Académique Documents
Professionnel Documents
Culture Documents
Author:
Dipl.- Ing. (FH) Alexander Muth (VDE) / (VGB)
Editor:
Dr.-Ing. Udo Drechsler
Design Concept:
Sarah Schulze
Images:
Martin Vehma
Publisher:
SAREX Communications
www.electrical-engineering.academy info@electrical-engineering.academy
The Toolbox
by Alexander Muth
www.electrical-engineering.academy
Table of Contents
Preface S. 5
Chapter 3 VT-Test S. 38
Chapter 5 Index S. 64
www.electrical-engineering.academy
Preface
Preface
Heartfelt Welcome!
This freee e-book is the plug’n’play bible for everyone, who wants to bene-
fit of years of practical experience, when it comes to the commissioning of
current- and voltage transformers.
Our Tool Box contains all our knowledge about the essential issues about
commissioning current- and voltage transformers. We explain all the
elementary tests of current- and voltage transformers, the linking and
isolation elements between the primary measured values and the secondary
measuring signals processed in the protection system.
www.electrical-engineering.academy 5
Preface
After the successful start of our book „The Bible of Generator Protection
Engineering“ we decided to publish the Tool Box 100% for free. We return
something valuable and say thank you to all members of our community
proconplanet.com.
We hope that this “slightly unusual” text book will inspire you to pluck up
the courage and give you the confidence to take matters into your own
hands and discover for yourself the fun that is always to be had when
commissioning a protection system.
PS: As every individual is only as good as his, or her, team, I've decided to
use the first person plural form (“we”) throughout this manual.
Alexander Muth
www.electrical-engineering.academy 6
Safety Notice
Failure to observe the following points can result in death, serious injury
or material damage!
Hazardous voltages may be present when carrying out the tests and checks
described in this manual. The safety rules and regulations regarding
electrical systems must be strictly observed at all times. The generator must
always be shut down when working on the primary system; appropriate
grounding and short-circuiting facilities are to be provided at the respective
workplaces. When carrying out a primary check on a turbine set, take care
to ensure that no overheating of the turbine occurs.
The work described in this manual may only be carried out by qualified
personnel, who must be conversant with the relevant safety regulations and
safety measures as well as the warnings in the manuals provided by the
suppliers of the various components. The contents of this manual must
not construed as work instructions. All statements in this manual must
www.electrical-engineering.academy 7
be carefully considered in light of the safety rules and regulations. The
information presented in this manual does not claim to be complete.
www.electrical-engineering.academy 8
“I’ve never made a mistake.
I’ve only learned from experience.”
Thomas A. Edison
www.electrical-engineering.academy 9
Chapter 1 - CT-Priliminary Test
✮ Insulation test
✮ Wiring check
✮ Measurement of rated burden
www.electrical-engineering.academy 11
Chapter 1 - CT-Priliminary Test
Firstly, we decide which terminal block to use for our tests in the direction
of the protection devices or transducers. The obvious candidates in this
case are the terminal blocks in the transformer terminal box or on-site
control cubicle. It's always good to use an accessible transformer terminal
board, as the closer we are to the transformer the better. These terminals
are then slid open and short-circuited on the transformer side.
Insulation Test
To protect the device and prevent the measuring circuit influencing our
results, we disconnect the wires of the current transformer circuit on the
corresponding field device and screen them with insulating sleeves up to 1
kV.
www.electrical-engineering.academy 12
Chapter 1 - CT-Priliminary Test
Wiring Check
With the help of a suitable secondary testing device, we inject a
symmetrical three-phase system with differing amplitudes in the direction
of the field device. This enables us to make a phase-selective assignment.
Choosing the test values shown below permits “metrological labeling” of
the phases:
The test values do not need to be any higher, as we need to keep an eye on
the pickup thresholds of connected protection devices. Ideally, a current of
0.1 A*√3 / 150° (173 mA) will be measured in the outgoing conductor.
www.electrical-engineering.academy 13
Chapter 1 - CT-Priliminary Test
Another good tip is to inject the test values using a modern testing device
from Omicron©. Using CPol-Tools© enables the current direction from the
first terminal block to be “checked in advance”, before the current test.
www.electrical-engineering.academy 14
Chapter 1 - CT-Priliminary Test
to the result, as digital relays usually have internal burdens of less than
100 mΩ.
