• Pile sleeve should be checked for leaks (Positive Pressure- Bulging Diaphragm).
• Inspect the installation riggings and aids are clear from any structural obstruction.
GROUTING SYSTEM
• FABRICATOR to inspect all piping routes, to grout stations and pipe spacing should
be no greater than 2m (2000mm).
• FABRICATOR to confirm the positions and number of supports between the grouting lines
3 which is 0.15m (150mm) apart and measured from the weld toe.
• Check the grout stations to see if the grouting lines are positioned properly and the color
coding matches the AFC drawings no: xxxxxxxxxx. The grout connection station should be
accessible by the jacket seadeck walkway.