Vous êtes sur la page 1sur 13

of

Fire in
After seven years of smooth operation of an ammonia plant, an explosion occurred in
the synthesis section. This paper analyzes the likely causes of the accident and
describes the actions taken for rehabilitation of the plant along with remedial
measures taken to prevent recurrence of the accident.

A.K. Mukhopadhyay and P.P. Singh


Krishak Bharati Cooperative Ltd., Gujarat, India

INTRODUCTION; section in this plant is partially


modified compared to other
KRISHAK BHARATI COOPERATIVE LIMITED, 'Conventional Kellogg' plants. Instead
(KRIBHGO) operates a fertilizer of mixing the compressed make up gas
complex at Hazira, near Surat city in with converter outlet gas from gas to
India, consisting of two Amnonia gas exchanger (121C) at the inlet of
Plants of 1350 MIPD each and four Urea water cooled exchanger (124C), here
(Prilled) plants of 1100 MIPD each on another water cooled exchanger (156C)
natural gas as feed stock. The basic has been introduced at the 3rd stage
engineering for Amnonia and Urea discharge of the syn gas compressor
Plants were supplied by M.W.Kellogg, and the syn gas is further cooled by
USA and Snamprogetti, Italy anmonia in a second exchanger (140C)
respectively. before mixing with converter outlet
All the above plants were ccnmissioned gas. It has been specifically
during Nov/Dec.1985 and operated designed this way to be able to send a
consistently at capacities well over part of cooled syn gas to an adjacent
100%. Based on the excellent processing plant. Syn gas return from
operating experiences in terms of this plant is also mixed up with
design energy norms, capacity converter effluent prior to separation
utilisation and high on stream days, of MHL in Anmonia separator and
energy optimisation retrofit /debottle sending the gas to recirculator.
-necking of these Anmonia Plants have Converter in this plant is a bottle
been planned in phased manner. shaped, three bed, axial flow catalyst
reactor with inter bed quenches
PROCESS DESCRIPTION; (ref.simplified PFD Fig.l).

Process flow in Anmonia Synthesis


171
TO tOt,.C

115.C

I22X
TO »3-E

105-0
SYN.CONVtH

FIG-1 PROCESS FLOW


DIAGRAM OF AMMONIA SYNTHESIS

TO NHj
REFRIG

There are two vent headers, one in the as cold vent which connects the
front end upto CO? removal referred to discharges of all relief valves and
as hot vent which connects all the control process gas vents of synthesis
discharges of relief valves and few section and releases in the atmosphere
control process gas vents and releases through a silencer located at the top
in the atmosphere through silencer of Œ>2 stripper (réf. P&I of cold vent
located at the top of steam drum header Fig.2).
structure. The other is referred to
-00-££— DRAIN FROM VENT
HEADER

0450
Seh .40 WPt 200,
woo
.
2-0
i SILENCER GATED
ASIDE STRIPPER TOP

GOO

DRAIN TO HUB

^rrt
rtuT" ~fr5 i "P
"

MODIFIED DRAINS WITH WATER SEAL


«s AT GRADE
PROVIDES
SEAL LOOP

FIG-2 P&I COLD VENT


HEADER WITH MODIFICATIONS

172
totally cut off. Anmonia plant Unit-I
BACKGROUND OF THE INCIDENT; was isolated but continued to run.
Isolation of gas also became difficult
The incident occurred on 26th as the motorised actuators of the
September 1991 at 0117 hours when the valves were burnt and could not be
Airmonia Plant (Unit-II) was running approached for manual closure.
normally at around 117% load.
However, a few minutes earlier to the OF DAMAGE:
occurrence of incident, operating
staff in the control room acknowledged During the outbreak of fire, the main
an alarm on the annunciator panel due power supply and plant lighting cables
to "low steam flow to reformer." got burnt off and power supply was
While the operators were busy in disrupted within about three minutes.
analysing the cause of the alarm, a Hence, extent of damage was assessed
loud explosion was heard in the partly on the following morning and
synthesis section, opposite to the balance after two days when the
control room. A large flame was compressor house and pump bay area
noticed in the area on 3rd stage could be approached after airmonia
discharge pipeline of synthesis gas liquid drain, due to rupture of
compressor (103J) where a relief valve anmonia line, could be controlled and
(RV 156C) with lead pipe was found debris was cleared off from the area.
knocked off from the pipeline. The general observations made are as
follows :-
During dépressurisâtion of the plant
and venting the process gas through 1) The pilot operated relief valve
cold vent header through valve PIC4(V) RV156C was uprooted from its
the hydrogen rich gas also came back existing position on the pipeline
through the sheared off tail pipe of (réf. Photo 1). The discharge tail
the same safety valve (RV 156C) and pipe was knocked out of position
caused a secondary source of fire in and a portion immediately after the
the nearby area. tail pipe with expander 4"x8" was
found sheared and blown open (réf.
Fire was controlled within about one Photo 4,5 & 6).
hour when the supply of process gas

