Vous êtes sur la page 1sur 18

WELL CEMENTATION

BY

K. P. M O S C R I P *

Synopsis mouvement alterné des tubes de revêtement pendant


The author sets forth the major lessons learned ces périodes.
from an investigation of cementing practices during L’application de cette technique a abouti à une
which a successful centralizer-scratcher-reciprocation économie considérable, vu qu’on obtient un plus haut
technique was developed. pourcentage de cimentations initiales satisfaisantcc et,
Caliper, radioactivity and temperature surveys, par conséquent, l’élimination de beaucoup d’injections
scratcher and centralizer equipment, and running de ciment bien coûteuses. On compte réaliser de plus
of casing are briefly discussed. Circulation, cemen- grandes économies encore en mettant au point les
tation and the movement of the casing during these remises en état dans des zones plus hautes qu’on
periods is more fully covered. croyait suffisamment protégées. L‘injection de ciment
Use of this technique has resulted in a considerable à, titre de précaution comme mesure standard avant
monetary saving by obtaining a greater percentage l’achèvement a été supprimée.
of successful primary cementations and the conse- Une sérieuse préparation du revêtement et une
quent elimination of many expensive squeeze jobs. surveillance par des experts de l’insertion et de la
Even greater savings are anticipated during future cimentation sont essentielles au succès. Dans des con-
recompletions in higher zones believed to be ade- ditions normales, en appliquant correctement la
quately protected. Precautionary squeezing as a technique de l’alternance centraíiseur-grattoir, on
standard practice prior to completion has been elim- peut logiquement s’attendre à obtenir une cimentation
nated. initiale satisfaisante des zones de p o o pieds ou plus
Thorough advance planning of the casing job and au-dessus du sabot du tube.
competent supervision of both the running and
cementation phases are essential to success. Under I-Introduction
normal conditions, with correct application of the
centralizer-scratcher-reciprocation technique, it is I n cementing casing in a drilled hole, the main
reasonable to expect that satisfactory primary purpose has always been so to place the cement
cementation of zones 5,000 feet, or more, above throughout the length to be protected, that the casing
the casing shoe may be obtained. would be completely encircled by a solid sheath of
cement, free from channels, mud pockets, and weak,
contaminated sections. That this hope has many times
Résumé failed of fulfilment, has been evidenced by failure
L’auteur donne un exposé des leçons importantes to obtain complete shutoff both at the shoe and
apprises par l’investigation de la pratique de la adjacent to perforated sections.
cimentation au cours de laquelle on a développé une The two factors which probably have contributed
technique satisfaisante de l’alternance centraliseur- most to these failures are first, the mud sheath on
grattoir. the wall of the hole is only partially removed by the
O n discute brièvement les diagrammes de diamé- passing cement, and second, the casing hangs eccen-
treur de carottage radioactif et de thermométrie, trically in the hole touching the side wall and prevent-
l’emploi des grattoirs et des centraliseurs ainsi que ing placement of cement between the two.
de l’insertion des tubes de revêtement. On traite plus One method suggested for overcoming these troub-
amplement de la circulation, de la cimentation et du les was to install bow-shaped springs on the casing
so as to “centralize” it, and spring wire scratchers
* Mechanical Engineer Shell Oil Company, Houston, to remove wall cake by rotation or reciprocation of
Texas, U.S.A. the casing string.
R. P. MOSCRIP-WELL CEMENTATION I45
Objectives to be gained from successful use of “approximate top”. ( A similar change occurs in a
this technique were : radioactivity survey curve.)
I-Elimination of leakage at the casing shoe. Effective Voluwetric Efficiency : This is the ratio
a-Elimination of precautionary squeeze jobs be- of the volume of the annulus fully-filled with cement
fore perforation, both at the time of original com- to the annular volume expected to be filled. I t is
pletion, and at a later date when a new producing determined by dividing the annular volume between
horizon is opened. the shoe and the full-hole top by the annular volume
3-Elimination of remedial squeeze jobs, at the between the shoe and the calculated top. (This latter
time of completion, to reduce water production or is the same as the set volume of the cement to be
gas-oil ratios in producing zones, resulting from placed outside the pipe.) Any “effective volumetric
channeling or poor bonding. efficiency” over 100 ”/o would indicate appreciable
4-Simplification of squeezing off perforations a t channeling in the annulus below the full-hole top,
time of abandonment of a zone. while an unusually low efficiency would indicate
This paper sets forth as concisely as possible the either excessive channeling above the full-hole top
major lessons learned during the development of a or loss of cement to the formations below that point.
successful centralizer-scratcher-reciprocation tech-
nique. The discussion deals with the problems more II-Caliper surveys
or less in the order in which they arise during the Without definite knowledge as to the annular
actual planning and execution of the job. For the volume to be filled, it is impossible to know how
most part, the terminology used is standard in the much cement should be placed behind the casing. Rule
oil industry, but it was found advisable to adopt and of thumb methods proved entirely unsatisfactory and
define the four following terms: it was found essential to run caliper surveys in each
Calculated Top: The calculated top is the height new field until an average pattern was obtained.
to which it is expected the cement will fill the Besides making possible calculation of hole volumes,
annulus. I t may be a point arbitrarily selected, or it caliper surveys also indicated under-gauge spots
may be established by a predetermined amount of where precaution should be taken when running
cement to be used. I n the first instance, the volume casing, and abnormally washed out sections to be
of the hole to the selected point is determined from avoided in placing centralizers, and which should be
the caliper survey, and the volume occupied by the taken into account in planning a program for pro-
casing subtracted to give the annular volume. The gressive circulation when running casing.
amount of cement required to fill this volume is then Caliper survey logs plot either average hole dia-
calculated. In the second case, the set volume of the meter or areas as specified. They are not difficult
predetermined amount of cement is calculated and to interpret, but it should be borne in mind that,
then from the caliper survey and the volume occupied because of the different scales used to indicate depth
by the casing, the height is calculated at which the and diameter, the relationship between these two is
annular volume is equal to the volume of cement to badly distorted. Actually, the changes in hole dia-
be used. The annular volume from the shoe to this top meter are much more gradual than they appear to
is used in calculating the effective volumetric ef f i- be. This can be clearly illustrated by plotting a short
ciency. section of the log to true scale, i.e., using a horizontal
Full-Hole T o p : The full hole top is determined scale equal to the vertical scale.
from the temperature survey and is the point at which III-Radioactivity surveys
the temperature curve veers noticeably and perma-
Largely because of the costs involved, the radio-
nently from a higher temperature, trending parallel
activity survey has greater practical application in
with the normal temperature gradient, to a lower
determining distribution of cement in squeeze and
temperature much nearer the normal gradient. (The
liner cementations than it has in locating the cement
same type of deviation occurs in a radio-activity
top or indicating cement distribution in the regular
survey.)
oil string job. Temperature surveys, as discussed
Contaminated Top : The contaminated top is also later, were found to be sufficiently accurate for
determined from the temperature survey and is the ordinary purposes, this accuracy being confirmed by
point above the full-hole top where the rapid de- the use of the radioactivity survey.
crease in temperature halts and the temperature curve
again trends parallel to and practically coincides with, IV-Scratchers
the normal temperature gradient. I t is the point The primary function of the scratcher is to remove
generally selected by the service company as the mud cake from the sidewalls of the bore hole. At
Proceedings 3rd W.P.C., Section II 10
146 PROCEEDINGS THIRD WORLD PETROLEUM CONGRESS-SECTION If

