract wishing to have recourse to arbitration by the parties will not be precluded from electing to
the Construction Industry Arbitration submit their dispute before the CIAC because
Commission (CIAC) shall submit its Request for this right has been vested upon each party by
Arbitration in sufficient copies to the Secretariat law,” -
of the CIAC; PROVIDED, that in the case of
government construction contracts, all Case within the case: Tesco
administrative remedies available to the parties On the other hand, Section 1 of Article III of the
must have been exhausted within 90 days from new Rules of Procedure Governing Construction
the time the dispute arose.” Arbitration has dispensed with this requirement
and recourse to the CIAC may now be availed of
there is no more need to file a request with the whenever a contract "contains a clause for the
CIAC in order to vest it with jurisdiction to submission of a future controversy to arbitration,"
decide a construction dispute. The arbitral clause in this wise: "SECTION 1.Submission to CIAC
in the Agreement is a commitment on the part of Jurisdiction — An arbitration clause in a
construction contract or a submission to
the parties to submit to arbitration the disputes arbitration of a construction dispute shall be
covered therein. Because that clause is binding, deemed an agreement to submit an existing or
they are expected to abide by it in good faith. future controversy to CIAC jurisdiction,
And because it covers the dispute between the notwithstanding the reference to a different
parties in the present case, either of them may arbitration institution or arbitral body in such
compel the other to arbitrate contract or submission. When a contract contains
a clause for the submission of a future
controversy to arbitration, it is not necessary for
the parties to enter into a submission agreement Dismiss 6 separately against Bridestone's
before the claimant may invoke the jurisdiction of complaint and Anaconda's complaint. Both
CIAC." The foregoing amendments in the Rules
motions to dismiss presented similar grounds
were formalized by CIAC Resolution Nos. 2- 91
and 3-93 for dismissal. They contended that the RTC
could not acquire jurisdiction over Consolidated
Iron because it was a foreign corporation that
had never transacted business in the
Philippines. Likewise, they argued that the RTC
had no jurisdiction over the subject matter
because of an arbitration clause in the TPAA.

The RTC ruled that it had jurisdiction over the


LUZON IRON vs. BRIDESTONE MINING subject matter because under clause 14.8 of the
TPAA, the parties could go directly to courts
Mendoza, J. when a direct and/or blatant violation of the
provisions of the TPAA had been committed.
Tickler:
The CA also sustained the jurisdiction of the RTC
Form: Petition for review on certiorari with
over the subject matter opining that the
prayer for the issuance of a writ of preliminary
injunction and/or temporary restraining order arbitration clause in the TPAA provided for an
(TRO) seeks to reverse CA decision affirming exception where parties could directly go to
RTC order for rescission of contract and court.
damages. GRANTED- ARBITRATION
Issue: Whether the court of appeals erred in
NECESSARY, RTC CANT RULE YET
ruling that the trial court has jurisdiction over
Facts: Bridestone and Anaconda filed separate the subject matter of the consolidated cases;
complaints before the RTC for rescission of (other issues not adr related: jurisdiction over
contract and damages against petitioners Luzon the person of consolidated iron and forum
and Consolidated Iron. shopping)

Both complaints sought the rescission of the Ruling: Controversy must be referred for
Tenement Partnership and Acquisition arbitration
Agreement (TPAA) entered into by Luzon Iron
The petitioners insisted that the RTC had no
and Consolidated Iron, on one hand, and
jurisdiction over the subject matter because
Bridestone and Anaconda, on the other, for the
under Paragraph 15.1 of the TPAA, any dispute
assignment of the Exploration Permit
out of or in connection with the TPAA must be
Application of the former in favor of the latter.
resolved by arbitration. The said provision
The complaints also sought the return of the
provides: If, for any reasonable reason, the
Exploration Permits to Bridestone and
Parties cannot resolve a material fact, material
Anaconda.
event or any dispute arising out of or in
Thereafter, Luzon Iron and Consolidated Iron connection with this TPAA, including any
?led their Special Appearance with Motion to question regarding its existence, validity or
termination, within 90 days from its notice, constitutionality of: (a) the assignments of the
shall be referred to and finally resolved by EP to Luzon Iron; (b) any other assignments
arbitration in Singapore in accordance with the contemplated by the TPAA; or (c) any
Arbitration Rules of the Singapore International agreement to which the EPs may be converted,
Arbitration Centre ("SIAC Rules") for the time may be instituted only when there is a direct
being in force, which rules are deemed to be and/or blatant violation of the TPAA. In turn,
incorporated by reference in this clause 15.1. the said action or claim is commenced by
proceeding with arbitration, as espoused in the
The RTC, as the CA agreed, countered that
TPAA.