Table 1: Secondary burden P / VA (function of nominal current, cross section of a single conductor)
www.electrical-engineering.academy 17
Chapter 1 - CT-Priliminary Test
The one-way wire length is used for the length l. The computed result
naturally corresponds to the secondary burden of the entire line loop,
including the incoming and outgoing conductors.
Once the wiring check has been completed, the terminals opened at the
start of the process are slid closed and the short circuit to the transformer
removed.
www.electrical-engineering.academy 18
Chapter 1 - CT-Priliminary Test
Now that we've checked the secondary loop wiring, we can move onto the
testing of the transformer.
✮ Visual check
✮ Measurement of winding resistance
✮ Insulation test
✮ Checking the nominal transformer power and rated accuracy limit factor
✮ Checking the winding direction (polarity)
✮ Checking the grounding
✮ Checking the assignment of the cores
✮ Measuring the ratio
www.electrical-engineering.academy 19
Chapter 1 - CT-Priliminary Test
Visual Check
Suggesting that a visual check be carried out sounds trivial. However, it's
difficult to believe just how many of the possible faults can be detected
simply by looking. Most of them are indeed “blindingly obvious”. So it's
always worth starting by having a look at the transformer and the rating
plate. Take a moment to check and make a note of the following
transformer parameters, as they're important:
- Transformer type
- Rated ratio
- Accuracy class
- Nominal accuracy limit factor
- Nominal power
- Load rating
www.electrical-engineering.academy 20
Chapter 1 - CT-Priliminary Test
- Mounting direction
- Grounding
- Serial number
In addition, the transformer and the primary terminals must not display
any visible damage, dirtiness or corrosion.
As it's important to know what the labels on the current transformer mean,
we've used a couple of examples here to explain them.
www.electrical-engineering.academy 21
Chapter 1 - CT-Priliminary Test
Insulation Test
Before starting the test, we need to ensure that the terminals in the
direction of the protection are slid open or that the wires are disconnected.
We then measure all the phase-to-phase and phase-to-ground loops from
the first accessible terminal block in the direction of the transformer. A
test voltage of 2.5 kV DC is used. To comply with DIN VDE and the
Austrian ÖNORM standard, the measured insulation resistance should be
≥ 1 MΩ. When the test is finished we can re-establish the connection to
the field device.
www.electrical-engineering.academy 24
Chapter 1 - CT-Priliminary Test
www.electrical-engineering.academy 25
Chapter 1 - CT-Priliminary Test
90"
80"
70"
10 %
60" UKnie
50"
40"
50 %
30"
20"
10"
0"
0" 50" 100" 150" 200" 250"
www.electrical-engineering.academy 26
Chapter 1 - CT-Priliminary Test
Computations are carried out to check that the following conditions relating
to the transformer nominal power and overcurrent factor are satisfied:
P ≥ Pn (1-2)
⎛ 1,25 ⋅U Knie ⎞
P = In ⎜ − Ri ⋅ I n ⎟ (1-3)
⎝ nn ⎠
P - calculated transformer power (measurement based) [ VA ]
Pn - transformer nominal power [ VA ]
n - calculated accuracy limit factor (measurement based)
nn - nominal accuracy limit factor
I n - secondary nominal transformer current [ A ]
Ri - measured winding resistance [ Ω ]
U Knee - identified knee point voltage [V ] 27
Chapter 1 - CT-Priliminary Test
n ≥ nn (1-4)
1,25 ⋅U Knee ⋅ I n
n=
( Pn + Ri ⋅ I n2 )
(1-5)
The mysterious factor of 1.25 is there to allow for the fact that the
underlying saturation voltage for both equations always refers to the total
error of the current and not just to the rise in the magnetization
characteristic. This limit-EMF is in fact about 25 % higher than the
measured knee point voltage.
