Commissioning Service Department

Commissioning Standard Test Formats


Description: END TO END TEST - DISTANCE Record No.:
Bay no.: Drawing ref.: Sheet: 1 of 2
Contractor: Contract no.: Substation No :

Notes:
1. This test format is the minimum for END-to-END test of distance protection.
2. The following forms should be according to schematic drawing and type of
relays and devices used.

1. INDICATION AND ALARM CHECKING:


Note: (CP)—Communication Panel

Simulation From Local S/S


Local S/S Remote S/S
Ind. On IND. Control panel IND.
Equ.no & Descriptio Ind. On Control panel
Item NSD /FLAG on Ann. / /FLAG on
name n NSD(CP) Ann /HIMU
(CP) Relay panel HIMU Relay panel
1
2
3
4
5

2. DISTANCE PROTECTION COMMUNICATION SCHEME AND INTER-TRIP


INDICATION AND ALARM CHECK:

Local Station Remote Station


Alam In Flags In Indicatio
Signal Indication At Signal Indication At Remarks
Control Panel Relay n At
Initiated NSD (OLS) Received NSD (OLS)
/ Himu Panel Relay
FPFM-1 FPFM-1
Permissive Permissive
Send Received
FPFM-2 FPFM-2
Permissive Permissive
Send Received
Inter Trip-1 Inter Trip-1
Send (INST.) Received
Inter Trip-2 Inter Trip-2
Send(INST.) Received
FPFM-1
FPFM-1 Block
Block
Send
Received
FPFM-2
FPFM-2 Block
Block
Send
Received

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats
Description: END TO END TEST - DISTANCE Record No.:
Bay no.: Drawing ref.: Sheet: 2 of 2
Contractor: Contract no.: Substation No :

3. DISTANCE PROTECTION COMMUNICATION SCHEME AND INTER-TRIP


CHECK

Simulation From Local Substation


Local Substation Remote Substation
Con
Indication
Trip IND / CP Indication NSD IND / Panel
Simula-Ted NSD
Item Relay FLAG ANN / A/R FLAG On ANN A/R
Fault
In Rp on RP HIMU Relay Panel /HIM
OLS PLCC OLS PLCC
U
FPFM-1 Z1
1
optd
FPFM-1 Z2
2
optd
FPFM-1 Z3
3
optd
FPFM-1 Z1
4
SOTF optd
FPFM-2 inst
5
optd
FPFM-2 time
6
delay
FPSM-1 Z1
7
optd
FPSM-1 Z2
8
optd
FPSM-1 Z3
9
optd
FPSM-1 Z1
10
SOTF optd
FPSM-2 inst
11
optd
FPSM-2delay
12
Trip
13 CBF ½ optd

Checked:

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date: