Urgent Need of Procurement Management Information System (PMIS)

For Improving Public Procurements

Shree Ram Dhakal


Consulting Engineer
PDE, Rural Access Improvement and Decentralization Project (RAIDP)
District Technical Office, Surkhet
dhakal.shreeram@gmail.com

1. Background public authoritarians have often found to have vested


Sound Public Procurement Policies and interest to make certain bidder successful
Practices are among the essential elements of good prejudicially and alterations in the posted documents
governance. Good practices reduce cost and produce of bidders have taken place with motive of unethical
timely results in efficient manner. Poor practices financial gain.
lead to wastage and delays and often become the
All such unfair practices have made the
cause of allegations in corruption and government
procurement practices unfaithful and government
inefficiencies. It is government’s duty to take
works and services ineffective compared to their
measures to ensure adequate principles and practices
objectives. So, there is urgent need of adopting a
are followed in public works and services. Sufficient
smart system which minimizes the chances of
regulatory provisions have been made; meanwhile
alteration and manipulation before, during and after
sufficient threats and weep holes have been
bidding process. To make procurements efficient
identified along with in our procurement practices.
and unaltered, Procurement Management
Prevailing Public Procurement Act 2063, Information System (PMIS) can be a smart remedy
along with previous FAR had, has adopted the in reducing inefficiencies, manipulations and fraud
competitive bidding process for procuring works, & corruption during tendering and contract
goods and services. It is aimed to acquire the execution.
reasonable standard of delivery in the least cost
through capable deliverer/supplier. Despite such 2. What is PMIS?
provision, current practices have not attained Procurement Management Information
sufficient satisfactory result as aimed in the System (PMIS) is a smart system which collects,
regulatory provisions. It has been a big challenge for stores and synthesizes the procurement related
every public authority to get the reasonable standard information all over the country. It is an online based
of delivery. Manipulations are often found both from central and integrated data management system
contracting parties during bid preparation as well as concerning to the procurement activities. PMIS uses
procuring authority during the evaluation process. centrally updated data warehouse to track, record
During bidding process major alterations the bidders and verify the procurement history and current
make is the faulty information about the work capabilities of the contracting parties’ viz.
experience, financial turnover, faulty equipment and contractors/suppliers/ consultants. During bidding,
manpower capability information. It is often bid evaluation and contract execution PMIS serves
observed that the bidders have a wide tendency to as necessary source of transformation of authentic
make fake documents to show that they meet the information and bridges between the bidders and
qualifying criteria mentioned in the bidding procuring authority. PPMO can be an appropriate
documents. Likewise, during evaluation process authority to undertake the central data management
system.

A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4, 2013
pp 209-213
3. Components of PMIS and Registration system by certifying their
Components of PMIS are more similar to that of procurement needs by the
e-submission system being adopted till date. The government departments with
difference lies in the continuous receiving and authorized lettering.
updating of the capabilities and procurement
information by PMIS unlike to e-submission system. iii. Registration of
Following are the component units of PMIS. contractors/suppliers/consultant
a. Central Data server- a data warehouse s: - Registration of bidding
b. Online Service Package parties in PMIS should be
c. System Members managed in such a way that they
i. System administrator, say are bound to enter in the PMIS
PPMO by written request with
ii. Procuring Authorities supporting documents rightly
iii. Bidding Parties i.e. contractors/ after they are registered in the
suppliers/consultants firm/company registration
iv. Scheduled Banks authority. At the time of
registration the current
4. Work Flow Steps in PMIS capabilities i.e. Manpower,
equipments, financial resources
Work flow of adopting PMIS should take in and other technical capabilities
the following sequential order. should be registered along with.

