Question 1 Make sure you review the Faculty of Engineering and Computer Science Expectations
Complete of Originality and standards of academic integrity, available at
http://www.concordia.ca/content/dam/encs/docs/Expectations-of-Originality-Feb14-
Not graded
2012.pdf.
I certify that I have conformed to the Faculty’s Expectations of Originality and standards
of academic integrity.

Note: By answering this question, you effectively sign the form and submit it
electronically. There is thus no need to submit a printed copy.

Select one:
Yes

No

The correct answer is: Yes

Question 2
The majority of the project budget is expended on
Correct

Mark 1.00 out of Select one:


1.00 Project plan development

Project plan execution

Project termination

Project communication

The correct answer is: Project plan execution

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1113015 1/3
2019/6/1 Assignment 1- Due Friday May 17 at 23:59
Question 3
Which of the following is the most critical component of the triple constraint?
Correct

Mark 1.00 out of Select one:


1.00 Time, then cost, then quality

Quality, then budget, then time


Scope

The other answers are all of equal importance unless otherwise stated

The correct answer is: The other answers are all of equal importance unless otherwise
stated

Question 4
Which of the following best describes a project stakeholder?
Correct

Mark 1.00 out of Select one:


1.00 A team member

The project manager

Someone who works in an area affected by the project

All other answers describe stakeholders

The correct answer is: All other answers describe stakeholders

Question 5
All of the following are elements in the definition of a project, except
Correct

Mark 1.00 out of Select one:


1.00 A project is time-limited

A project is unique

A project is composed of unrelated activities

A project is undertaken for a purpose

The correct answer is: A project is composed of unrelated activities

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1113015 2/3
2019/6/1 Assignment 1- Due Friday May 17 at 23:59
Question 6
All of the following distinguish project management from other process activities, except
Incorrect

Mark 0.00 out of Select one:


1.00 There are no fundamental differences between project and process management

Project management often involves greater certainty of performance, cost, and


schedule

Process management operates outside of line organizations

None of the other answers correctly distinguish project from process


management

The correct answer is: None of the other answers correctly distinguish project from
process management

Question 7
Which of the following is NOT a step in benchmarking?
Incorrect

Mark 0.00 out of Select one:


1.00 Compare current organization practices against those of chief competitors or
some general industry standard
Compute an index score that measures the necessary rate of performance
improvement

Analyze and critically evaluate current practices

Define a systematic route for improving organizational project management


practices

The correct answer is: Compute an index score that measures the necessary rate of
performance improvement