Figure 4: Polarity
www.electrical-engineering.academy 29
Chapter 1 - CT-Priliminary Test
www.electrical-engineering.academy 30
Chapter 1 - CT-Priliminary Test
As soon as the primary current starts to flow, we short circuit all the cores
in turn using a short-circuit bridge and check that in each case the
measured values collapse at the expected metering points of our protection
and measuring devices. This approach is much more user-friendly in the
case of digital field devices, as we can read the operating measurement
values directly off their displays. Otherwise there's no harm in reverting to
the good old clamp meter and its faithful companion, the multimeter.
www.electrical-engineering.academy 31
Chapter 1 - CT-Priliminary Test
www.electrical-engineering.academy 32
Chapter 1 - CT-Priliminary Test
After all the relevant tests of the transformer circuits have been completed,
we must check once again that the terminals on all terminal blocks and all
the connected cores are secure. It's important not to forget the good old-
fashioned “pull test”.
www.electrical-engineering.academy 33
„ Quality is much better than quantity.
One home run is much better than two doubles. “
Steve Jobs
www.electrical-engineering.academy 34
Chapter 2 - CT-Primary Test
Ct’s of big power units can only get testet during a primary current test
with generator current. The detailed way of a primary current test is
described step by step in Chapter 8 of our book „The Bible of Generator
Protection Engineering“.
outside of the protection zone. Now we apply the 400 V rotating field of a
low-voltage supply, to the three phases on the hi-voltage side of the
transformer to be tested. The current flowing through the short-circuit
impedance of the transformer is used for the investigation of magnitudes,
pointers as well as the diff- and stab-values of differential protection
functions.
uk% - short-circuit-voltage
100% I n _OS In_OS - rated current HV
I TEST = ⋅ ⋅U TEST Un_OS - rated voltage HV
u k % U n _OS
UTest - test voltage (e.g. 400 V)
(2-1)
www.electrical-engineering.academy 36
Chapter 2 - CT-Primary Test
In the event that the 400 V test can not be carried out from the socket, a
suitable 3-phase transformer is helpful.
www.electrical-engineering.academy 37
Chapter 3 - VT-Test
Chapter 3 - VT-Test
The commissioning of voltage transformers is normally a much speedier
process than that of current transformers. That doesn't mean to say we can
be any less cautious; short-circuited or overburdened secondary circuits
must be avoided at all costs. This is particularly critical in the case of
voltage transformers that supply synchronizing relays. Unimaginable forces
would be set free if incorrect synchronization was carried out in phase
opposition. The extent of the damage to the primary system would be far
more extensive than anything a bit of sticking plaster could fix.
www.electrical-engineering.academy 38
Chapter 3 - VT-Test
and provide the base measurement for detecting a ground fault. The
following test methods refer explicitly to these single-pole transformers.
Preliminary Check
The preliminary check of the voltage transformers comprises 7 steps:
✮ Visual check
✮ Checking the grounding
✮ Insulation test of secondary loop wiring
✮ Checking the wiring of the star winding
www.electrical-engineering.academy 39
Chapter 3 - VT-Test
Visual Check
We apply the same procedure here as with the current transformer: First,
have a good look at the transformer and its rating plate. We compare the
transformer parameters listed below with the project values and enter them
in a report:
www.electrical-engineering.academy 40
Chapter 3 - VT-Test
In addition, the transformer and the primary terminals must not display
any visible damage, dirtiness or corrosion.
There's only one way of connecting the grounds, and it's shown in the
following diagram, so don't try any other method:
www.electrical-engineering.academy 41
Chapter 3 - VT-Test
We do this by sliding the terminals open or removing the cables from the
terminals in the on-site control cubicle. If we have to disconnect the cables,
they must be fitted with 1 kV insulating sleeves. As we are also checking
the secondary loop wiring of the delta winding, this will also have to be
slid open or disconnected.