LOCATION OF
RV 156 G LEAD
PIPE ON SYN
GAS PIPING

Photo-1

173
Due to intensity of explosion the located after two days. The pilot
relief valve was thrown off to the valve of this relief valve was also
nearby pipe rack and could be found detached and lying on the
ground.

PHOTO -4 BURST OPEN PORTION OF TAIL PIPE

PHOTO-5 RV-156C WITH SHEARED OFF INLET LEAD PIPE & PORTION OF TAIL
74 PIPE
2) Nearby exchangers like 120C,130C 3) Cold insulation of expanded
and 117C (réf.plot plan of polysterene of almost all the other
synthesis section Fig.3) got exchangers/pressure vessels
directly exposed to flame coming including above in the nearby area
out from the opening created due to got burnt off (réf.Photo 7). Cold

PHOTO-6

SHEARED OFF
PORTION OF
TAIL PIPE
CONNECTED TO
R.V.

detachment of the RV 156C. The insulation on the long multishell


shells of the exchangers were amnonia separator (110F,112F etc.)
heated to red condition and also got burnt off.
simultaneously subjected to water
spray during fire fighting.

N r} t
'

t
K •

\\
J

jt a
;r
ir ti 123-C
1 1

J
1 > i
105. D
X f
o;
^ i TI 122-d
u
C!
<n .XI
to "• rhrii
» 5 »I o: 111l ES
«•—S
<TU»
II * 102-B

I AREA.B AREA.A
l

CONTROL ROOM

FIG-3 PLOT PLAN OF SYNTHESIS SECTION


175
4) Mstorised actuators of valves were 9) With the waves of explosion which
found burnt. could be heard about four k»m.aways
5) Many power cables, lighting cables, control roan window panes and
instrument cables and tube found frames were shattered, false
severely damaged alongwith their eel ings had given way« Seme
supporting trays. annunciator panels and instruments
6) Concrete foundations of two were dislodged but fortunately no
exchangers developed cracks and major human injury was caused
structural members of a few pipe (ref.Fhoto 9).
supports found twisted/bent. 10)20 control valves were damaged in
7) Almost all the low pressure pipes varying degrees. Two pumps with

PHOTO-7 AMMONIA SYNTHESIS SECTION AFTER ACCIDENT


found damaged in the nearby area their drive motors were found
particularly in anrnonia partially burnt.
refrigeration section including
cold anmonia pump discharge which OBSERVATIONS:
resulted in draining of anmonia in
the pump bay behind the synthesis Inspection on the integrity of the
section. The cold vent header on fire affected plant equipments and
the pice rack where the tail pipe piping were carried simultaneously
of the RV 156C is connected, found with the rehabilitation of the plant
badly damaged and moved towards the on top priority. Separate specialist
open vent on the rack by nearly one group were formed inhouse as well as
metre (réf.Fig.4). outside experts from other operating
8) Another relief valve (RV 104F) on plants and engineering consultants®
the suction to syn gas compressor The process licencer and detailed
knock out drum was also found engineering consultants were also
damaged. The discharge tail pipe contacted. The aims were two fold»
of this valve is also connected to
the cold vent header. i) To find out the probable cause of
176
DETAILS:
COLD VENT HEADER
DON. PRESS : 21 Kg/cm 2
DON. TEMP : 120*C
DAMAGED AND
MATERIAL :C.S. (A53.B SML) SHIFTED TOWARDS
THICKNESS :8". STD. NORTH AFTER EXPLOSION
WISTD.
i^" «CM tn
INSUL. THK. : 40 MM