Paragraph 14.8 of the TPAA allowed the parties
to directly resort to courts in case of a direct The Court disagrees with the respondents that
and/or blatant violation of the provisions of the Paragraph 14.8 of the TPAA should be
TPAA. Paragraph 14.8 stated: Each Party agrees construed as an exception to the arbitration
not to commence or procure the clause where direct court action may be
commencement of any challenge or claim, resorted to in case of direct and/or blatant
action, judicial or legislative enquiry, review or violation of the TPAA occurs. If such
other investigation into the suf?ciency, validity, interpretation is to be espoused, the arbitration
legality or constitutionality of (i) the clause would be rendered inutile as practically
assignments of the Exploration Permit all matters may be directly brought before the
Applications(s) (sic) to LIDGC, (ii) any other courts. Such construction is anathema to the
assignments contemplated by this TPAA, and/or policy favoring arbitration.
(iii) or (sic) any agreement to which the
A closer perusal of the TPAA will also reveal that
Exploration Permit Application(s) may be
converted, unless a direct and/or blatant paragraph 14 and all its subparagraphs are
violation of the provisions of the TPAA has been general provisions, whereas paragraphs 15 and
all its sub-clauses specifically refer to
committed.
arbitration. When general and specific
Consistent with the state policy of favoring provisions are inconsistent, the specific
arbitration, the present TPAA must be provision shall be paramount and govern the
construed in such a manner that would give life general provision.
to the arbitration clause rather than defeat it, if
such interpretation is permissible. With this in The petitioners' failure to refer the case for
mind, the Court views the interpretation arbitration, however, does not render the
forwarded by the petitioners as more in line arbitration clause in the TPAA inoperative.
with the state policy favoring arbitration. RULE 4: REFERRAL TO ADR Rule 4.1. Who makes
Paragraphs 14.8 and 15.1 of the TPAA should be the request. — A party to a pending action ?led
harmonized in such a way that the arbitration in violation of the arbitration agreement,
clause is given life, especially since such whether contained in an arbitration clause or in
construction is possible in the case at bench. A a submission agreement, may request the court
synchronized reading of the abovementioned to refer the parties to arbitration in accordance
TPAA provisions will show that a claim or action with such agreement.
raising the suf?ciency, validity, legality or
In using the word "may" to qualify the act of competence or jurisdiction of an arbitral
filing a "request" under Section 24 of R.A. No. tribunal in a dispute brought before it, either
9285, the Special ADR Rules clearly did not before or after the arbitral tribunal is
intend to limit the invocation of an arbitration constituted, the court must exercise judicial
agreement in a pending suit solely via such restraint and defer to the competence or
"request." After all, non-compliance with an jurisdiction of the arbitral tribunal by allowing
arbitration agreement is a valid defense to any the arbitral tribunal the first opportunity to rule
offending suit and, as such, may even be raised upon such issues. Where the court is asked to
in an answer as provided in our ordinary rules make a determination of whether the
of procedure. arbitration agreement is null and void,
inoperative or incapable of being performed,
It is undisputed that the petitioners Luzon Iron under this policy of judicial restraint, the court
and Consolidated Iron never made any formal must make no more than a prima facie
request for arbitration. As expounded in determination of that issue. Unless the court,
Koppel, however, a formal request is not the pursuant to such prima facie determination,
sole means of invoking an arbitration clause in a concludes that the arbitration agreement is null
pending suit. Similar to the said case, the and void, inoperative or incapable of being
petitioners here made the RTC aware of the performed, the court must suspend the action
existence of the arbitration clause in the TPAA before it and refer the parties to arbitration
as they repeatedly raised this as an issue in all pursuant to the arbitration
their motions to dismiss. As such, it was enough agreement.Generally, the action of the court is
to activate the arbitration clause and, thus, stayed if the matter raised before it is subject to
should have alerted the RTC in proceeding with arbitration. The parties, nevertheless, are
the case. directed to initiate arbitration proceedings as
Competence-competence principle provided under Paragraph 15.1 of the TPAA.