the start of reciprocation or rotation, the desire is 2-NO annular restriction-leaves open path up side
to remove and replace the filter cake which has been of casing.
in place for some time and which may have become 3-Vertical movement need not exceed six feet and
thick and leathery o r waxy. Then during the cemen- may be less if blank spaces are covered as casing
tation period, it is again desired to remove the freshly goes in hole. Little danger of sticking casing above
placed filter cake so that the cement slurry, as it pro- casing point. No need for additional hole below
gresses up the hole, can make intimate and complete casing point.
contact with the actual wall of the well bore. 4-Only one’size required for all casing sizes and
A secondary, but nevertheless important, function no splitting necessary.
is to baffle and cause turbulence of the cement slurry
so that it does not channel but is distributed over theRotary Type Disadvantages
entire annular area, and even to some extent into I-Higher material and installation cost per foot.
those cavities which have been enlarged beyond the 2-Tendency of casing to stick not easily recog-
actual reach of the fully extended scratcher wires. nized. Torque applied to casing may be sufficient to
A third, but much less important function of the twist it o f f down the hole or damage threads and
scratcher, is its “centralizing” effect. This is not ofcause casing leaks.
much consequence up the hole where 15 foot spacing 3-If welding fails, may tear off and twist around
is more or less general, but does assume somewhat casing, sticking or damaging it.
greater importance on short liners or on the bottom 4-Greater danger of damage to heat treated casing
joint of a casing string where from five to seven as individual welds cover appreciable area and total
weld is in a line extending over a 5 foot interval
scratchers may be used on a thirty or forty foot joint.
There are two general types of scratchers availableparallel to longitudinal axis of casing.
-the reciprocating, or ring type, and the rotating, The spacing of ring type scratchers posed two
or strip type. Several different designs offered are questions ; how far apart should they be placed and
illustrated and described at length in the Composite should they be spaced equally over the entire interval
Catalog. Quite naturally, both types of scratchers to be cemented, or would it suffice to place them
have their good and bad features and many argu- opposite prospective producing zones only? With
ments may be advanced for and against the use of range two casing, the bottom joint spacing selected
either. Some of these are: was 2 , 4 and I I feet from the shoe and 7% feet from
the top collar, and on range three, 2, 4, I I , 22 feet
Ring Type Advantages from the shoe and 7% feet from the top collar. On
I-Lower material cost per foot of interval covered. other than shoe joints, the spacing generally was
2-Lower installation cost. 7% feet from each end of range two casing, and
3-Tendency of casing to stick is indicated by up 7% feet from each end and one in the middle of
and down weights on indicator. range three casing. I n a few instances where a large
+-Merely slides on casing if lug welding fails. amount of the casing on which scratchers were to
5-Less danger of damage to heat treated casing be installed averaged 34 to 38 feet in length, spacing
as area of individual welds und total area affected was actually measured off at 15 foot intervals, care
are small. being taken not to spot a scratcher closer than 4 feet
from the end of a joint to allow room for slips and
Ring Type Disadvantages tongs. This spacing proved to be wholly satisfactory
I-Greater tendency toward removing side wall where a 20 foot reciprocation stroke was used. Later
cake while lowering in. experimentation in a different locality with 20 foot
2-Extends into annulus all the way around pre- spacing above the shoe joint and 25 foot reciprocation
senting possible bridging hazard. has given equally satisfactory results.
3-Casing must be reciprocated vertically and may A few jobs have been performed where a direct
stick above casing point unless sufficient additional comparison could be made between results obtained
hole and casing have been provided below. by using scratchers over the entire interval to be
+-Different size required for each casing OD cemented rather than in groups. The number is not
and must be split for installation on externally upset suf ficient to allow definite conclusions to be drawn,
casing. but indications are that scratchers should be equally
spaced over the entire section and this practice has
Rotary Type Advantages been adopted. The most important reasons for this
I-Less tendency to remove sidewall cake going in are: I ) Some channeling would be almost certain in
hole. the interval between the scratchers, resulting in un-
R. P. MOSCRIP-WELL CEMENTATION I47
satisfactory protection at these points ; and 2), which c) Do spring ends transmit forces directly to
is by far the more important, there is the danger that casing or through butt or transverse welds or rivets ?
the cement which eventually comes to rest opposite d ) Is there danger of fatigue damage to springs
the productive zones, would be badly contaminated by resulting from their bending over sharp corners ?
mud cake picked up by and mixed with the slurry as it e ) Is spring material and its temper such as to
passed the unscratched intervals, resulting in a poorly keep permanent set to a minimum?
consolidated, porous sheath opposite those zones it f ) Has centralizer sufficient hold-off power?
is desired to protect. The amount of hold-off power required of central-
The distance the highest scratcher was placed above izers and the distance apart they should be placed
the top of the highest zone to be protected was 250- have long been moot questions, and it is not within
300 feet at the start of the work, was reduced to 100 the scope of this paper to outline the involved
feet by the time the study was concluded and, in all mathematics utilized in the theoretical solution of the
probability, future experience will indicate that this problems. The following conclusions were reached,
can be reduced to 50 feet or less. however, after considering both the theoretical and
As it was standard practice to space scratchers over practical aspects of the matter:
the entire interval to be cemented, the cost advantage a ) Except in special cases, spacing centralizers one
of ring type scratchers became important. This was just above the shoe, one at the bottom of the second
because, except on the bottom joint, one ring type joint above the shoe, and one each 90’ thereafter,
scratcher is used approximately each 15 feet while should give satisfactory results.
the strip type must be installed continuously. There- b) Centralizers should be used over the entire
fore, at a cost of about $ 6.60 each for the 5%” ring section to be cemented, that is, from the shoe to
type and $ 11.00 each for a 5 foot section of the approximately 100 feet above the highest zone to
strip type, the material cost alone to cover a 500 foot be protected.
section of casing would approximate $ 250 for the c) Because tension, bending and compression
ring type and $ 925 for the rotary type. forces of unknown magnitude may be present
throughout the length of casing to be cemented, and
V-Centralizers because the blades may cut into the sidewall to an
The centralizer actually does not need to center unknown extent, only centralizers with maximum
the casing in the hole, but it should hold the casing hold-off power should be used so as to assure suffi-
away from the sidewall and out of contact with it a t cient standoff at all points.
all points. This accomplishes two things. First, it
allows good circulation and the placement of a solid VI-Running casing
cement sheath around the entire circumference of the Only slight additional care is required in handling
casing (and the hold-off distance should be great scratcher and centralizer equipped casing on the rack
enough to make this possible); and, second, by and while running it in the hole. Precaution should
reducing the area of the casing string in contact with be taken to prevent excessive bending of the scratcher
the side wall, it lessens friction and the danger of wires and centralizer springs when rolling the casing
sticking casing. and picking it up into the “V”. The driller should
Roth of the main types of centralizers-straight be careful in lowering through the rotary table as the
and spiral-were used in this work with the result OD of the centralizer springs often is greater than
that the straight type was adopted as standard. While the opening in the master bushing or spider, and the
the spiral type may have some theoretical advantages, scratchers, particularly if they are of the ring type,
it has an inherent structural weakness which quite may catch on the edge of the opening. T h e floorman
often results in fatigue failure of the springs at the handling the spinning rope must be alert to see that
weld point. Several designs of straight type centrali- the coils do not catch on the scratcher wires.
Zers are available, and detailed information on them I n general, it is possible to lower scratcher-cen-
may be found in the Composite Catalog. tralizer equipped casing into the hole as fast or
In selecting a centralizer and considering the faster than would be done if the equipment were not
method used to attach it to the casing string, the fol- used. The fear that the centralizers and scratchers
lowing points should be kept in mind: increase the friction and might tend to stick the
a ) Is the casing free to rotate without turning the casing has proved to be entirely unfounded. In fact,
centralizer ? it has been our experience that with scratchers and
b) Is centralizer always pulled through tight places centralizers, the casing actually seems to be more free
(either direction) and are both ends free to move and to move into the hole more smoothly. This is
along casing? probably due to the fact that an appreciable length
148 PROCEEDINGS THIRD WORLD PETROLEUM CONGRESS-SECTION 11

