Académique Documents
Professionnel Documents
Culture Documents
E. EXECUTIVE SUMMARY
E.1 INTRODUCTION
The contract for providing consultancy services for Preparation of Detailed Project
Report for Dausa-Lalsot-Kauthun section of NH 11A Ext. under NHDP in the state of
Rajasthan was awarded to the joint venture of M/s Aarvee Associates Architects
Engineers & Consultants Pvt Ltd and M/s Nag Infrastructure Consulting Engineers Pvt
Ltd vide NHAI letter no NHAI/ RJ/11019/EPC/2011/3277 dated 11.12.2012.
This executive summary presents a synopsis of the Final Feasibility Project Report
pertaining to Dausa to Kauthun section of NH 11A Extn. which is now under
submission.
The Project road roughly forms a quarter-circle shape to the east of Jaipur extending
from Dausa on NH 11 on the East and Kauthun on NH 12 in South. The project road
starts at Km. 0.000 at Dausa (Km. 164.300 of NH 11) and ends at Km 82.850 in
Kauthun village on NH 12 (Km. 37.500 of NH 12). The development of the project
into Four Lane/ Two lane with paved shoulders will result in safe and efficient traffic
operation and will facilitate through traffic coming from North of Jaipur and going to
East of Jaipur and vice versa.
The total length of the project is about 82.850 km. Existing chainages are normally
referred in this report and design chainages are stated specifically in sections where
they seemed relevant.
Ministry of Road Transport and Highways has rationalized the numbering of National
Highways and renumbered National Highways vide Gazette Notification dated 4th
April, 2011. As per revised highway numbers, the part of the project highway from
Dausa to Lalsot is part of highway No 148 originating at Manoharpur and ending in
Lalsot. The remaining section of Kauthun to Lalsot is part of NH 23 originating from
Kauthun and ending in Dhaulpur in Rajasthan. Since it would be confusing to have
different chainages starting from Manoharpur and Kauthun, the design chainage is
reckoned from Dausa and continued to Kauthun.
The location map of the project stretch is shown in the Figure-1 below.
JV
E-1
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
The surveys and investigations carried out on the project comprise mainly of the
following:
The details of road inventory & Condition survey are collected at every 100 m
and the following is the summary of the findings.
• The project road has two-lane with 7.0 m wide carriageway with earthen
shoulders varying from 1.0 m to 1.5 m on either side.
• The entire project section traverses through plain and rolling terrain.
• The predominant land use along the project road is agriculture. The
important crop grown along the project stretch is Mustard Seeds
• There are 8 major junctions and 54 minor junctions along the project road
JV
E-2
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
Detailed inventory of the bridges has been carried out as per the guidelines in
IRC SP: 35 – 1990 and the results of the inventory are presented in the
format prescribed in IRC SP 35.
• Major bridges 1
• ROB 1
• Minor bridges 9
• Pipe culverts 20
• Slab culverts 40
• Causeways 5
Topographic surveys along the existing alignment and along proposed bypass
and realignments.
Traffic surveys viz., Volume Count, Axle Load surveys, O-D surveys,
Intersection volume count surveys etc. including collection of secondary data
for traffic projections.
Investigations of the existing pavement and sub grade involving BBD test,
Roughness test, DCP test.
Collection of samples from pits adjacent to the existing road & testing in the
laboratory.
The project road runs through three districts of Rajasthan viz. Dausa, Tonk and
Jaipur. Located in the Eastern Rajasthan, the project road mostly caters to intra-state
traffic than inter-state traffic.
According to the 2011 Census, the State has a total population of 68,621,012. Out of
this, 75.1% is rural and 24.9% is urban population. It shows that the level of
JV
E-3
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
The literacy rate in Rajasthan has seen upward trend and is 67.06% as per 2011
population census. Of that, male literacy is 80.51% while female literacy is 52.66%.
Based on requirements of TOR, reconnaissance and map studies, the project road
has been divided into three traffic homogeneous sections and all the traffic surveys
viz. Classified Traffic Count Surveys, Origin – Destination and Commodity Surveys,
Intersection Volume Surveys, Axle Load surveys and Speed and delay Surveys etc.,
have been carried out. Secondary data has been collected for the purpose of
determining the Seasonal Variation Factors and Growth Rates for various count
stations and for vehicle categories respectively.