Moreover, judicial restraint should be exercised In Bases Conversion Development Authority v.


DMCI Project Developers, Inc., 32 the Court
pursuant to the competence-competence
emphasized that the State favored arbitration,
principle embodied in Rule 2.4 of the Special to wit: The state adopts a policy in favor of
Rules of Court on Alternative Dispute arbitration. Republic Act No. 9285 expresses
Resolution. this policy: SEC. 2. Declaration of Policy. — It is
hereby declared the policy of the State to
The said provision reads: RULE 2.4. Policy actively promote party autonomy in the
Implementing Competence-Competence resolution of disputes or the freedom of the
Principle. — The arbitral tribunal shall be parties to make their own arrangements to
accorded the first opportunity or competence resolve their disputes. Towards this end, the
to rule on the issue of whether or not it has State shall encourage and actively promote the
use of Alternative Dispute Resolution (ADR) as
the competence or jurisdiction to decide a
an important means to achieve speedy and
dispute submitted to it for decision, including impartial justice and declog court dockets. As
any objection with respect to the existence or such, the State shall provide means for the use
validity of the arbitration agreement. When a of ADR as an ef?cient tool and an alternative
court is asked to rule upon issue/s affecting the procedure for the resolution of appropriate
cases. Likewise, the State shall enlist active performed.
private sector participation in the settlement of STEAMSHIP MUTUAL UNDERWRITING
disputes through ADR. This Act shall be without ASSOCIATION (BERMUDA) LIMITED, petitioner,
prejudice to the adoption by the Supreme Court vs. SULPICIO LINES, INC., respondent.
of any ADR system, such as mediation,
conciliation, arbitration, or any combination Leonen, J.
thereof as a means of achieving speedy and
ef?cient means of resolving cases pending Facts:
before all courts in the Philippines which shall
be governed by such rules as the Supreme Steamship was a Bermuda-based Protection
Court may approve from time to time. and Indemnity Club, managed outside London,
Our policy in favor of party autonomy in England. Sulpicio insured its fleet of inter-island
resolving disputes has been reJected in our laws
vessels with Steamship for Protection &
as early as 1949 when our Civil Code was
approved. Republic Act No. 876 later explicitly Indemnity risks through local insurance agents,
recognized the validity and enforceability of Pioneer Insurance and Surety Corporation
parties' decision to submit disputes and related (Pioneer Insurance) or Seaboard-Eastern
issues to arbitration. Arbitration agreements Insurance Co., Inc. (SeaboardEastern). One (1)
are liberally construed in favor of proceeding to of these vessels was the M/V Princess of the
arbitration. We adopt the interpretation that World, evidenced by a Certificate of Entry and
would render effective an arbitration clause if
Acceptance issued by Steamship.
the terms of the agreement allow for such
interpretation. On July 7, 2005, M/V Princess of the World was
gutted by fire while on voyage from Iloilo to
In Koppel, Inc. v. Makati Rotary Club Zamboanga City, resulting in total loss of its
Foundation, Inc. (Koppel), 35 the Court cargoes. The fire incident was found by the
explained that an arbitration clause becomes Department of the Interior and Local
operative, notwithstanding the lack of a formal Government to be "accidental" in nature.
request, when a party has appraised the trial
court of the existence of an arbitration clause, Sulpicio claimed indemnity from Steamship but
viz.: xxx The operation of the arbitration clause it denied the former, on ground that it was
in this case is not at all defeated by the failure “grossly negligent in conducting its business
of the petitioner to ?le a formal "request" or
regarding safety, maintaining the seaworthiness
application therefor with the MeTC. We ?nd
that the ?ling of a "request" pursuant to Section of its vessels as well as proper training of its
24 of RA. No. 9285 is not the sole means by crew."
which an arbitration clause may be validly
invoked in a pending suit. Section 24 of R.A. No. Sulpicio filed a claim for specific performance
9285 reads: SEC. 24. Referral to Arbitration. — with the Regional Trial Court of Makati.
