Vous êtes sur la page 1sur 13

Journal of Loss Prevention in the Process Industries xxx (2013) 1e13

Contents lists available at ScienceDirect

Journal of Loss Prevention in the Process Industries


journal homepage: www.elsevier.com/locate/jlp

Integrated risk assessment for LNG terminals


O.N. Aneziris*, I.A. Papazoglou, M. Konstantinidou, Z. Nivolianitou
National Centre for Scientific Research “DEMOKRITOS”, Terma Patriarchou Grigoriou, Aghia Paraskevi 15310, Greece

a r t i c l e i n f o a b s t r a c t

Article history: This paper presents an integrated risk assessment framework for Liquefied Natural Gas (LNG) terminals.
Received 17 December 2012 The basic steps for risk assessment are the following: a) hazard identification, b) accident sequence
Received in revised form modeling, where logic models such as Event Trees and Fault Trees are developed c) data acquisition and
26 July 2013
parameter estimation, used to estimate frequencies of the initiating events, component unavailability and
Accepted 26 July 2013
probabilities of human actions, d) accident sequence quantification, where all accident sequences are
assessed, e) consequence assessment, where release, evaporation rate, radiation levels and overpressure
Keywords:
owing to immediate or delayed ignition of LNG is performed and f) integration of results where risk indices
Quantified risk assessment
LNG, consequences
are assessed. Risk assessment of an onshore and an offshore LNG terminal is performed, according to the
Fault Trees and Event Trees for LNG basic methodological steps, and the distances where individual risk levels equal to 105e107/yr are
terminals assessed and presented in the form of individual contours. A section dedicated to I.A. Papazoglou, pioneer in
Initiating events Quantitative Risk Assessment both in the nuclear and chemical industry is also provided.
Greek pioneer in process safety Ó 2013 Published by Elsevier Ltd.

1. Introduction Cozzani (2012). A thorough analysis on the siting regulations and


industrial standards for LNG terminals and their differently
This paper presents the methodological and procedural steps for evolving paths within Europe and the United States (U.S.) is pre-
quantitative risk assessment of liquefied natural gas (LNG) and its sented by Licari and Weimer (2011). On the other hand risk analysis
application to two LNG terminals, an onshore and an offshore one. has been performed for LNG carrier operations by Vanem, Antão,
The onshore plant consists of two storage tanks with total capacity Østvik, and de Comas (2008) and for LNG tankers approaching a
of 100,000 m3 and the offshore of four double containment marine terminal by Bubbico, Cave, and Mazzarotta (2009). Finally,
spherical tanks, each with capacity of 34,672 m3. This analysis was high pressure natural gas pipelines have been studied by Jo and
performed in the framework of the iNTeg-Risk project, coordinated Ahn (2002, 2005).
by Steinbeis (Jovanovic, 2010), where the ultimate scope was to Extensive research has been performed in the area of conse-
compare the two LNG terminals with different siting. Over the last quence analysis after an LNG release. The behavior of an LNG spill in
years risk assessment methodology has been widely used for esti- the atmosphere has been extensively studied on ground, over water
mating risk of chemical plants storing flammable and toxic sub- and under water. Results of experiments and modeling concerning
stances, such as ammonia, LPG and fuels, as discussed by CCPS LNG outflow, dispersion, pool fires and vapor explosions have been
(2000), ISO 17776 (2000), Lees (1996), Papazoglou, Aneziris, presented by Cleaver, Johnson, and Ho (2007), Hanlin (2006),
Bonanos, and Christou (1996), Papazoglou, Nivolianitou, Aneziris, Koopman and Ermak (2007), Ohba, Kouchi, Hara, Vieillard, and
and Christou (1992), Taveau (2010) and Tixier, Dussere, Salvi, and Nedelka (2004) and more recently by Giannissi, Venetsanos,
Gaston (2002). More specifically, quantified risk assessment of Markatos, and Bartzis (2013), Ivings, Lea, Webber, Jagger, and
LNG installations appears in several cases in the literature, such as Coldrick (2013), Raj (2011) and Raj and Bowdoin (2010). Conse-
the risk assessment of LNG importation terminals using the quence analysis for estimating hazard distances for LNG vessel
Bayesian-LOPA methodology, as presented by Yun, Rogers, and cargo releases during transit and while at berth with spills on water
Mannan (2009), the analysis by Raj and Lemoff (2009) for siting have been studied by ABS Consulting (2004). In addition a Sandia
LNG facilities based on the NFPA 59A standard and risk analysis of Report (2004) presents risk assessment methods of LNG spills on
LNG terminals in case of terrorist attack by Landucci, Tugnoli, water. Consequence analyses have been also performed for LNG
Spadoni, and Cozzani (2012) and Tugnoli, Landucci, Salzano, and marine incidents by Pitblado, Baik, Hughes, Ferro, and Shaw (2004)
and by Taylor (2007) for siting LNG facilities.
* Corresponding author. Additional studies to mitigate the effects of an LNG outflow
E-mail address: olga@ipta.demokritos.gr (O.N. Aneziris). together with limiting its volume involved in accidents have been

0950-4230/$ e see front matter Ó 2013 Published by Elsevier Ltd.


http://dx.doi.org/10.1016/j.jlp.2013.07.014

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
2 O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13

set off as early as 1996 by using high expansion foam to cover d) Data assessment and parameter evaluation
dispersed LNG as described by Takeno et al. (1996) and water
curtains as described by Olewski, Nayak, Basha, Waldram, and Parameters which must be estimated include the frequencies of
Véchot (2011), Rana, Cormier, Suardin, Zhang, and Mannan the initiating events (external events, human errors, component
(2008) and Rana and Mannan (2010). failures) component unavailability and probabilities of human ac-
This paper is organized as follows. After the introduction of tions. Estimation of these parameters is based on generic values.
Section 1, Section 2 presents in brief the methodological and pro-
cedural steps for risk assessment in LNG installations, Section 3 e) Accident sequence and plant-damage state quantification
describes the LNG terminals and Section 4 presents the major
steps of quantitative risk analysis for LNG terminals. Finally Section This task quantifies the accident sequences and the plant-
5 presents the conclusions of this study and at Section 6 a dedi- damage states, that is, calculates their frequency of occurrence. In
cation to I.A. Papazoglou, pioneer in Quantitative Risk Assessment particular, the plant model built in the step “Accident sequence
both in the nuclear and chemical industry is presented. determination” is quantified using the parameter values estimated
in the previous task. Accident sequences to be quantified in the
2. Methodological and procedural steps for risk assessment Event Trees are specified and manipulated according to the laws of
Boolean algebra in order to be put in a form suitable for quantifi-
The methodology and procedures to be followed for the quan- cation. The results of this task are the calculation of the frequency of
tification of risk from installations handling flammable substances occurrence of each accident sequence and consequently of each
can be distinguished into three major phases, as already presented plant-damage state.
by Papazoglou et al. (1992), which are the following: Once the plant-damage states and their frequencies are estab-
lished, the consequences to the public and worker’s health must be
a) Assessment of plant-damage states and their frequency of established. It is not necessary to estimate consequences for each and
occurrence every plant-damage state. A screening procedure can be followed
b) Assessment of consequences of flammable substances release where only those plant-damage states with significant frequency will
c) Risk integration. be retained. Caution must be exercised, however, to avoid excluding
states with extremely severe consequences. Alternatively, conse-
2.1. Assessment of plant-damage states and their frequency of quences may be quantified for all identified plant-damage states
occurrence prior to the frequency estimation. Then, frequency calculations are
performed only for those states with non-negligible consequences.
The first phase of an integrated risk assessment consists of
analyzing the installation to identify potential accident initiators, 2.2. Consequences of flammable substance releases
assess the response of the plant to these initiators and establish end
damage states of the plant resulting in the release of a dangerous The second phase of the integrated risk assessment aims at the
substance in the environment. Furthermore, the frequency with establishment of the consequences of the released flammable LNG,
which the identified plant-damage states are expected to occur is which may be either thermal radiation or overpressure.
estimated. This phase can be distinguished in the following five
procedural tasks: a) Determination of release categories of flammable material