of the casing is being held off the sidewalls, reducing of hitherto undisturbed cuttings and thickened filter
the area in actual contact with the walls and thereby cake may be removed from cavities. With stage
reducing the friction. circulation, this material is not all removed at the
Where there is any danger of loss of circulation, same time and tendency to bridge the hole is reduced.
care must be taken to see that an excessive lowering It follows then that progressive circulation is in-
speed is not reached. The scratchers, particularly, dicated when :
may remove enough material from the side walls, to a ) Returns have been lost while drilling, or when
allow circulation loss. Also, this material can ball up it is expected that returns may be .lost during circu-
to some extent underneath the scratchers and cen- lation if too high pump pressure is required.
tralizers and greatly increase the piston effect
normally present in some degree when casing is run
b) Any section, during drilling produced excessive
cuttings or cavings, o r it is expected that excessive
.
in the hole. Under these conditions, close watch must amounts of wall cake, cuttings or shale will be
be kept on the level of the pits, and the speed of removed from the side walls by the scratchers and
running reduced if excessive loss of fluid is evi- centralizers while casing is being run.
denced. c) Numerous washed out places or cavities exist
As the last five to ten joints are run in the hole, from which excessive material may be removed
the indicated weight of the casing string should be during circulation.
observed and the variations in weight watched to d) The weight indicator shows an unexpected
see how smoothly the casing picks up and lowers. The dragging or tendency to stick, even though the next
maximum and minimum weights on both pick up and circulation point has not been reached, or it had been
lowering should be noted so that they may be com- decided at the start that progressive circulation was
pared with the corresponding weights at the start of not to be employed.
reciprocation. An exception to (a) may occur when a well has
“kicked” fluid from the hole at some depths and lost
VI I-Circdation circulation at others. After a proper balance has been
The first decision which must be made relative to attained before running casing, it may be advisable
circulation is whether the casing string shall be to forego progressive circulation and combat possible
lowered to the casing point before any circulating is loss into the formation by using some circulation loss
done, or whether running should be interrupted at material such as Cellophane.
intervals and circulation established so as to remove The conditions which prompted the decision to
from the hole the drilling fluid and material above circulate by stages will also dictate the points at which
that point. No hard and fast rules have yet been circulation should take piace, final selection taking
established as to when progressive circulation should place after study has been made of the caliper log.
be decided upon, or as to what intervals should be Care must be taken not to include too many washed
allowed between circulation points. One scratcher out spots, or sections which are expected to produce
manufacturer who has had considerable experience large quantities of material. Generally speaking, the
in cementing casing s t r i n e , recommends stage circu- first point of progressive circulation should be a
lation every 1000 feet as practically standard proce- short distance above the shoe of the last string pre-
dure for all holes. Our limited experience has in- viously run, that is the surface casing or an inter-
dicated that stage circulation is not always necessary mediate string. The purpose of this is three fold.
and that intervals exceeding 1000 feet may be used. First, it allows a check to be made of the equipment
Further work along this line must be done before to be used for circulating; second, it determines that
definite rules can be laid down. the annulus between the two strings is clear; and,
The most important reason for the use of stage third, it gives the crew practice so that, at later points,
circulation is to keep to a minimum the pump pres- there will be a minimum of delay in getting circu-
sure required to “break” circulation off bottom or lation started.
at any other point higher in the hole. This is accom- Procedure in breaking circulation is the same at
plished by removing in small increments (a) the wall both the casing point and progressive circulation
cake, cuttings and weighting material that may have points. The first and most important rule is to start
been dislodged from the side wall3 by the scratchers slowly. Pump pressure is built up gradually to be-
and centralizers and (b) the drilling fluid which has tween 200 and 300 psi and kept there until returns
thickened and increased in viscosity during the period are established. The pump is then gradually speeded
since the drill pipe was laid down. A further reason up to full throttle or to whatever lower speed is
is that, because of the higher annular velocities necessary to avoid loss of mud into the formation.
attained in comparison with drill pipe, a large amount Constant close watch should be kept of the pits
R.' P. MOSCRIP-WELL CEMENTATION 149
during this period so that any loss of fluid may be points or a t the casing point. In general, circulation
detected and the pump speed reduced accordingly. should continue at least until all of the fluid which
This gradual build up of pump pressure and has been standing in the hole above the circulation
circulation rate is important for several reasons. The point has been replaced with fresh. The length of
scratchers and centralizers remove appreciable quan- time required therefore is dependent not only on the
tities of wall cake while going in the hole. Therefore, amount of material to be removed from the hole, but
the least possible pressure needed should be used so also on the size of the hole, size of the casing, circu-
as to avoid starting circulation losses at points where lating depth, condition of the fluid in the hole, and
the filter cake may be quite thin. Also, in many cases, pump capacity and speed.
there may be a zone below the casing point which As a rule, compared with the weight and viscosity
has not been plugged off and into which circulation of the drilling fluid at the time drill pipe was laid
might be lost at excessive pressure. Furthermore, too down, the fluid to be circulated from the hole will
high a pressure or too rapid a circulation rate before be heavier and of higher viscosity. The time then
pipe movement has started may cause wall cake and when circulation should be stopped is when the
cuttings to bridge around or below the scratchers and returns are reasonably free of heavy wall cake and
centralizers causing lost circulation, or worse still, large quantities of wall cuttings and shale, and the
stuck casing. After circulation has been built up to fluid weight and viscosity have approached normal,
full speed, the danger of lost circulation is consider- or at least have started to show a decided downward
ably lessened, but frequent check should be made of trend. Picking the precise moment, however, is a
the pits throughout the circulation period so that any matter of experience and judgment.
loss which does occur may be detected and corrected Some idea as to how mud viscosities and weights,
before it becomes serious. as well as indicated casing weights, change during
There is no set rule governing the length of time stage circulation periods may be gained from study
circulation should be maintained either at progressive of the curves in Figure I , which present data taken
vj
m
-I

O
O
0
I
t

u
O
I-
Q
2
n
" Z

1 THIRD STAGE 4000'


CIRCULATING TIME - MINUTES
Fig. I. Mud conditions during stage circulations.
as

1.50 PROCEEDINGS THIRD WORLD PETROLEUM CONGRESS-SECTION II

during an actual job on a 6300 foot well in South is started with the full length of the circulation joint
Texas. The times shown are typical for this field. I n in the derrick, generally requires 30 minutes or less,
other fields, stage circulation time at 4000 feet has and rarely, if ever, need exceed 45 minutes. The joint
run as much as 35 minutes, while at 6ooo to 7000 of casing usually being between 30 and 45 feet in
feet it has varied from 35 to as long as 45 minutes. length, customary practice is to lower the casing a
Considerable variation in time may also be expected foot or two every two or three minutes. This drop
when circulating at the casing point. At that time, the will clean out any material which may have collected
casing is being reciprocated, or rotated, as discussed underneath the scratchers or centralizers.
later, and the purpose is to clear the bore hole tho- Reciprocation of the casing is commenced as soon
roughly of loose shale, well cuttings and the old as the rig pump has been started for circulation at
thickened mud cake, and the amount of the material the casing point. If returns are not immediately forth-
removed varies widely from field to field and well coming, it is best to move the casing up and down
to well. only four or five feet until returns have been esta-
Casing point circulation time for 44 typical wells blished. As soon as returns are observed, full reci-
of various depths and distributed throughout Eastern procation stroke and speed may be attained. The
Texas is shown in the following tabulation : length of full stroke depends on scratcher spacing
Minutes Circulating at Casing
___ Point and whether it is desired to pass scratchers once
Well Depth No. of Wells Minimum Maxitniim Average or twice during the stroke. I n this work, scratcher
3000-4000 4 50 56 53 spacing was 15 feet or less and reciprocation stroke
4000-5000 I4 45 76 62 was 20 feet. In later work, a spacing of 20 feet with
6000-7000 9 60 123 89
7000-8000 2 60 80 70 movement of 25 feet has been used with equal suc-
8000-9000 I2 60 I IO 78 cess. This phase of the problem requires additional
9000-11,000 3 80 90 85 study. Whatever stroke is decided upon should be
Ordinarily, the amount of wall cake and cuttings maintained until the casing is landed.
removed increases gradually to a peak and then No work was done to determine if there is an op-
tapers o f f , though occasionally rapid increase and timum speed at which the casing should be raised
decrease is noted. Mud weight and viscosity generally and lowered during the time it is being reciprocated.
rise rapidly, stay high throughout most of the scrat- It is doubtful that it makes much difference so long
ching period, and then decline almost as rapidly as as a reasonable speed is maintained. In this work, a
they rose. Ordinarily mud weight will not increase cycle of approximately two minutes was used, that
much over one half pound per gallon though it may is, one minute to raise the casing and one minute to
reach one pound. Peak mud viscosity (Marsh funnel, lower it. The important thing about the speed of the
1 5 0 0 ccs. in, I quart out) will often reach 120 cycle is that it should remain the same during the
seconds and occasionally will go so high as to prevent entire time the casing is reciprocated. The reason f o r
accurate measurement. this, as will appear more clearly later, is that the in-
dicated weight, both on the upstroke and downstroke,
VIII-Movement of casing will vary with the speed of reciprocation. Inasmuch
Movement of the casing string during circulation as it is desired to compare these weights, and how
and cementation is one of the most important factors they vary, as nearly a constant speed as possible is
in obtaining a satisfactory cementation. This idea, required. Once reciprocation of the casing has com-
however, is often times directly contrary to the esta- menced, every effort should be made to continue reci-
blished practices of a drilling department, and it is procation at the same speed and stroke, until the plug
therefore necessary to explain carefully to all con- has bumpzd and cementation is complete. This is ,

cerned what is to be accomplished by pipe move- not always possible, as will be brought out later, but
ments, and what takes place while it is going on. the times when it cannot be done should be few.
In progressive circulation, it is desired to remove It is exceedingly important that a careful and con-
from the hole the well cuttings and thick wall cake tinuous watch be kept of the indicated weight of the
which have been dislodged by the downward passage casing string, both on the up and down strokes, from
of scratchers and centralizers, but it is not the idea the time reciprocation starts until it is finished. Not
at this time to clean the side wall of the filter cake only should these weights be observed, but they
and cuttings in place. Recause of this, casing is never should be recorded at intervals of five minutes or less
rotated or reciprocated at a stage circulation point. or whenever a significant change takes place. It is
Occasional movement of the casing is desirable and true that the weight indicator pointer will swing and
often essential, however, to overcome a tendency to jump considerably, particularly at the start' of the
stick. As mentioned before, stage circulation, which reciprocation period. Ordinarily, the downstroke
_ _ _ _ ~ ~~ ~ ~

