REMAINING WORKS - SCHEDULE

CHANGE ROOM & POLYCLINIC ETEX 2019


ID Task Task Name DurationAug '19 Start Finish Sep '19 Oct '19 Nov '19
Mode 26 02 09 16 23 30 07 14 21 28
1 Demolish work #1 (Pekerjaan Pembongkaran #1) 4,69 days Thu 05/09/19 Sun 08/09/19
2 Install water pipe from existing tank to the new water 1 day Thu 05/09/19 Thu 05/09/19
tank
3 Transfer water from existing to the new water tank 1 day Thu 05/09/19 Fri 06/09/19
4 Dismantling existing water tank & all structures (use 1 day Sun 08/09/19 Sun 08/09/19
forklift)
5 Pekerjaan Civil (Civil Works) 16,03 days Mon 02/09/19 Sat 14/09/19
6 Demolish wall at west side building (Existing) 3 days Mon 02/09/19 Wed 04/09/19
7 Installation wall tile's shower room (Male) 2 days Tue 03/09/19 Wed 04/09/19
8 Installation wall tile's toilet room (Male) 5 days Tue 03/09/19 Fri 06/09/19
9 Installation wall tile's toilet room (Female) 2 days Tue 10/09/19 Thu 12/09/19
10 Installation floor tile's toilet room (Female) 1 day Thu 12/09/19 Thu 12/09/19
11 Installation floor tile for Warehouse & Polyclinic 2 days Thu 12/09/19 Sat 14/09/19
12 Accessories Installation (Urinoir+WC+Wastafel) 2 days Thu 12/09/19 Sat 14/09/19
13 Interior & Exterior work (Pekerjaan 28 days Wed 04/09/19 Thu 26/09/19
Partisi+Plamir+Pengecatan)
14 Install Plafond Frameworks Warehouse & Polyclinic Room
1 day Fri 13/09/19 Sat 14/09/19
15 Install Plafond Warehouse & Polyclinic Room 3 days Sat 14/09/19 Mon 16/09/19
16 Install Partion Warehouse & Polyclinic Room 3 days Mon 16/09/19 Thu 19/09/19
17 Plamer works for all plafonds 4 days Wed 04/09/19 Fri 06/09/19
18 Plamer works for all wall & partion 4 days Sat 07/09/19 Wed 11/09/19
19 Primary Paint for Plafonds 2 days Wed 11/09/19 Fri 13/09/19
20 Finishing Paint for Plafonds 4 days Sat 14/09/19 Tue 17/09/19
21 Primary Paint for Plafonds 4 days Thu 19/09/19 Sun 22/09/19
22 Finishing Paint for All Wall 4 days Mon 23/09/19 Thu 26/09/19
23 Steel Structure work (Pekerjaan Konstruksi Baja) 20,44 days Wed 04/09/19 Fri 20/09/19
24 Drilling Existing Coloum (west side) 2 days Wed 04/09/19 Thu 05/09/19
25 Install Coloum no.#12 and Tie Beam Top side 3 days Mon 09/09/19 Wed 11/09/19
(Warehouse & Polyclinic Area)
26 Crane Mobilization 1 day Sat 14/09/19 Sat 14/09/19
27 Erection Rafter (20ea) 7 days Sun 15/09/19 Fri 20/09/19
28 Demolish Works #2 (Change Room & Polyclinic Existing) 45 days Wed 25/09/19 Thu 31/10/19

Task Project Summary Manual Task Start-only Deadline

Project: Summary Works - Chan Split Inactive Task Duration-only Finish-only Progress
Date: Wed 04/09/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
REMAINING WORKS - SCHEDULE
CHANGE ROOM & POLYCLINIC ETEX 2019
Nov '19 Dec '19 Jan '20 Feb '20 Mar '20
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 02 09 16

Task Project Summary Manual Task Start-only Deadline

Project: Summary Works - Chan Split Inactive Task Duration-only Finish-only Progress
Date: Wed 04/09/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone