To determine the gradient of the drainage by calculated the reduced level for each
point of the drainage.
Taking the drainage level reading from the main gate of POLIMAS until drainage
near the Plastic Workshop.
±5√6 = 0.012
Correction
0.111
= 0.0185 𝑝𝑒𝑟 𝑠𝑡𝑎𝑡𝑖𝑜𝑛
6
Conclusion
For this traversing method, we used angle and distance (Total Station Survey) and for the traverse
type we has a loop traverse which means it is geometrically closed and mathematically closed. The
class for our traverse is class 2 based on our traverse. We used total station to measure angle at point
1,2,3,4,5 and 6 which is in form of closed loop traverse . We encountered an error in closed traverse
which caused by numerical precision or measurement error . What we read was 184°0’55” but the
bearing which supposed to be read was 183°59’55” , so the correction for each station is 11’5” to get
the same reading. In a traverse, the summation of all departures and latitudes of each of its sides
should always be equal to zero. The difference in latitude was 0.03 while the difference in departure
was 0.173. After making calculation for correction in Latitude and Departure we achieve the
summation of the latitude was 0.001 while departure was 0.000.
Reference
W Schofield, M. B. (14 Feb 2007). Engineering Surveying, Sixth Edition. Mishawaka: Taylor
& Francis.
Frank Bell. (30 Nov 2007). Surveying and Setting Out Procedures. The University of
Michigan: Avebury
Basil George Grenville Manton. (15 May 2009). Highway Surveying and Setting Out. The
University of Michigan : E. Arnold.
Basak. (1 Oct 1994). Surveying and Levelling: Tata McGraw-Hill Education.
S. S. Bhavikatti. (11 Mar 2010). Surveying and Levelling: I. K. International Pvt Ltd, 2010.