Vous êtes sur la page 1sur 15

Company Name:paMcon

Qty Of Excavation
S.no Descrption No Length (m) Breadth(m) Height(m) Qty (Cu.m) Total Qty (Cu.m) Remarks
1 Wall No 1 2 15.675 0.3 0.6 5.643
2 Wall no 2 4 7.275 0.3 0.6 5.238
3 Wall no 3 2 1.725 0.3 0.6 0.621
4 WaLL NO 4 1 3.525 0.3 0.6 0.6345
5 Wall no 5 1 4.125 0.3 0.6 0.7425
6 Wall No 6 1 3.45 0.3 0.6 0.621
7 Wall No 7 1 4.35 0.3 0.6 0.783
8 Wall No 8 1 1.725 0.3 0.6 0.3105
9 Wall No 9 2 3.525 0.3 0.6 1.269

15.8625
Company Name:paMcon

Qty Of P.C.C
S.no Descrption No Length (m) Breadth(m) Thickness( Qty (Cu.m) Total Qty ( Remarks
1 Wall No 1 2 15.675 0.3 0.1 0.9405
2 Wall no 2 4 7.275 0.3 0.1 0.873
3 Wall no 3 2 1.725 0.3 0.1 0.1035
4 WaLL NO 4 1 3.525 0.3 0.1 0.10575
5 Wall no 5 1 4.125 0.3 0.1 0.12375
6 Wall No 6 1 3.45 0.3 0.1 0.1035
7 Wall No 7 1 4.35 0.3 0.1 0.1305
8 Wall No 8 1 1.725 0.3 0.1 0.05175
9 Wall No 9 2 3.525 0.3 0.1 0.2115

2.64375
Company Name:paMcon

Qty Of Brick Work In Foundation


S.no Descrption No Length (m) Breadth(m) Height(m) Qty (Cu.m) Total Qty ( Remarks
1 Wall No 1 2 15.6 0.225 0.5 3.51
2 Wall no 2 4 7.35 0.225 0.5 3.3075
3 Wall no 3 2 1.8 0.225 0.5 0.405
4 WaLL NO 4 1 3.6 0.225 0.5 0.405
5 Wall no 5 1 4.05 0.225 0.5 0.455625
6 Wall No 6 1 3.525 0.225 0.5 0.396563
7 Wall No 7 1 4.425 0.225 0.5 0.497813
8 Wall No 8 1 1.8 0.225 0.5 0.2025
9 Wall No 9 2 3.6 0.225 0.5 0.81
Deduction
C1 -14 0.225 0.225 0.5 -0.354375
C2 -2 0.225 0.15 0.5 -0.03375

9.601875
Company Name:paMcon

Qty Of Columns Necks


S.no Descrption No Length (m) Breadth(m Height(m) Qty (Cu.m) Total Qty ( Remarks
C1 14 0.225 0.225 0.5 0.354375
C2 2 0.225 0.15 0.5 0.03375

0.388125
Company Name:paMcon

Qty Of Conc Beam On Foundation


S.no Descrption No Length (m) Breadth(m) Thickness(m) Qty (Cu.m) Total Qty ( Remarks
1 Wall No 1 2 15.6 0.225 0.225 1.5795
2 Wall no 2 4 7.35 0.225 0.225 1.488375
3 Wall no 3 2 1.8 0.225 0.225 0.18225
4 WaLL NO 4 1 3.6 0.225 0.225 0.18225
5 Wall no 5 1 4.05 0.225 0.225 0.205031
6 Wall No 6 1 3.525 0.225 0.225 0.178453
7 Wall No 7 1 4.425 0.225 0.225 0.224016
8 Wall No 8 1 1.8 0.225 0.225 0.091125
9 Wall No 9 2 3.6 0.225 0.225 0.3645