FIG-4 PIPING DRAWING OF COLD VENT HEADER

accident. the basis of different hypothesis on


ii) To work out remedial measures to the causes of the accident and also
avoid recurrence of similar the recccrmendation made to avoid
accident in future. More so as recurrence of similar incident.
the second plant of identical
design was under operation with OBSERVATION:
potential for similar hazard.
a) The pilot operated relief valve RV
Investigating groups had examined 156-C popped in 1986, when the
physically the failed pieces of piping discharge pipe got dislodged from
and relief valve attachments, damaged the cold vent header. The
vent header, process licencer's supporting system was modified and
technology transfer document, recorder a drain line was added at tail pipe
chart of operating parameters during (réf. fig. 5) to drain out
the time the accident happened, intermittantly the condensate
visited accident site and also likely to get accumulated.
discussed with operating and b) The RV 156-C again popped in 1988.
maintenance staff. This time also it caused seme
On delibration the following
observations were made which formed
177
damage to the discharge tail pipe. this valve is left accidentaly open
c) Quite a few deviation had been or not shut tightly.
noted in the execution of cold vent
header with reference to P&I. Observations on operating conditionsi
Discharge leg of the RV 156C and a
few other connections were found to 1) The plant was running normal at an
have no self draining provisions. average load of over 115% for
To drain the header fron the likely around 100 days prior to accident.
condensate accumulation, float 2) A few minutes before the accident,
traps are provided but were steam to carbon (S/C) ratio to
reportedly not functioning primary reformer dropped to about
properly. 3.3 with alarm indication on the
d) The vent headers are provided with panel (alarm set at 3.35 and trip
purging steam connection at the end at 3.10).
of headers which are used only 3) Apparently there had been no
during start up and shutdown of increase of H.P. steam to syn gas
plant and for extinguishing fire at drive turbine.
the vent silencer, but due to lack 4) No increase in temperature to
of seat tightness small amount of synthesis converter catalyst bed.
steam always passes through. 5) At the adjacent plant where syn gas
e) The header is designed for is sent for processing, a pressure
atmospheric pressure but increase of 1.2 kg/cm g was
simultanaeous blowing of more than recorded.
one R.V. can build?up back pressure 6) Pressure recorder on the third
to around 12 kg/cm g. stage discharge was not functioning
f) The subject RV 156C is having 'J' hence actual pressure developing by
size orifice (réf.API RP-520), the compressor during accident
which is just adequate for 100% could not be ascertained.
capacity of plant operation, but
since the plant is normally Observations on Mechanical failure;
operated above 110% capacity the
'J' orifice is found undersized. 1) Inlet lead pipe 3" NB Sch.140 was
g) All the four pilot operated RVs in sheared off fron the parent pipe
synthesis section had escaped the 10" NB Seh. XXS (réf. Photo 4). It
attention and had not been tested may be seen that 3" branch was
since conmissioning of the plant. taken directly on 10" NB with a
h) The supporting of RV 156C was found reinforcement pad.
inadequate having overhung 2) The failure took place at the HAZ
unsupported length of nearly two of welding whereas there had been
metre from the main pipe. no apparent damage to the parent
i) The P&I of synthesis section had a pipe or welding.
specific cannent for RV 156C to 3) Sheared edges of the branch pipe
locate the same as close as clearly indicates reverse slant
possible to the cooler 156C, fracture which is usually
probably leading to the existing associated with internal explosion.
piping configuration of both lead 4) Above 1.5 metre portion of RV tail
pipe and discharge pipe of RV. pipe (8" NB Sch.std.wt. smls)
j) During physical check it was found sheared off and ripped open (réf.
that in other unit of Atrmonia photo 4)). Opening of the pipe is
plant, appreciable vacuum is felt on the bottom where the drain pipe
at the end of the drain pipe on RV was connected. The drain pipe
tail pipe if the drain valve is could not be located.
opened, due to natural draft. It 5) The vertical support on exhaust
suggests that ingress of air pipe near RV 156C was pulled out of
through this line is possible if foundation.
178
6) Pilot valve of RV 156C got detached Micrographs clearly indicates that
and fell on the ground. failure at first location was purely
mechanical indicating a ductile
Failure analysis; fracture (réf.photo 10, 11), where
samples at other two locations
Metallographie investigations were indicated decarburisation and
carried out at three locations of the overheating (photo 12,13,14 & 15).
ruptured pipes connected to RV 156C. Thus the investigation proved that
explosion had taken place inside the
1) at the inlet lead pipe at the point discharge tail pipe of the RV.
of detachment.
2) at the point where the drain line
was attached to the discharge tail
pipe.
3) at the end of the ruptured tail
pipe.