R , P. MOSCRIP-WELL CEMENTATION

nioveinent is less smooth than the up, and the weight mainly by friction which adds to the up weight and
indicator pointer moves so rapidly over such a large subtracts from the down weight. It is the difference
range that it is somewhat more difficult to estimate in weight between the up and down strokes that is
this down weight average. I t takes only a small impoitant. As long as this difference remains fairly
amount of practice and experience, however, to be constant, or decreases somewhat, there is little danger
able to estimate both weights with a minimum of of sticking the casing, even though the weights them-
difficulty. These weights give an indication of the selves may increase or decrease appreciably and
progress of the job. and are the only means of rapidly. I t is when the difference in up and down
knowing whether the casing is showing a tendency weights increases to any great extent, that danger is
to stick. present. When the up weight is increasing as the
Curves similar to the one shown in F‘g ‘ 1 ure 2 were down weight is decreasing, it indicates that greater
found very helpful in explaining to drilling crews friction forces are acting on the casing, tending to
the casing string weight changes which take place hold it still. When these friction forces become too
during circulation and cementation, and in over- great, the casing “sticks”. Consequently, when the
coming their fears relative to sticking the casing. The difference in weights increases appreciably, it is
curve in Figure 2 approaches the ideal, but was never- necessary immediately to make a decision as to
theless plotted from actual data tabulated during whether reciprocation should be continued, or stopped
ceinentation of a well. and the casing landed. In general, this situation is not
At A on the curve is shown the indicated weight as apt to arise during the circulation period as it is
of the casing string as it hung in the derrick just be- during cementation, particularly after the cement has
fore the start of reciprocation, and this weight is left the shoe and is being placed in the annulus.
projected across the graph as a reference line. The Continuing with Figure 2, the upstroke weight in-
average up and down weight curves follow each other creased at the start due to the force exerted by the
quite well, the differences in the two being caused centralizers and scratchers in removing the old
100

ch
m
-I

O
O 90
0
I
I-
I
2 80
W
3

U
O
i- 70
a
2
o
z
-

60

v)
W
I-
O
z
o
3
2

7 eo
152 PROCEEDINGS T H I R D WORLD PETROLEUM CONGRESS-SECTION II

thickened wall cake and cuttings. These frictional reading the average down weight because of wide
forces soon started to decrease, as new wall cake oscillation of the indicator pointer.
replaced the old, the effect being shown more by the A somewhat less perfect job is represented by
increase in down weight than in a decrease in up the curve in Figure 3. The large increases in up
weight, until the point B was reached, when up weight weight required to start the casing moving again
started to decrease. after reciprocation had ceased for a short time il-
There was a short delay between the time the rig lustrate the tendency of the casing to stick in the
pump shut down and the time the cementing company locality in which this well was drilled. Illustrated
started mixing cement and pumping into the casing. also is a situation in which the difference in up
During this period, reciprocation ceased. Note that, and down weights increased considerably and it
when it was again started a t C, the up weight had almost became necessary to land the casing to avoid
increased and the down weight had decreased, in- sticking it. Due to an accident, there was a 25 minute
dicating that the danger of sticking is always present period in which circulation ceased and there were
when the casing is not kept moving. no returns. I t was possible to continue reciprocation
Between points C and D, the up and down weights of the casing although the difference in weights in-
both steadily increased because the heavier cement creased from 2000 to 9000 lbs. Just as it was feared
slurry was replacing the mud in the casing. D is the that the casing would h a w to be landed, the weight
point at which the cement started to leave the shoe, difference decreased for some unknown reason and
and in this case, it practically corresponded with the a completely successful cementation was eventually
point at which all cement had been mixed and dis- obtained.
placement with drilling fluid had commenced. From When casing is to be reciprocated, a check should
then on, the indicated weight fell off very rapidly due be made to see that the hoisting equipment is of
to the lightening of the load inside the casing and ample size and in good repair. Clutches and brakes
the increasing bouyancy effect of the cement on the must go through a cycle every two minutes during
outside. It should then follow that when the equali- a period of from two and one half to as much as
zation point was reached, the hanging weight of the four hours. Stringing up an increased number of
casing (assumed to be half way between the up and lines lightens the load.
down weights) should have returned to where it was
at the start of reciprocation. E on the curve repre- IX-Cementation
sents the calculated time at which the equalization Cements, themselves, were not studied during this
point would be reached and it will be noted that a work. Regular Portland cement was employed to
point at E, half way between the up and down cement two strings of surface casing, while the “slow
weights, falls on the “hanging weight” line. set” type was used for all oil strings. The cements
A further interesting calculation checks the dif- were the products of several manufacturers and were
ference in the original hanging weight and the final furnished from the regular stocks of the cementing
indicated weight. From the curve the former is service companies. Sacked cement was used in only
78,000 ibs. and the latter 63,000 lbs., a difference of a few instances when there was a shortage of the
15,000 lbs. I n this well, the height of the cement bulk product.
column placed behind the casing was 2300 feet above Cellophane flakes were used in the cement when
the shoe. The mud weighed 10.9 lbs. per gallon near it was felt that there was danger of excessive loss
the end of the job an,d the cement slurry weighed of cement slurry to the formation and on several jobs
16.4 lbs. per gallon. The casing was 5%” OD. The 2 % by weight of dry bentonite was added to the
additional bouyancy effect of the 2300 foot cement dry cement. The four main reasons for the use of
column can therefore be calculated to be 15,630 lbs., bentonite are :
which varies only about 600 Ibs. from the indicator I-To obtain a lighter weight slurry and thus
reading difference. displace the cement to its final height with minimum
pump preCsure.
In one portion of the curves between C and D,
2-To increase pumpability, lubricating value and
it will be seen that the up weight continued to in- flow characteristics of the slurry, thereby reducing
crease while the down weight remained constant, friction in the annulus thus further decreasing the
in other words, the difference between the two pressure required.
weights increased. Such a condition must be viewed 3-To reduce the amount of water separation and
with suspicion, and in this case, it was. Reciprocation settling, and filtration loss to the formation and con-
was continued, however, as it was felt that the con- sequent tendency of the slurry to thicken o r “flash
dition was due largely to difficulty in accurately set”,
~-

R. P. RIOSCRIP-WELL CEMENTATIOF I53

4-To obtain increased set volume of the slurry water rapidly enough, or if the capacity of steam
and reduce the amount of cement required and the boilers for instance, is not great enough to keep the
cost. cementing wagons running at full speed and still have
One of the most important things about mixing enough steam left to pump the displacing plug down
cement is to be ready to do so when the time comes. at maximum speed, it is better to recognize these facts
Preparations should be completed well before the end at the start and run the wagons at a reduced speed
of the circulation period so that mixing may be that can be maintained.
started immediately and the whole operation carried Arrangements should be made to weigh the cement
on continuously according to a previous thoroughly slurry continually during the mixing period. This is
thought-out plan. After mixing of cement is started, necessary to obtain a uniform slurry. The average
every effort should be made to keep the cement cementer is quite adept at estimating slurry weight,
column moving until cementation is completed. but he cannot watch the mixing tub continuously and,
Probably one of the most frequent causes of in any event, accurate weighing is better than good
slowing down, and sometimes stopping cement estimating. Maintenance of the correct slurry weight
‘mixing is lack of sufficient water at the cementing during mixing is likewise necessary if it is desired
wagons. Therefore, before mixing starts, it should later to check the efficiency of the cementation, that
be determined not only that an ample supply of water is, compare the height to which the column actually
is available, but also that the pumps which are to was placed with the predicted or calculated height.
deliver it have sufficient capacity, are in good Slurry volume obtained from a certain amount of
working condition, can be started without delay, and dry cement varies with weight and only by weighing
that all valves in the lines are open or can be opened can the set volume be determined, and the calculated
immediately when the need arises. A short amount top be figured. Control of slurry weight is also a
of time spent checking these things pays big divi- “must” when circulation losses have been experienced
dends later. If there is any question about delivering and weight must not exceed the previously set maxi-