4.4955
Company Name:paMcon

Qty Of Brick Work In Superstructure


S.no Descrption No Length (m) Breadth(m) Height(m) Qty (Cu.m) Total Qty ( Remarks
1 Wall No 1 2 15.6 0.225 2.775 19.4805
2 Wall no 2 3 7.35 0.225 2.775 13.76747
Wall No 2A 1 3.91 0.225 1.5
3 Wall no 3 2 1.8 0.225 2.775 2.24775
4 WaLL NO 4 1 3.6 0.225 2.775 2.24775
5 Wall no 5 1 4.05 0.225 2.775 2.528719
6 Wall No 6 1 3.525 0.225 2.775 2.200922
7 Wall No 7 1 4.425 0.225 2.775 2.762859
8 Wall No 8 1 1.8 0.225 2.775 1.123875
9 Wall No 9 2 3.6 0.225 2.775 4.4955
Deductions
D2 -1 1.2 0.225 2.1 -0.567
D3 -5 0.9 0.225 2.1 -2.12625
D4 -3 0.75 0.225 2.1 -1.063125
W1 -1 1.5 0.225 1.2 -0.405
W2 -1 1.2 0.225 1.2 -0.324
W3 -1 0.9 0.225 1.2 -0.243
V1 -1 0.6 0.225 0.6 -0.081
C1 -12 0.225 0.225 2.775 -1.685813
Beams
Wall No 1 -2 15.6 0.225 0.15 -1.053
Wall no 2 -3 7.35 0.225 0.15 -0.744188
Wall no 3 -2 1.8 0.225 0.15 -0.1215
WaLL NO 4 -1 3.6 0.225 0.15 -0.1215
Wall no 5 -1 4.05 0.225 0.15 -0.136688
Wall No 6 -1 3.525 0.225 0.15 -0.118969
Wall No 7 -1 4.425 0.225 0.15 -0.149344
Wall No 8 -1 1.8 0.225 0.15 -0.06075
Wall No 9 -2 3.6 0.225 0.15 -0.243

41.61122
Company Name:paMcon

Qty Of Columns Necks


S.no Descrption No Length (m) Breadth(m Height(m) Qty (Cu.m) Total Qty (Cu.m) Remarks
C1 12 0.225 0.225 2.625 1.594688
C1 2 0.225 0.225 2.775 0.280969
C2 2 0.225 0.15 2.775 0.187313

2.06296875
Company Name:paMcon

Qty Of Brick In Parapet Wall


S.no Descrption No Length (m) Breadth(m Height(m) Qty (Cu.m) Total Qty (Cu.m) Remarks
1 Parapet Wall 1 46.87 0.1125 0.9 4.7455875
2 Mumty(Wall no 1) 2 2.175 0.1125 2.4 1.1745
Wall No 2 1 2.775 0.1125 2.4 0.74925
Deductions -1 0.75 0.1125 2.1 -0.1771875
Wall no 3 1 3 0.225 2.4 1.62

8.11215
Barbending Schedule Sheet

TOTAL LENGTH IN METERS

S.no Description Of Item Φ of bar Spacing No of items No of bars T.NO C/L of bar T.L 8mm 10mm 12mm Shapes

