Vous êtes sur la page 1sur 1

PLANT ILLUMINATION

Frequency -- Monthly Date:

SR.N CHECK POINTS Is % Of installed Is MCB easily Are MCBs Isemergency Remarks
O illumination lamps glowing. approachable? properly earthed? lighting glowing?
adequate?
YES / NO YES / NO YES / NO YES / NO YES / NO
1 Fire pump house

2 Fuel tank area

3 Boiler area
4 STG area ( Turbine floor )

5 STG area ( Condenser


area)
6 MCC Room
7 IAC House
8 Water reservoir area

9 Pretreatment plant area

10 DM plant area

11 Cooling tower area

12 ACW & MCP pump area

13 Control Room / AVR


Room
14 UPS Room & Eng. station
15 Aux. Tr. Yard
16 All stair case
17 Out side area to STG
building
18 Out side area to office

Checked by designation date time