A court before which an action is brought in a
matter which is the subject matter of an Steamship filed its Motion to Dismiss and/or to
arbitration agreement shall, if at least one party Refer Case to Arbitration 15 pursuant to
so requests not later that the pre-trial Republic Act No. 9285, or the Alternative
conference, or upon the request of both parties Dispute Resolution Act of 2004 (ADR Law), and
thereafter, refer the parties to arbitration to Rule 47 16 of the 2005/2006 Club Rules,
unless it ?nds that the arbitration agreement is
which supposedly provided for arbitration in
null and void, inoperative or incapable of being
London of disputes between Steamship and its importantly, without the prior approval of this
members. The other defendants filed separate Honorable Court, Steamship initiated and
motions to dismiss. "concluded" said London "arbitration" during
the pendency of this G.R. No. 196072 and
The Court of Appeals found no grave abuse of
before this Honorable Court could render its
discretion on the part of the trial court in ruling or decision
denying Steamship's Motion to Dismiss and/or
to Refer Case to Arbitration 27 or any Issues:
convincing evidence to show that a valid
arbitration agreement existed between the Whether or not there is a valid and binding
parties. Steamship's Motion for Reconsideration arbitration agreement between Steamship
Mutual Underwriting (Bermuda) Limited and
of this Decision was likewise denied.
Sulpicio Lines, Inc.;
Steamship filed before this Court this Petition
for Review, docketed as G.R. No. 196072. Third, whether or not the Court of Appeals
gravely erred in affrming the Regional Trial
Sulpicio filed with this Court a Petition for Court Order denying referral of Sulpicio Lines,
Indirect Contempt under Rule 71 of the Rules of Inc.'s complaint to arbitration in London in
Court against Steamship. This Petition was accordance with the 2005/2006 Club Rules;
docketed as G.R. No. 208603.
Rulings:
Sulpicio accuses Steamship of indirect contempt
The Regional Trial Court should suspend
the following acts: (a) Without Sulpicio's
knowledge or consent, Steamship initiated and proceedings to give way to arbitration. Even if
"concluded" during the pendency of this case there are other defendants who are not parties
to the arbitration agreement, arbitration is still
an alleged "arbitration proceeding" in London
for the "Arbitrator" there to "resolve" the very proper.
dispute involved in this case; (b) Without The Regional Trial Court denied Steamship's
Sulpicio's knowledge or consent, Steamship Motion to Dismiss and/or to Refer Case to
proclaimed itself the "victor" entitled to Arbitration and directed it to file an answer.
arbitration costs from Sulpicio; (c) Without This Court finds that the Regional Trial Court
Sulpicio's knowledge or consent, Steamship acted in excess of its jurisdiction. Where a
unceremoniously deducted from the refund due motion is filed in court for the referral of a
to Sulpicio in the separate "Unabia Case" the dispute to arbitration, Section 24 of Republic
huge amount of U.S.$69,570.99 despite the fact Act No. 9285 ordains that the dispute shall be
that: (a) Said "Unabia Case" is unrelated to the referred "to arbitration unless it finds that the
instant case; (b) The propriety of a London arbitration agreement is null and void,
arbitration is still to be resolved in this case by inoperative or incapable of being performed."
this Honorable Court; (c) Steamship "enforced" Thus, the Regional Trial Court went beyond its
by itself said "arbitration costs" against Sulpicio authority of determining only the issue of
without the courtesy of even informing this whether or not there was a valid arbitration
Honorable Court about it[; and] (d) Without agreement between the parties when it denied
Sulpicio's knowledge or consent, and more Steamship's Motion to Dismiss and/or to Refer
Case to Arbitration solely on the ground that it DEPARTMENT OF PUBLIC WORKS AND
would not be the most prudent action under HIGHWAYS , vs. CMC/MONARK/PACIFIC/HI-TRI
the circumstances of the case. The Regional JOINT VENTURE,
Trial Court went against the express mandate of
Form: Review on Certiorari 1 assailing the Court
Republic Act No. 9285. Consequently, the Court
of Appeals erred in finding no grave abuse of of Appeals Decision 2 dated September 20,
discretion on the part of the trial court in 2007 in CA-G.R. SP Nos. 88953 and 88911,
which affirmed the March 1, 2005 Award of the
denying referral to arbitration.
Construction Industry Arbitration Commission
Steamship's commencement of arbitration even (CIAC)
before the Regional Trial Court had ruled on its
motion to dismiss and suspend proceedings Department of Public Works and Highways
(DPWH), and CMC/Monark/Paci>c/Hi-Tri J.V.
does not constitute an "improper conduct" that
"impede[s], obstruct[s] or degrade[s] the (the Joint Venture) executed "Contract
Agreement for the Construction of Contract
administration of justice."
