In this Agreement, the under listed documents shall together with this Agreement form
the Contract documents, viz:
The above Contract documents shall be mutually explanatory and in case of conflict
or discrepancy amongst the documents forming the Contract documents the same
shall be resolved by giving effect to the terms and conditions stipulated in this
Agreement which shall prevail over the terms and conditions contained in the other
documents.
3.1 The services which Contractor shall perform pursuant to this Agreement shall include but
not limited to the following:
3.1.1 Provision of Produced Water Project Documentation & Close-out Engineer (Produced
Water Project)
6
EPT shall supply Produced Water Project Documentation & Close-out Engineer. The
personnel shall be responsible for the acceptance of all mechanical scope at
produced water handling and ensuring that all Mechanical and Piping Commissioning
has been successfully tested, and documented, in line with Site Standards and
Technical Practices.
The personnel task shall include but not limited to the following:
3.1.1.4 Execute all mechanical & piping pre -commissioning, commissioning and
start-up activities for assigned sub -systems. This includes preparatory
activities, coordinating resources (technicians, equipment and other
departments), expediting documentation- in particular handover dossiers,
participating in walk -downs from construction to commissioning and from
commissioning to operations and formally agreeing and categorizing
punch -list items.
3.1.1.7 Raise site materials requests (SMRs), technical queries (TQs), field instructions
(Hs) for activities where necessary and livening up notices (LUNs) where
piping/mechanical equipment or lines require energizing.