a) Hazard source identification A release category for flammables defines all necessary condi-
tions that uniquely determine the level of overpressure or heat ra-
The main sources of potential hazardous-substance releases are diation at each point in the area around the release of flammable
identified and the initiating events that can cause such releases are material (LNG in this case). A release category uniquely determines
determined. the type of the physical phenomenon that could result in fatalities or
injuries. For example, in the case of LNG releases, it is established
b) Accident sequence determination whether a pool fire will take place or whether an explosion or
deflagration will result, following atmospheric dispersion of the gas.
A logic model for the installation is developed, which includes
each and every initiator of potential accident and the response of b) Estimation of heat radiation and peak overpressure
the installation to these initiators. Specific accident sequences are
defined (in models called Event Trees) which consist of an initiating In this step, a model for simulating the heat radiation or the
event, specific system failures or successes, their timing and human peak overpressure resulting from the released flammable material
responses. Accident sequences result in plant-damage states, which and the associated physical phenomenon is established. The SOC-
involve release of the hazardous substance. RATES computer code (Papazoglou et al., 1996) has been used for
System failures are in turn modeled (in models called Fault consequence analysis and risk integration. Fire and explosion
Trees) in terms of basic component failures and human errors to models incorporated, are based on the pool fire and deflagration
identify their basic causes and to allow for the quantification of the models presented in the Yellow Book (TNO, 1992) for estimation of
system failure probabilities and accident sequence frequencies. heat radiation and peak overpressure respectively. Dispersion of
LNG in case of delayed ignition is based on the simple dense box
c) Plant-damage state definition model, presented by Bais, Zerefos, and Ziomas (1989).

A plant-damage state uniquely characterizes the installation- c) Dose assessment


dependent conditions of release of the hazardous substance. Acci-
dent sequences resulting into the same conditions of release are The integrated, over time, exposure of an individual to the
grouped into categories each corresponding to a particular plant- extreme phenomenon generated by the flammable material is
damage state. calculated. This defines the “dose” an individual receives.

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13 3

The effects of thermal radiation and overpressure effects on P0 ¼ 14:9 þ 2:56 ln Dðx; yÞ (6)
exposed individuals are calculated with the following equations,
according to the Green Book (CCPS, 2000; Lees, 1996; TNO, 1989): which in turn yields the probability of death for an individual
standing at a distance from the source for t seconds.
Dðx; yÞ ¼ ½qðx; yÞ4=3 t104 (1) As presented by Papazoglou et al. (1996) for the flash fire phe-
nomenon, it is assumed that any person within the trace of the
where: q(x,y) is the thermal flux at distance r, r ¼ (x2 þ y2)1/2 from flammable cloud receives a lethal dose of thermal radiation while
the center of the fire (W/m2), D(x,y): dose at point r of the center of for any person outside the trace the probability of death is assumed
the fire with coordinates x, y, t: duration of exposure (s). equal to zero.
For overpressure, the dose function is calculated as follows,
according to the Green Book (CCPS, 2000; Lees, 1996; TNO, 1989): 2.3. Risk integration

Dðx; yÞ ¼ 7:38103 þ 1:310


9
In this last phase integration of the results obtained so far,
Ps P s Is
(2) that is combining the frequencies of the various accidents with
Is ¼ 1P t
2 s p the corresponding consequences, results in the quantification of
risk, as presented by Papazoglou et al. (1992, 1996). Two risk
where: Ps is the overpressure, Is the impulse of the shock wave and measures are usually used to quantify risk, namely individual
tp is the duration of the positive shock wave. fatality risk at a location and group fatality risk in a given area. In
this analysis individual fatality risk at a location has been
d) Consequence assessment assessed.

Appropriate dose/response models receiving as input the dose 3. Brief description of LNG terminals
of heat radiation or overpressure calculate the probability of fatality
or injury of the individual receiving the dose. Two LNG terminals have been studied, an onshore and an
The probability that an individual will die as a result of its offshore. The onshore terminal, as presented in Fig. 1, comprises the
exposure to the extreme phenomenon is estimated in terms of following sections: jetty, storage, boil-off recovery and vapor-
doseeresponse models receiving as input the dose calculated by ization. The jetty is composed by the docking area for LNG ships and
the dose module. All doseeresponse models employed in SOCRA- equipped with unloading arms. A pipeline goes along the jetty to
TES are based on a “probit” function for the substance and/or the storage tanks and permits the LNG transfer. The storage section
phenomenon, as presented in the Green Book (CCPS, 2000; Lees, is composed by two double containment tanks and three sub-
1996; TNO, 1989). merged pumps delivering LNG from the tanks. The boil-off recovery
The probit model can be described as follows: it is assumed that section is composed by cryogenic compressors and a blower. The
each individual into a population exhibits a different “strength” in role of the compressors is to recover boil-off gas generated during
coping with a dose, D, of an adverse effect. Furthermore, the model the normal operation and the unloading phase, and transfer it to
assumes that this strength, S, is normally distributed with mean the recondenser. The vaporisation section is composed by four
value 5 and standard deviation 1. It is also stipulated that a dose “D” vaporizers with primary and booster pumping systems. High
generates a “stress” P0 on each individual that is a function of the pressure natural gas exiting the vaporiser is transmitted to the
dose and of the substance. In particular pipeline network.
The LNG offshore terminal consists of four double containment
P0 ¼ Probit ¼ A þ BlnD (3) spherical tanks, each with capacity 34,672 m3, booster pumps,
compressors of the boil-off LNG, a recondenser, an intermediate
where A, B are substance (or phenomenon) dependent constants. fluid vaporiser and the relevant liquid and vapor LNG pipelines. The
The model assumes that a person dies if its strength, S, is lower unloading area consists of the unloading arm and the liquid and
or equal than the dose induced stress P0; that is, the probability of vapor pipelines connecting the LNG tank to the arm, as presented in
an individual dying, pd, as a result of a dose (D) is given by the box diagram of Fig. 2. A pipeline exiting the vaporiser transfers
natural gas to the pipeline network. More details on both terminals
ZP0 " #
1 ðu  5Þ2 are presented by Uguccioni (2010).
pd ¼ Pr fS  P0 g ¼ pffiffiffiffiffiffi exp  du The operation of both LNG terminals can be described in the
2p 2
N following phases:

or a) LNG is transferred from a ship via the loading arm and a


pipeline to the storage tanks. This transfer is achieved through
PZ0 5 " #
the ship’s pumps and lasts for 24 h for each loading, depending
1 ðu  5Þ2
pd ¼ pffiffiffiffiffiffi exp  du (4) on the quantity which is transferred.
2p 2
b) Storage of LNG at 1 bar.
N
c) Transfer of LNG from tanks to the vaporisers, where natural gas
It is noteworthy that pd, implies that if N people receive dose D,
is produced and transferred to the pipeline net.
then the expected number of fatalities is (pd$N).
The probability of lethality owing to the impact of the whole
body from the shock wave created by an unconfined vapor explo-
4. Quantified risk assessment of LNG terminals
sion (UVCE) is given by the following probit function (TNO, 1989).
4.1. Hazard source identification of LNG terminals
P0 ¼ 5  2:44 ln Dðx; yÞ (5)
TNO (1989) also provides the probit function for exposure to The main objective of this step is to identify the sources of LNG
thermal radiation as release in the installation and the initiating events that can lead to

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
4 O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13