Package 6MI-9, Pagadian-Buug Section,
This Court =nds no clear and contumacious Zamboanga del Sur, Sixth Road Project, Road
conduct on the part of Steamship. It does not Improvement Component Loan No.
appear that Steamship was motivated by bad
faith in initiating the arbitration proceedings. While the project was ongoing, the Joint
Rather, its act of commencing arbitration in Venture's truck and equipment were set on >re.
London is but a bona =de attempt to preserve On March 11, 2003, a bomb exploded at Joint
and enforce its rights under the Club Rules. Venture's batching plant located at Brgy. West
There was no legal impediment at the time Boyogan, Kumalarang, Zamboanga del Sur.
Steamship initiated London arbitration According to reports, the bombing incident was
proceedings. Steamship commenced arbitration caused by members of the Moro Islamic
on July 31, 2007 even before the Regional Trial Liberation Front.
Court denied its Motion to Dismiss and/or Refer There were several demands for extension and
Case to Arbitration on July 11, 2008. There was payment of the foreign component of the
no order from the Regional Trial Court enjoining contract, and efforts between both parties to
Steamship from initiating arbitration settle unpaid claims amounting to
proceedings in London. Besides, the 2009 P26,737,029.49..
Special ADR Rules speci=cally provided that
arbitration proceedings may be commenced or BCEOM French Engineering Consultants
continued and an award may be made, while, recommended that DPWH promptly pay the
the motion for the stay of civil action and for outstanding monies due the Joint Venture
referral to arbitration is pending resolution by amounting to Php77,206,047.88
the court.

The Joint Venture sent a "Notice of Mutual


Termination of Contract" 13 to DPWH
requesting for a mutual termination of the
contract subject of the arbitration case.
After hearing and submission of the parties' was forthcoming. It would therefore be an
respective memoranda, 15 CIAC promulgated exercise in futility if Claimant, after it had sent
an Award 16 on March 1, 2005, directing DPWH respondent the seventeen (17) demand letters
to pay the Joint Venture its money claims plus and despite the unequivocal admission by
legal interest. . CIAC, however, denied the Joint Respondent's foreign consultant in charge of
Venture's claim for price adjustment due to the the project of respondent's liability and failure
delay in the issuance of a Notice to Proceed. to pay (Annex C of the Complaint), will further
be required to undergo another series of
Issue: According to petitioner, the filing of the presentation and exchange of documentation.
claim before CIAC was premature, since under Moreover, Respondent has not indicated any
CIAC rules, there must be an exhaustion of practical bene>t of resending the demand to
administrative remedies first before the Secretary nor any prejudice for not doing
government contracts are brought to it for so. In this particular contract project, the
arbitration. procedural requirements governing the
Respondent, on the other hand, denies violating Settlement of Disputes is speci>cally provided
the rule on exhaustion of administrative under Clause 67 of the Conditions of the
remedies. It claims that it sent at least 17 Contract which Claimant has complied with
demand letters to petitioner, four (4) of which pursuant to the >rst paragraph of its letter
were sent to the DPWH Secretary directly dated September 10, 2004 (annex R) pertinent
provisions thereof is read, as follows:
Ruling: Petitioner's argument fails to convince.
The case is not premature. The pertinent A total of 17 demand letters were sent to
provision on available administrative remedies petitioner to no avail. To require respondent to
can be found in Sub-Clause 67.1 of the wait for the DPWH Secretary's response while
Conditions of Contract: respondent continued to suffer >nancially
would be to condone petitioner's avoidance of
Under the doctrine of exhaustion of its obligations to respondent. Hence, even
administrative remedies, the concerned assuming that sub-clause 67.1 was not
administrative agency must be given the applicable, the case would still fall within the
opportunity to decide a matter within its exceptions to the doctrine of exhaustion of
jurisdiction before an action is brought before administrative remedies 56 since strict
the courts, otherwise, the action will be application of the doctrine will be set aside
declared premature. 54 In this case, CIAC found when requiring it would only be unreasonable
and correctly ruled that respondent had duly under the circumstances.
complied with the contractual obligation to
exhaust administrative remedies provided for BASES CONVERSION DEVELOPMENT
under sub-clause 67.1 of the Conditions of AUTHORITY, petitioner, vs. DMCI PROJECT
Contract before it brought the case before the DEVELOPERS, INC., respondent. [G.R. No.
tribunal: 173170. January 11, 2016.] NORTH LUZON
RAILWAYS CORPORATION , petitioner, v s .