The classified Traffic Volume Count (TVC) surveys are carried out during the month of
November,2015 at Km. 7.000, Km. 36.500 and at Km. 60.000. The seasonal variation
factor for the month of November has been considered for all the traffic volumes.
AADT for different homogeneous sections are given in Table - E.1
JV
E-4
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
2 AT 668 334
3 AT 882 441
M AT 652 326
JV
E-5
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
Axle load surveys have been conducted at 2 different locations spread along the
project highway. The VDF values assessed for different types of vehicles at each
location are given below in Table – E.3. The high VDF values are observed on Lalsot
to Dausa section on account of overloaded sand trucks.
Km 36.500 Km 60.000
Mode
To Dausa To Lalsot To Lalsot To Kauthun
JV
E-6
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
The years in which different sections of project highway reach the maximum capacity
of 2-lane with paved shoulders and 4-lane highway are given in Table – E.6.
Table – E.6: Year requiring capacity augmentation
JV
E-7
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
JV
E-8
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
Option 4: Bituminous surfacing over treated RAP and cemented sub base
JV
E-9
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
Life Cycle Cost (LCC) has been carried out with the following options, for the sections
as mentioned below:
The above said two alternatives have been compared with the base case (Do
minimum / standalone project) for a period of 30 years for the both cases.
Net Present Value of 30 years for Flexible and Rigid Pavement options are given
below.
Flexible
Rigid Pavement
Package Section Pavement
(Rs. Cr)
(Rs. Cr)
By considering the life cycle cost analysis, existing road condition, VDFs of the order
of 50 in Dausa to Lalsot section, and keeping in view of the guidelines given in
Ministry’s circular No. RW/NH-33044/31/2014/S&R (R) (Pt) dated 04/08/2014, it is
recommended to provide Rigid pavement for the stretch from Dausa to Lalsot.
The recommended pavement compositions for different sections are given hereunder
JV
E-10
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
3 GSB, mm 150
Dc in Overlay Thickness in mm
S.No. From To Length MSA
mm BC DBM Total
1 49.900 51.000 1.100 1.27 30 40 50 90
2 51.000 53.000 2.000 1.48 30 40 70 110
3 53.000 56.000 3.000 1.21 30 40 50 90
4 56.000 62.000 6.000 1.58 30 40 75 115
5 63.300 64.200 0.900 1.58 30 40 75 115
JV
E-11
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
Based on the project capacity requirements, the consultants recommend that the
project be up-graded to Four Lane (Dausa – Lalsot) and 2 lane with paved shoulder
configuration (Lalsot-Kauthun).
Nangal Bypass
Nangal
16.250 19.150 16.200 19.300 (Four lane Rigid
Rajawatan
Pavement)
Nangal
Four lane Rigid
Rajwathan - 19.150 35.600 19.300 34.225
Pavement
Lalsot
JV
E-12
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
Lalsot Bypass
(Two lane with
Lalsot 35.600 49.837 34.225 49.725
paved shoulders
Rigid Pavement)
Two lane with
paved shoulders
Lalsot - Kareda 49.837 73.160 49.725 73.044
Flexible
Pavement
Kareda Bypass
(Two lane with
Kareda 73.160 75.512 73.044 76.136
paved shoulders
Rigid Pavement)
Two lane with
Kareda - paved shoulders
75.512 82.850 76.136 83.453
Kauthun Flexible
Pavement
The proposed Right of Way for the Project Highway from Dausa to Kauthun is given
in the table below E.16.
Dausa – End of
0.00 49.875 0.000 49.400 45
Lalsot Bypass
End of Kareda
bypass - 75.400 82.850 76.103 83.453 30
Kauthun
JV
E-13
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
Seventeen types of typical cross sections have been developed for meeting the
project requirements. The description of the TCS is given hereunder. The applicable
TCS type for different sections of the project road is provided in the schedules for
tender documents.
JV
E-14
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
JV
E-15
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
JV
E-16
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
JV
E-17
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
JV
E-18
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
JV
E-19
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
E.7.3.1 Bypasses
Three bypasses are proposed in the Project Highway. The details of the same are
given in the table E.17 below.
