Académique Documents
Professionnel Documents
Culture Documents
Construction
Management
ENGR. UBAID AHMAD MUGHAL
DEPARTMENT OF CIVIL ENGINEERING,
U.E.T LAHORE
Related Books 3
Milestones are significant events that are either reached within the
project (such as completion of a phase of work) or imposed upon a
project (such as dead line by which to apply for funding).
Because milestone itself doesn’t normally include any work,
milestones are represented as tasks with zero duration.
Deliverable 8
Deliverable is a term used in project management to describe a
tangible or intangible object produced as a result of the project
that is intended to be delivered to a customer(either internal or
external).
A deliverable could be a report, a document, a work package, a
server upgrade or any other building block of an overall project.
Management ..? 9
Management in businesses and organizations is the function that
coordinates the efforts of people to accomplish goals and objectives
by using available resources efficiently and effectively.
Management includes
planning
organizing
staffing
SCHEDULING
Scheduling is the
determination of the
timing and sequence of
operations in the project
and their assembly to give
the overall completion
time. As mentioned
previously, scheduling
focuses on one part of the
planning effort.
Project planning answers the questions What is going to be
done How Where By whom and When (in general terms, the 15
project’s start and end) Scheduling deals with when on a
detailed level.
To get an idea about the relationship between project planning and
scheduling, assume that you are planning a vacation ‘‘project’’ for next
summer. Your plan may include considerations such as these:
• Who will go on the trip?
• Which places do you want to visit?
• What is the time frame for the vacation (just the starting and ending
dates)?
• What is the total budget for the ‘‘project’’
• What types of activities do you want to participate in during the trip ?
• What means of transportation do you plan to use (your car, a rental car, air,
• train, bus, RV, bicycles, etc.)?
• What other issues, such as accommodations, food, and clothing, need to
be addressed?
The project schedule will be such as this:
Leave home in Tampa, Florida, on June 8, 2010. 16
Arrive in Panama City, Florida, on June 8, 2010.
Leave Panama City on June 15, 2010.
Arrive in Atlanta, Georgia, on June 15, 2010.
Leave Atlanta on June 22, 2010.
Arrive in Gatlinburg, Tennessee, on June 22, 2010.
Return home to Tampa on July 7, 2010.
Structure (OBS)
An Organizational Breakdown
Structure defines the different
responsibility levels and their
appropriate reporting needs.
The Figure on the right
describes responsibilities of
different individuals in the
form of an Organizational
Breakdown Structure.
How WBS can be linked to the OBS. 26
WBS Coding 27
A project code system provides the framework for
project planning and control in which each work
package in a WBS is given a unique code that is used in
project planning and control.
An example of this coding system is the MasterFormat as
shown in image which was developed through a joint
effort of 8 industry & professional associations including:
Construction Specifications Institute (CSI); and
Construction Specifications Canada (CSC).
MasterFormat is the specifications-writing standard for
most commercial building design and construction
projects in North America. It lists titles and section
numbers for organizing data about construction
requirements, products, and activities. By standardizing
such information, MasterFormat facilitates
communication among architects, specifiers, contractors
and suppliers, which helps them meet building owners'
requirements, timelines and budgets.
The Master format is divided into 16 divisions as follows:
1) General Requirements. 28
2) Site work.
3) Concrete.
4) Masonry.
5) Metals.
6) Woods & Plastics.
7) Thermal & Moisture Protection.
8) Doors & Windows.
9) Finishes.
10) Specialties.
11) Equipment.
12) Furnishings.
13) Special Construction.
14) Conveying Systems.
15) Mechanical.
16) Electrical.
Bar Chart 29
A bar chart is ‘‘a graphic representation of
project activities, shown in a time-scaled bar
line with no links shown between activities’’
The bar chart was originally developed by
Henry L. Gantt in 1917 and is alternatively
called a Gantt chart.
It quickly became popular—especially in the construction industry—
because of its ability to graphically represent a project’s activities on a
time scale.
Before a bar chart can be constructed for a project, the project must
be broken into smaller, usually homogeneous components, each of
which is called an activity, or a task.