www.electrical-engineering.academy 43
Chapter 3 - VT-Test
www.electrical-engineering.academy 44
Chapter 3 - VT-Test
www.electrical-engineering.academy 45
Chapter 3 - VT-Test
www.electrical-engineering.academy 46
Chapter 3 - VT-Test
www.electrical-engineering.academy 47
Chapter 3 - VT-Test
Modern 3-phase test tools can easily handle 300 V AC. The test voltages
shown in the table have stood the test of time:
Table 2: Test values for checking the wiring of the star winding
6 kV / √3 100 V / √3 60 120 V AC 2 V AC
A rotary field measuring device is employed to confirm that the rotary field
is OK. If no rotary field measuring device is available, or if the measuring
device we used did not detect the low secondary voltage, we can use the
negative sequence system detection (symmetrical components) of one of the
www.electrical-engineering.academy 49
Chapter 3 - VT-Test
connected digital protection devices to achieve our goal. If the rotary field
is correct, the negative sequence system must show 0 V.
The voltage across the Udelta windings of the delta winding is also
checked. This must measure about 0 V as well.
To check that the phases are allocated properly, we can now modify the
amplitudes of our 3 test voltages. We do this by increasing the amplitude of
P1 by about 10 % while at the same time reducing the voltage of P3 by
approx. 10 %. This change must of course be reflected in the secondary
phase-to-ground measuring loops.
Does everything look OK? If so, we can then move on to the broken delta
winding.
www.electrical-engineering.academy 50
Chapter 3 - VT-Test
www.electrical-engineering.academy 51
Chapter 3 - VT-Test
The test voltages that we recommend are shown in the following table.
When using these test voltages, the result of the measurement on the
broken delta winding must always be around 1.73 V:
Table 3: Test values for checking the wiring of the delta winding
then the only possible answer is a wiring error in the windings of the
secondary circuit. Finding this wiring error is what makes all this so much
fun.
Ratio Test
Before carrying out the ratio test, all work on the primary and secondary
parts of the plant must be complete and the plant must be ready for
operation.
A test voltage is injected phase by phase on the primary side of the voltage
transformer; a high voltage close to the primary nominal voltage of the
transformer is selected. We normally carry out this measurement using the
maximum available 2 kV AC and then extrapolate linearly to obtain the
secondary measured value (see table below). The transformer ratio is
computed phase by phase for the star and delta windings of the voltage
transformer.
www.electrical-engineering.academy 54
Chapter 3 - VT-Test
www.electrical-engineering.academy 56
Chapter 3 - VT-Test
To carry out the check, we first switch off all the voltage transformer
protection switches so as to disconnect the secondary circuit safely from the
primary part of the system.
The power is then given by the product of the currents and voltages and
must not exceed the nominal power of the transformer windings.
The diagram below shows the measuring configuration for the methods
described here:
www.electrical-engineering.academy 57
Chapter 3 - VT-Test
The preliminary tests of the voltage transformers are now complete. After
the system has been switched on, the verification of the secondary
parameters at the terminal blocks of the transformer circuits and the field
devices, as well as the measurement of the rotating field and, if necessary,
the phase-out by means of existing voltage transformers.
www.electrical-engineering.academy 59
„Try and fail,
but never fail to try.“
Jared Leto
www.electrical-engineering.academy 60
Chapter 4 - Test Checklists
www.electrical-engineering.academy 61
Chapter 4 - Test Checklists
www.electrical-engineering.academy 62
„ Life is precious. “
www.electrical-engineering.academy 63
Chapter 5 - Index
Chapter 5 - Index
A
accuracy class, current transformer 22
accuracy class, voltage transformer 40
assignment of the cores, current transformer test 30
B
British Standard 3938 25
C
checklists 60
CPC100©, Omicron© 28, 57
CPolTool©, Omicron© 14, 30
current test 31, 32, 35
current transformer 10, 35
current transformer test 10, 35