BOIL - OFF
UNLOADING ARMS
VAPOR RETURN ARM
SUBMERGED SUBMERGED PUMPS

L
L

JETTY STORAGE LNG TANK


STORAGE LNG TANK BLOWER

L BOIL - OFF
VENT COMPRESSOR
BOIL - OFF
ABSORPT AIR
TO PIPELINE
NETWORK
NATURAL GAS

MEMBRANES

FUEL- GAS

VAPORIZERS AIR
BOOSTER
PRIMARY COMPRESSORS
PUMPS
PUMPS RISER

Fig. 1. Simple diagram of the process of the onshore LNG terminal.

the release of this substance to the environment. This methodo- Initiating event selection
logical step can be distinguished in the following tasks:
Events which may create a disturbance in the installation and
Plant familiarization and information gathering have the potential to lead to the release of LNG are identified and
listed. The aim is to make this list as complete as possible, including
This task involves the familiarization of the analysts with the events beyond the design basis of the plant. Two different ap-
plant design and operation. This included a study of the plant proaches, namely the Master Logic Diagrams (Papazoglou &
documentation supplied by the plant through the coordinators of Aneziris, 2003) and the use of check lists have been followed for
iNTeg-Risk and a visit to an onshore LNG terminal in Greece, similar the identification of the initiating events. Master Logic Diagrams
to the one analyzed. The plant documentation contained short (MLD) have been developed for all sections of the installation
plant description, process flow and block diagrams and description resulting in the identification of a list of initiating events. This list
of equipment and LNG flow rates. was further checked for completeness with recorded initiating
events of past accidents and/or studies (check lists).
Identification of release sources of concern The Master Logic Diagrams resembles to Fault Trees, but without
any formal mathematical properties. They start with a “Top Event”
The aim is to identify all possible sources of LNG release (within which is the undesired event (like “Loss of Containment”) and
the boundary of the study). To this end, the installation was divided continue decomposing it into simpler contributing events until
into sub-compartments, each representing a possible release events of lower levels cause the events of the immediately above
source, as described in the following paragraph “Development of one. The development continues until a level is reached where
Master Logic Diagram”. events directly challenging the various safety functions of the plant
are identified. For a chemical installation the “Top Event” of interest
Identification of plant operating states of concern is the potential of release of a hazardous substance to the envi-
ronment. Loss of Containment (LOC) means a discontinuity or loss
Three operating states of the installation were established, of the pressure boundary between the hazardous substance and the
which are the following: a) loading of LNG from the ship to the tank, environment, resulting in release of hazardous substances. A
b) storage of LNG in the tank and c) transfer of LNG from the tank to generic MLD for LOC in installations handling hazardous substances
the pipeline. is presented by Papazoglou and Aneziris (2003). There are two
Consideration of all operating states of the LNG storage facility major categories of events leading to Loss of Containment: those
was deemed necessary since it affects the possible release sources, resulting in a structural failure of the containment and those
release mode, as well as the amount of the LNG released. resulting in containment bypassing because of an inadvertent

Fig. 2. Simple box diagram of the process of the offshore LNG terminal.

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13 5

opening of an engineered discontinuity in the containment (e.g. loading, in case of onshore installations, may be achieved in the
valves, hatches). Seven general ways (or direct “causes”) in which a following ways: snow, ice, earthquake, flooding and extra loads.
structural failure of the containment may occur can be distin- The Master Logic Diagrams for both terminals onshore and
guished, which are the following: overpressure, underpressure, offshore are similar, since they are general diagrams taking into
corrosion, erosion, external loading, high temperature and vibra- account the major phases and processes. The main difference be-
tion. The second major category of causes for “loss of containment” tween onshore and offshore installation is that in the first case the
results to containment bypass, either because operations start natural phenomena which may cause external loading to the LNG
while it is open, or because the containment opens during tanks are snow/ice, earthquakes or flooding, while in the second
operations. case (offshore) only ice, winds and wave/currents can lead to
structural failure owing to external loading.
4.1.1. Development of Master Logic Diagram All initiating events, identified for the onshore LNG tanks during
The detailed MLD for the onshore LNG storage plant has been the storage phase are presented in Table 1. A literature review con-
developed, for all possible sites of LNG release and for all plant cerning past accidents and their causes in LNG storage facilities was
operation states (storage, loading, unloading). The basic step for the performed, in order to check the initiating events identified with
construction of the MLDs is the identification of critical areas. MLD, as presented by Aneziris, Papazoglou, and Konstantinidou
Critical areas contain considerable quantity LNG. On the basis of the (2010). The results showed good agreement, since all accidents
extent of possible consequences the onshore installation has been initiating events such as overfilling, rollover, leakages, overpressure,
divided into four sections as follows: corrosion, natural phenomena, water hammer, disconnection of
unloading arms, external fire and external load, were adequately
a) Unloading arm section. It comprises the jetty and the unload- identified.
ing arms for the LNG transfer from ship to tanks. It also com-
prises the transfer pipeline from the jetty to the storage tanks. 4.1.2. Screening of initiating events
b) Storage tanks section. It comprises the two containment tanks Screening of the initiating events has been performed on the
with their submerged pumps. basis of their release category. Release categories with relatively
c) Absorption/Vaporizer section. This section covers the absorp- small releases are not quantified. For example liquid releases which
tion tower, the vaporizers as well as their pumping system and occur if there is containment bypass or corrosion in the LNG tank
the transfer line to distribution net. may be ignored in the unloading and loading phase of the tank.
d) Boil-off recovery section. This section comprises the cryogenic Table 2 presents the initiating events from both LNG plants which
compressors and the blower. are quantified and Table 3 the corresponding damage states. Both
LNG plants have many common initiating events such as boil-off
Master Logic Diagrams have been constructed for the four crit- removal malfunction, high temperature in LNG coming from ship,
ical areas and for all operational phases of the storage tanks. The excess external heat, external fire, overfilling, rollover, low level etc.
MLD for LNG storage tanks during storage phase is presented in Initiating events of the onshore LNG tanks are snow/ice, earth-
Fig. 3. The generic MLD, as described by Papazoglou and Aneziris quakes or flooding, while for the offshore LNG only ice, winds and
(2003), when applied to the Loss of Containment of the LNG stor- wave/currents are applicable.
age tanks, during storage results in the following direct causes for
LOC: corrosion, overpressure, external loading, and containment 4.2. Accident sequence modeling
bypass. Overpressure is decomposed in rollover and internal
pressure increase. Internal pressure increase may be caused by boil- Accident sequence modeling can be distinguished in the
off gas removal malfunction or excess external heat. External following four tasks: event sequence modeling, system modeling,

LOSS OF
CONTAINMENT

LOSS OF
STRUCTURAL BOUNDARY
FAILURE CONTAINMENT
BYPASS

OVER EXTERNAL
CORROSION
PRESSURE LOADING

OPEN WHEN OPEN


OPERATION DURING
STARTS OPERATION

INTERNAL NATURAL EXTRA


PRESSURE ROLL OVER PHENOMENA LOAD
INCREASE

COOLING EXCESS SNOW, ICE EARTHQUAKE FLOODING


MALFUNCTION HEAT

BOIL OFF
REMOVAL EXTERNAL
MALFUNCTION

Fig. 3. Master Logic Diagram of the LNG storage tank during storage phase.