FIG-1Î MICROGRAPH OF LOCATION-1


FRACTURE : ABSENCE OF
DECARBURISÂTION-DEFORMED PEARLITE

FIG-10 LOCATION 1 FRACTURE

/ Jf

^V
f

/ , •*?
>

^f**?
A
f

'à *
'

^
"""

*w#f
€^
i ^J* tty $& ' **'

r** /*-*^
-f^>^
v
V - *' ^ *
i- % v
k
\& é ^ ^* -îfej*?' * .aw

FIG-13 MICROGRAPH OF LOCATION-2


EVIDENCE OF DECARBURISATION AND
OVERHEATING

FIG-12 LOCATION 2 FRACTURE

FIG-15 MICROGRAPH OF LOCATION-3


EVIDENCE OF DECARBURISATION AND
FIG-14 LOCATION 3 FRACTURE OVERHEATING
179
Probable causes of accident and Causes for blowing of Relief Valve (RV
analysis; 156G);
Based on the above observations, 1) Due to existing trip logic of syn
following probable causes emerged:- gas compressor, there was
possibility of discharge MOV's
1) EKplosive mixture can be formed in closing without tripping of the
the vent system/tail pipe due to; compressor either due to low
governor oil pressure or due to
a) passing of RV 156C or other RV tripping of back end of plant.
and valves connected to this Since the compressor is not
vent system. provided with unloading facility to
b) Popping of RV 156-C. minimum governor speed, with the
2) Accumulation of condensate in the closure of discharge MOV's the
vent header/tail pipe of RV 156C pressure in the compressor system
due to passing of steam purging shall rise causing RV 156C to blow.
valve and popping of RV 156C Similar incident of RV blowing had
resulting in severe water hatrmer occurred earlier also. But in this
and consequent mechanical failure. particular case there had been no
3) Mechanical failure of the branch indication of compressor unloading
inlet pipe of RV 156C during due to process upset.
popping due to inadequate 2) Possibility of speed fluctuation of
supporting arrangement. With the the turbine was also looked into
failure at RV inlet, flamable gas but in absence of speed recording
rushing out may cause explosion and no positive clue was available.
fire due to friction. After the rehabilitation of the
4) Popping of RV 156C with discharge plant, during reconmissioning, the
of IrL, rich syn gas entering the syn gas turbine speed was found to
vent systen and forming explosive fluctuate uncontrollably between
mixture with 0 from air ingress 8200 and 9700 rpm due to
through the drain on the tail pipe malfunctioning of the governing
(réf. fig.5). Due to high velocity system.
of discharged gas and expansion, On a check up after shutdown of the
temperature of PL shall rise (due turbine the pilot piston was found
to inverse ïïoules Thompson not moving freely.
Phenomena) and spark may be
generated by friction in contact It may, therefore, be inferred that
with weld metal etc. inside the during the accident the turbine
pipe in presence of C^ already under high operating load might
present. have experienced similar speed
fluctuation due to governor
Analysing the probable causes it manfunctioning leading to over
appears that the strongest possibility pressurisation of the system
exists for popping of RV 156C causing momentarily causing blowing of
explosive mixture in the vent coupled relief valve. In absence of
with ingress of air (O^) from the' pressure and speed recording it
drain on the tail pipe efae to valve went unnoticed. The pressure
being left partially open accidentaly setting of RV 156C was 219.05
after manual draining of condensate or kg/cm g against a normal operating
not shut tight. Spark for ignition pressure of the third stage
might have been provided by friction discharge of around 180 kg/cm g»
in the pipeline at uneven welding Since the same was not tested for a
penetration and rise in temperature long time, the change of its
due to hydrogen gas expansion. popping at lower than the set
pressure cannot be ruled out.
180
Circumstantial evidence in the form of f) Optical boroscopy inside the tubes
pressure rise at the adjacent plant of the exchangers to check for
where part of syn gas is sent for defect/deformation.
their process requirement through one g) Soundness of concrete foundation.
kilometre long piping, and less M.P.
steam flow to reformer (syn gas Fortunately no damage to equipments
turbine extraction being the only and high pressure piping was notified.
source of MP steam) give credence to Damaged insulation of around 2500 M
this theory. area was redone after removal of burnt
out material by polyurethane foam with
Assessment of damages and external cladding by G.I. sheets in
rehabilitation; place of expanded polysterene. Prior
to start up pressure testing was
Separate groups were organised with carried out in stages to identify
properly identified job responsibility deficiencies. Plant started anmonia
and by and large all jobs were production merely after 24 days of
simultaneously started through shutdown between production to
following major groups:- production as a result of meticulous
planning, monitoring, control, quick
1) L.P.piping and structural supports resource mobilisation and work
2) H.P.Piping distribution. All the jobs were
3) Instrumentation repair, new carried out round the clock under
installation and cabling close supervision.
4) Electrical repair, modification and Remedial measures taken:
cabling.
5) Remaking of civil foundation for 1) Location of RV 156C - changed from
equipments and piping present position to the pipe rack
6) Equipment isolation, purging and with proper supporting. New R.V.
handing over for inspection, with 'K' orifice was installed in
insulation etc. place of 'J' orifice valve.
7) Inspection and redesign of piping, Supports of similar RVs like 105D
supports etc. and 103J were strengthened. This
8) Repair of relief valves, was also checked from the process/
developments of H.P. testing and engineering consultant (réf.fig.6).
certification.
For assessment of damages of
equipments and piping, following NOT
methods were employed:-