The Claimant further alleged that, despite of DMCI PROJECT DEVELOPERS, INC., respondent.
such knowledge, no relief from the Secretary
An arbitration clause in a document of contract corresponding representation in the Northrail
may extend to subsequent documents of Board. b) DMCI PDI/FBDC was privy to all the
contract executed for the same purpose. deliberations of the Northrail Board and
Nominees of a party to and bene8ciaries of a participated in the decisions made and policies
contract containing an arbitration clause may adopted to pursue the project. c) DMCI
become parties to a proceeding initiated based PDI/FBDC had full access to the 8nancial
on that arbitration clause. statements of Northrail and was regularly
informed of the corporation's financial
On June 10, 1995, Bases Conversion
condition
Development Authority (BCDA) entered into a
Joint Venture Agreement 1 with Philippine Upon BCDA's request, the Of8ce of the
National Railways (PNR) and other foreign Government Corporate Counsel (OGCC) issued
corporations. 2 Under the Joint Venture Opinion No. 116, Series of 2001 31 on June 27,
Agreement, the parties agreed to construct a 2001. The OGCC stated that "since no increase
railroad system from Manila to Clark with in capital stock was implemented, it is but
possible extensions to Subic Bay and La Union proper to return the investments of both FBDC
and later, possibly to Ilocos Norte and Nueva and DMCI
Ecija. 3 BCDA shall establish North Luzon
Railways Corporation (Northrail) for purposes of : In a January 19, 2005 letter, 33 DMCI-PDI
reiterated the request for the refund of its P300
constructing, operating, and managing the
railroad system. 4 The Joint Venture Agreement million deposit for future Northrail subscription.
contained an arbitration clause On March 18, 2005, BCDA denied 34 DMCI-PDI's
request: We regret to say that we are of the
Later, Northrail withdrew from the Securities position that the P300 [million] contribution
and Exchange Commission its application for should not be returned to DMCI for the
increased authorized capital stock. 24 following reasons: a. the P300 million was in the
Moreover, according to DMCI-PDI, BCDA nature of a contribution, not deposits for future
applied for Of8cial Development Assistance subscription; and b. DMCI, as a joint venture
from Obuchi Fund of Japan. 25 This required partner, must share in pro8ts and losses. 35
Northrail to be a 100% government-owned and
controlled corporation. 26 On September 27,
2000, DMCI-PDI started demanding from BCDA BCDA 8led a Motion to Dismiss 43 on the
and Northrail the return of its P300 million ground that there was no arbitration clause that
deposit. 27 DMCI-PDI cited Northrail's failure to DMCI-PDI could enforce since DMCI-PDI was
increase its authorized capital stock as reason not a party to the Joint Venture Agreement
for the demand. 28 BCDA and Northrail refused containing the arbitration clause. 44 Northrail
to return the deposit 29 for the following 8led a separate Motion to Dismiss 45 on the
reasons: ground that the court did not have jurisdiction
a) At the outset, DMCI PDI/FBDC's participation over it and that DMCI-PDI had no cause for
in Northrail was as a joint venture partner and arbitration against it.
co-investor in the Manila Clark Rapid Railway Ruling:
Project, and as such, was granted
A reading of all the documents of agreement WHEREFORE, the petitions are DENIED. The
shows that they were executed by the same February 9, 2006 Regional Trial Court Decision
parties. Initially, the Joint Venture Agreement and the June 9, 2006 Regional Trial Court Order
was executed only by BCDA, PNR, and the are AFFIRMED.
foreign corporations. When the Joint Venture
Agreement was amended to include D.M. Frehaf v Technology
Consunji, Inc. and/or its nominee, D.M. In 1978, Fruehauf Electronics Philippines Corp. (
Consunji, Inc. and/or its nominee were deemed F r u e h a u f ) leased several parcels of land in
to have been also a party to the original Joint Pasig City to Signetics Filipinas Corporation ( Sig
Venture Agreement executed by BCDA, PNR, n e tic s ) for a period of 25 years (until May 28,
and the foreign corporations. D.M. Consunji, 2003). Signetics constructed a semiconductor
Inc. and/or its nominee became bound to the assembly factory on the land on its own
terms of both the Joint Venture Agreement and account. In 1983, Signetics ceased its operations
its amendment. after the Board of Investments ( B O I) withdrew
Moreover, each document was executed to the investment incentives granted to electronic
achieve the single purpose of implementing the industries based in Metro Manila. In 1986,
railroad project, such that documents of Team Holdings Limited (THL) bought Signetics.
