AKASH VERMA
75166007
MM SCHOOL OF ARCHITECTURE
MMU SADOPUR – AMBALA
IN PARTIAL FULFILLMENT OF THE REQUIREMENT FOR THE DEGREE OF
BACHELOR OF ARCHITECTURE
JULY 2019
SHRI PRATAB SINGH LIBRARY
MA ROAD SRINAGAR
I would like to thank the School of Architecture, M.M University, Sadopur, Ambala for giving me
the opportunity of doing this training, to gain practical experience and understand the demands of the
professional environment. I am thankful for the experience I’ve gained, which has given me
confidence, enhanced my professional skills and increased my level of competence in the practical
Architectural field.
I am highly grateful to the architect of the building AR. SANJU BOSE (S BOSE LANDSCAPE
CONSULTANTS) for , valuable information and immense support. His guidance has given me
immense help and encouragement in completing my training in the given duration. I respect him for
his understanding of the problems faced by the students, and his ability to solve them with ease.
I am also grateful to our principal– Ar. Aradhana Jindal and members of the department for their
support and guidance.
I take this opportunity to thank all of them, whose names have been inadvertently missed out, for
having rendered their assistance, no matter how little may be, during the completion of this project.
With Gratitude,
AKASH VERMA
B-Arch 7th Sem
Roll No.: 75166007
TABLE OF CONTENT
1. Introduction
• Name of the project and location
• Name of the architect
• Current status
• Type of project-Commercial /Residential/Educational etc.
2. Site Analysis
• Area of the site in acres (sqm)
• Site approach and major /minor roads abutting site
• Orientation of site
• Soil type
• Topography
• Location of site with key plan (Distances from Airport, Railway station and Bus stand)
• Site surroundings with major nearby landmarks
3. Built Form Analysis 4
• Super area of building
• Achieved Bye-laws (Ground Coverage, FAR, parking)
• Plans of all tower (2BHK & 3BHK)
• Structure system
• Materials used in interior and exterior of building
• Aesthetics
• Light and ventilation
4. Building Services
• Fire fighting
• Service core
• Vertical circulation (Lifts, Stair Cases, Escalators etc)
• Rainwater harvesting and rainwater disposal system
• Electrical services
• HVAC
• Sewerage disposal system
• Water Supply system
• Parking
Critical analysis of the building study is to be done keeping in mind the following aspects*:
Construction Space Energy Other
Area Function Aesthetics Services system utilization efficiency criteria
Building
Study
5. Critical Analysis
6. Conclusion
1. Introduction
1.1. The project is delivered successfully on time and offers wonderful 2 and 3 BHK apartments which are ready to move in.
Ace City has 11 towers which are built with supreme construction technology and specifications. The best part about
Ace City is its closeness to Express Highway, Delhi and proposed metro station making voyaging and networks a
considerable measure less demanding. The project also offers considerably easy connectivity from South and East Delhi.
1.2. Name of the project and location: Ace City, sec – 1, Greater Noida West(NCR)
1.3. Name of the Architect: AR. SANJU BOSE
1.4. Current status: Ready to move.
1.5. Type of project-Commercial /Residential/Educational etc.: Residential
2. Site Analysis
2.1 Area of the site in Acres: - 15.00 Acres, OPEN AREA:- (53%)
2.2 Site approach and major /minor roads abutting site: -
From Noida bus stand: -
1
2
3
4
5
6
3.6 Structure System:
External paint
Asian paints
Internal paint
Asian paints
Lifts
Thyssen krupp
Vitrified tiles in drawing/dining/bedrooms and kitchen.
Wooden textures tiles in master bedroom
Flooring
Granite stone
Door locks
Harrison
UPVC doors/windows
Kitchen
Toilet
European standard
PHOTO GALLERY
(INTERIOR)
3.8 Aesthetics: - The aesthetics of the building depict rich heritage as well as contemporary look
3.9 Light and ventilation: - Natural lighting and ventilation has been the main focus in the building.
4. CIRCULATION
4.1 Firefighting: - Two systems are installed in the building:
Foam based system .
Sprinkler system.
4.2 Service Core: - Two lifts and a staircase with Ramp have been provided in the Basement.
4.3 Vertical circulation (Lifts, Stair Cases, Escalators etc.): - Two lifts and a staircase is provided in the building.
4.4 Electrical services: - Both power and electrical layout is been given and executed properly in the towers.
4.5 HVAC- HVAC has been done in the building. Acoustic boards are used at some places, rest wooden boards are
used.
4.6 Sewerage disposal system: - Building sewerage gets disposed of to the main deep drain/sewer
4.7 Water Supply system: - Sump and Water pumps have been used on the site.
4.8 Parking: - Parking is a stilt & Basement parking.
5. Critical Analysis
Critical Analysis
Area Function Aesthetics Services Construction Space Energy Other Criteria
System Utilization Efficiency
Buildin Total RESIDENTIA .‘Floral Relief Services According to The space The Overall all
g Study Project L Panels’ are the is utilized building is the building
provided construction well. As it designed in is designed
Area: No. of Towers: Imported
in the systems the has a way that properly and
15.00 11 Towers from island building. building is a 11Tower, there is no the
Acres of Denpasar (Rainwater heavyweight the space is use of connection
No. of Floors: Bali is used in Harvesting constructed well artificial between the
Open 25 Floors the project. , STP were building, organised lighting in user and the
The entrance present. keeping in and proper the day functioning
Area: There was mind the space time and of the
53% 2560 Units gate is
only 1 durability, low division is there is building is
completely staircase maintenance, done proper well
. made up of used as good thermal keeping in natural performed.
stones fire mass which is mind the. ventilation Ace City has
mainly staircase in well suited for With 53% making it a 3 level
Dholpur and each the harsh of green an energy
security
tower. climate. area of 1 efficient
teakwood to system in
acres All building to
give the the spaces a large place from
project a rich are well extent. the
heritage as utilized entrance to
well as with parking and
contemporar minimal or
upto the
no
y look. lobbies.
discomfort
to the user Security
equipments
of HikVision
and CP Plus
have been
used which
shows no
amount of
compromise
in terms of
security of
its
residents.
6. Conclusion