Académique Documents
Professionnel Documents
Culture Documents
Reconstruction and Rehabilitation of Tareech Nakhatar Langloot Road (06 KM)-Cost Comparison
SUMMARY
1 Earth Works
3 Surfacing
12,100,000 12,461,500 3% 0 0% 12,461,500 0 -12,461,500 0
4 Structures (Cross
Drainage and
Slope Protection
Structures) 25,492,500 21,029,500 -18% 38,671,728 184% 14,988,045 35,207,031 19,769,419 3,464,697
5 Ancillary Works
253,500 253,500 0% 598,303 236% 253,500 42,841 -210,659 555,462
G. TOTAL AMOUNT
54,561,000 90,300,245 66% 61,776,050 68% 28,112,166 40,450,199 11,876,193 21,325,851
truction and Rehabilitation Project
SUMMARY
Remarks
CM
Earthquake Reconstruction a
Reconstruction and Rehabilitation of Tareech Nakhatar L
Abstract of Cost
Bill No 1: Earthworks
As Per Original PC-I/BOQ As Per Revised PC-I As per Balance W
Roadway Excavation in
Pay Item Surplus / Unsuitable
Description Unit
No Rock (Medium)
03-59-c Material requiring 331.67 12000.00 3980000 365.31 94,278 34440540 674.17 6009.0
blasting
CM
Structural Excavation in
03-60-a Common Material 179.55 11000.00 1975000 171.74 5,749 987350 315.25 2853.0
CM
Structural Backfill using
Granular Material
03-60-d brought from outside. 400 700 280000 400 1,407 562800 1127.50 492.0
CM
Structural backfill using
Common Material
03-60-c available at site. 200 2000 400000 200 1,805 361000 442.27 1500.0
CM
Formation of
Embankment from
Roadway Excavation in
Common Material
03-61-a including compaction 300 3000 900000 300 4,795 1438500 335.28 4800.0
by power roller.
CM
Earthquake Reconstruction a
Reconstruction and Rehabilitation of Tareech Nakhatar L
Abstract of Cost
Bill No 1: Earthworks
As Per Original PC-I/BOQ As Per Revised PC-I As per Balance W
Formation of
Pay Item Embankment from
108 bii Description
Excavation in Unit 300 1000 300000 300 5 1500 0.00 0.0
No Roadway
Medium Rock Material
CM
Formation of
Embankment from
108 biii Roadway Excavation in 300 2000 600000 300 5 1500 0.00 0.0
Soft Rock Material
CM
Sub grade Preparation
03-62-a in Earth Cut 5 24000 120000 5 5 25 29.41 36600.0
CM
Sub Total Schedule for Bill No. 01 13,175,000 56,404,495
Add 3% for Difficulty Factor for Abbottabad 0 0
Total for Bill No. 01 13,175,000 56,404,495
on and Rehabilitation Project
tar Langloot Road(06 KM)-Cost & Quantities Comparison.
Cost & Quantity
nce Works
Difference Amount of Difference in Difference in Cost
Amount of
Quantity Remaining between Balance Works as Balance Works Cost Due to Due to Quantities
executed by Quantity as Balance Works & Per approved as Rates(Rs.) on
Per approved as per site Remarks
Previous per Revised Remaining Revised PC-I on Revised PC-I on approved
Revised PC-I requirement
Amount(Rs.) on
Contractor PC-I Quantity as Per Contractor Quoted MRS-2017 MRS-2017(Rs.)
Revised PC-I Rates Quantities
0 0 10 -10 50 0 -50 0
nce Works
Difference Amount of Difference in Difference in Cost
Amount of
Quantity Remaining between Balance Works as Balance Works Cost Due to Due to Quantities
executed by Quantity as Balance Works & Per approved as Rates(Rs.) on
Per approved as per site Remarks
Previous per Revised Remaining Revised PC-I on Revised PC-I on approved
4,051,088 93,397.49
Contractor 881
PC-I 5,128as Per Contractor
Quantity 321,659
Quoted 593,617 PC-I requirement
271,957
Revised 3,457,471 on
MRS-2017 MRS-2017(Rs.)
Revised PC-I Rates Quantities
nce Works
Difference Amount of Difference in Difference in Cost
Amount of
Quantity Remaining between Balance Works as Balance Works Cost Due to Due to Quantities
executed by Quantity as Balance Works & Per approved Rates(Rs.) on
0 0 5 -5 1,500 as Per approved
0 -1,500 as per
0 site Remarks
Previous per Revised Remaining Revised PC-I on Revised PC-I on approved
Revised PC-I requirement on
Contractor PC-I Quantity as Per Contractor Quoted MRS-2017 MRS-2017(Rs.)