a. Registration of Users iv. Registration of Scheduled Banks: -


Registration of different users Registration of Banks takes place on
should follow different methods. demand to the system by bidding parties
Adequate review and verification (for presenting bid charge amount, bid
should be done prior to the security guaranty or performance
registration since the users are made guaranty during bidding process) or by
authorized, with designated powers procuring authorities (during payments).
according to the type of user, to
participate in the public b. Electronic Bidding
procurement by registering them in
the system. Registration of users’ Invitation of bids, quotations, RFPs
takes place with following etc should be called officially through
hierarchical order. electronic bidding process. For doing so
i. Registration of System every procuring authority should keep
administrator:- This is a single online based centralized service
entity type of user. PPMO (or package/software. Preparation of bid
any central authority) is a single documents can be simplified by already
and one time registration prepared templates by administrator where
process. necessary entries can be made pertaining to
the unique details of that contract. Posting of
ii. Registration of Procuring bid notice to the system automatically
Authorities:- All the procuring generates email notification to every
entities should enter into the members registered to the system.

A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4,
2013 pp 209-213
On receiving the notification, along with the bid document template,
bidders can prepare his bid by providing his Lowest Eligible Bidder is easily determined.
necessary entries of item rates and other The case of responsive and non responsive
required customization to the provided bid bidders can be omitted by filtering during
template. Also the bidding parties have to the bidding process i.e. not allowing the
manage the appropriate bank to issue bid non-responsive bids for particular contract
security guaranty which too, gets submitted during bidding.
through online in the PMIS system along
with the bid. There is no need to mention the d. Contract Award and Monitoring
experience information, manpower and
equipment capabilities and financial After evaluation of bid, contract is
turnover etc. by the bidders on their own as awarded to the successful bidder through the
these things are automatically stored and system. Going through the contract award
updated continuously in the system. Bidding terminal by the buyer, contract agreement
by that time only indicates the willingness of template document already created in the
the particular bidder. system is modified and customized in the
required field only (i.e name and ID of
c. Bid Opening and Evaluation contract, SCC, Priced BOQ, time of
Opening of bid will not be a big deal execution, milestones etc) which gets
after going online system of PMIS as there entered in the data warehouse. It can be
is no chance of manipulations and utilized by the system for real-time tracking
alterations as like in case of hard copy of contract.
submission. So, it follows a regular office By the help of set data in the system
day process. Bidding period can also be (or say in the contract document) PMIS
reduced as online system gives a reduced regulated and notifies the necessary
effort on bid preparation. After opening of information like milestones, time frame,
bids on the specified date and time, it can be guaranty times, and progress and suggests
automated in the PMIS system to send the action to the concerned party. Mandatory
abstract details of submitted bids to all the actions cannot be modified or altered by
bidders as bid opening checklist (muchulka none of the registered users (neither buyer
as we say). nor the administrator). For example, if the
After opening of bids evaluation of milestone provisioned in the contract is not
the bid takes place. This section in the achieved, it suggests charging Liquidated
system is only accessible from the terminal Damage as in the contract document and it
of procuring authority (the buyer). Through has to be done by the buyer otherwise
this section the buyer generates the checklist payment order by the system does not
of Requirement Details of the contract as proceed. Hence the chance of manipulations
indicated in the bid document already in the contract execution is highly reduced.
prepared and also the detail capability of the
bidders though the PMIS central data e. Payments and Completion of
warehouse. On comparison of both, system Contract
automatically indicates the eligible and During or on completion of contract
ineligible bidders. After generating the execution series of payment shall be
Comparative Chart of proposed item rates in released. The payments can be released to
the BOQ provided by the eligible bidders the contracting parties upon the billing of

A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4,
2013 pp 209-213
executing works through the billing section
of the PMIS accessible only to the buyer. 5. Advantages of PMIS over Traditional
Payment can be issued through the System
scheduled banks upon the online request Adoption of PMIS can make vast difference
order through the system. On completion of in the current procurement practices. There
works or services, completion report is is very little or no chance of manipulations
prepared with contract execution details and during the bidding process as well as
final payment is released. contract execution. Following are some of
the advantages.