1 Column Necks

C1 (Longitudnal Bars) 12mm 14 4 56 1.27 71.12 71.12

Stirrups 8mm 250 14 6 84 0.9 75.6 75.6

C2 (Longitudnal Bars) 10mm 2 4 8 1.27 10.16 10.16

Stirrups 8mm 250 2 6 12 0.65 7.8 7.8

Steel In Foundation Beam

Beam On Wall No 1 12mm 2 4 8 15.95 127.6 127.6

Stirrups 8mm 250 2 64 128 1.27 162.56 162.56

Beam On Wall No 2 12mm 4 4 16 7.75 124 124

Stirrups 8mm 250 4 33 132 1.27 167.64 167.64

Steel For Slab

Main Bar 12mm 150 1 69.5 69.5 7.67 533.065 533.065

Main Bar 2 12mm 150 1 26.34 26.34 5.44 143.2896 143.2896

Main Bar 3 12mm 150 1 12.63 12.63 7.67 96.8721 96.8721

Distribution Bars 1 10mm 250 1 10 10 10.64 106.4 106.4

Distribution Bars 2 10mm 250 1 23 23 15.7 361.1 361.1

Distribution Bar 3 10mm 250 1 9.5 9.5 1.95 18.525 18.525

Total Length of bars 413.6 496.185 1095.947

Total Weight 163.2343 305.9811 973.2016

TOTAL Weight in ton 0.163234 0.305981 0.973202


Company Name:paMcon

Qty Of Internal And Ext Plaster


S.no Descrption No Length (m) Height(m) Thickness(m) Qty (Sq.m) Qty (Cu.m) Total Qty (Sq.m) Total Qty (Cu.m) Remarks
1 Toilet 2 7.8 0.9 0.012 14.04 0.16848
Deductions
V1 -1 0.6 0.6 0.012 -0.36 -0.00432
2 Open Area 1 9 3 0.012 27 0.324
Deductions
D4 -2 0.75 2.1 0.012 -3.15 -0.0378
W3 -1 0.9 1.2 0.012 -1.08 -0.01296
V1 -1 0.6 0.6 0.012 -0.36 -0.00432
3 Rooms 2 14.325 3 0.012 85.95 1.0314
Deductions
D4 -2 0.75 2.1 0.012 -3.15 -0.0378
W3 -1 0.9 1.2 0.012 -1.08 -0.01296
D3 -2 0.9 2.1 0.012 -3.78 -0.04536
4 TV Lounge 1 19.5 3 0.012 58.5 0.702
Deductions
D3 -4 0.9 2.1 0.012 -7.56 -0.09072
D2 -1 1.2 2.1 0.012 -2.52 -0.03024
Outer Wall 1 4.05 1.5 0.012 6.075 0.0729
Ceilling Plaster
Toilet 2 A=3.78 0.01 7.56 0.0756
External Plaster
Long Wall 1 15.6 4 0.014 62.4 0.8736

238.485 2.9715
Company Name:paMcon

Qty Of Tiles
S.no Descrption No Length (m) Breadth(m) Height(m) Qty (Sq.m) Total Qty (Sq.m) Remarks
1 Toilets
Floor Tiles 2 A=3.95 7.9
Wall Tiles 2 7.8 2.1 32.76
Deductions
D4 -2 0.75 2.1 -3.15

37.51
Company Name:paMcon

Qty Of Marble
S.no Descrption No Length (m) Breadth(m) Height(m) Qty (Sq.m) Total Qty (Sq.m) Remarks
1 Opening 1 A=4.86 4.86
2 Rooms 2 A=13.2 26.4
3 Store 1 A=3.44 3.44
4 Carporch and open area 1 A=22.5 22.5

57.2
Company Name:paMcon

Qty Of Skirting
S.no Descrption No Length (m) Qty (m) Total Qty (m) Remarks
1 Open Area 1 9 9
Deduction 0
D4 -2 0.75 -1.5
2 Rooms 2 14.325 28.65
D4 -2 0.75 -1.5
D3 -2 0.9 -1.8

32.85
Company Name:paMcon

Qty Of Internal And Ext Plaster


S.no Descrption No Length (m) Height(m) Qty (Sq.m) Total Qty (Sq.m) Remarks
1 Toilet 2 7.8 0.9 14.04
Deductions
V1 -1 0.6 0.6 -0.36
2 Open Area 1 9 2.8 25.2
Deductions
D4 -2 0.75 2.1 -3.15
W3 -1 0.9 1.2 -1.08
V1 -1 0.6 0.6 -0.36
3 Rooms 2 14.325 2.8 80.22
Deductions
D4 -2 0.75 2.1 -3.15
W3 -1 0.9 1.2 -1.08
D3 -2 0.9 2.1 -3.78
4 TV Lounge 1 19.5 2.8 54.6
Deductions
D3 -4 0.9 2.1 -7.56
D2 -1 1.2 2.1 -2.52
Outer Wall 1 4.05 1.3 5.265
Ceilling Plaster
Toilet 2 A=3.78 7.56
External Plaster
Long Wall 1 15.6 4 62.4

226.245
Material Statement
Ratio Steel(Tons)
Cement Sand Bajri Bricks Marble Skirting Tiles Paint Doors Windows Door Frames
S.no Description Of Item Area/Volume/ m.L C : S : B (Bags) (cu.m) (cu.m) (No) (sq.m) (m) (sq.m) (sq.m) Ø8 Ø10 Ø12 (No) (No) (No)
1 Excavation 15.8625
2 P.c.c 2.64375 1 : 4 : 8 8.95 1.25 2.51
3 B.W In FOUNDATION 9.601875 1 : 4 16.46 2.30 4800.938
4 Conc For Coloumn Necks 0.388125 1 : 2 : 4
5 Conc For Beam ON Foundation 4.50 1 : 2 : 4
6 Brick Work In S.S 41.61 1 : 4
7 Conc For Colm In S.S 2.06 1 : 2 : 4
8 Brick Work In Parapet wall 8.11215 1 : 5
9 Steel For Beams,Colmn,Slab 0.163234 0.305981 0.973202
10 Internal And External Plaster 2.97 1 : 5 17.97 3.14
11 Tiles 37.51 37.51
12 Marble 57.20 57.20
13 Skirting 32.85 32.85
14 Internal And External Painting 226.245 226.245
15 Doors
D4 3
16 Windows
W1 1