UJ
m
J
O
O
0
t
I
2
W
3
[L
O
I-
U
2
o
f

o
æ
I

:20

TIME
Fig. 3. Variation of casing string weight during cementation (well L 5).
I54 PK0CEEr)INGC T H I R D WORLD PETROLEUM CONGRESS-SECTION II

inum for fear of formation breakdown and loss of should not be necessary to stop reciprocation during
cement into incompetent zones. this change over.
As was brought out previously, constant watch If the cementing head used is not the plug con-
should be kept of the indicated weight of the casing taining type and reciprocation must be stopped and
string during the mixing operation. Unless the cement displacement discontinued during the period re-
slurry leaves the shoe before mixing is completed, the quired to insert the displacing plug in the head, the
danger of sticking the casing at this time is not too operation should be planned with especial care so that
great. There is, however, the increase in weight which the time the casing is standing still is kept to a mini-
takes place due to filling the casing with cement, and mum. This is a most critical period, particularly if
the driller is apt to overlook the fact that both up and a portion of the cement slurry has left the shoe. Of
down weights are increasing and become nervous the four strings of casing which became stuck during
through fear that the casing may stick. It is well to the course of this investigation, two of them stuck
have someone standing by the driller to assure him. during the time reciprocation was shut down to drop
The actual displacement of the cement slurry from the displacing plug. These two jobs, incidentally, were
within the casing into the annulus, is the most the only ones where squeize cementing was indicated
hazardous of all of the cementing operations. It, as being necessary to overcome failure of the primary
therefore, is extremely important to have this phase cementation.
well organized and to have an approximate knowledge I n any event, after the displacing plug has been
at all times of the locations of the front and rear dropped, and just as the by-pass valve on the mud
ends of the column of cement. This can be accom- line is closed and the rig pump starts discharging
plished by calculating the amount of time and the fluid into the casing, a stop watch should be started
number of rig pump strokes which should elapse to measure elapsed time and a count of the pump
between start of displacement and the time: strokes should be begun.
(a) The cement slurry starts to leave the casing Howard and Clark in their A.P.I. paper a t Chicago
at the shoe. in November 1948 stated that their tests indicated
(b) The top of the cement column in the annulus that the flow rate of the cement slurry in the casing-
passes the highest scratcher. hole annulus should never be less than five and one
half feet per second, and, if possible, should exceed
(c) The two cement columns, in the annulus and seven feet per second. Such high flow rates are, a t
in the casing, reach the equalization point. present, impractical in actual field operations but
(d) The plug displacing the cement bumps the further study should be given to finding ways and
float collar. means of more nearly approaching them. In the
Since it is believed that the cement and fluid meantime, it is necessary to compromise by using the
columns should be kept moving, if possible, plans rig pump or combination of rig pumps which will
should be made ahead of time to drop the displacing discharge the greatest volume at the pressures to be
plug immediately upon completion of cement mixing encountered. The pump is then operated at maximum
and to follow it without interruption with drilling possible speed until necessary to slow it down just
fluid supplied from the pits by the rig slush pump. before the plug bumps. Pressures should, of course,
To do this, it is necessary to use a cementing head in be watched closely at all times and a man should be
which at least one plug may be held out of the flow stationed a t the pump prime mover controls ready
stream during mixing, but which will allow the plug to shut the pump down instantly if necessary.
to be instantly released ahead of the displacing fluid A n attempt should be made to continue reci-
as soon as mixing is completed. The use of such a procation of the casing until the plug bumps. It may,
head is strongly recommended in preference to a however, be necessary to stop reciprocation and to
swage or the type head which has a removable cap land the casing very rapidly to prevent sticking the
through which the plug is inserted after mixing is string above the casing point. When this necessity
complete. arises, the decision must be made without delay.
A constant check should be kept on the progress Therefore, it is important to have the man responsible
of cement mixing in its final stages, and the rig for the job, or his thoroughly experienced delegate,
pump should be started up and be idling before the stationed at the driller’s side, not only to give him
last of the slurry has been placed in the casing. As specific instructions relative to landing the casing,
soon as the last of the cement has been pumped from but also to explain to him what is taking place and
the mixing tub, the displacing plug should be released, to reassure him.
the by-pass valve on the mud line closed, and dis- During this period, it is necessary that close ob-
placement of the cement begun immediately. I t servation be made of the indicated casing weight and
R. P, MOSCRIP-WELL CEMENTATION . I55

that a constant check be kept on the elapsed time and ment passes through it. The survey is run from the
number of pump strokes, the latter by a stroke top of the hole to bottom, rather than from bottom to
counter on the pump or by someone assigned to count top, so as to record the temperature of the fluid
them. before the strata of different temperatures have been
All who have been assigned any responsibilities disturbed.
should have a copy of the time stroke calculations. As the cement slurry behind the casing sets, it
The man at the throttle of the pump prime mover is gives off a certain amount of heat which is trans-
especially interested in the time and strokes at which mitted through the casing to the fluid inside the
the plug should bump, but he must be constantly on casing. Rroadly speaking, the greater the amount of
the alert to shut the pump down should the pressure cernent around the casing at any one point, the greater
rise too high. The man watching pump pressures is the total amount of heat given off and the greater the
more interested in the equalization point, when the temperature rise in the fluid inside the casing. Thus,
pressure should start to increase steadily, anti in th6 if no cement is present behind the casinx, the tem-
time the plug is to bump so that he can watch for perature of the fluid at that point should approach
the exact moment the pressure starts to rise pre- the normal earth temperature at that point, while if
cipitously. (A pressure gauge connected directly into there is cement behind the casing, the temperature of
the cementing head gives a much better indication of the fluid should be increased somewhat in proportion
true pressure in the casing than does the gauge on the to the mass of the cement at that point.
rig floor.) I n most of this work, temperature surveys were run
The observer with the driller is interested first in eight to ten hours after the plug was bumped, and
the time at which the cement slurry leaves the shoe. entirely satisfactory curves were obtained. In some.
This is considered a dangerous point as far as cases, delays as much as 15 and 20 hours were ex-
sticking the casing is concerned, and it is the point a t perienced without serious loss of detail in the curves.
which the indicated casing weight should start to There seems to be no reason, however, to wait beyond
decrease. (This decrease in weight gives a good check the eight hour period, and a standard waiting period
on the accuracy of the calculated time schedule.) The should be established so as to allow more accurate
next point of interest may be either the equalization comparison of the curves from different wells.
point, or the point at which the top of the cement The temperature survey will generally show a
slurry passes the last scratcher (which one comes readily 'distinguishable top of the cement column and
first is determined by the height of the scratchers irt will give some indication of where appreciable
relation to hole volume and amount of cement used). amounts of cement have been lost to the formation.
At the equalization point, the indicated weight begins The survey is of very little value, however, as an
to fall off very rapidly and the driller may become aid in attempting to estimate cross sectional distri-
quite worried because the casing appears to be bution of the cement, but occasionally gives good in-
sticking on the down stroke due to the much lighter dication of any channeling which may have occurred.
weight. IIis attention should be called to the fact that Upon completion of this work, it was decided that
the up weight is decreasing just as rapidly. temperature surveys should be run in all wells in
WJhen the top of the cement slurry has passed the which caliper surveys have been run so as to check
last scratcher, one of the main functions of the the cement top and allow efficiency to be calculated.
scratchers-that of cleaning the mud from the walls I n any well where two or more zones are to be pro-
and placing cement next to the formation-has been duced either at time of completion or at a later date,
accomplished. Consequently, should the casing be a temperature survey should be run as a positive
showing any tendency to stick, the length of the check on the cement top, and as an indication of
reciprocation stroke can be reduced so that the chance cement distribution, regardless of whether a caliper
of landing the casing at the proper point is greatly survey was made. In any particular field after a
increased. Ordinarily, this reduction in stroke length caliper pattern and a normal cement top have been
is not necescary. established, it should be satisfactory, in wells where
The final point-the one in which every one is just one productive zone exists, to run check tem-
most interested-is when the plug finally bumps and perature surveys only in every third to fifth well.
the casing comes to rest at the designated casing point. The length of this paper does not permit a dis-
cussion of the interpretation of the temperature
X-Temperature surveys curves obtained after cementation. While much still
The temperature survey instrument is a device remains to be learned, it is possible, by studying the
which measures and records graphically the tempe- temperature curve in conjunction with the Schlum-
rature of the fluid in the well at the time the instru- berger self-potential curve and the caliper log, to
156 P R O C E E D I N G S TIIIRD W O R L D PETROLEUM CONGRESS-SECTION II

