1) Tools / Fixtures
2) Procedures
2.1) Prepare the Permit to Work (PTW) and attached JHA for approval by Approved
Authority (OIM) before start the work.
2.2) Perform buddy system to use ladder during take the reading.
2.3) After switched ON the system, let the system run for at least 20 minutes before
taken the data.
2.4) Measure air flow using thermal anemometer (hot wire) in the supply diffuser.
Make sure locate 6-8 point in the supply diffuser for average air flow data.
Formula for air flow rate (Q).
2.5) Record the data air flow for each air supply diffuser in CFM unit.
2.6) Housekeeping.
1) Tools / Fixtures
1.1) Ladder
1.2) Balometer
2) Procedure
2.1) . Prepare the Permit to Work (PTW) and attached JHA for approval by Approved
Authority (OIM) before start the work.
2.2) Perform buddy system to use ladder during take the reading.
d. Insert the second pole into the pole mount on the opposite side of the base.
e. Repeat step 3 for the second support pole.
f. Repeat step 4 and 5 for the remaining two support pole.
2.7) Flow measurement using capture hood
1) Tools / Fixtures
1.2) Multimeter
1.3) Manometer
2) Procedures
2.1) Prepare the Permit to Work (PTW) and attached JHA for approval by Approved
Authority (OIM) before start the work.
2.2) Before commencing job, unit must be disconnected supply power by using “LOTO”
method and must do by platform authorized electrician.
2.4) Clean the fan blades to remove dirt and foreign materials.
2.5) Check and ensure motor mounting bolts are properly tightened.
2.7) Check the V-belt condition. Ensure belt tension and alignment are correct (JMS
2.2.2.18).
2.9) Lubricate motor bearing and fan bearing if grease nipple is available (JMS 2.2.2.6)
2.10) Check and ensure all cabling termination are not loose.
2.11) Visual inspection to ensure the stability function of Fan and Motor
2.12) Perform de-isolate power supply remove “LOTO” method and must do by a platform
authorized electrician.
2.15) Housekeeping.
3) Record data pressurization procedures
3.1) Prepare the Permit to Work (PTW) and attached JHA for approval by Approved
Authority (OIM) before start the work.
3.2) Start-up instrument
3.3) Zeroing the manometer
i. Manometer is equipped with both a gauge and differential pressure sensor,
allowing for simultaneous measurement and display of high-side gauge and
deferential pressure. The gauge and differential pressure sensors are zeroed
independently of one another.
ii. To measure most accurate gauge pressure measurement, the gauge pressure
sensor should be zeroed prior to taking readings on each new system. Gauge
pressure sensor is zeroed as follow:
1. Enter the main menu by pressing the ENTER key.
2. Select zero-gauge pressure.
3. Follow the on-screen instruction to complete the gauge pressure
sensor zeroing process.
4. Allow the manometer to stand undisturbed for five second until the zero-
gauge pressure sensor function has completed
3.4) Zeroing the differential pressure sensor
i. To ensure the most accurate differential pressure measurement and calculate
flow values, differential pressure sensor should be zeroed prior to taking
reading on each new system. The differential pressure sensor is zeroed as
follows:
1. Go to the measurement system
2. Turn the valve handle on the manometer to bypass position.
3. The instrument will automatically zero differential pressure sensor.
Follow the on-screen instruction and return the knob to measure once
this is done.
3.5) Connect the manometer to the test point
i. Attaching the hose to manometer
ii. Bleeding the entrained ai
3.6) Performing pressure measurement
i. Accessing the pressure measurement screen