CONVEYOR BELT
OF LIME PLANT
FORMAT NO: EESL (H).PRA.DM.025.F01
Page 1
ESSAR STEEL (HAZIRA) LIMITED
5.0 MT INTEGRATED STEEEL PLANT
ESSAR STEEL
(HAZIRA)
LIMITED TECHNICAL SPECIFICATION FOR
ESSAR ENGINERING
CONVEYOR BELT OF
SERVICES LTD -
LIME PLANT (KILN IV) HAZIRA
TS NO :- 1001191100TSP27H063 (R-0)
CONTENTS
Page
Chapter No. Description
No.
1 GENERAL INFORMATION 4
2 SCOPE OF WORK, BATTERY LIMITS & EXCLUSIONS 5
3 TECHNICAL SPECIFICATION 6
4 INSPECTION & TESTING 7
5 HSE REQUIRMENT 8
6 DELIVERY 9
7 PAINTING 10
8 WORKMANSHIP & PERFORMANCE GUARANTEE 11
9 SPECIAL INSTRUCTIONS TO THE TENDERER 12
DOCUMENTS TO BE SUPPLIED BY TENDERER WITH
10 OFFER 13
ANNEXURES
I SITE CONDITIONS 14
II FORMAT FOR DEVIATION FROM TENDER DOCUMENT 15
QUESTIONNAIRE TO BE FILLED IN AND SUBMITTED
III WITH OFFER 16
IV OVERALL SUPPLY & IMPLEMENTATION SCHEDULE 17
V BILL OF QUANTITY 18
VI QUALITY ASSURANCE PLAN 19
VII TECHNICAL DATA SHEETS 20
Confidential
Chapter 01
01 GENERAL INFORMATION
ESSAR Steel (Hazira) Ltd. is setting up 5.0 MTPA integrated steel plant at
Hazira, Surat, close to the existing ESSAR steel plant.
ESSAR Steels (Hazira) Ltd. uses the Corex technology for making of hot
metal.
Chapter 02
02.02 The scope of work shall stand supplement by such details as are given in the
specification or purchase order / contract or general specifications..
Confidential
Chapter 03
03 TECHNICAL SPECIFICATION.
Chapter 04
04 INSPECTION & TESTING
ESHL reserves the right to verify the quality program and entire product
characteristics during manufacturing to ensure the intended and specified
quality of the product.
Confidential
Chapter 05
05 HSE REQUIREMENT
Vendor shall ensure that all the HSE related issues are taken care in
equipment design and calculation. Vendor shall be responsible for
compliance with all the statutory requirements.
Confidential
Chapter 06
06 DELIVERY
06.01 The delivery of all the equipment covered under this specification shall be
F.O.R. M/s. ESSAR Steel (Hazira) Ltd, site stores at Hazira and as per the
address and delivery schedule to suit commissioning of plant within 6 months
from the date of placement of order.
06.02 Unless requested by Purchaser, supplier shall dispatch equipment with all its
attachments, parts, components, spares, documents etc as a single lot with
logical identification of packing.
06.03 All equipment shall be packed properly for prevention of damage during
transit and deterioration during storage.
Confidential
Chapter 07
07 PAINTING
Since conveyor belt does not required any painting, painting is not applicable.
Confidential
Chapter 08
08 WORKMANSHIP & PERFORMANCE GUARANTEE
08.01 The material used shall be new and best of its kind available and shall
conform to relevant latest Indian and international standards.
08.02 The warrantee shall cover faulty design / material / workmanship. All
rectifications or replacement under the warrantee shall be done by the
supplier free of cost.
08.04 The supplier shall warrantee for satisfactory performance of the facilities for a
period of 18 months from the date of receipt at site by the purchaser or 12
months from the date of commissioning whichever is earlier.
Confidential
Chapter 09
09 SPECIAL INSTRUCTIONS TO TENDERER.
09.01 The vendor shall design the equipment considering the "site conditions".
09.02 Metric system shall be followed and English shall be the language of all
communication.
09.03 This specification is issued for manufacture and supply of conveyor belt.
Confidential
Chapter 10
10 Documents to be supplied by the tenderer with offer
10.04 Catalogues / leaflets for all equipment including bought out items. Details of
bought out items with makes shall be given separately.
10.05 The deviation list filled in and submitted by the tenderer as per annexure: II.
10.06 The questionnaire filled in and submitted by the tenderer as per annexure: III.
Annexure I
SITE CONDITIONS
Temperature
Rainfall
Wind
Predominant wind Direction : South to West
Avg. speed : 12.2 Km/h
Confidential
Annexure II
FORMAT FOR DEVIATIONS FROM TENDERER DOCUMENT
The Tenderer hereby certifies that the above mentioned are the only deviations
from the tender documents.
Signature :
Name :
Designation :
Company seal :
Confidential
Annexure III
QUESTIONAIRE TO BE FILLED & SUBMITTED BY THE TENDERER
1) General
i) Tenderer's name and address.
ii) Quotation number and date.
iii) Total estimated transporting weight of items offered by tenderer in
tabular form.
iv) Weight and dimension of the heaviest single package.
v) Special transport requirement.
vi) Special storage requirement.
vii) Available manufacturing facility.
viii) Available spare capacity.
2) Technical Data
Sr.No DESCRIPTION
1 Belt Length (m) :
2 Cover Thickness :
3 Cover Grade :
4 Breaker ply bet. Cover & carcass for all belting :
5 Skim coating :
6 rot & mildew resistance :
7 Trough ability :
8 Abrasion of Cover Rubber for EP belt :
9 Hardness of Cover Rubber for EP belt :
10 Roll weight :
11 Belt length in each roll :
12 :
Confidential
Vulcanizing kit
13. Belt Wt. Kg/m :
Annexure IV
OVERALL SUPPLY & IMPLEMENTATION SCHEDULE
Annexure V
Bill of Quantity.
Annexure V
QUALITY ASSURANCE PLAN (QAP)
01. QAP shall be prepared and furnished by supplier for all components in attached
Essar’s format for approval.
02. Inspection and test requirements shall be decided with due consideration of
factors like safety, duty cycle, operating conditions, equipment life, environment
conditions, place of installation and statutory regulations, as applicable for a
particular equipment.
03. QAP shall clearly indicate the followings through use of codes in the appropriate
columns:
i) Range of inspection & tests to be carried out by manufacturer and cross
checked during manufacturing of equipment from raw materials to finishing
stage.
ii) Suggestive check / hold points for ESHL inspection and witnessing of tests
during manufacturing and final product inspection.
iii) Details of test certificates, internal inspection reports and calibration
certificates to be furnished by supplier / manufacturer to ESHL.
iv) Inspection documents to be furnished by supplier / manufacturers to ESHL
for reference during inspection along with acceptable norms as per codes /
regulations.
Test Certificates and Documents
For each of the items being manufactured, following test certificates and documents
in requisite copies including original shall be submitted to inspection agency. All test
certificates must be endorsed by the manufactures and contractor with linkage to
project, purchase order and acceptance criteria.
i) Details of stage wise inspection