arrive at a decision as to whether the cement job at Sheet”. Copies of the Casing Cementation Report
any particular point in the hole is sufficicntly good and the Casing Cementation Data Sheets along with
that precautionary squeezing is unnecessary, copies of the caliper and temperature surveys should
be filed in the permanent well files for future use in
X I - C o s t of scratcher-centralizer job recompletion work. A complete analysis of the cement
A question often asked is “what is the additional job should be made at the time of completion and, if
cost of using scratchers and centralizers ?” Naturally indications are that all zones have been satisfactorily
this cost will vary somewhat, the height to which the protected, the file should be marked “Primary cemen-
cement column is to be placed being the most im- tation satisfactory. O.K. to perforate all zones with-
portant factor, with casing size and well depth con- out additional cementation.”
tributing to a lesser degree. A rough cost estimate XI I I-Results obtained
can easily be made, however, as shown by the follow-
The table which follows lists pertinent data on
ing figures for a 5%” O D casing job. The well
49 cementation jobs performed and reported upon
depths and casing column heights were selected at
during this study. Geographically, the jobs were
random.
distributed throughout the eastern half of Texas.
Depth o f Well, Feet 4000 6000 8000 Two of the jobs were 10%’’ OD surface casing in
Ht. above Shoe, last Scratcher, Ft. 500 IMX) 1500 15 inch hole, while the remainder were oil strings.
No. of Centralizers 8 14 zo In depth, these latter varied from 3600 feet in Field
No. of Scratchers 41 77 116
costs C to almost 10,500 feet in Field M. The casing sizes
. Caliper Survey (No service varied from 4%” OD to 7%’’ and drilled hole sizes
charge) $ 160 $ 240 $ 320 from 8%‘’ to 9%“.
Centralizers 210 370 530 The greatest number of centralizers and scratchers
Scratchers (Ring type) 250 460 700
Welding Time 20 30 50 used was 42 and 248 respectively in Well D-I, closely
Temperature Survey 200 240 28% followed by the 39 and 239 respectively used in Well
Total $ &,O $ I340 $ J880 J-8. The latter well was cemented with 1700 sacks
Cost per foot of hole while 1ó00 were used in the former. The highest
covered by scratchers $ 1.68 $ 1.34 $ 1.25 cement column was placed in Well D-I resulting in
a full hole top over 5000 feet above the shoe, com-
O n the same basis, a 2000 foot column in a 4000 pared with a full hole top of slightly over 4000 feet
foot well would cost $2,010 or $1.05 per foot and in Well J-8.
a 500 foot column in a 10,000 foot well would cost Final evaluation of the results of this work must,
$1200 or $2.40 per foot. Generally, an estimate of of course, await later recompletions in higher for-
$1.25 per foot protected will not be far wrong. mations presumed to be productive. Also, no exten-
For a routine shoe job where 50 feet of scratchers sive comparison has yet been made with the results
might be used and caliper and temperature surveys obtained in past years before any scratchers or cen-
were unnecessary, the cost would be approximately tralizers were used, or with the results obtained by
$ Ioo.00. using scratcher-ccntralizer techniques other than that
reported on here.
XII-Recording cementation data The table shows that, of the 47 oil string jobs
In order that the results of an investigation of this listed, 43 were completely successful in that the
nature may be watched and later analyzed, it is casing was landed and cemented according to plan.
essential that on-the-job notes be taken and then Of the remaining four, two were entirely successful
compiled into a field report as soon as possible. from a practical standpoint in that the primary
Examples have already been cited of the curves which cement job was satisiactory, even though the casing
were drawn to illustrate conditions during stage cir- was landed slightly higher than planned-II feet in
culation, and during the period from the time reci- one case and I O feet in the other. Inasmuch as an
procation and circulation at the casing point started extra joint of casing had been used in each case, no
until the plug was bumped. I n addition to these ill effects resulted. This leaves two of the jobs, B-I
curves, a lengthy written report setting out pertinent and L-3, to be classed as unsuccessful. I n both of
data and describing various phases of the job was these instances, the casing stuck on bottom at the time
also prepared. Later, this report was shortened to reciprocation was halted to effect release of the dis-
the one page “Casing Cementation Report” included placing plug. I n each case, the cement slurry was
at the end of this paper along with a companion displaced from the casing, but a satisfactory shutoff
blank form entitled “Casing Cementation Data was not obtained at the point at which the casing was
R. P. MOCCRIP-WELL CEMENTATION I57
TABLE I
Cem,entation data
-
~- -- -
~ ~ ~
-
~

I pth, feet
~. .-
Ht. above shoe, f t .
Field iize holedril No. No. No. Wt. ~ ___
and led-casing of of jacks Additives ;lurrJ csg. Calc Cont. Full Calc. Full
Ccr., Ce- used TOP TOP
Well D.D., inche :ent.
nent tf-/gal shoe top top hole scr., tap hole ser.*
Ser.
-- - - -- - - - - - - top top
AI 7 %-4 42 6 32 200 16.0 4118 3425 3435 3505 3639 693 613 479
2 7 %-4 Y? 4 20 200 16.0 4108 3385 3390 3555 3840 723 553 268
BI 8 %-5 42 5 25 600 16.0 7847 7000 6970 7305 7527 847 542 320
C I 7 %-5 5 22 150 15.9 3732 3200 3130 3210 3452 532 522 2 80
2 7 %-4 Y? 5 22 I75 16.2 3652 3150 3110 3360 3351 502 292 301
3 7 %-4 Yi 5 22 I75 16.0 3727 3250 3110 3285 3426 477 442 301
4 7 %-4 Y? 5 22 I75 16.0 3703 3085 3090 3180 3401 618 523 302
DI a %>8 %-5 9 42 248 c 600 2% Bent. 14.5 6817 2000 I800 3130 4817 5017; 3687
EI 9 %-7 6 34 800 16.0 9020 7780 7800 7900 8571 1240 II20 449
FI 9 %-7 % 5 28 800 16.0 7779 6550 6375 6500 7465 1229 I279 314
GI 7 %-5 Y? 6 20 235 16.0 4082 3595 3315 3365 3805 487 717 997
HI 8 %a-? 4 19 ;o0 16.0 4592 3750 3935 4025 4351 842 567 241
2 8 %-5 Y? 5 26 350 16.2 4648 3830 3905 4015 43'2 818 633 336
3 9-7 5 22 300 15.8 4598 3610 3610 3675 4308 988 923 290
4 9-7 6 31 350 16.0 462 I 3630 3620 3725 4203 99 1 896 418
5 9-7 6 28 300 16.2 4580 3580 3500 3520 4241 I O00 1060 339
I I 9 %-7 8 46 500 16.4 8820 8050 6700 6750 8259 770 2070 5'61
2 9 %-5 Yi 5 21 500 16.0 8818 8060 8075 8130 8523 758 688 295
3 8 %-5 Y? 4 20 500 15.8 8817 7663 7545 7568 8530 I254 I249 287
4 9 %-7 5 25 500 16.0 8652 7050 6615 6950 8330 1602 1702 322
5 9 %-7 5 25 500 16.4 8668 7230 6960 7005 8368 I438 I 663 300
J I 8 %-5 Yi 6 40 500 16.4 8814 7852 7710 7915 8261 962 899 553
2 8 %-5 Y? 7 35 500 16.0 8791 7830 7830 7940 8293 96 I 85 1 498
3 15-10 % O O 800 16.0 1518 O 20 65 - 1518 I453 -
4 8 %-5 Y? 6 30 500 16.0 8758 7715 7550 7715 8357 I043 I043 401
5 9 %-7 5 27 500 16.6 8785 6820 7780 7900 8435 1965 885 350
6 15-10 % I3 86 750 16.0 I367 I95 67 525 85 1367 842 1282
7 8 %-5 Yi 7 35 500 16.0 8789 7790 7670 7820 8306 999 969 483
8 8 %-5 Y? 39 239 [ 700 2% Bent. 14.9 8795 3350 4630 4740 5267 5445 4055 3528
KI 7 %-5 Y2 7 38 350 16.0 4254 3000 3030 3200 3786 I254 I054 468
2 8 %-5 Y? 6 28 500 16.2 6330 5250 5290 5330 5955 I080 I O00 375
3 8 %-5 Y? 5 22 300 16.0 6284 5480 5485 5512 6030 804 772 254
4 8 %-5 42 8 38 500 16.0 4304 3710 3620 3850 3784 594 454 520
5 7 %-5 Y? 5 26 350 16.0 4228 3330 3370 3580 3915 898 648 313
G 7 %-5 Y? 6 30 350 15.9 4318 3105 3275 3425 3943 1213 893 375
7 7 %-5 4 - 350 16.0 4064 2805 3052 3200 3808 1259 864 256
8 774-5 Y? 6 35 350 16.0 4233 3335 3280 3500. 3817 888 723 416
9 7 %-5 Y? 8 40 275 16.0 4307 3620 3640 - 3828 687 - 479
LI 8 %-5 Y? I3 72 800 Radioactive 16.4 6030 3660 3700 3720 4930 2370 2310 I I 0 0 '

