WorkFace Planning Prerequisites

Document Number: COP-WFP-SPD-05-2013-v1

DOCUMENT VERSION

Revision Description Date

Rev. A Document imported to 2013 template 04 Mar 13

AUTHORSHIP AND APPROVALS

Originated By COAA WFP Committee 01 JAN 07 Signature

Reviewed By COAA WFP Committee 01 JAN 07 Signature

Approved By COAA WFP Committee 01 JAN 07 Signature

WFP Prerequisites.docx
Record of Revision

Revision Date Revision Description Originated By Reviewed By Approved By

Rev. 0 01 JAN 07 Original WFP COAA WFP COAA WFP COAA WFP
Prerequisites published Committee Committee Committee
Rev. A 04 MAR 13 WFP Prerequisites COAA WFP COAA WFP COAA WFP
document imported to Committee Committee Committee
COAA template 2013

Copyright and Disclaimer Information

COAA and respective logos are either registered trademarks or trademarks of Construction Owners
Association of Alberta in Canada and / or other countries. All other trademarks are the property of their
respective owners.

© 2013 COAA. All rights reserved.

WFP Prerequisites.docx
Contents
WORKFACE PLANNING PREREQUISITES ........................................................................................................ 1

THE OBJECTIVE .......................................................................................................................................... 1

BEGIN WITH THE END IN MIND ................................................................................................................ 1

CODING ..................................................................................................................................................... 1

CONTRACTING........................................................................................................................................... 2

ENGINEERING ............................................................................................................................................ 2

PROJECT TRACKING ................................................................................................................................... 2

WFP Prerequisites.docx
WFP-PRC-2013-105-A WFP Prerequisites
Document Number:Error! Reference source not found. WFP-PRC-2013-105-A
Revision: A

WORKFACE PLANNING PREREQUISITES

In order to implement WorkFace Planning there are a number of issues an organization needs to
consider, some of the major issues include:

THE OBJECTIVE

WorkFace Planning is a method to get the right things, to the right place, at the right time. Remember
this planning will occur; the only questions are when, by whom, and at what level of detail.

BEGIN WITH THE END IN MIND

 Systems drive commissioning and start-up


 Commissioning and start-up drive construction
 Construction drives engineering and procurement

Plan forward and prioritize (sequence) backward

CODING

A project is normally coded by area, and then at about 60% complete the focus changes to systems. In
WorkFace Planning both systems and area need to be identified as early as possible, ideally at the
start of engineering.

The company responsible for managing the project should specify the minimum information they
require the contractors to collect as they will be ultimately be responsible for integration of the
project. The information requirements should be clearly identified prior to the work being tendered
and included in the contract. This should not limit a contractor’s ability to collect additional
information as they need to ensure they have all the data necessary to manage the project.

WFP-PRC-2013-105-A WFP Prerequisites.docx Page 1 of 2


WFP-PRC-2013-105-A WFP Prerequisites
Document Number:Error! Reference source not found. WFP-PRC-2013-105-A
Revision: A

CONTRACTING

The nature of the contracting strategy (Lump sum, Cost Reimbursable, or Unit Rate) is irrelevant to
WorkFace Planning with the exception that in Lump Sum or Unit Rate the need to specify WorkFace
Planning as a contractual requirement is greater. This is because the contractors bid will be based on
their scope of work which will change if WorkFace Planning is added later, even though contractors
should see an overall cost reduction as a result of WorkFace Planning. In a cost reimbursable contract
the contractor is compensated for the WorkFace Planning related costs by the owner how will realize
the benefits of increased productivity.

ENGINEERING

The way in which the project is engineered will not change but the order of delivery of the
engineering documents will change. The engineering of the FIWP must be complete in order for the
packages to be finalized. This will require the construction to be involved earlier in the engineering
process and they will need to identify the path of construction in far more detail than is traditionally
done.

PROJECT TRACKING

FIWP are deliverable based and progress will need to be reported based on completed FIWP this will
require changes in project controls.

WFP-PRC-2013-105-A WFP Prerequisites.docx Page 2 of 2