Académique Documents
Professionnel Documents
Culture Documents
www.PowerQualityInternational.com
IEEE STD 57.12.90 and IEEE STD 57.12.91 categorize of losses and the calculation of efficiency under lin-
transformer losses as No-Load Losses (PNL ) or Exci- ear loading. The measurement of No-Load Losses is
tation Losses and Load Losses (PLL ) or Impedance made during an Open-Circuit Test and the measure-
Losses. The sum of these losses is referred to as Total ment of Load Losses is made during a Short-Circuit
Losses (PLOSS ): Test. These measurements can be used to calculate
efficiency as follows:
PLOSS = PNL + PLL (1) POUT
h = (4)
POUT + PLoss
Excitation Losses[4] are primarily losses in the
magnetic core and are due to magnetic hys- Where:
teresis and eddy currents. Load Losses are di- h = Transformer Efficiency
vided into I 2R Losses and Stray Losses. I 2R Pout = Output Power (Watts)
Losses can be obtained, as follows: PLoss = Transformer Power Losses (Watts)
1’ 2’
www.PowerQualityInternational.com
Depending on its kVA rating, the efficiency of a distri- New Method of Measurements Transformer Losses
bution transformer is usually in the 92% to 98% range. and Efficiency[6] – Considering the transformer as a
To comply with NEMA TP1, CSA C802.2-00 and the EPA two-port network (Figure 1), instantaneous power ab-
Energy Star® Program, efficiencies must be in the 97% sorbed by the transformer is defined by equation (5).
to 98.9%. However, NEMA TP1, and all other current By creating a new two-port network, which is shown
standards, specifically excludes transformers that sup- in Figure 3, we introduce a current generator ( i* =
ply non-linear loads. i1 - i2 / K ), which is parallel to port 1p- 1p’, and voltage
generator ( v* = v1 / K − v2 ), which is in series with port
We can derive the maximum full scale errors for the 2p-2p’. Both Input and Output Power coincide with v1
voltages and currents, and the maximum errors for i2 / K. The overall absorbed power through ports 1p-
losses and efficiency, for 75 kVA 480/120:208 three- 1p’ and 2p-2p’ is zero.
phase transformer, as follows: No-Load Losses = 286
Watts, Load Losses at 100% load = 1,714 Watts, Effi- The instantaneous power absorbed will be equal to
ciency = 98.15 @35%, when the instrument transform- the sum of the power delivered by these generators.
ers are 0.3% accuracy class, the voltmeter and amme- The power losses of the transformer can be expressed
ters have an accuracy of 0.1%FS, and the wattmeters by:
have an accuracy of 0.2%FS, as shown in Figure 2. The
instrumentation is summarized in Table1. pL =(i1 - i2 / K)v1 + (vi / K - v2)i2 = p’ + p” (6)
VT2 – – i* = i1 - i2/K i2
CT1 100/5 0.0150 TRANSFORMER
CT2 400/5 0.0150 v1 Kt = N1/N v2 v1/K
V1 300 0.300
V2 300 0.300
A1 5 0.005
1p’ 2p’
A2 5 0.005
A Transformer as a Two-Port Network
Table 1 Figure 3
Losses and efficiency measurement errors, at unity Average power for some period of time T can be ex-
power factor and 100% load can be calculated as fol- pressed by:
lows:
ΔPloss = (120 ± εvt1 ± εV1)(5 ± εCT1 ± εA1)x20 1 ∫ ( i - i / K )v dt + 1 ∫ (v / K - v )i dt = P’ +P”
PLm= T 1 2 1 T 1 2 2 m m
-(120 ± εV2 )(5 ± εCt2 + εA2)x45 (7)
= 75.6338kW - 74.6010kW
= 1.032kW Equation (6) is valid for any constant K . Based on this
The losses measurement error is: formulation, a new measuring method is presented,
with the connection diagram shown in Figure 4.
