Académique Documents
Professionnel Documents
Culture Documents
Mounting
Abstract
This section discusses the purpose and types of foundations and grouts for
machinery; common methods for mounting machinery; factors to consider in
machinery foundations; the importance of anchor bolts; and finally, repair tech-
niques for foundations, grout, and anchor bolts.
The material is intended primarily for design and construction and plant engineers,
but some sections such as “Repairs” will also be useful to personnel involved in
reliability and maintenance.
Civil and structural design such as foundation sizing, soil types and loading, and
vibration limits are not covered in this section. These designs are discussed in the
Civil and Structural Manual. For additional information, refer to the References
section of this manual.
MAC-MS-3907, Grouting of Machinery, is available in the Specifications Section.
This is primarily for new installations, but will also be useful for repairs. All specifi-
cations referred to in this section can be accessed on the Technical Standards
website at http://techstds.rrc.chevron.com/tech_standards/.
Contents Page
342 Grouting
350 Design Considerations 300-21
351 Rotating Equipment
352 Reciprocating Equipment
353 Vibration Limits
354 Maintenance Considerations
355 Offshore Installations
360 Repairs 300-28
361 Repairs to Foundations
362 Repairs to Anchor Bolts
363 Repairs to Grout
364 Regrouting
310 Introduction
The majority of the machinery used in our industry is mounted on some sort of
foundation. Concrete foundations are the most common type found in refineries and
chemical plants; fabricated steel foundations are used on offshore platforms and,
frequently, in oil fields where skid mounted equipment is often moved from place to
place.
Concrete foundations are usually capped with a layer of grout a few inches thick.
The machine may be placed directly on the grout or on some intermediate surface
such as a baseplate, soleplate or epoxy chocks. Fabricated steel units may be bolted
(and possibly grouted) to a concrete pad, bolted to other structural steel, or just rest
on the ground. A skid is a fabricated steel structure that supports the machine for
transport. It may or may not have the required mass to be a complete foundation.
In summary, this section emphasizes several points regarding machinery mounting:
• Foundations are critical support systems for machinery and must be constructed
properly the first time to ensure reliable machinery.
• Grouting is meant to provide a surface for the machinery/baseplate to sit on and
not for lateral restraining (regrout jobs are sometimes unnecessary).
• Loose anchor bolts are the most prevalent and common cause of problems and
expense for engine driven reciprocating compressors.
• Long-term exposure to oil will deteriorate foundations; therefore, good house-
keeping is in order to prevent this problem.
Vibration Reduction
Some machines vibrate more than others. A well-balanced centrifugal pump or
compressor, for example, will run with relatively little vibration compared to a large
engine-driven reciprocating compressor with high unbalanced forces and moments.
These vibrations must be kept below certain limits to be sure that no damage is done
to the machine itself or the auxiliary equipment such as instruments and piping. The
detrimental effects of the vibrations may not be limited to the source unit. Vibra-
tions may be transmitted through steel (as in the case of an offshore platform) or
through soil and may have adverse effects on other equipment or on personnel
comfort.
Vibration is a cyclical form of acceleration, and because acceleration (for a given
force) is inversely proportional to mass, we can dampen the overall system vibra-
tion by bolting the machine to a large mass (foundation).
Maintaining Alignment
Maintaining alignment may refer to either of two things: (1) a set of two or more
machines all of which must be held firmly and precisely in position with respect to
each other; or (2) a single machine such as a large engine driven compressor which
must have its frame held straight and true to prevent crankshaft web deflections
from exceeding allowable limits. In addition to adding mass, foundations must be
sufficiently rigid to resist flexing and distortion, durable enough to last for years
without breaking down, and they must not produce any unwanted thermal
distortions.
322 Grout
Purpose of Grout
The main purpose of grout is to provide a suitable surface at the correct elevation on
which the machine (or mounting plate) will sit. It is actually part of the foundation.
Grout is also used in many cases to add stiffness to baseplates. Without it, some
baseplates may twist or flex, allowing the machine to vibrate due to internal or
external misalignment. It is a common misconception that this is the primary
purpose of grout. A lot of money is unnecessarily spent grouting or re-grouting in an
attempt to reduce excessive vibration. This is discussed further in subsequent
sections.
It is not practical to mount equipment directly on a concrete foundation for two
reasons:
• It is too difficult to form and pour concrete so that the surface elevation comes
out within the required tolerances for such things as piping hookup; and
• The weak surface (laitance) produced when concrete is cast or troweled is not
strong enough to keep dynamic equipment in precise alignment.