a) Thorough visual inspection


b) Dye penetrant and MPI of affected
areas and other vulnerable areas
inside the exchangers and vessels
particularly at the saddle support
and plates, corner radius of forged
tube sheets, curbed surface of
bends and pipe supporting shoes,
nozzle connections etc.
c) Hardness survey of all affected
areas FIG-6 MODIFIED PIPING OF RV 156C
d) Insitu metallography to study the AFTER REHABILITATION
changes in the grain structure in
2) Synthesis gas compressor was
the worst heat affected areas. prov ided wi th : -
e) Ultrasonic flaw detection in
selected areas
181
operating plants using similar
a) high pressure trip at 205kg/orug technology all over the world were
with a prealarm at 195 kg/cm g contacted. The feedback showed that
to avoid blowing of RV 156C» almost all the operators of similar
b) earlier logic of unloading of plants till date were quite unaware of
compressor at a low governor oil the potential hazard that exists in
pressure was found unsafe and the cold vent system.
modified to trip. It was also noted during discussion/
c) Considering normal operating personal visits to some of these
speed of the compressor even plants that except for one plant in
with 120% load at around 10,300 UK, none had used continuous purging
rpm trip setting was reduced to by N to control combustible mixture
10,700 rpm from 12,430 rpm with in tne vent header that may form due
a prealarm at 10,430 rpm. to passing of any of the relief or
control valves connected to the
3) Continuous purging of cold vent header. Even the vent header and
system with NL has been implemented connecting relief valves supports were
(réf.fig.3) to ensure blanketing of not adequate and properly designed for
combustible, if any, inside the actual operating (blowing of relief
header. valves) condition.
4) To prevent ingress of air inside Further the ends of manual drains have
the vent header during manual also been left open in most of the
draining, water seal pots have been plants without any kind of sealing
introduced on drain lines. arrangement to prevent ingress of air
5) Power cables to the plant have been in the system.
rerouted behind the control room The accident brought out another fact
burying them underground. that the significance of the built in
6) Opening to the control room safety vtfiich was envisaged in the P&I,
(particularly glass windows) have was not reflected properly during
been practically removed leaving a detailed engineering and execution of
few smaller openings to watch the the project. It overlooked an
plant through blast proof glass. intrinsic unsafe condition which was
Blast wall is also provided at the otherwise avoidable. After the
entrance of the control room. accident during discussion with the
7) Approach of synthesis area improved original process designer in USA and
by relocating the general lighting co-consultant in India, it was also
tower. Additional fire fighting found that there had been a
monitors have been installed. communication gap between the
8) For self draining of the hot and consultant and co-consultant with
cold vent headers, improvements in respect to interpretation of the P&I
layout as far as practical, have resulting in deviations in detailed
been carried out. engineering.
On overall analysis, it may be
As a long term measure, study of suggested that after gaining
entire vent systems with relief valves sufficient experience of the plant
has been initiated, involving the operation, a detailed HAZOP analysis
process consultants. All should be carried out in the plant by
modifications shall be implemented as experienced consultant with thorough
far as practicable looking into the knowledge of the process and with
safe operation of the plants taking involvement of the plant operating
into account the retrofit of the plant personnel, so that the potential
for higher operating load. hazard situation like above may be
avoided for safe operation of the
CONCLUSION:
plant.
After the incident, a number of ***@@@***
182
P.P. Singh A.K. Mukhopadhyay

183

Vous aimerez peut-être aussi