Slip/ Service roads shall be constructed at the locations and for the lengths indicated
below
Table E.19 Service Road Locations
Existing Design Design
Chainage(Km) Chainage (Km) Width
S.No. Side Length Remarks
(m)
From To From To (km)
1 2.042 4.621 2.025 4.600 Both 2.575 7.00 Dausa
JV
E-20
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
JV
E-21
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
As per revised norms of MOEF issued in August, 2013, the project doesn’t require
environment clearance since the additional width of land being acquired along
existing alignment is less than 40 m and along realignments and bypasses is less
than 60 m. Baseline studies are to be carried out as per the standard ToR of MOEF
when Environment Clearance is not required.
Detailed public consultations are being conducted with PAPs, NHAI officials,
concerned village representatives and revenue authorities. The demand of most of
the PAPs is for adequate compensation commensurate with prevailing market rates.
The final survey of the PAPs along the project stretch is in progress and the results
will be presented in the Detailed Project Report. Land acquisition plans are under
preparation with the help of village maps and these will be physically verified on
ground with the help of revenue authorities and discrepancies, if any, will be
rectified. After this exercise, the exact land extents as per revenue records will be
known. This will facilitate in finalizing the information required for 3(A) and 3(D)
notification in accordance with NH Act, 1956.
The entitlement matrix for the PAPs will be prepared in accordance with the NH Act
and National Policy for Resettlement and Rehabilitation for the Project Affected
Families, 2003. The detailed implementation schedule will be part of the final RAP
that will be submitted along with the Detailed project Report.
JV
E-22
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
Lalsot – Kauthun
Km. 77.872 Km. 78.500
(Two Lane with paved shoulders)
Land plans for toll plaza locations are being prepared and these will be submitted in
due course.
• In this project corridor, truck parking has been observed near Salempura
& Sri Roopura area. Local consultations were held at the places of petty
repair shops, restaurants/dhaba etc. and subjective opinion of the drivers
regarding necessity of truck lay bye is gathered.
• Sufficient working area and space for roadside establishments such as
repair shops, vulcanizing shops, service centre, spare parts shops,
telephone booth and light refreshments with first aid facilities may be
provided.
• The capacity of proposed truck parking is 15 bays, which are bearing the
size of 7.5m x 3.5m to accommodate 2-axle trucks. The proposed truck
parking is to be contained within the proposed ROW and maximum curb
length of 200m. The deceleration and acceleration lanes with adequate
length have also been proposed.
Existing Design
Section
Chainage Chainage
Lalsot – Kauthun
Km. 64.573 Km 64.453
JV
E-23
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
Two Rest Areas are proposed in project corridor based on the field survey and
Land availability. Adequate land to accommodate the facilities shall be
acquired at following locations.
1 1.700 (LHS)
Dausa
2.300 (RHS)
2 5.950(LHS)
Khedla Khurda
6.300(RHS)
3 7.750(LHS)
Khedla Khurda
8.100(RHS)
4 9.808(LHS)
Bhijawas
10.307(RHS)
5 10.832(LHS)
Badegaon
10.968(RHS)
JV
E-24
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
6 12.600(LHS)
Badegaon
13.000(RHS)
7 13.700(LHS)
Kanpuria
14.100(RHS)
8 19.700(LHS)
Talameena
19.400(RHS)
9 21.300(LHS)
Nayawas
21.100(RHS)
10 22.600(LHS)
Patalwas
23.400(RHS)
11 24.300(LHS)
Rawas
24.450(RHS)
12 26.300(LHS)
Patalwas
26.000(RHS)
13 27.342(LHS)
Dholawas
27.924(RHS)
14 30.400(LHS)
Salempura
30.700(RHS)
15 31.818(LHS)
Ralas
32.000(RHS)
16 33.230(LHS)
Dhidwana
33.500(RHS)
17 49.922(LHS)
Lakhanpura
50.082(RHS)
18 52.407(LHS)
BadaKapada
52.567(RHS)
JV
E-25
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
19 54.122(LHS)
Shivsingapura
54.285(RHS)
20 58.425(LHS)
Samel
58.585(RHS)
21 59.943(LHS)
Samel
59.802(RHS)
22 63.024(LHS)
Datwas
63.185(RHS)
23 65.042(LHS)
Shirpura
65.202(RHS)
24 69.642(LHS)
Turkiya
69.802(RHS)
25 71.622(LHS)
Nangal Nehar
71.782(RHS)
26 77.392(LHS)
Saawaliya
77.552(RHS)
27 78.982(LHS)
Harvhawata
79.153(RHS)
28 80.292(LHS)
Bhurtiya
80.452(RHS)
29 83.022(LHS)
Kauthan
83.182(RHS)
The bill of quantities prepared during PPR stage is revised based on the changes in
the up-gradation proposals, revised cost of materials such as bitumen. Unit rates are
computed based on the guidelines given in MORT&H Standard Data Book and
material rates are taken either from BSR of Rajasthan or Market rates.