f. Updating the Contract Execution i. During bidding process, bidders


Report cannot present the fake
information of experience,
Since every action is preceded turnover and equipment as in
through the online based software package the current hard copy
of PMIS connected to the central server it is submission system since tracked
gets automatically saved to server. On factual data are given by the
termination of contract, summary of contract system server.
execution, milestones, progress record, ii. One equipment, manpower or
billing information and payment history is vehicles allocated by bidder for
recorded by the system removing the other particular contract in the bid can
tracking histories. be made used for that contract
Compilation of such executive only making unable to allocate
summaries of all contracts handled by a for other contracts.
particular contracting party, yearly work iii. Opening and evaluation of bids
experience and financial turnover can be is highly simplified work in
easily generated by the system. Turnover PMIS. There is no chance of
Report of all the registered contracting manipulations and alterations in
parties can be published in the system in the the documents by evaluation
yearly basis. Such reports are usable for team. Chance of unethical
future bidding actions and contract processing is reduced.
management. iv. PMIS timely informs and
alarms about the milestones,
g. Updating the Increased Capability of critical activities and time
Bidders frames which we often forget
The system should support the during contract execution in our
update of the increased capability of bidding present practice.
parties. Increment in the resources, v. Every detail of all ongoing as
manpower, equipment and other capital well as completed contracts is
assets etc should be updated with written tracked by the system server
request by the contracting parties on enabling the generation of status
verification of the requested update with of contracts overally, particular
supporting documents (i.e. purchase receipt to a contract or particular record
and departmental registration slip etc.) by of a contracting party. Helps in
the system administrator. taking necessary action.
A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4,
2013 pp 209-213
vi. Since PMIS eliminated major corruption; a properly controlled, dynamic
alterations, it greatly reduces the and smart system in our procurement
cases of fraud and corruption as practice is urgently needed. Procurement
procurement is the major source Management Information System plays a
of corruption. vital role in curbing corruption eliminating
6. Current Challenges of Adopting PMIS the chances of manipulations.
Every new starts faces some challenges. PMIS does not make the
Adoption of PMIS too, will not be free from procurement different but makes it proceed
hindrances and obstacles at its start. differently. The reduced effort, lesser
Following are our challenges to go for chances in alterations, elimination of
adopting PMIS in public procurements. unhealthy competition, reduction in chances
i. Reluctance of public authorities of undue benefits are the results PMIS
and political circle to adopt a provides. Many of the countries in the world
smart and alteration –free including Bangladesh, whom we used to call
system. a major country of procurement mishmash
ii. PMIS is fully online based. in South Asia, has already gone for complete
Lack of continuous electricity online based procurement system. So, it’s
supply and internet connections our time to leap into a prosperous and
every places of country. mechanized country through procurement
iii. Limitation of proper level of reforms and good-governance. It’s a crucial
computer skills among public time that PPMO is undertaking the process
personnel’s and contracting of replacing of the current Public
parties. Procurement Act with a new one and is a
iv. Proper mechanism of data better instance to quest for an efficient and
encryption in online system smart system. The recent budget speech of
should be established. FY 2070 has too, proclaimed its
v. Without clearly stating in the commitment for electronic government
procurement act and until detail procurement i.e. e-GP system, which should
regulations and guidelines to go be advocated to make happened in real.
for an online based system is
made, it is difficult to adopt References
PMIS. i. World Bank Country Procurement
Assessment Report (October 2002)
7. Emerging from the Challenges and ii. Asian Development Bank, “Curbing
Corruption in Public Procurement in Asia
Way Forward
and the Pacific, Progress and Challenges in
Despite a nos. of limitations and
25 Countries”,2006
reluctance in our current system, we are
iii. E-GP Guidelines of Government of Peoples
bound to correct them as we are, now or
Republic of Bangladesh, 2009
then, bound to rise from our misery. It’s
iv. E-procurement Portal of DoLIDAR,
only we and our generation to make our
Nepal,<https://www.edolidar.gov.np>
environment a better place. If we sought for
a dynamic and well mechanized system in
our governance, the result is efficient service
delivery with a lesser operation cost. Since
procurement sector is a major area of
A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4,
2013 pp 209-213