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
6 O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13

Table 1 Table 3
Initiating events and associated plant-damage states for LNG tanks, during storage Damage states of LNG terminals.
phase.
LNG tank
Initiating events Plant-damage states 1. Tank rupture (roof failure) owing to overpressure
2. Tank rupture (roof failure) owing to overfilling
1. Corrosion Hole in tank, equivalent to 1 inch
3. Tank rupture owing to underpressure
2. Boil-off removal malfunction Tank rupture (roof failure)
Loading section
during storage owing to overpressure
4. Pipe rupture (tank to pumps)
3. Excess external heat Tank rupture (roof failure)
Unloading section
during storage owing to overpressure
5. Pipe rupture (ship to tank)
4. Rollover Tank rupture (roof failure)
Outlet pipeline
owing to overpressure
6. Full bore
5. Earthquake Catastrophic rupture of tank
6. Snow, ice Catastrophic rupture of tank
7. Floods Catastrophic rupture of tank
8. Extra loads Catastrophic rupture of tank
safety system from the required operation initiates a transient and
9. Valve left open Exit of LNG through 1 inch drainage valve requires certain safety functions to avoid release of natural gas.
10. Containment bypass Exit of LNG through 1 inch drainage valve
during storage b) Standby compressor available

Following the malfunction of one compressor of the boil-off


human performance analysis and classification of accident se- removal system, the standby compressor may start operating. If it
quences into plant-damage states. More details are presented by starts operating successfully the boil-off is removed and tank
Papazoglou et al. (1992). pressure is within safe limits.
The completion of the Hazard Identification methodological
step resulted in the identification of nineteen initiating events, as c) Manual stop of send out
presented in Table 2, leading to twenty-one Event Trees for quan-
tification, for both LNG terminals. In this section two Event Trees Following the failure of both compressors, operators both at the
are presented, one for the onshore plant and one for the offshore. plant and at the ship should recognize the pressure increase in the
The Event Tree developed for initiating event “Boil-off removal tank, communicate this fact among themselves and should termi-
malfunction during unloading from ship to tank” (ET-1) for the nate the unloading operation.
onshore terminal is presented in Fig. 4. This model presents the
possible response of the storage facility to boil-off removal mal- d) Pressure control system
function during unloading from ship to tank. It comprises the
following heading events (see Fig. 4): This event corresponds to the successful sensing of the pressure
rise and the closing of the appropriate valves and pumps by the
a) Boil-off removal malfunction during unloading from ship automatic pressure control system for emergency shut down (ESD).
to tank
e) Pressure Safety Valves (PSVs)
During unloading of LNG from ship to tank the operation of one
compressor is required to remove LNG vapors and keep the pres- This event models the successful operation of the pressure
sure within safety limits. Any deviation of the boil-off removal safety valves in the event of a continuing pressure rise beyond and
above the nominal safety valves set points.
This event tree determines five accident sequences. Three of
Table 2 them (#le#3) constitute successful termination of the incident.
Initiating events of LNG terminals. One (#4) results in release of LNG from the PSVs and one (#5)
LNG tank sequence leads to tank rupture and release of LNG.
1. Boil-off removal malfunction, during unloading The Event Tree developed for the initiating event “Strong waves
2. Boil-off removal malfunction, during storage during unloading” (ET-2) of the offshore plant, is presented in Fig. 5.
3. High temperature in LNG, coming from ship
4. Excess external heat in storage tank area
This model presents the possible response of the offshore storage
5. Level rise beyond safety height, or overfilling facility to strong waves during unloading from ship to tank. It
6. Rollover during unloading comprises the following events (headings) (see Fig. 5):
7. Rollover during storage
8. Inadvertent starting of additional compressors
a) Strong waves during unloading from ship to tank
9. Continuation of unloading beyond lower safety level
10. Increase of send out rate from tank
Unloading section (from ship to tank) During unloading of LNG from ship to tank the presence of
11. Excess external heat in jetty area strong waves initiates a transient and requires certain safety
12. Water hammer in loading arm, due to inadvertent valve closure functions to avoid release of LNG. The release may be the result of
13. Inadequate cooling of loading arm
14. High winds during unloading
the impact of the ship on the offshore facility.
Sendout section
15. Inadvertent closure of valve in send out b) Manual termination of unloading
Recondenser
16. Inadvertent start of compressor
In case of strong waves operators both at the offshore plant and
17. Booster pump malfunction
18. External fire at the ship should recognize the criticality of the situation, should
Outlet pipeline communicate this fact among themselves and should terminate the
19. Vaporiser failure leading to pipebreak owing to low temperature of line unloading operation.
20. Strong waves during unloading (only for offshore plant)
21.Strong waves during storage (only for offshore plant)
c) Floating barriers

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13 7

Fig. 4. Event Tree with initiating event “Boil-off removal malfunction during unloading from ship to tank” (onshore plant).

This event models the successful intervention of the floating Fault Tree for compressor malfunction
barriers that may prevent the violent contact of the ship on the
offshore facility. The Fault Tree for the event “Compressor malfunction”
The event tree determines three accident sequences. Two of following boil-off removal malfunction in ET-1 is presented in Fig. 7.
them (#l, #2) constitute successful termination of the incident. The The top event in this tree will occur if the second (standby)
last (#3) sequence leads to tank rupture and release of LNG. compressor is unavailable, if the valves (inlet or outlet) fail to
Accident sequences developed in this phase have been classified operate, if there is a loss of industrial air (support system further
in the following plant-damage states: a) tank rupture owing to analyzed in a separate Fault Tree, see Fig. 9) or if there is a loss of
overpressure or overfilling, b) tank rupture owing to underpressure electrical power (support system further analyzed in a separate
(implosion) and c) pipebreak in the piping between ship and tank. Fault Tree, see Fig. 10).

4.2.1. System Fault Trees Fault Tree for manual termination of unloading due to pressure
Fault trees have been developed for system modeling of all increase
safety systems identified in the event sequence modeling of the
LNG terminals. In this section Fault trees developed for the event The Fault Tree for the event “No manual stop of operation”
tree with initiating event “Boil-off removal malfunction during following boil-off removal malfunction in ET-1 is presented in
unloading from ship to tank” (see Fig. 4) are presented. These Fault Fig. 8. The top event in this tree will occur if either the operators on
Trees have the following top events: a) Boil-off removal malfunc- the ship do not act, or if the operators at the storage facility do not
tion during unloading from ship to tank b) Standby compressor act, or if the pumps of the ship fail to stop. The non reaction of
malfunction c) No manual stop of operation d) Pressure control operators on ship will occur if the operators fail to stop the loading
system fails to stop unloading from ship e) Loss of instrument air procedure, or if the operator fails to communicate the problem or if
and f) Loss of electrical power supply and are depicted in Figs. 6e10. the communication between the ship and the facility has failed. The
non reaction of operators on site will occur if operators ignore the
Fault tree for boil-off removal malfunction during unloading alarm, or if the alarm fails or if the communication of pressure
from ship to tank signal between the jetty and the control room fails.

The boil-off removal system mainly consists of two compressors. Fault Tree for the loss of industrial air
Operation of one of them is required to maintain LNG in the desired
temperature. Any reduction of operating compressor’s capacity The Fault Tree for the event “Loss of industrial air” which is a
initiates an incident. The Fault Tree for boil-off removal malfunc- support system is presented in Fig. 9. The top event in this tree will
tion, is shown in Fig. 6. The top event of this tree occurs if the occur if there is loss of electrical power or if there is a failure of the
operating compressor fails, if there is a loss of industrial air (sup- air compressor.
port system further analyzed in separate Fault Tree) or if there is a
loss of electrical power (support system further analyzed in sepa-
rate Fault Tree). BOIL OFF REMOVAL
MALFUNCTION -
UNLOADING

@IE-1-1

COMPRESSOR #1 LOSS OF IA LOSS OF ELECTRICAL


FAILURE POWER

COMP. FAIL#1 @LOSS IA-1 LOSS OF EL. SUPPLY

Fig. 5. Event Tree with initiating event “Strong waves during unloading” (offshore LNG Fig. 6. Fault Tree for boil-off removal malfunction during unloading from ship to tank.
plant).

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
8 O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13

Fig. 7. Fault Tree for compressor malfunction.