JV
E-26
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
Pavement design is done for both flexible and rigid options. The flexible pavement
design is done using IRC: 37 – 2012 and checked with AASHTO-1993 pavement
design procedure. The rigid pavement design is done using IRC and CMA methods.
The overlay design is done using IRC: 81-1997 and checked with AASHTO-1993. The
Sub grade CBR for the new carriage way is considered as 10%.
JV
E-27
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
The Economic Analysis has been done to check the viability of the Project. The
analysis was done using the HDM-4. The principle benefits considered are savings in
vehicle operating costs, savings in travel time and reduction in accidents. The options
considered are as follows:
Base Option Maintain the Existing Project Road without any improvement.
Improvement Widen the existing Highway to Two lane with Paved Shoulders and
Option four lane configuration along with construction of bypasses.
The annual cost and benefit streams are used to derive the net cash flow for the
project. The EIRR and NPV @ 12% discount rate are determined using the discounted
cash flow technique for all the Sections. The results for the different improvement
schemes are presented below.
JV
E-28
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
EIRR (%)
Sections 15 Years 20 years 30 years
NH-11A Ext. From Dausa to Kauthun 20.8 23.0 24.2
From the results of the Economic Analysis, it can be seen that for the improvement
scheme, the EIRR is getting higher than minimum threshold value of 12%.
So it can be concluded that the project of Four lane with paved shoulder option for
HS-1 and Two laning with paved shoulder option for HS-1.1 & HS-2 are economically
viable and recommended for implementation.
Case-IV Base cost plus 15% and Base Benefits minus 15%
Summary for the Sensitivity analysis for the three sections are given below:
JV
E-29
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
As per ToR of the scope of consultancy services, the Consultants are required to
examine the viability of development of the existing 2 lane road to 4-lane / 2-lane
with paved shoulder facility by means of Build, Operate and Transfer (BOT) / Annuity
BOT / other forms of financing.
The main objective of undertaking this study is to assess whether the project is
financially viable or not. It is important to note that the proposal should be an
attractive proposition for private sector participation under Build, Operate and
Transfer (BOT) system. The basic methodology followed for estimating the financial
viability of the project is to calculate the FIRR (Financial Internal Rate of Return) on
the investment for the project.
Cost stream of the project is assessed based on the upgradation proposals discussed
in the preceding sections and associated costs in terms of interest during
construction, maintenance after construction etc.
Following assumptions are taken into consideration for the financial analysis: -
Escalation – 5%
Based on the project structure traffic study and toll rate analysis, financial feasibility
analysis has been carried out as per the methodology outlined in earlier sections. The
objective of the financial analysis is to ascertain the existence of sustainable project
returns, which shall successfully meet the expectations of its financial investors.
JV
E-30
Four Laning/ Two Laning with Paved Shoulder from Km 0.000 to Final Feasibility Report
Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A Extn.
in the State of Rajasthan under NHDP Phase-IV on Executive Summary
Hybrid Annuity Mode
The analysis reveals various FIRR values corresponding to each year of toll operation.
FIRR for the Returns on Investment and Returns on Equity for the concession period
of 30 years has been examined and tabulated below.
The section of the project road from Dausa (Km 0.000) to Lalsot (Km 34.225) is
proposed to be upgraded to 4 lane and the remaining stretch from Lalsot (Km
34.225) to Kauthun (Km 83.450) is proposed to be upgraded to 2 lane with paved
shoulder.
This combined section achieved a negative equity NPV of Rs. 235.48 Cr. with 40%
grant whereas an equity IRR of 15% with 60% grant and 30 years concession period
is achieved with positive equity NPV of Rs. 76.97 Cr.
a) The section of the project road from Dausa (Km 0.000) to Lalsot (Km
35.600) is proposed to be upgraded to Four Lane with rigid pavement,
Lalost (Km. 35.600) to Kauthun (Km 82.850) to Two Lane with paved
shoulder and Flexible pavement.
f) Two toll plazas are proposed – one in four lane section and the second
in the two lane section.
JV
E-31