Estimating Cheat Sheet for Building Construction
2
www.acivilengineer.com
Estimating Cheat Sheet for Building Construction
10. ½” thick Plaster work with NCF (1:4) - 100 Square feet
3
www.acivilengineer.com
Estimating Cheat Sheet for Building Construction
13. ¾” thick Plaster work with NCF (1:6) - 100 Square feet
4
www.acivilengineer.com
Estimating Cheat Sheet for Building Construction
5
www.acivilengineer.com
Estimating Cheat Sheet for Building Construction
28. Ponding work for slab curing (2” x 2”) – 100 RFT*
Cement: 0.30 Bag
Sand: 4.0 Cubic feet
6
www.acivilengineer.com
Estimating Cheat Sheet for Building Construction
***Note***