PROVISION OF EPCIC OF
YETAGUN AGRU PROJECT, MYANMAR

ESTIMATED PIPING QTY.


TH
(16 AUGUST 2019)
PROVISION OF EPCIC OF YETAGUN AGRU PROJECT, MYANMAR
- PIPING WORK QUEST
(Quality Through Efficiency Safety & Teamwork)

QTY. OF PIPE SPOOL FOR SHOP FABRICATION (RECEIVED ON 23RD APRIL 2019)

ESTIMATED ESTIMATED ESTIMATED


NO. DESCRIPTION SYSTEM REMARKS
SPOOL QTY. DIA. INCH JOINT QTY.
A YETAGUN-C (Installation)
(a) Open Drain AD 21 241 50
(b) LP Fuel Gas FGL 25 83 42
(c) Instrument Air IA 18 35 22
(d) Instrument Gas IG 9 26 13
(e) Process P 34 790 82
(f) Process Drain PD 7 30 13
(g) Relief System RV 86 910 74
SUB-TOTAL FOR YET-C 7 200 2,115 296
B YETAGUN-B (Installation)
(a) LP Fuel Gas FGL 24 28 28
(b) Relief System RV 32 324 22
(c) Utility Air UA 17 100 10
SUB-TOTAL FOR YET-B 3 73 452 60
GRAND TOTAL 10 273 2,567 356
PROVISION OF EPCIC OF YETAGUN AGRU PROJECT, MYANMAR
- PIPING WORK QUEST
(Quality Through Efficiency Safety & Teamwork)

QTY. OF PIPE SPOOL FOR SHOP FABRICATION (RECALCULATED ON 16TH AUGUST 2019)

ESTIMATED ESTIMATED ESTIMATED


NO. DESCRIPTION SYSTEM REMARKS
SPOOL QTY. DIA. INCH JOINT QTY.
A YETAGUN-C (Installation)
(a) Open Drain AD - 883 246 FFW received on 14 July & 5 August 2019
(b) LP Fuel Gas FGL - 93 82 FFW received on 5 – 6 August 2019
(c) Instrument Air IA - 178 89 FFW received on 5 – 6 August 2019
(d) Instrument Gas IG - 79 40 FFW received on 5 – 6 August 2019
(e) Process P - 1,991 534 FFW received on 1 – 5 August 2019
(f) Process Drain PD - 58 25 FFW received on 25 July 2019
(g) Relief System RV - 1,812 345 FFW received on 25 – 31 July 2019
SUB-TOTAL FOR YET-C 7 T.B.A. 5,094 1,361
B YETAGUN-B (Installation)
(a) LP Fuel Gas FGL - T.B.A. T.B.A. FFW not received yet
(b) Relief System RV - T.B.A. T.B.A. FFW not received yet
(c) Utility Air UA - T.B.A. T.B.A. FFW not received yet
SUB-TOTAL FOR YET-B 3 T.B.A. T.B.A. T.B.A.
GRAND TOTAL 10 T.B.A. 5,094 1,361
PROVISION OF EPCIC OF YETAGUN AGRU PROJECT, MYANMAR
- PIPING WORK QUEST
(Quality Through Efficiency Safety & Teamwork)

QTY. OF PIPE SPOOL FOR FIELD WELD (RECALCULATED ON 16TH AUGUST 2019)

ESTIMATED ESTIMATED ESTIMATED


NO. DESCRIPTION SYSTEM REMARKS
SPOOL QTY. DIA. INCH JOINT QTY.
A YETAGUN-C (Installation)
(a) Open Drain AD - 102 24 FFW received on 14 July & 5 August 2019
(b) LP Fuel Gas FGL - 14 13 FFW received on 5 – 6 August 2019
(c) Instrument Air IA - 14 7 FFW received on 5 – 6 August 2019
(d) Instrument Gas IG - 12 6 FFW received on 5 – 6 August 2019
(e) Process P - 356 97 FFW received on 1 – 5 August 2019
(f) Process Drain PD - 10 5 FFW received on 25 July 2019
(g) Relief System RV - 535 76 FFW received on 25 – 31 July 2019
SUB-TOTAL FOR YET-C 7 T.B.A. 1,043 228
B YETAGUN-B (Installation)
(a) LP Fuel Gas FGL - T.B.A. T.B.A. FFW not received yet
(b) Relief System RV - T.B.A. T.B.A. FFW not received yet
(c) Utility Air UA - T.B.A. T.B.A. FFW not received yet
SUB-TOTAL FOR YET-B 3 T.B.A. T.B.A. T.B.A.
GRAND TOTAL 10 T.B.A. 1,043 228 Shop + Field = 6,137 DI / 1,589 Jts.