When a concrete foundation is constructed, the concrete is poured to the required
elevation. It is then chipped down to remove the unsound material, cleaned and
roughened to permit a solid interface between the grout and concrete. Once this is
complete, the machine or mounting plate is positioned on the foundation a few inches
above the freshly prepared surface and leveled and aligned using jacking screws or
blocks and wedges. The space is filled in completely with grout, and the blocks and
wedges (or screws) are removed to allow the load (the weight of the machine plus the
force from the tightened anchor bolts) to be transferred entirely to the grout.
Keep in mind that during this process, there is the possibility of introducing distor-
tions. With directly grouted reciprocating compressors for example, crankshaft web
deflections should be taken before grouting, after the grout has cured, and after
30 days of operation.
Sand/Cement
Sand/Cement refers to a mixture of one or two parts sand to one part Portland
cement. It is the least expensive type of grout and is generally used for light duty
applications. It may be poured or applied by a method called “dry packing” which is
described in Section 342. Keep in mind that sand/cement mixtures shrink when they
cure.
Sand/Cement is recommended for rotating equipment 50 HP and less that operates
at 3600 RPM or less, although many small machines (50 HP and less) are not
grouted at all.
Nonshrink Cementitious
Nonshrink cementitious grout is recommended for rotating equipment that satisfies
all of the following requirements:
• Driver horsepower greater than 50 but less than 500
• Speed of 3600 RPM or less
• Combined weight of machine, driver, and base plate up to 5000 pounds
Often this type of grout is simply called “nonshrink,” but since epoxy grouts are
essentially nonshrink too, it is advisable to be specific. Nonshrink cementitious
grouts use Portland cement but also contain other ingredients specifically added to
prevent shrinkage.
During the 1960s and 1970s, many problems occurred with a particular brand of
nonshrink grout that used iron particles for shrinkage control. The grout suffered
serious degradation not long after it was poured and all of these installations required
complete regrouting with a different product.
A survey conducted by the Company in 1985 found that for nonshrink grout appli-
cations, the majority of users favored 5-Star Grout made by the U.S. Grout Corpora-
tion.
Epoxy
Epoxy grout is tough and hard, with excellent chemical resistance, very low
shrinkage, and high abrasion resistance. Its compressive strength is more than
double that of cementitious grout at room temperature, but its properties do change
with higher operating temperatures. Nevertheless, it is the best material for critical
Grout Strength
The sections on equipment mounting methods make repeated reference to the
importance of unit loading and the compressive strength of grout. Cementitious
grouts typically have compressive strengths in the range of 4000 to 5000 psi after
curing for 7 days. Epoxy grouts on the other hand have more complex curing char-
acteristics. With epoxy there is a secondary curing that is produced by the elevated
temperature (from machine heat transferred to the foundation).
The following example is based on laboratory tests. Although it is unlikely that a
machine would raise the grout temperature to 160°F, it serves to illustrate the effect
of temperature on epoxy grout strength and the importance of keeping temperature
effects in mind when selecting a grout and mounting method:
After curing 7 days at 77°F, epoxy typically has a compressive strength of 8,000
to 10,000 psi when tested at 77°F. However, if the grout is then heated to 160°F
for 8 hours and tested at 160°F, the compressive strength will drop to 1,000 to
3,000 psi. If the temperature is held at 160°F for 7 days and then the testing is
repeated at 160°F, the compressive strength will range from 4,000 to 7,000 psi.
Finally, if the grout is then allowed to cool back to 77°F, the strength will range
from 12,000 to 18,000 psi.
Often, those involved in equipment grouting are not aware of the unique curing
properties of epoxy. In fact, grout manufacturers do not always report test tempera-
tures when they list physical properties in their technical literature. As a result, there
is increased risk that there will be a period during which the strength is exceeded
and the grout distorts from creep. If undetected, this condition could result in major
bearing or shaft damage to a machine.
In summary, it is important to understand the manufacturer’s recommended curing
procedure for two reasons: (1) the cure must be properly executed for the desired
compressive strength to be attained; and (2) no one should be misled by the
published maximum compressive strength which can be attained at a temperature
higher than the actual curing temperature.
Fig. 300-2 Preferred Elevation for Grout Level Fig. 300-3 Not Recommended: Surface of Grout
Showing Slight Slope Away from Machine Shown Above Bottom of Machine Frame
Courtesy of Adhesive Services Company Courtesy of Adhesive Services Company
Purpose
Foundation anchor bolts serve two purposes:
• They reduce vibration by securely fastening the machinery to its foundation,
thus creating a single “system” or single “mass”.
• They maintain precise alignment by holding the machinery firmly in place.
Keep in mind that tightly torqued anchor bolts create a great deal of clamping force
between the machinery and the foundation. Along with that force goes a high degree
of friction that prevents any relative movement in the horizontal direction. As
already mentioned, this friction force, not adhesion or a lip of grout, prevents the
machinery from moving sideways.
