Column1 Column2 Column3 Column4 Column5

NO PARTICULARS NO L B

Excavation for foundation in hard murum


removing the excavated material upto distance of
50 meteres beyond the building area and stacking
and spreading as directed, dewatering preparing
1 the bed for the foundation and necessory
backfilling, ramming, watering including shoring
and strutting etc.complete By Manual means with
lift upto 1.5m.

Earthwork in excavation in soft marum with "30m"


lead & 1.5m lift etc complete.
Septic tank 1 3 1.9
For soak pit upto 3m depth (π ÷ 4) ×(1.4²) = 3.2 m² 1 3.2

Soak pit lower portion


(π ÷ 4) × (1.4²) =1.54 m² 1 1.54

Providing and laying in situ cement concrete M-


10/ 1:3:6 of trap/ granite/ gniessmetal for
foundation and bedding including bailing-out
water manually formwork,compacting, covering
2 newly laid concrete by gunny bag, plastic or
tarpulin, curing etc.Complete. (wooden planks /
Shuttering will not be allowed. The shuttering
should beof waterproof playwood or tailor made
angle and steel plate)

P.C.C bed in cc (1:3:6)


Providing and laying
compacting curing etc.
complete.
Floor and foundation sloping floor 1 3 1.9

Avarage depth =
(10÷2) = 50 mm = 0.5 m 1 3 0.9

Providing machine manufactured 1st class burnt


brick mesonary with convential/I.S.Type bricks in
cement morter 1:6 in superstructuer for exposed
ornamental work including striking joints,racking
3 out joints, Watering and scaffolding
complete.Specification no.:As directed by engineer
in charge (general application-For exposed
ornamental brick work and not to be used for
plaster for exposed face.)

First class brickwork providing masonary


with bricks in cement mortor (1:6) in superstrure
for exposed ornamental work including skirting
joints, raking out joints, watering & scaffolding
complete.
Long mass
First step 2 2.6 0.3
Second step 2 2.4 0.2
Short mass
First step 2 0.9 0.3
Second step 2 0.9 0.2

4 Second class brickwork prouiding brickmasonary


in cement mortar (1:6) using second class bricks
in superstructure including skitring,joints,raking
out joints, watering & scaffolding
complete.
Long wall pit upper portion
(π×1.2) = 3.77 1 3.77 0.2
Lower portion
(π×1.2) = 3.77 1 3.77 0.2

5 Second class dry brickwork in soak pit


π×1.2 = 3.77 1 3.77 0.2

6 Precast R.C.C work finisheal smoath including


stees rainforcement roof couer slab on septic
tank 1 2.4 1.3
Roof cover slab on soak pit
(π ÷ 4) ×(1.4²) = 1.54 1 1.54

Bottle wall in septic tank 1 1 0.04

7 providing internal cement plaster 12 mm thick in


single coat in cement mortar (1:4) without neeru
finish to conreate or brick suarface ,in all positions
including scaffolding & curing complete. 2 2
2 0.9

8 Providing internal cement plaster "20mm" thick in


two cost in cement morter (1:4) without neeru
finish to conreate or brick suarface ,in all position
including scaffolding & curing complete. 1 2 0.9

9 "50mm" size brick aggregate outer side soak peet.


(π×1.55) =4.86 1 4.86 0.15
At bottom of soak pit
(π×4)×(1.10²) =1.21 1 1.21
10 Outer coarse sand
(π÷1.85) = 5.81 1 5.81 0.15

11 Providing & Fixing C.I steps for manhole, septic


tank including painting etc. complete. 4

12 Providing & making lead joints for "100mm"


diameter cast iron pipe line including lead and
testing etc. complete.
Inlet end from latrine to septic tank
Outer end from septic 1 3
Tank to soak pit 1 3.3

13 S.W tee"100mm"diameter with one leg of "40"cm 1

14 S.W bend "100mm" diameter. 1

15 "50mm" diameter C.I. Ventilating pipe. 1 2

16 "50mm" diameter C.I. cowl at top of Ventilating


pipe. 1

ABSTRACT SHEET

SR. NO. PARTICULARS QUANTITY UNIT RATE

1 Earthwork in excavation. 20.835 m³ 138


Earthwork in excavation in soft marum with "30m"
lead & 1.5m lift etc complete.
Septic tank
For soak pit upto 3m depth (π ÷ 4) ×(1.4²) = 3.2 m²
Soak pit lower portion
(π ÷ 4) × (1.4²) =1.54 m²

2 Cement concrete (1:3:6) in Fondation and Floor. 1.275 m³ 925


P.C.C bed in cc (1:3:6)
Providing and laying
compacting curing etc.
complete.
Floor and foundation sloping floor
Avarage depth =
(10÷2) = 50 mm = 0.5 m

3 First class brickwork 2.78 m³ 4761


First class brickwork providing masonary
with bricks in cement mortor (1:6) in superstrure
for exposed ornamental work including skirting
joints, raking out joints, watering & scaffolding
complete.