2 3 %>8 %-5 4 I3 78 800 15.6 6118 3770 4200 4300 5097 2448 1818 I O 2 1
3 9 %-5 Y? I4 84 800 16.5 6161 4450 4700 4750 4966 1711 1411 I I95
4 9 76-7 I7 IO0 800 16.0 6287 4380 4410 4420 4848 1907 I 867 I439
5 9 %-5 Y? 16 92 800 2% Bent. 15.4 6100 4430 4460 4490 4916 1670 1610 1184
6 9 74-5 Yi I4 81 800 2% Bent. 15.5 6144 3638 3565 3595 5059 2506 2549 1085
M I 9 %-7 I4 108 [ IO0 16.0 [O448 7480 7310 7440 8886 2968 3008 1562
2 9 %-7 7 28 500 16.2 8234 7240 6890 7070 7855 994 I 164 379
3 9 %-5 42 5 24 500 16.0 8150 7050 6910 7150 7857 I IO0 1000 293
KI 9 74-7 % 8 41 600 2% Bent. 14.4 9914 7654 7835 7920 9378 2260 I994 536
'/4 # Cell.
0 1 8 %-5 Yi 23 130 [ 300 16.0 6777 4508 4608 4620 4996 2269 2157 1781
1-Ceni lizer . a-Scratchers 3-Contaminated
TABLE I Cementation data (Continued)
- -
Height above highest scratcher. feet
Field - Effective
and :alculated Contami- Full hole rolumetric Remarks
Well top nated top top Fficiency yo

A I 214 204 I34 94 *


2 455 450 285 89 *
B I 527 557 222 54 Two Stage Circulation. Casing stuck a t casing point
while reciprocation was stopped to release plug.
Squeeze job indicated.
C I 252 322 242 99
2 201 241 -9 56
3 176 316 141 90
4 317 311 221 84
D I 1130 ? I330? J o5 30% excess cement used.
E I 791 771 671 94 *
F I 815 1090 965 ? Caliper survey incorrect - reciprocation stopped early.
G I 210 490 440 ? I77? F.H.T. very doubtful - temperature survey did not
go low enough.
€1 I 601 416 326 66 *
2 482 407 297 82 *
3 698 698 633 81
4 573 583 478 79 Casing stuck I I feet high, 2 minutes before plug
bumped.
5 661 741 721 114 Rector 2 plug system used. Reciprocation stopped
five minutes early.
I I 209 ? 559 509 269 Caliper survey apparently not correct - Calc. top
2 463 448 393 91 [too high.
3 867 995 955 106 Stage circulated at 6,500’. Recip. stopped 3 minu-
4 1280 1715 1380 I 06 [tes early.
5 1138 1408 1363 116
J I 409 551 346 94 Stage circulated a t 4 depths.
2 463 463 353 89
- - - - Temperature survey run to check top of cement.
3
4 642 807 642 IO 0 Stage circulated a t 2 depths.
5 1615 655 535 48 No caliper survey - Calc. top & Eff.based on bit size.
6 -I IO 18 -440 53 Insufficient cement used.
7 516 636 486 97 Stage circulated a t 3 depths. Recip. stopped I min-
8 1917 637 527 75 Stage circulated a t 3 depths. [ute early.
I< I 786 756 586 86 *
2 705 665 625 82 Rector 2 plug system - Recip. stopped 2 min. early.
3 804 799 518 78 Rector 2 plug system - Recip. stopped I min. early.
4 74 164 -66 93 * Doubtful that temperature survey is correct.
5 585 545 335 78 *
6 838 668 518 85 * Plug found 103‘ high - Special plug did not hold.
7 1003 756 358 87 Rotary type scratchers used.
a 482 537 317 92 *
9 208 188 __ - Casing stuck IO feet high - Plug not pumped down
and was found 602 ‘ high - 78 sacks cement left in
casing. Temperature survey instrument stopped
a t 3670 ’.
L I 1270 1230 ZIO 98
2 I327 897 797 SI *
3 516 266 216 83 Casing stuck 3 feet off bottom - Squeeze job requir-
4 468 438 428 96 Stage circulated a t 3 depths. [ed.
5 486 456 426 96
6 1421 I494 I464 102 No caliper survey - Calculated top estimated.
M I 1406 I576 I446 I02 Stage circulated a t 2 depths. Precautionary squeeze
2 615 965 785 109 Stage circulated a t 2 depths. [performed.
3 807 947 707 91 Stage circulated a t 3 depths. Recip. stopped 3 minu-
tes early.
N I I724 I543 I458 89 Reciprocation stopped I 7 minutes early.
0 1 488 388 376 98
i:: This efficiency is based on an “Equivalent Top”, and is slightly higher than one based on the Fi111 Hole Top.
The ilse of the Equivalent Top was discontinned after a short time as it proved to be unsatisfactory.
R. P, MOSCRIP-WELL CEMENTATION I59
CASING C E M E N T A T I O N REPlORT
Date .......................................... \\'ell . .....................................................................................
Fi e 1tl ........................ County .................................................. State ..........................................

Toial depth .... PRTD ........................... RECI P R O CATI O N


Last caciiix run prcvioiisly Max. length of stroke ............ Ave. time one stroke ............
Size .................. Wt. ................. Aixt. ............ If length of stroke reduced, give time ..................... and
Casing being run stroke .....................
W t . .................. Amt. ..................
whoin was hole calipered ?
........................................................................................ CEMEN T A T I O N
Deptb highest zone to be protected ................................. Cementing company ........................................................
Ueptli of highest scratcher . _ . _ _ Kind and type of cement ...... ...............................
Hr. last scratcher above highest Kind and amount of additive
Centralizers : Number, make 8r .........................................................................
........................................................................................ W t . of cement slurry: Est. ............... Actiial ...............
Scratchers : Number, make & typc ................................. Slurry vol. ft3/sack: E s ual ...............
.............................................................. Sacks of cement used-To .....................
alizer spacing ......................................................... In annulus ............... .....................
........................................................................................ Cu. ft. cement in annulus ..........................
Pump used to pump plug down:
i Scratclier spacing ................................................... Liner size and stroke ................................................
........................... .................................................... Vol. per stroke ........... ...... Gals. (100 %)
........................................................................................ SPM: Max. ................
Pipe covered by scratchers & centralizers Number of strokes required to pump plug down ..................
1No. of joints .............. footage ........ By whom was temperature. survey run? ..............................
Welding time required ............................................ Hrs. ................................ Depth reached .....................
List shoe, float collar, number of plugs, cementing liead ement tops : Calculated
and any special cementing eqiiipnient used ........................ Contaminated .............
........................................................................................ Annujar volumes, cubic feet :
........................................................................................ T o calc. top .................. To full hole top ...............
Effective volumetric efficiency ... .. %
........................................................................................
Mud: Type, wt. & visc. before running casing ............... TIME
.................................... #/gai. ........................... Secs. Casing started in hole ........ .:.............
Required to install cementing head ..............................
CIRCULATION Required to connect hose .............................................
~-. ___ ...............................
1
~~ ~

~-
Time Mud W t . & V i x .
Depth
Start 1 Finish 1 Start 1 Finish
Cement mixing started ...................................................
I l Cement mixing finished ........................
....................