= x100 = ± 51.62%
This method also requires two wattmeters, or two sets
The efficiency measurement error is: of voltmeters and ammeters. One set for a full range
Δeff = ± 1.34% of voltages and small currents and the other set for
WP 006-A 4/6
www.PowerQualityInternational.com
small voltages and full range of currents. Physical inter- and VTs, and specially design differential CTs and VTs.
pretation of this method can be explained using Figure The instrumentation is summarized in Table 2.
4.
Instruments Full Scale Full Scale Error
VT1 480/120 0.360
i1 i2
A2 VT2 120/120 0.360
CT1 5/5 0.015
INPUT i1-i2’ A1 OUTPUT
CT2 225/5 0.015
CT 1 CT 2 V1 120 0.120
V2 120 0.120
i1 i2
A1 1 0.001
TRANSFORMER A2 1 0.001
V1 V1 VT 2 V2
Table 2
VT 1
Exciting current error is:
V2 Δ(i1 - i’2 ) ± εCT1 ± εA1
V1-V2’ (i1 - i’2 ) (i1 - i’2 ) / 20
1 ∫ ( v - v K )i dt = 1 ∫ i v dt + 1 ∫ i v dt (9)
P”m = T 1 2 t 2 T 21 1A T 21 AC Output current is measured with error:
Δi’2 ± εCT2 ± εA2
Equation (9) represents the sum i’2 i’2 / 20
of the losses in the primary
and secondary of the transformer, due to load cur- The copper losses are measured with the error:
rent, which is equivalent to a transformer short-cir- ΔPCu Δi’2 Δ( v1 - v’2 )
cuit test. With this method, it is possible to separately PCu i’2 ( v1 - v’2 )
measure the core and copper losses of the transform-
er. Measurement under non-linear load conditions is The core losses are measured with the error:
also possible. ΔPFe Δv1 Δ( i1 - i’2 )
PFe v1 ( i1 - i’2 )
To evaluate the new measuring method, using the pro-
posed connection diagram in Figure 4, we analyze the The total losses are measured with the error:
same example evaluated with the conventional mea- ΔPLoss ΔPcu + ΔPFe
suring approach, with standard Metering Class CTs PLoss PLoss
WP 006-A 5/6
www.PowerQualityInternational.com
3.0
surement error in the 1.31% range. With the more
accurate current and voltage transformers (0.1%),
the accuracy of measurement is improved to 0.94%,
which is still not satisfactory for the measurement of
0.0
0.25 0.45 0.65 0.85 transformer losses.
Load (pu)
Losses Measurement Error Claims of high transformer efficiencies under non-lin-
Figure 5 ear loading, when tested by this conventional meth-
ods, that is, by measuring the input and output pow-
Rated Efficiency
er, will not be valid or technical meaningful since it
Power In & Out ‘Minus’ Error produces an error of 1.31%. By comparison, the
Power In & Out ‘Plus’ Error method based on Voltage and Current Difference has
V & C Difference ‘Minus’ Error
V & C Difference ‘Plus’ Error an error of less then 0.035%.
1.00
0.90
0.25 0.45 0.65 0.85
Load (pu)
Efficiency Measurement Error
Figure 6
WP 006-A 6/6
www.PowerQualityInternational.com
[3] NEMA Standard Publication TP1-2002, ‘Guide for De- Gregory N. C. Ferguson, B.Sc., Life Member IEEE, is the
termining Energy Efficiency for Distribution Trans- Principal Engineer and Board Member for PSO Glob-
formers.’ al, LLC (2012), a leading player in the emerging power
system optimization market. Prior to his role at PSO
[4] IEEEStandardC57.12.91-1995,‘TestCodeforDry-Type Global, he was founder and President of Power Qual-
Distribution Power Transformers.’ ity International, Inc. (1993). Mr. Ferguson is also the
founder of Ferguson Engineering Services Inc. (1968)
[5] NEMA Standard Publication TP2-1998, ‘Standard and FES International Ltd. (1985). Prior to incorporat-
Test Method for Measuring the Energy Consump- ing these companies, he was a Protection & Control
tion of Distribution Transformers’ Engineer with Ontario Hydro [Canada].
(888) 539-7712
www.PowerQualityInternational.com WP 006-A