4 Second class brickwork 0.53 m³ 4551


Second class brickwork prouiding brickmasonary
in cement mortar (1:6) using second class bricks
in superstructure including skitring,joints,raking
out joints, watering & scaffolding
complete.
Long wall pit upper portion
(π×1.2) = 3.77
Lower portion
(π×1.2) = 3.77

5 Second class dry-brickwork 1.88 m³ 180


Second class dry brickwork in soak pit
π×1.2 = 3.77

6 Precast R.C.C work 0.367 m³ 900


Precast R.C.C work finisheal smoath including
stees rainforcement roof couer slab on septic
tank
Roof cover slab on soak pit
(π ÷ 4) ×(1.4²) = 1.54
Bottle wall in septic tank

7 "12mm" cement plaster 9.86 m³ 124


Providing internal cement plaster 12 mm thick in
single coat in cement mortar (1:4) without neeru
finish to conreate or brick suarface ,in all positions
including scaffolding & curing complete.

8 "20mm" cement plaster 1.8 m² 2.21


Providig internal cement plaster "20mm" thick in
two cost in cement morter (1:4) without neeru
finish to conreate or brick suarface ,in all position
including scaffolding & curing complete.

9 "50mm" brick aggregate 2 m³ 150


50mm size brick aggregate outer side soak peet.
(π×1.55) =4.86
At bottom of soak pit
(π×4)×(1.10²) =1.21

10 Coarse sand outer 2.18 m³ 110


Outer coarse sand
(π÷1.85) = 5.81
11 Iron foot step 4 No. 40
Providing & Fixing C.I steps for manhole, septic
tank including painting etc. complete.

12 "100mm" diameter S.W. pipe 6.3 m 45


Providing & making lead joints for "100mm"
diameter cast iron pipe line including lead and
testing etc. complete.
Inlet end from latrine to septic tank
Outer end from septic
Tank to soak pit

13 S.W.Tee 1 No. 25
S.W tee"100mm"diameter with one leg of "40"cm

14 S.W bend 1 No. 55


S.W bend "100mm" diameter.

15 "50mm" diameter C.I. Pipe 2 m 15


50mm diameter C.I. Ventilating pipe.

16 "50" Diameter cowl 1 No. 30


50mm diameter C.I. cowl at top of Ventilating
pipe.

ADD WATERCHARGE 1.5% = 23,174.66×(1.5÷100) =


ADD CONTRACTOR PROFIT 10% = 23174.66× (10÷100) =
GRAND TOTAL = 45,839
Column6 Column7 Column72 Column8
H QUANTITY TOTAL QUANTITY UNIT

1.95 11.115
3 9.42

0.2 0.3
20.835 m³

0.2 1.14

0.05 0.135
1.275 m³
0.6 0.94
1.15 1.1

0.6 0.94
1.15 0.42
3.4 m³

0.5 38

0.25 0.15
0.53 m³

2.5 1.88
1.88 m³

0.057 0.234

0.075 0.115

0.45 0.018
0.367 m³

1.7 6.8
1.7 3.06
9.86 m³

1.8
1.8 m³

2.5 1.84

0.2 0.16
2 m³
2.5 2.18
2.18 m³

4 NOS

3
3.3
6.3 m³

1 NOS

1 No.

2 RM

1 No.

PER AMOUNT

m³ 2875.23

m³ 1179.38

m³ 13235.58
m³ 2412.03

m³ 338.4

m³ 330.3

m³ 1222.64

m² 397.8

m³ 300

m³ 299.8
No. 160

m 283.5

No. 25

No. 55

mm 30

No. 30

TOTAL = 23,174.66
= 23,174.66×(1.5÷100) = 347.619
= 23174.66× (10÷100) = 22,317.46
GRAND TOTAL = 45,839.739