www.electrical-engineering.academy 64
Chapter 5 - Index
D
delta winding 38, 41, 43, 46, 51, 53, 54
differential protection 36
DIN VDE 12, 24, 46
G
grounding 30, 41
grounding, current transformer 30
grounding, voltage transformer 41
I
insulation resistance 12, 24
K
knee point voltage 25, 27, 28
L
limit-EMF 28
www.electrical-engineering.academy 65
Chapter 5 - Index
M
magnetization characteristic 25, 26, 28
measurement of rated burden, current transformer, CT 16
measurement of rated burden, current transformer, VT 56
measurment of rotating field 49, 59
measuring the ratio, current transformer 32
measuring winding resistance, current transformer 24
measuring winding resistance, voltage transformer 43, 45
N
negative sequence system 50
nominal accuracy limit factor 20, 22, 25, 27, 28, 29
O
Omicron© 14, 28, 30, 57
open-delta 50, 51, 52
overcurrent factor 20, 22, 25, 27, 28, 29
www.electrical-engineering.academy 66
Chapter 5 - Index
P
phase allocation 50
phase-angle error 29
polarity, current transformer 29
R
rating plate 16, 20, 23, 40
ratio 14, 20, 22, 23, 32
S
safety notice 7
safety measures 7
star winding 47, 48, 49, 53
synchronization 38
T
test check lists 61
test voltage 24, 36, 43, 47, 49, 53, 56
www.electrical-engineering.academy 67
Chapter 5 - Index
TPS 21
TPX 21
TPY 22, 23
TPZ 22, 23
transformation test 54
transformer nominal power, current transformer 24, 25
U
Udelta voltage 53
Udelta winding 50, 53
V
visual check, current transformer 20
visual check, voltage transformer 40
voltage test 39, 59
voltage transformer 38
voltage transformer test 38
voltage withstand test, current transformer 24
www.electrical-engineering.academy 68
Chapter 5 - Index
W
winding direction check, current transformer 29
winding resistance 24, 27
wiring check, current transformer 11, 13
wiring check, voltage transformer broken delta 51
wiring check, voltage transformer star winding 47
Z
zero sequence voltage 38
Tables
Table 1: Secondary burden f (nominal current and cross section) 17
Table 2: Star winding wiring check test values 49
Table 3: Delta winding wiring check test value 53
Table 4: Secondary measured values transformation test 2 kV AC 56
www.electrical-engineering.academy 69
Chapter 5 - Index
Figures
Figure 1: Wiring check test arrangement 15
Figure 2: Current transformer rating plate 23
Figure 3: Magnetization characteristic 26
Figure 4: Polarity 29
Figure 5: Grounding of voltage transformer 42
Figure 6: Insulation test 45
Figure 7: Star winding wiring check 48
Figure 8: Broken delta wiring check 52
Figure 9: Transformation test 55
Figure 10: Measurement of rated burden 58
www.electrical-engineering.academy 70
Literature
Literature
1 Herrmann, Hans-Joachim: Digitale Schutztechnik [Digital
Protection Engineering], VDE Verlag 1997
2 IEEE Power Engineering Society: Guide for AC Generator
Protection, IEEE Std C37.102™-2006
3 Weßnigk: Kraftwerkselektrotechnik [Electrical Engineering for
Power Plants], VDE Verlag 1993
4 Siemens: Handbuch Siprotec 7UM62, Multifunktionaler
Maschinenschutz [Siprotec 7UM62 Manual, Multifunctional
Machine Protection], Release 4.10.01
5 Clemens/Rothe: Schutztechnik in Elektroenergiesystemen
[Protection Engineering in Electrical Power Systems], VDE Verlag
1991
6 Ziegler, Gerhard: Digitaler Differentialschutz - Grundlagen und
Anwendung [Digital Differential Protection - Principles and
Application], Publicis Corporate Publishing 2004
7 British Standard 3938: Current Transformers, 1982
www.electrical-engineering.academy 71
Literature
www.electrical-engineering.academy 72
Many thanks to
Martin Vehma for the brilliant support in the production of the “technical
drawings” and figures, for proofreading the manuscript and the never-
ending stream of technical discussions.
Sarah Schulze for the loving support, innovative ideas and no end of
inspiration.
My family.
73
Dipl.-Ing. (FH) Alexander Muth
(born 1978) is founder and owner of
the network www.electrical-engineering.academy.
After obtaining his degree in electrical engineering at the
University of Lausitz in Senftenberg with a grade of “out-
standing” and receiving an award for his doctorate from the
VDE, he started work as an international commissioner
of electrical protection systems and released several publications.