30
31
Assignment # 1 [5] 32
What are the Advantages and Disadvantages
of Bar Charts ..
Assignment # 2 [5]
Prepare a Work Breakdown Structure of any Project.
Assignment # 3 [5]
PrepareOrganizational Breakdown Structure of any
Organization.
Project Stakeholders 33
Stakeholders include all members of the project team as well
as all interested entities that are internal or external to the
organization.
The project team identifies internal and external, positive and
negative, and performing and advising stakeholders in order
to determine the project requirements and the expectations
of all parties involved.
The project manager should manage the influences of these
various stakeholders in relation to the project requirements to
ensure a successful outcome. Figure illustrates the relationship
between the project, the project team, and various
stakeholders.
34
The following are some examples of project 35
stakeholders:
Sponsor
A sponsor is the person or group who
provides resources and support for the
project and is accountable for enabling
success. The sponsor may be external or
internal to the project manager’s
organization.
The sponsor may also be involved in other
important issues such as authorizing changes
in scope, phase-end reviews, and go/no-go
decisions when risks are particularly high.
Customers and users 36
Customers are the persons or organizations who will approve and
manage the project’s product, service, or result.
Users are the persons or organizations who will use the project’s
product, service, or result.
Customers and users may be internal or external to the
performing organization and may also exist in multiple layers. For
example, the customers for a new pharmaceutical product
could include the doctors who prescribe it, the patients who use
it and the insurers who pay for it. In some application areas,
customers and users are synonymous, while in others, customers
refer to the entity acquiring the project’s product, and users refer
to those who will directly utilize the project’s product.
Sellers
Sellers, also called vendors, suppliers, or contractors, are external companies that 37
enter into a contractual agreement to provide components or services
necessary for the project.
Business partners
Business partners are external organizations that have a special relationship with the
enterprise, sometimes attained through a certification process. Business partners provide
specialized expertise or fill a specified role such as installation, customization, training, or
support.
Organizational groups
Organizational groups are internal stakeholders who are affected by the activities of the
project team.
Functional managers
Functional managers are key individuals who play a management role within an
administrative or functional area of the business, such as human resources, finance,
accounting, or procurement. They are assigned their own permanent staff to carry out the
ongoing work, and they have a clear directive to manage all tasks within their functional area
of responsibility. The functional manager may provide subject matter expertise or their function
may provide services to the project.
Other stakeholders
Additional stakeholders, such as procurement entities, financial institutions, 38
government regulators, subject matter experts, consultants, and others, may have a
financial interest in the project, contribute inputs to the project, or have an interest in the
outcome of the project.
Responsibilities and Competencies of a
39
Friend
Maintaining friendships and professional relationships with the
same people is difficult. However, if you can do it, you'll
benefit greatly. An open, informal, and comfortable
communication linkage is much more likely to keep you
supplied with more of the information you need than formal,
rigorous, and stiff team meetings. Finally, avoid the trap of
believing that because you’ve been put “in charge” of a
project you’ve risen above your peers and friendships no
longer matter. Big mistake!
Network 45
A network is a logical and chronological graphic
representation of the activities (and events) composing a
project. Network diagrams are basically of two types: arrow
networks and node networks. Arrow networks were more
popular in the 1960s and 1970s. Network scheduling has
revolutionized the management of construction projects.
ARROW NETWORKS 46
Arrow networks are also called the arrow diagramming method
(ADM), activity on arrow (AOA) networks, or the I–J method
(because activities are defined by the from node, I, and the to
node, J). Following are some of the examples of arrow networks.
47
Solution
In the above example, the project has only five activities, each represented
by an arrow. Each arrow connects two nodes (depicted by circles with
numbers in them): the from node and the to node. These nodes represent
events: an event is a point in time when an activity starts or ends.
Activity A starts the project. Activities B and C follow, but independently.
In reality, depending on the availability of resources and other factors, 48
activities B and C may occur concurrently, overlap, or occur consecutively.
However, both B and C cannot start till A is complete. Activity D must wait till
activity B is complete. Once both C and D are done, activity E can start. The end
of activity E means the end of the project. Activity A is considered a predecessor
activity to activities B and C. Similarly, activity B is a predecessor to activity D.