agreement succeeding the original Joint THL later changed its name to Technology
Electronics Assembly and Management Pacific
Venture Agreement merely amended or
supplemented the provisions of the original Corp. ( T E A M ) . In March 1987, Fruehauf led
Joint Venture Agreement. an unlawful detainer case against TEAM. In an
effort to amicably settle the dispute, both
In other words, each document of agreement parties executed a Memorandum of Agreement
represents a step toward the implementation of ( M O A ) on June 9, 1988. 33 Under the MOA,
the project, such that the three agreements TEAM undertook to pay Fruehauf 14.7 million
must be read together for a complete pesos as unpaid rent (for the period of
understanding of the parties' whole agreement. December 1986 to June 1988). aScITE They also
The Joint Venture Agreement, the amended entered a 15-year lease contract 44 (expiring on
Joint Venture Agreement, and the June 9, 2003) that was renewable for another
Memorandum of Agreement should be treated 25 years upon mutual agreement. The contract
as one contract because they all form part of a included an arbitration agreement:
whole agreement. HESIcT Hence, the arbitration
clause in the Joint Venture Agreement should
not be interpreted as applicable only to the
Joint Venture Agreement's original parties. The
succeeding agreements are deemed part of or a
continuation of the Joint Venture Agreement.
The arbitration clause should extend to all the
agreements and its parties since it is still
consistent with all the terms and conditions of
the amendments and supplements. I
PRINCIPLE OF KOMETENCE-KOMPETENCE and (5) Such further and/or other relief as the
Arbitral Tribunal deems Jt and just.
Mabuhay and IDHI incorporated Water Jet
Shipping Corporation (WJSC) in the Philippines Mabuhay argued that the dispute is an intra-
to engage in the venture of carrying passengers corporate controversy, hence, excluded from
on a common carriage by inter-island fast ferry. the scope of the arbitration clause in the
they also incorporated Water Jet Netherlands Agreement. It alleged that on March 13, 1997,
Antilles, N.V. (WJNA) in Curasao, Netherlands. Sembcorp became the controlling stockholder
They entered into a shareholders agreement. of IDHI by acquiring substantial shares of stocks
through its nominee, Mr. Pablo N. Sare (Sare).
Sembcorp decided to invest in the said Mabuhay thus claimed that it has already been
corporations. As a result of Sembcorp's released from the joint obligation with IDHI as
acquisition of shares, Mabuhay and IDHI's
Sembcorp assumed the risk of loss when it
shareholding percentage in the said acquired absolute ownership over the aforesaid
corporations were reduced. shares. Moreover, Mabuhay argued that the
Pursuant to Article 13 of the Agreement, appointment of Dr. ChantaraOpakorn was not
Mabuhay and IDHI voluntarily agreed to jointly in accordance with the arbitral clause as he did
guarantee that Sembcorp would receive a not have the expertise in the matter at issue,
minimum accounting return of US$929,875.50 which involved application of Philippine law.
(Guaranteed Return) at the end of the 24th Finally, Mabuhay argued that the imposition of
month. twelve percent (12%) interest from the date of
the Final Award was contrary to the Philippine
On November 26, 1999, Sembcorp requested law and jurisprudence. 21
for the payment of its Guaranteed Return from
Mabuhay and IDHI. Mabuhay admitted its
liability but asserted that since the obligation is
joint, it is only liable for Jfty percent (50%) of
the claim or US$464,937.75. 13 On February 24,
2000, Sembcorp sent a Final Demand to
Mabuhay to pay the Guaranteed Return.
Mabuhay requested for three (3) months to
raise the necessary funds but still failed to pay
any amount after the lapse of the said period.
14 On December 4, 2000, Sembcorp Jled a
Request for Arbitration before the International
Court of Arbitration of the International
Chamber of Commerce (ICC) in accordance with
the Agreement and sought the following reliefs:
(1) payment of the sum of US$929,875.50; (2)
alternatively, damages; (3) interest on the
above sum at such rate as the Arbitral Tribunal
deems Jt and just; (4) cost of the arbitration;

Vous aimerez peut-être aussi