Fault Tree for the loss of electrical power Component failure data have been estimated by using data of
OREDA (1992, 1997) database and by assuming that components
The Fault Tree for the event “Loss of electrical power” which is a follow the exponential law for times to failure. Frequencies of
support system is presented in Fig. 10. The top event in this tree will failure and unavailabilities on demand have been calculated for
occur if there is a loss of offsite power and the diesel generator does Fault Tree quantification. More details on calculated data for Fault
not start. Tree quantification and are provided by Aneziris et al. (2010).
In total twenty six Fault Trees have been developed for quanti- Most of the human actions incorporated in the logic models are
fication of all Event Trees, of the LNG plants and were quantified action errors or errors of detection and can be classified as of the
according to the methodology developed and with data from the “cognitive” type according to the definition of Hannaman, Spurgin,
OREDA (1992, 1997) database. More details for all Fault Trees are and Lukic (1985). This means that they consist of actions not
provided by Aneziris et al. (2010). The top events of all Fault Trees routinely performed, but actions required as a response to events
constructed for system modeling are presented in Table 4. not included in normal operation (e.g. fire, problem in unloading).
Following the model suggested by Hannaman et al. (1985), the
4.2.2. Data assessment and parameter evaluation probability of failing to perform a required action of the cognitive
In order to quantify the models described three major categories type depends on the time available to the operator for thinking out
of parameters must be estimated which are frequencies of initiating the cause of the symptoms available to him and identifying the
events, component failure data and probabilities of human errors. required response. The failure probability for these types of errors
Frequencies of initiating events can be estimated from historical was assessed to be 0.01/demand for action and communication
data, or detailed logic models or engineering judgment. In the errors and 0.001/demand for detection errors.
analysis of the LNG terminals Fault Trees have been developed for
two initiating events, namely for boil-off removal malfunction 4.2.3. Accident sequence and plant-damage state quantification
during loading and storage. All others have been estimated and The step of the probabilistic safety assessment includes all tasks
presented in Table 5. associated with the quantification of accident sequences. The plant

Fig. 8. Fault Tree for no manual termination of unloading related to pressure increase.

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13 9

Table 4
List of top events of Fault Trees constructed for LNG risk assessment.

1. Boil-off removal malfunction during unloading


2. Compressor malfunction
3. No manual termination of unloading due to pressure increase
4. Pressure control system fails to stop unloading from ship
5. Loss of industrial air
6. Loss of electrical power
7. Pressure signal failure
8. Fire fighting system failure on jetty
9. No manual termination of unloading due to high temperature
10. No manual termination of loading due to high winds
11. No manual termination of loading due to high level
12. High level control system failure
13. Level signal failure
14. Recirculation between tanks failure
15. Temperature signal failure
16. No manual stop of compressor
17. Automatic system fails to stop compressor
Fig. 9. Fault Tree for loss of industrial air. 18. Boil-off removal malfunction during storage
19. Fire fighting system failure, in tanks area
20. Sprinklers failure in tanks and vessels
21. No manual stop of operation due to low level in tank
model built during the major step “accident sequence determina-
22. Low level control failure
tion” has been quantified using parameter values estimated in the 23. No manual stop of send out due to low pressure in tank
previous step of “data assessment and parameter evaluation”. The 24. Pressure control in send out failure
quantification of accident sequences includes the determination in 25. Failure of pressure control of vaporizer
the Event Trees of the accident sequences to be quantified, and 26. No manual stop of send out to vaporizer
27. Boil-off removal malfunction during loading
their manipulation. Manipulation utilizes the laws of Boolean
algebra to put the sequences into a form suitable for quantification.
Results of this step consist of the cutsets for each accident sequence
and their associated frequencies. For example the cutsets of acci- The frequency with which each of these plant-damage states is
dent sequence #5 of event tree developed for initiating event “Boil- estimated according to CPR 18E (1999) as 5  107/m and a 20 m
off removal malfunction during unloading from ship to tank” (see length has been assumed for pipe sections from LNG tanks to
Fig. 4) are presented in Table 6. Cutsets for the event tree developed pumps, outlet pipeline of onshore terminal and double length for
for the initiating event “Strong waves during unloading” for the outlet pipeline of offshore terminal. Frequencies of occurrence per
offshore LNG plant are presented in Table 7. year of all plant-damage states of this analysis are presented in
As already presented in accident sequence modeling, accident Table 8.
sequences have been classified in the following plant-damage
states: a) tank rupture owing to overpressure or overfilling, b) tank 4.3. Consequence analysis
rupture owing to underpressure and c) pipebreak in the piping
between ship and tank. The frequency of each plant-damage state In the installations under analysis six damage states have been
has been calculated by adding the frequencies of the accident se- considered for each terminal, as presented in Table 3, which are
quences forming the plant-damage state and considering the
duration of each phase. It has been assumed the duration of loading
Table 5
is 1000 h/yr and the duration of storageeunloading 7660 h/yr.
Frequencies of initiating events.
Two more plant-damage states have been considered as
resulting from single events namely: pipebreak between LNG tanks Initiating events Frequency (/yr)
and pumps, full bore outlet pipeline break. These plant-damage Excess external heat (or high temperature in product) 101
states have the potential of releasing LNG into the environment. during unloading from ship to tank
External fire in jetty during unloading from ship to tank 101
Inadvertent valve closure during unloading 102
from ship to tank
Inadequate cooling of Loading arm during 102
unloading from ship to tank
High winds during unloading from ship to tank 101
High level in tank during unloading from ship to tank 101
Rollover in tank during unloading from ship to tank 101
Rollover in tank during storage 101
Inadvertent Start of Compressor during storage 101
External fire near tank during storage 1
Low level in tank during send out 101
Increased send out rate from tank 101
Closed valve in send out from tank 102
Inadvertent Starting of Compressor e Increased 101
flow rate to recondenser
Booster pumps malfunction at the exit of recondenser 101
External fire near recondenser 1
Vaporizer failure 5  101
Strong waves during unloading from ship to tank 102
of offshore LNG plant
Strong winds or currents during storage of 103
offshore LNG plant
Fig. 10. Fault Tree for loss of electrical power.

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
10 O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13

Table 6
Cutsets of accident sequence# 5 of Event Tree with initiating event “Boil-off removal malfunction during unloading from ship to tank”.

Frequency (/h) Cutsets

1 3.31E-11 DIESEL GENER LOSS AC PRESSURE ALARM PSV


2 2.00E-11 AIR COMPRESSOR PRESSURE ALARM PSV
3 1.98E-11 DIESEL GENER LOSS AC OP. COMMUNICATION PSV
4 1.98E-11 DIESEL GENER LOSSAC OP. SHIP PUMP PSV
5 1.00E-11 AIR COMPRESSOR OP. COMMUNICATION PSV
6 1.00E-11 AIR COMPRESSOR OP. SHIP PUMP PSV
7 1.98E-12 DIESEL GENER LOSS AC OP. ALARM PSV
8 1.74E-12 COMP. FAIL#1 IN. VALVE FAIL. PRESSURE ALARM PRESSURE SIGNAL PSV
9 1.12E-12 COMMUNICATION DIESEL GENER LOSS AC PSV
10 1.12E-12 COMM_MANUAL DIESEL GENER LOSS AC PSV
11 1.04E-12 COMP. FAIL#1 IN. VALVE FAIL. OP. SHIP PUMP PRESSURE SIGNAL PSV
12 1.04E-12 COMP. FAIL#1 IN. VALVE FAIL. OP. COMMUNICATION PRESSURE SIGNAL PSV
13 1.00E-12 AIR COMPRESSOR OP. ALARM PSV
14 6.63E-13 AIR COMPRESSOR COMMUNICATION PSV
15 6.63E-13 AIR COMPRESSOR COMM_MANUAL PSV
16 1.00E-14 AIR COMPRESSOR PSV PUMPS
TOTAL 1.23E-10

