TECHNICAL REPORT
I. SCOPE
This inspection covers the minimum requirements for piping standard conformance
base on Philippine Mechanical Engineering Code of the Philippines.
II. Objective
The objective is to certify the filling line for Air Banks are compliance in Philippine
Mechanical Code of the Philippines.
1007.0 Testing of
4. Verification of Air banks Air Banks have hydrostatic test and
Philippine Mechanical
hydrostatic certification. certificates.
Engineering Code
Confidential Page 2 of 3
TECHNICAL REPORT
V. Conclusion
Base on results filling line for Air Banks are conforms Philippines Mechanical Engineering
Code and it is safe to use for any filling purposes. Material used based on the standard 316
6mm seamless steel tubing and relief valves with holding pressure of 10,000 psi.