Conversely, we can say that activities B and C are successor activities to activity A,
activity D is a successor to activity B, and so on. Activity A has successors but no
predecessors. Activity E has predecessors but no successors. All other activities
have both successors and predecessors. As mentioned previously, a node in an
arrow network represents an event or a point in time. This event is the starting or
ending point of an activity (or activities). Node 10 represents the start of activity A
(and hence the start of the project). Node 20 represents the end of activity A and
the start of activities B and C. Node 30 represents the end of activity B and the
start of activity D. Node 40 represents the end of activities C and D, and the start
of activity E. Node 50 represents the end of activity E and the project.
Example 2 49
Solution A 50
The main problem in this case is that both activities B and C start from
node 20 and finish at node 30. Hence, both are identified as 20–30. This
situation will create an identity problem. To solve this problem, we
introduce a fictitious activity and an additional node. This fictitious
activity is called a dummy activity, d.
Correct Solution 51
C
Example 4 55
Solution 56
Solution
Draw a Node Network for the 60
following project
Solution 61
For aesthetic reasons only, we like to start any network with one node
(whether this node represents an event or an activity) and end it with one
node. Doing so may require one or two fictitious activities in node diagrams
that start or end with more than one activity. We call these activities PS
(project start) and PF (project finish),displayed as diamond-shaped nodes.
Draw a Node Network for the 62
following project
Solution 63
Lags and Leads 64
In some situations, an activity cannot start until a
certain time after the end of its predecessor. A
typical example is concrete operations. Let us
imagine this sequence:
1. Form the concrete column.
2. Install steel reinforcement (commonly known as
rebar).
3. Place the concrete.
4. Wait for the concrete to set (attain sufficient
strength).
5. Strip the forms.
Note that the fourth step is not a ‘‘real’’ activity to which we
must allocate resources and a budget. It is merely a waiting 65
period, commonly known as a lag.
A node network can accommodate such a lag if we simply put the lag
on the relationship line between Place Concrete and Strip Forms, as
shown in figures. This 3-day lag means a minimum waiting period of 3
days. Waiting less than 3 days violates the preceding logic, whereas
waiting more than 3 days does not violate the logic. In some networks,
the lag number is put inside a little box for better visibility.
LAG 66
A lag is defined as a minimum waiting period between
the finish (or start) of an activity and the start (or finish)
of its successor.
LEAD
The term lead simply means a
negative lag. It is seldom used
in construction. In simple
language: A positive time gap
(lag) means ‘‘after’’ and a
negative time gap (lead)
means ‘‘before.’’
Critical Path Method (CPM) 67
Suppose that you meet with two friends and decide to go on a
hunting trip. One friend will go to get the food, the other will go to
get the hunting gear, and you will go to prepare your Jeep. After
each person finishes his or her assignment, you will drive together
to the hunting location. Also suppose that the first activity (getting
the food) requires 2 hours; the second activity (getting the
hunting gear), 3 hours; and the third (getting the Jeep ready), 4
hours. If all three activities started at 8:00 A.M. (when each of you
would leave to perform his or her task), the following activity
(driving to the hunting location) cannot start until all three of you
return (i.e., when all three preparation activities are complete). If
everything works according to plan, the first person will return with
the food at 10:00 A.M.; the second, with the hunting gear, at
11:00 A.M.; and you, with the Jeep ready, at 12:00 P.M.
Now, ask yourself the following question: Which activity ‘‘drives,’’ 68
or controls, the schedule?
The answer is the third activity (preparing the Jeep). Any delay in
your return will delay the trip (past 12:00 P.M.). In contrast, your first
friend will have 2 extra hours to ‘‘waste,’’ and your second friend,
1 extra hour. They can choose to use the extra time however they
like. For instance, they could do the following:
Get an early start, finish early, then take a break
Get a late start (10:00 A.M. for the first person and 9:00 A.M. for
the second) and finish at 12:00 P.M.
Take breaks between work periods.
We will call this extra time float.
69