the following: a) LNG tank rupture, owing to overpressure, over- 4.3.2. Pipe rupture in unloading section (ship to tank)
filling or underpressure b) pipe rupture containing LNG, unloaded A number of accident sequences could result in a pipebreak in
from ship with rate 2000 m3/h for the onshore plant and with the piping which connects the ship to the LNG tank. For this plant-
4000 m3/h for the offshore plant c) pipe rupture containing LNG damage state it is assumed that: in the onshore plant LNG is
pumped from the send out pumps to the plant with rate 250 m3/h released at the unloading rate equal to 2000 m3/h for 10 min and in
in the onshore and 4330 m3/h in the offshore d) pipe rupture the offshore plant LNG is released at the unloading rate equal to
containing natural gas which is transferred to the outlet section of 4000 m3/h for 10 min. In case of pipe rupture containing LNG im-
the plant with rate 2000 m3/h for the onshore plant and 9600 m3/h mediate ignition will cause a pool fire (see Fig. 11, branch #1), while
for the offshore one. in case of delayed ignition LNG will vaporize at a rate equal to the
release rate and produce a cloud denser than air spreading ac-
4.3.1. LNG tank rupture, owing to overpressure, overfilling or cording to the weather conditions. If the cloud reaches concentra-
underpressure tions between upper and lower flammability level (5e15% by
In case of LNG tank rupture it is assumed that the roof of the volume) the mixture can be ignited if contacted by an ignition
tank will fail and either immediate or delayed ignition will occur. In source and either a flash fire (see Fig. 11, branch #2) or an explosion
case of immediate ignition there will be a pool fire (see Fig. 8, will take place (see Fig. 11, branch #3). In all cases of pipe rupture it
branch #1), while in case of delayed ignition LNG will vaporize and has been assumed that 10 min are required for operators to close
produce a cloud denser than air spreading according to the weather the appropriate valves and stop the release, following personal
conditions (wind speed, ambient temperature, class of atmospheric communication with safety engineers of LNG plants.
stability, humidity). LNG concentrations depend on the amount of
the released LNG and the atmospheric and meteorological condi- 4.3.3. Pipe rupture in loading section (after send out pump)
tions. An accident sequence resulting in LNG release to the envi- There are no additional events which mitigate such an accident,
ronment, if precisely determined, would lead to a unique type of and the event was not reduced to other simpler events to deter-
release. Such precise knowledge is not always available, however, mine its frequency. The frequency of this event is assessed directly,
and in such cases there is an uncertainty about the possible release based on engineering data and the pipe length. The assumption
category following the accident. If the cloud reaches concentrations made is the following: the pipe rupture in the onshore plant con-
between upper and lower flammability level (5e15% by volume) taining LNG pumped from the send out pumps to the plant with
the mixture can be ignited if contacted by an ignition source and rate 250 m3/h for 10 min, while in the offshore plant the relevant
either a flash fire (see Fig. 11, branch #2) or an explosion will take rate is 4330 m3/h for 10 min.
place (see Fig. 11, branch #3).

Table 8
Frequency (/yr) of all plant-damage states.

Plant-damage state Frequency (events/yr)


Table 7
Cutsets of accident sequence# 3, of Event Tree with initiating event “Strong waves ONSHORE LNG FACILITY
during unloading” (offshore LNG plant). 1 Tank rupture owing to overpressure 1.79  106
2 Tank rupture owing to overfilling 1.55  107
Frequency Cutsets
3 Tank rupture owing to underpressure 2.63  109
(/yr)
4 Pipebreak in the piping between ship and tank 1.55  105
1 1.00E-05 FLOAT_BARRIER OP. COMMUNICATION WAVE_UNLOADING 5 Pipebreak between LNG tanks and pumps 1.0  105
2 1.00E-05 FLOAT_BARRIER OP. SHIP PUMP WAVE_UNLOADING 6 Pipebreak in the outlet pipeline 1.0  105
3 1.13E-06 FLOAT_BARRIER MOVEMENT WAVE_UNLOADING OFFSHORE LNG FACILITY
SENSOR 7 Tank rupture owing to overpressure 4.10  106
4 1.00E-06 FLOAT_BARRIER OP. ALARM WAVE_UNLOADING 8 Tank rupture owing to overfilling 1.55  107
5 5.64E-07 COMMUNICATION FLOAT_BARRIER WAVE_UNLOADING 9 Tank rupture owing to underpressure 2.63  109
6 5.64E-07 COMM_MANUAL FLOAT_BARRIER WAVE_UNLOADING 10 Pipebreak in the piping between ship and tank 1.55  105
7 1.00E-08 FLOAT_BARRIER PUMPS WAVE_UNLOADING 11 Pipebreak between LNG tanks and pumps 1.0  105
TOTAL 2.3E-05 12 Pipebreak in the outlet pipeline 2.0  105

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13 11

In case of pipe rupture containing LNG immediate ignition will


cause a pool fire (see Fig. 11, branch #1), while in case of delayed
ignition LNG will vaporize at a rate equal to the release rate and
produce a cloud denser than air spreading according to the
weather conditions. If the cloud reaches concentrations between
upper and lower flammability level (5e15% by volume) the
mixture can be ignited if contacted by an ignition source and either
a flash fire (see Fig. 11, branch #2) or an explosion will take place
(see Fig. 11, branch #3).

4.3.4. Pipe rupture in outlet section


There are no additional events which mitigate such an accident,
and the event was not reduced to other simpler events to deter-
mine its frequency. The frequency of this event is assessed directly,
based on engineering data and the pipe length. The assumption
made is the following: in the onshore plant pipe rupture containing
NG which is transferred to the outlet section of the plant with rate
Fig. 11. Consequences following the rupture of an LNG tank or liquid pipeline.
750 m3/h for 10 min, while in the offshore plant the relevant rate is
9600 m3/h for 10 min.
In case of pipe rupture containing high pressure natural gas
immediate ignition will cause a jet fire (see Fig. 12, branch #1),
while in case of delayed ignition natural gas will disperse according
to the weather conditions. If the cloud reaches concentrations be-
tween upper and lower flammability level (5e15% by volume) the
mixture can be ignited if contacted by an ignition source and either
a flash fire (see Fig. 12, branch #2) or an explosion will take place
(see Fig. 12, branch #3).

4.4. Risk integration and results

For all plant-damage states presented in Table 3, all types of


release which might occur such as pool fire, jet fire, flash fire and
explosion have been considered and the individual risk profile has
been assessed. Parameters with variability such as wind speed,
wind direction, atmospheric stability, ambient temperature and
position of ignition source have been considered as random vari-
Fig. 12. Consequences following the rupture of a high pressure natural gas pipeline. ables, along with the probability density functions that quantify the
uncertainty about them, as presented in Table 9. The computer code
SOCRATES (Papazoglou et al., 1996) has been used for consequence
assessment and integration of results.

Fig. 13. Individual risk contours for onshore LNG terminal (distance in m).

