PROGRAMA Y CUMPLIMIENTO MENSUAL JULIO- 2019

FECHA: lunes, 8 de Julio de 2019


DESCRIPCION UM PROGRAMA EJECUCION CUMPLIMIENTO Cumpl. GLOBAL PU SUB TOTAL
Mineral Plomo TMS 0.00 0.00 N.P. S/ 8.86 S/ -
Mineral Cobre TMS 32,000.00 14,604.88 45.64% 41.15% S/ 9.23 S/ 134,803.05
Mineral a COFRE TMS 13,000.00 3,914.24 30.11% S/ 7.20 S/ 28,182.53
Desmonte Roto m3 65,000.00 19,750.00 30.38% S/ 12.30 S/ 242,925.00
34.20%
Desmonte Excavado m3 0.00 2,480.00 N.P. S/ 7.30 S/ 18,104.00
Mineral de Segunda TMS 0.00 0.00 0.00% S/ 6.65 S/ -
Produccion GLOBAL M3 83,518.52 29,851.04 35.74% TOTAL S/ 424,014.57

TODO EN M³
EJECUCIÓN Y CUMPLIMIENTO - JUNIO 2019
RESUMEN EJECUTIVO MENSUAL Julio-2019
FECHA: 50.00% 45.64% lunes, 8 de Julio de 2019
DESCRIPCION45.00% UM PROGRAMA EJECUCION CUMPLIMIENTO Cumpl. GLOBAL
Mineral Plomo 40.00% m3 0.00 0.00 N.P.
Mineral Cobre m3 13,168.72 6,010.24 45.64% 41.2%
Mineral a COFRE 35.00% m3 5,349.79 30.11%
1,610.80 30.11% 30.38%
Desmonte Roto 30.00% m3 65,000.00 19,750.00 30.38%
34.2%
Desmonte Excavado m3 0.00 2,480.00 N.P.
25.00%
Mineral de Segunda 20.00% m3 0.00 0.00 0.00%

15.00%
Produccion GLOBAL M3 83,518.52 29,851.04 35.74%
10.00%
5.00% 0.00%
0.00%
m3 m3 m3 m3
Mineral a Desmonte
Mineral Cobre Desmonte Roto
COFRE Excavado
PROGRAMA 13,168.72 5,349.79 65,000.00 0.00
EJECUCION 6,010.24 1,610.80 19,750.00 2,480.00
CUMPLIMIENTO 45.64% 30.11% 30.38% 0.00%
INGRESAR
INGRESARAQUI
AQUI
Coempsa
Andermac RESUMEN EJECUTIVO

FECHA: lunes, 8 de Julio de 2019

PERFORACIÓN
MALLA
GUARDIA EQUIPO Hrs. Netas TAJO BANCO № TAL Mtrs. Perf. Altura Prom. Burden Espac. ø Tal. (Pulg.)
Día Rock-Drill 7.73 T-CN (ESTE) 4345 40 185.5 4.64 3.5 4 3.5
Día Track-Drill N° 1 7.37 T-CN (ESTE) 4345 44 195.9 4.45 3.5 4 3.5
Noche Rock-Drill 9.23 T-CN (ESTE) 4345 32 175.2 5.48 3.5 4 3.5
TOTAL 24.33 - - 116 556.6 72

COMPRENSORA

GUARDIA EQUIPO Hrs. Netas COMENTARIOS


Día Compresora Ingersollrand 1101 7.70 Suministro de aire.
TOTAL 7.70

ACARREO

№ DE VIAJES
ANDERMAC COEMPSA

Tacaza Tacaza Cofre Cofre Min. B.L. Min. B.L.


GUARDIA VOLQUETE Hrs. Netas TAJO BANCO VOLADURA Desmonte Desbroce Deslizado Top-Soil № viajes
Cu Pb Cu Pb Cu Pb
Día D8U-724 2.25 0 0 0 0 0 0 0 0 0 0 9 0 0 9
Día V9S-730 2.25 0 0 0 0 0 0 0 0 0 0 9 0 0 9
Día F4Z-911 2.25 0 0 0 0 0 0 0 0 0 0 9 0 0 9
Día AXK-714 2.75 0 0 0 0 0 0 0 0 0 0 11 0 0 11
Día V7C-893 0.00 T-CN (OESTE) 4315 45 0 0 1 0 0 0 0 0 0 0 1
T-CN (OESTE) 4315 45 0 0 1 0 0 0 0 0 0 0
Día F6X-918 3.00 13
T-CN (ESTE) 4350 47 0 0 0 0 0 0 12 0 0 0
T-CN (OESTE) 4315 45 0 0 1 0 0 0 0 0 0 0
Día B5F-782 1.00 5
T-CN (ESTE) 4345 49 0 0 0 0 0 0 4 0 0 0
T-CN (OESTE) 4315 45 0 0 1 0 0 0 0 0 0 0
Día AJK-810 2.50 11
T-CN (ESTE) 4350 47 0 0 0 0 0 0 10 0 0 0
TAJO-CENTRAL NORTE (ESTE) 0 0 0 0 0 0 26 0 0 0
TOTAL 16.00
TAJO-CENTRAL NORTE (OESTE) 0 0 4 0 0 0 0 0 0 0
TOTAL 30

CARGUIO

GUARDIA EQUIPO Hrs. Netas COMENTARIO


Día Jhon Deere (Coempsa) 10.10 Carguio de desmonte roto
Día CAT DL (Coempsa) 2.75 Carguio de mineral
TOTAL 12.85

AUXILIARES

GUARDIA EQUIPO Hrs. Netas COMENTARIO


Día Motoniveladora 3.58 Mantenimiento de acceso a banco
Día Retro excavadora 1.00 Empuje de desmonte
TOTAL 4.58