Revised PC-I Rates Quantities
0 0 5 -5 1,500 0 -1,500 0
Granular Sub
16-03-b Base Course using CM 150.00 3600.00 540000.00 150.00 981.00 147150.00 1278.77 5187.00 6632979.99
Pit Run Gravel.
Water Bound
206 b macadam base CM 800.00 3600.00 2880000.00 800.00 5.00 4000.00 0 0.00 0.00
with coarse
aggregate class-B
Amount of
Difference Amount of Difference in Difference in
Balance Works Balance
Quantity between Works Cost Due to Cost Due to
Remaining as Per
executed by Quantity as per Balance Works as Per Rates(Rs.) on Quantities as Remarks
approved
Previous & Remaining approved approved per site
Revised PC-I Revised PC-I on
Contractor Quantity as Per Revised PC-I on Revised PC-I requirement on
Contractor
Revised PC-I Quoted MRS-2017 Quantities MRS-2017(Rs.)
Rates
12,461,500 0 -12,461,500 0
0 0 0 0
12,461,500 0 -12,461,500 0
Earthquake Reconstruction
Reconstruction and Rehabilitation of Tareech Nakhata
Abstract of C
BILL NO. 4 : Structures (Cross Drainage and Slope Protection Structures)
06-05-c
Plain Cement Concrete
including placing,
compacting, finishing &
curing (Ratio 1:2:4) CM 4476.19 210.00 940000 4377.78 180 788000.00 7257.86
06-05-f
Plain Cement Concrete
including placing,
compacting, finishing &
curing (Ratio 1:4:8) CM 2884.62 1300.00 3750000 2783.53 753 2096000.00 5481.08
06-05-i
Supply & fabricate M.S.
reinforcement for
cement concrete (Hot
rolled deformed bars Ton 60000 22.00 1320000 60000.00 3.50 210000.00 111598.88
Grade 60)
06-07-b
Random rubble
masonry in foundn. &
plinth in cement, sand CM 2500 6900.00 17250000 2500.00 6964 17410000.00 5823.02
mortar : Ratio 1:4
08-01-d-02
Coursed rubble
masonry (Hammer
Dressed) in foundn. &
plinth in cement, sand CM 3000 250.00 750000 3000.00 30 90000.00 6138.70
mortar : Ratio 1:4
08-02-d-02
Reinforced Concrete
Pipe Culvert (AASHTO
M-170) Dia: 610mm M 0 0.00 0 0.00 0 0.00 3901.69
16-23-b
Reinforced Concrete
Pipe Culvert (AASHTO
M-170) Dia: 910mm M 1500 15.00 22500 1500.00 140 210000.00 8502.05
16-23-d
Providing and Laying
stone pitching with
hammer dressed stones
on surface, laid in CM 0 0.00 0 0.00 0 0.00 2603.58
courses
19-27
Grouting stone pitching
or apron etc, in :
Cement, sand mortar SM 0 0.00 0 0.00 0 0.00 719.75
(1:3)
19-31-a
Dismantling of Existing
Structures and CM 500 50.00 25000 500.00 5 2500.00 1612.78
Obstructions
NSI
Concrete class B in
Bedding of and
Encaasement of CM 5000 15.00 75000 5000.00 1 5000.00 0.00
Concrete Pipe Culvert
502 b
Steel Wire mesh for
Gabions CM 100 1600.00 160000 100.00 10 1000.00 0.00
507a
Rock Fill in Gabions
CM 500 200.00 100000 500.00 5 2500.00 0.00
507b
Riprap Class " A"
CM 1000 250.00 250000 1000.00 17 17000.00 0.00
509a
Ditch Lining with Rip
Rap Class- A(150mm) CM 100 1000.00 100000 100.00 225 22500.00 0.00
sp2
Sub Total Schedule for Bill No. 04(Schedule) 25,492,500 21,029,500
Remarks
Earthquake Reconstruction and
Reconstruction and Rehabilitation of Tareech Nakhatar Lang
NSI Each
Amount of
alance Works Difference Amount of Difference in Difference in
Balance Works Balance Works Cost Due to
Quantity Remaining between Cost Due to Quantities
as Per as
executed by Quantity as Balance Works & approved as Per Rates(Rs.) on per site Remarks
Previous per Revised Remaining approved approved
Revised PC-I Revised PC-I requirement
Contractor PC-I Quantity as Per on Revised PC-I
Contractor on MRS-2017 on MRS-
Revised PC-I Quoted Quantities
Amount(Rs.) Rates 2017(Rs.)