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
12 O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13

Table 9 HAZOP, FMEA and qualitative risk matrices, without real guidance
Variability of variables for consequence assessment of LNG damage states. how to use these methods in an integrated way.
Uncertain variable Distribution Application of the methodological steps of probabilistic safety
1 Wind speed distribution Normal (1e8 m/s)
analysis in LNG terminal, in the framework of iNTeg-Risk project
2 Wind direction 50.8% N, 4.32% NE, 4.28% E, resulted in the identification of 21 initiating events which can cause
2.90% SE, 18.26% S, 4.34% SW, accident and lead to one of the six plant-damage states identified
2.29% W, 11.82% NW and presented in Table 3. Risk from operation of LNG terminals has
3 Ambient temperature Normal (10e32  C)
been identified by calculating the probability of an individual fa-
4 Atmospheric stability 16.67% for each PeG Stability
Class (AeF) tality per year of facility operation and has been expressed in the
5 Distance of ignition for Uniform in the range form of isorisk curves. The most important contributor to individ-
delayed ignition following tank rupture of 50e500 m ual risk is the failure of the piping between ship and terminals
6 Distance of ignition for Uniform in the range
followed by delayed ignition. This is due to the amount of LNG
delayed ignition following pipe of 50e350 m
rupture (tank to pumps
released, followed by dispersion and ignition (either immediate or
7 Distance of ignition for delayed Uniform in the range delayed). Next follows the rupture of tank followed by delayed
ignition following pipe of 100e1000 m ignition (either flash or explosion) of vapors. The offshore terminal
rupture (ship to tank) has higher individual risk rates, owing to the number and size of the
8 Distance of ignition for delayed Uniform in the range
tanks, which handle larger quantities than the onshore.
ignition in send out pipeline: of 100e1000 m

6. The contribution of Ioannis Papazoglou to the


development of QRA in the process industry
5
Total individual risk of the onshore plant is equal to 10 e
108/yr at distance of 80, 400, 750 and 1000 m from the center of
the plant respectively. Total individual risk of the offshore plant
has also been calculated and is equal to 105e108/yr at distance
of 100, 500, 850 and 1100 m from the center of the plants
respectively. Individual risk contours for the onshore plant are
presented in Fig. 13 and are valid under the meteorological as-
sumptions described.
The offshore plant has higher frequencies of plant-damage
states compared to the onshore, owing to the following reasons: a)
larger number of LNG tanks (four compared to two for the onshore)
b) additional initiating event of strong winds, which is applicable Ioannis Papazoglou, was born in Athens in 1949, obtained his
only to the offshore plant and c) larger length of outlet pipeline diploma from the School of Electrical & Mechanical Engineering of
which might break. The consequences from LNG release from the the National Technical University of Athens (1972) and his Masters
offshore plant cause adverse effects (fatalities) to larger distance and PhD degree from the Department of Nuclear Engineering of
than the onshore, owing to higher quantities of release, but not MIT in the field of Reliability and Risk Assessment (1974, 1977).
proportional to the release rate. Meteorological conditions and the Between 1980 and 1984 he was leader of the Risk Evaluation Group
distance of ignition are important parameters in case of delayed of the Department of Nuclear Energy at the Brookhaven National
ignition, since they affect the quantity which will be ignited or Laboratory, U.S.A. He returned to Greece in 1985 and joined the
exploded. National Center for Scientific Research DEMOKRITOS (NCSRD),
where he became Director of the Institute of Nuclear Technology e
5. Conclusions Radiation Protection and member of the Board of NCSRD Directors
for ten years.
This paper presents an integrated risk assessment framework In 1989 he organized within the NCSRD the Laboratory of Sys-
for Liquefied Natural Gas (LNG) terminals. The major steps for risk tems Reliability and Industrial Safety (SRISL), which consists of six
assessment are hazard identification, accident sequence modeling, PhD researchers performing Research & Development in the areas
data acquisition and parameter estimation, accident sequence of risk assessment & management, decision analysis and uncer-
quantification, consequence assessment, and integration of results tainty quantification mainly applied in chemical installations and
where individual risk is assessed for any person who might be near systems. He is one of the pioneers in Quantitative Risk Assessment
the terminals. Probabilistic methods for risk assessment have both in the nuclear and chemical industry. While in the US he
extensively been used in the literature for toxic and flammable performed probabilistic safety analysis and reliability of nuclear
substances (CCPS, 2000; Lees, 1996; Papazoglou et al., 1992, 1996; power plants, review and evaluation of risk studies, probabilistic
Taveau, 2010; Tixier et al., 2002), but not for LNG. This probabi- analysis of specific safety issues, generic reliability issues, devel-
listic method for risk assessment assesses in a structured way all opment of NRC probabilistic safety analysis guide and audit manual
the existing hazards, all barriers and safety measures of the in- and application of multi-objective decision analysis on the disag-
stallations which may prevent the hazards from appearing, the gregation of global safety objectives to system reliability re-
ways this barriers might fail, the release which will occur, the quirements. As the Head of SRISL his major contribution was the
possible consequence to people surrounding the terminals and development of a methodology for Quantitative Risk Assessment
finally the risk the installation poses to people. Within this for the chemical industry handling toxic, flammable and explosive
framework Master Logic Diagrams provide a structured method for substances. This methodology has been applied to various in-
hazard identification and uncertainties in weather conditions and dustries, such as ammonia, LNG, LPG, refineries and explosive
position of sources of ignition are also taken into account in risk plants. He was also in charge of the development of a methodology
quantification. On the other hand the ISO 17776 presents general for the evaluation of safety reports of industrial installations subject
guidelines on tools and techniques for hazard identification and to the SEVESO-II Directive, applied to all major hazard industrial
risk assessment and presents briefly QRA, Fault Trees, Event Trees, plants in Greece. In addition, he contributed in the development of

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014
O.N. Aneziris et al. / Journal of Loss Prevention in the Process Industries xxx (2013) 1e13 13