.................................................
..............................
or .............................

......................

CASTNG C E M E N T A T I O N DAT'4 SHEET


nate .......................................... Well ...................................................................... .............................
Field ...................... .... County ................................................... State ........... .......
~_____ ~~ ~~~~ ~~ ~ ~ ~ ~ ~ ~ _ __
_ _ _ _ _
__ ~
_~ ~~ ~ ~ ~ ~

Time I DeDth
I
Thous. Lbs.
UP DN I UP
Pressure
DN 1 Wt.
Mud

visc. 1
Remarks
.........

I l l I l _. l
160 PROCEEDINGS T H I R D WORLD PETROLEUM CONGRESS-SECTION II

perforated, and a single squeeze cement job was per- sary control, and the temperature survey curves
formed. Besides these two remedial squeeze jobs, supply the proof of it.
there was also performed a purely precautionary, and 3-Thorough advance planning of the casing job
probably unnecessary, squeeze to check the shutof f and competent supervision of both the running and
opposite a sand which in the past had always been cementation phases are essential to successful ap-
squeezed before perforating for production. plication of the technique.
In comparison, oil strings were run in 32 wells in 4-It was possible to reduce remedial squeeze jobs
this same area during the previous year. One pre- from an average of .91 per oil string cemented,
cautionary squeeze job was performed in one well, to .04.
while remedial squeeze jobs were required in seven 5-Reduction in primary cementation failures
wells. The number of remedial squeeze jobs per well resulted in a minimum net saving of $ 20,000 on
varied from one to ten and the total number was 29. the original completion cost of 47 wells. Additional
This is an average of .91 squeeze jobs per well. If savings several times those already recorded should
the same percentage had applied to the wells shown result during future recompletions in higher zones
in the table, a total of 43 squeeze jobs should have believed to be adequately protected.
resulted, 41 more than actually took place. Since a 6-The average cost of using centralizers and
cingle squeeze attempt with the rig already on locationring type scratchers over a several hundred foot
will cost a minimum of $1500, this represents a gross interval, including running caliper and temperature
saving of at least $61,500. Using a cost of $1.25 per surveys, is $ 1.25 per foot of scratcher covered sec-
foot for the 33,2J3 feet covered by scratchers in the tion. For a routine shoe job where 50 feet of
47 wells, the total cost of using scratchers and cen- scratchers might be used and no caliper or tempera-
tralizers was $41,500, giving a minimum net saving ture surveys run, the total cost need not exceed
of $20,000 on original completions alone. Additional $ Ioo.OO.
savings of several times this amount should result in 7-Under normal conditions, with the use of
the future when recompletions are made in higher scratcher-centralizer-reciprocation technique, we may
zones believed to be adequateb protected by the reasonably expect to obtain satisfactory primary
primary cement job. cementation of zones 5,000 feet, or more, above the
casing shoe.
XIV-Conclusions 8-Temperature surveys generally can be inter-
The following conclusions appear justified ‘from preted well enough to indicate whether adequate
the work done so far: protection has been afforded to upper zones, or
I-The only time any real control can be exercised whether channeling or loss of cement to formations
over the placement of cement in a well bore is during has been excessive. .&
the primary cement job; and, unless costly radio- 9-Precautionary squeezing, as a standard prac-
activity surveys are employed, the only time the ap- tice preliminary to completion, can be eliminated,
proximate position and distribution of the cement can where temperature survey, or other check, has in-
be determined is very soon thereafter. dicated a successful primary cementation.
2-The scratcher-centralizer-reciprocation tech-
nique which has been developed provides this neces- :d Dec. 14, 1950.

Bibliograpny
( I ) Jones, P. H., and Berdine, Dennis, “Oil Well Cement- (6) Barkus, Bruce, and Wright, Kenneth A., “Effect of
ing-Factors Influencitig Bond between Cement and Hole Enlargement on Cementing and Completion
Formation”, A.P.I. Drilling and Prodnction Practice, Practices”, World Oil, Ilecember 1947.
1 5 (IWO). (7) Cannon, George E., “Improvement in Cementing Prac-
(2) Rarkus, Bruce, and Wright, Kenneth A., “Casing Move- tice and the Need for Uniform Cementing Regulations”,
ment While Cementing”, International Oil, October A.P.I. Drilling and Production Practice, 126 (1948).
1941. (8) Howard, George C., and Clark, J. B., “Factors to be
( 3 ) Teplitz, A. J., and Hassebroek, W. E., “Carnotite in Considered in Obtaining Proper Cementing of Casing”, ’
Squeeze Cementing”, Oil Weekly, October 29, 194.5. A.P.I. Drilling and Production Practice, 2j7 (1948).
(4) Teplitz, A. J., and Hassebroek, W. E., “An Investigation (9) Teplitz, A. J., “Review of Casing Cementing and
of Oil Weil Cenienting”, A.P.I. Drilling and Pro- Perforating Practices”, Oil and Gas Journal, Septem-
duction Practice, 76 (1946). ber 9, 1948.
(j) Rogers, J. L., “Cementing Practices Improved in Illi- (IO) Tinker, Jr., Nicholas A., “Planning, Running and Ce-
nois-Indiana-Kentucky Completions”, Oil and Gas Jour- menting Casing Strings”, Petroleum Engineer, July
nal, July 13, 1946. 1949.
R. P. MOSCRIP-WELL CEMENTATION 161

DISCUSSION
Mr. J. A. BOTTEMA (N.V. De Bataafsche Petroleum Mr. E. E. DAVIS.The main use of the bentonite is
Maatcchappij, The Hague, Netherlands). Attention to lighten the cement slurry where formations are
may be drawn to Mr. Moscrip’s statement (sub VI- weak and can break down ; lightening cement slurry
Running Casing), that it is in general possible to by adding up to 3% and 4% bentonite does not
lower scratcher-centralizer equipped casing into the appear to weaken the cement.
hole as fast or faster than would be done if the Mr. R. P. MOSCRIP,author (Shell Oil Co., Houston,
equipment were not used. I n general this may be true. Texas U.S.A.) written reply :
However it may be emphasized that the application of Mr. Botteina is right in that whenever abnormal
the combination of scratchers and centralizers may conditions are expected, or encountered, special care
cause serious trouble under abnormal conditions. Ab- should be exercised in running scratcher equipped
normal conditions exist for instance in case the for- casing. I t happens that the particular conditions of
mations consist of alternating sections of stable well- which he speaks were not encountered in our work.
consolidated sandstones and shales under severely However, as mentioned in the next paragraph of
unstable conditions. If the unstable conditions of the the paper, we did recognize that certain lost circu-
latter cause serious caving at regular intervals, even lation difficulties may have been caused by scratchers
when special contact with the rocks is absent, a con- removing material from the side walls and that under
tact with the wall of the hole should be avoided as those circumstances, casing running speed would have
completely as possible during running casing. Contact to be reduced. This practice was actually followed on
with scratchers might promote anew serious caving several wells. Undoubtedly there are quite a number
which might result in sticking of the casing during of fields throughout the world where abnormal con-
lowering. Conditions as mentioned above exist in ditions will make the use of scratchers hazardous and
certain areas in Indonesia. I n these areas it has undesirable.
proved a wise policy to provide the casing only with I n regard to Mr. Huisman’s comment, it may be
centralizers. that the paper was not entirely clear. As Mr. Davis
Mr. E. E. DAVIS(Houston, Texas, U.S.A.). I can- said, the main use of the bentonite is to make it pos-
not defend the paper in that respect as there are too sible to lighten the cement slurry by using a greater
many variables involved in caving conditions in which proportion of water. Ordinarily, i f the proportion
scratchers might add to the hazards. of water to cement is increased, the amount of settling
Mr. PH.H. HUISMAN (N.V. Nederlandse Aardolie and water separation which takes place during setting
Maatschappij, Oldenzaal, Netherlands). Mr. Moscrip is increased. Ry using bentonite a large amount of
discusses in his paper very clearly the many factors the water which would normally settle out is prevented
involved in cementing casing. However, I would like from doing so. As a result, less water is lost to the
to express my doubt whether 2% of bentonite added formation and the set volume of the cement slurry is
to dry cement will reduce the “water loss” of the greater. Halliburton Oil Well Cementing Company
slurry obtained. publish very good data and curves on this subject.

Proceedings 3rd W.P.C., Section II [I

Vous aimerez peut-être aussi