dynamic reliability of complex systems, decision analysis under Jovanovic, A. (2010). iNTeg-Risk project: concept and first results. In Proceedings of
the 2nd iNTeg-Risk conference: New technologies and emerging risks e Dealing
uncertainty, multi-objective techniques useful to determine the
with multiple and interconnected emerging risks. Stuttgart (Germany): Steinbeis
land use around hazardous chemical installations and methods for Edition, ISBN 978-3-938062-33-3.
emergency response planning. He elaborated the development of Koopman, R. P., & Ermak, D. L. (2007). Lessons learned from LNG safety research.
the Occupational Risk Model for quantifying the risk of the working Journal of Hazardous Materials, 140(3), 412e428.
Landucci, G., Tugnoli, A., Spadoni, G., & Cozzani, V. (2012). LNG regasification ter-
population in various professions. minals: assessment of accidents due to external acts of Interference. In Proc. of
Dr. Ioannis Papazoglou has been active in the European scene of 11th International probabilistic safety assessment and management conference and
risk assessment & management through various positions in Eu- the annual European safety and reliability conference 2012, PSAM11 ESREL 2012:
Vol. 6 (pp. 4373e4382).
ropean organizations and committees. Most recently he has been a Lees, F. P. (1996) (2nd ed.).. Loss prevention in the process industries, 3 Vol. London
Visiting Professor at Delft Technical University, in the faculty of and Baton: Butterworths.
Technology Policy and Management-Safety Science Group, orga- Licari, F. A., & Weimer, C. D. (2011). Risk-based siting considerations for LNG ter-
minals e comparative perspectives of United States & Europe. Journal of Loss
nizing and teaching a course in “Quantification Techniques for Risk Prevention in the Process Industries, 24(6), 736e752.
Analysis and Management” between 2006 and 2007. As head of Ohba, R., Kouchi, A., Hara, T., Vieillard, V., & Nedelka, D. (2004). Validation of heavy
SRISL he has supervised several PhD theses in the fields of dynamic and light gas dispersion models for the safety analysis of LNG tank. Journal of
Loss Prevention in the Process Industries, 17(5), 325e337.
reliability and emergency planning. He has published over two Olewski, T., Nayak, S., Basha, O., Waldram, S., & Véchot, L. (2011). Medium scale
hundred and seventy seven scientific publications comprising ar- LNG-related experiments and CFD simulation of water curtain. Journal of Loss
ticles in scientific peer reviewed journals, papers in peer reviewed Prevention in the Process Industries, 24(6), 798e804.
OREDA. (1992). Offshore reliability data handbook (2nd Ed.). Veritasveien 1, N-1322
conference proceedings, technical reports and book chapters. He
Hovik, Norway: Det Norske Veritas.
serves at the editorial board of the “Journal of Hazardous Mate- OREDA. (1997). Offshore reliability data handbook (3rd Ed.). Veritasveien 1, N-1322
rials”, “Reliability Engineering and System Safety” and the “Inter- Hovik, Norway: Det Norske Veritas.
national Journal of Risk Assessment and Management”. He has Papazoglou, I. A., & Aneziris, O. N. (2003). Master Logic Diagram: method for hazard
and Initiating event identification in process plants. Journal of Hazardous Ma-
served as Guest Editor in special issues of the “Journal of Hazardous terials, A97, 11e30.
Materials”, “Reliability Engineering and System Safety” and “Safety Papazoglou, I. A., Aneziris, O., Bonanos, G., & Christou, M. (1996). SOCRATES: a
Science”. He has been the General Chairman of ESREL’96 e PSAMIII computerized toolkit for quantification of the risk from accidental releases of
toxic and/or flammable substance. International Journal of Environment and
and of ESREL 2010 conferences both organized in Greece, and Pollution, 6(4e6), 500e533.
member of the Technical Committee of almost all ESREL confer- Papazoglou, I. A., Nivolianitou, Z., Aneziris, O., & Christou, M. (1992). Probabilistic
ences to date. He was the Chairman of the European Safety and safety analysis in chemical installations. Journal of Loss Prevention in the Process
Industries, 5(3), 181e191.
Reliability Association (ESRA) for several years, the President of the Pitblado, R., Baik, J., Hughes, G., Ferro, C., & Shaw, S. (2004). Consequences of LNG
International Association for Probabilistic Safety Assessment and marine incidents. In CCPS conference Orlando.
Management (IAPSAM) Board of Directors and Member of the same Raj, P. K. (2011). Evaporating liquid flow in a channel (an integral model based on
shallow water flow approximation). Journal of Loss Prevention in the Process
Board, and he has served at the Executive Committee of the Society Industries, 24(6), 886e899.
for Risk Analysis-Europe. Raj, P. K., & Bowdoin, L. A. (2010). Underwater LNG release: does a pool form on the
water surface? What are the characteristics of the vapor released? Journal of
Loss Prevention in the Process Industries, 23(6), 753e761.
References Raj, P. K., & Lemoff, T. (2009). Risk analysis based LNG facility siting standard in
NFPA 59A. Journal of Loss Prevention in the Process Industries, 22(6), 820e829.
ABS Consulting. (2004). Consequence assessment methods for incidents involving re- Rana, M. A., & Mannan, M. S. (2010). Forced dispersion of LNG vapor with water
leases from liquefied natural gas carriers. ABS Consulting. curtain. Journal of Loss Prevention in the Process Industries, 23(6), 768e772.
Aneziris, O., Papazoglou, I. A., & Konstantinidou, M. (2010). Quantitative risk analysis Rana, M. A., Cormier, B. R., Suardin, J. A., Zhang, Y., & Mannan, M. S. (2008).
of LNG plants. Report of iNTegRISK Project. Experimental study of effective water spray curtain application in dispersing
Bais, A. F., Zerefos, C. S., & Ziomas, I. C. (1989). Accidental releases form storage liquefied natural gas vapor clouds. Process Safety Progress, 27(4), 345e353.
installations. Journal of Loss Prevention in the Process Industries, 2, 155e160. Sandia Report. (2004). Guidance on risk analysis and safety implications of a large
Bubbico, R., Cave, S., & Mazzarotta, B. (2009). Preliminary risk analysis for LNG liquefied natural gas (LNG) spill over water. SAND 2004-6258.
tankers approaching a maritime terminal. Journal of Loss Prevention in the Takeno, K., Ichinose, T., Tokuda, K., Ohba, R., Yoshida, K., & Ogura, K. (1996). Effects
Process Industries, 22(5), 634e638. of high expansion foam dispersed onto leaked LNG on the atmospheric diffu-
CCPS. (2000). Guidelines for chemical process quantitative risk analysis (2nd ed.). New sion of vaporized gas. Journal of Loss Prevention in the Process Industries, 9(2),
York: AIChE. 125e133.
Cleaver, P., Johnson, M., & Ho, B. (2007). A summary of some experimental data on Taveau, J. (2010). Risk assessment and land-use planning regulations in France
LNG safety. Journal of Hazardous Materials, 140(3), 429e438. following the AZF disaster. Journal of Loss Prevention in the Process Industries, 23,
CPR 18E. (1999). Guidelines for quantitative risk assessment. In Publication series on 813e823.
dangerous substances (PSG 3). Purple Book. www.content.publicatiereeksgevaar Taylor, D. W. (2007). The role of consequence modeling in LNG facility siting. Journal
lijkestoffen.nl/documents/PGS3-1999-v0.1-quantitative-risk-assessment.pdf. of Hazardous Materials, 142(3), 776e785.
Giannissi, S. G., Venetsanos, A. G., Markatos, N., & Bartzis, J. G. (2013). Numerical Tixier, J., Dussere, G., Salvi, O., & Gaston, D. (2002). Review of 62 risk analysis
simulation of LNG dispersion under two-phase release conditions. Journal of methods of industrial plants. Journal of Loss Prevention in the Process Industries,
Loss Prevention in the Process Industries, 26(1), 245e254. 15, 291e303.
Hanlin, A. L. (2006). A review of large-scale LNG spills: experiments and modeling. TNO. (1989). Methods for determination of possible damage to people and objects
Journal of Hazardous Materials, 132(2e3), 119e140. resulting from releases of hazardous materials (Green Book). Voorburg.
Hannaman, G. W., Spurgin, A. J., & Lukic, Y. (1985). Model for assessing human TNO. (1992). Methods foe the calculation of physical effects resulting from releases of
cognitive reliability in PRA studies, In IEEE 3rd conf. on human factors and nu- hazardous materials (liquids and gases), (Yellow Book). Voorburg, The
clear power plants, Monterey, CA, June 23e27. Netherlands: Committee for the Prevention of Disasters.
ISO 17776. (2000). Petroleum and natural gas industries e Offshore production in- Tugnoli, A., Landucci, G., Salzano, E., & Cozzani, V. (2012). Supporting the selection
stallations e Guidelines on tools and techniques for hazard identification and risk of process and plant design options by inherent safety KPIs. Journal of Loss
assessment. Prevention in the Process Industries, 25(5), 830e842.
Ivings, M. J., Lea, C. J., Webber, D. M., Jagger, S. F., & Coldrick, S. (2013). A protocol for Uguccioni, G. (2010). Reference solution containing report documents, methods and
the evaluation of LNG vapour dispersion models. Journal of Loss Prevention in the tools for the assessment and management of emerging risks related to new and
Process Industries, 26(1), 153e163. intensified technologies available for LNG gasification terminals. Report of
Jo, Y. D., & Ahn, B. J. (2002). Analysis of hazard areas associated with high-pressure iNTegRISK Project.
natural-gas pipelines. Journal of Loss Prevention in the Process Industries, 15(3), Vanem, E., Antão, P., Østvik, I., & de Comas, F. D. C. (2008). Analysing the risk of LNG
179e188. carrier operation. Reliability Engineering & System Safety, 93(9), 1328e1344.
Jo, Y.-D., & Ahn, B. J. (2005). A method of quantitative risk assessment for trans- Yun, G., Rogers, W. J., & Mannan, M. S. (2009). Risk assessment of LNG importation
mission pipeline carrying natural gas. Journal of Hazardous Materials, 123(1e3), terminals using the Bayesian-LOPA methodology. Journal of Loss Prevention in
1e12. the Process Industries, 22(1), 91e96.

Please cite this article in press as: Aneziris, O. N., et al., Integrated risk assessment for LNG terminals, Journal of Loss Prevention in the Process
Industries (2013), http://dx.doi.org/10.1016/j.jlp.2013.07.014

Vous aimerez peut-être aussi