Retightening
As mentioned, it is a good practice to periodically check anchor bolts to be sure they
are tight, especially on reciprocating machinery. At locations where little or no
attention has been given to anchor-bolt torque, it is possible that some of the bolts
will be found to be cracked or completely broken. If this is the case, refer to
Section 362, “Repairs to Anchor Bolts.”
On new installations or after any sort of maintenance involving loosening of anchor
bolts, the torque should be checked first after running the machine for about an hour
and then again on the next day. After that, determine intervals based on the results
of the checks. The goal is to maintain the bolts in a fully preloaded condition at all
times and yet maximize the interval between checks. This interval will vary
depending on particular conditions.
A word of caution when tightening anchor bolts. If the material under the
machine foot has worn or deteriorated, the tightening may create distortion of the
Fig. 300-6 Anchor Bolt and Sleeve Courtesy of Adhesive Services Company
machine frame. This could affect alignment in a machine train or create excessive
web deflections (crankshaft bending) in an engine or compressor. Excessive web
deflections will cause a crankshaft to break. The usual practice is to place a dial
indicator on the machine foot and watch for any movement during tightening. If any
movement is detected, the effect must be determined by checking alignment or
taking web deflections. Tightening may improve the situation or it may make it
worse. In the latter case, it will be necessary to make corrections by adding shims,
repairing the foundation, or by some other means.
L-shaped bolts can break down the concrete at the inner radius and cause the bolt
to relax.
Straight bolts without enough embedment length may pull loose from the concrete.
331 Concrete
Concrete foundations are generally preferred for refineries, chemical plants, and
other installations where equipment is installed permanently.
Monolithic Block
The monolithic block-type foundation is used when there is no need to mount such
items as piping, vessels, or condensers directly under the machine. Block founda-
tions can be constructed to accommodate any size machine from the very smallest to
the very largest. They can also be built in a variety of shapes such as with steps,
clearance pits, pedestals, or holes.
Reciprocating compressors, for example, often have a large rectangular portion in
the center to support the crankcase and pedestals to support the ends of the cylin-
ders. The discharge bottles fit between the sides of the crankcase support and the
pedestals.
Platform Type
The term “platform” as used here should not be confused with offshore oil plat-
forms. It refers to a type of concrete foundation that stands on legs with the main
part of the machine above grade level. The platform has openings allowing some
parts that are attached to the machine to be mounted underneath. A condensing
steam turbine, for example, is typically mounted on a platform with the condenser
on the bottom. Large, horizontally split centrifugal compressors are often
constructed with the piping attached to the lower half of the casing so that the top
half can be removed more easily for service. The platform foundation can be
designed to allow ample room for the piping, vessels, and other hardware under the
machine.
Tall platforms usually require a “spread footing” for stability. A spread footing is a
sturdy concrete slab or pad formed below grade level that provides attachment
points for the platform legs and offers resistance to horizontal forces acting above
grade.
Note Unless absolutely necessary, platform type foundations should not be used
for reciprocating machinery.
Offshore Foundations
Fabricated steel foundations used on offshore platforms are a special case because
they are so securely fastened to the platform. In effect, their mass is borrowed from
the platform structure, and so mass is not as important as the stiffness of the
members.
The potential for resonance is great on a platform so it is especially important for
the designer to be aware of the forcing functions generated by the machine and to
take them into account in the design. It is also important to resist being misled by
the argument that any resonance problems discovered after startup can be easily
fixed by welding on additional members. Such modifications may be very costly to
execute and should never be seen as a substitute for thorough engineering in the
design stage.
For assistance consult the Civil, Structural, and Building Division and the Engi-
neering Analysis Division of the Engineering Technology Department.
Baseplates
A baseplate is a rectangular steel plate onto which machinery is mounted. The base
plate is in turn bolted and usually grouted to the foundation. It may be strengthened
with bracing underneath and often has a rim around its perimeter to collect and pipe
away spilled liquids. They are generally not much larger than about 5 feet by
10 feet. Figure 300-7 illustrates a typical baseplate.
Baseplates are most commonly used for mounting a centrifugal pump and electric
motor driver. The pump manufacturer usually purchases the driver and coupling,
supplies the baseplate, and then ships the units already attached.
4. Pads that are supposed to be at the same elevation (but are not) may be
compensated for by using shims (stainless steel) as long as the pads are hori-
zontally true.
5. Pads that are sloped (when they should be horizontal) are difficult to compen-
sate for by using shims. Here there is a danger of creating distortions in the
machine case when the foot is bolted down. Machining may be the only alter-
native.
6. New baseplates that contain machining errors should be returned to the vendor
to be corrected at their expense if time permits. If this is not feasible because of
scheduling and if field or shop machining is necessary at the site, the vendor
should be backcharged for the costs.
Rails
Rails are long sections of rectangular flat bar steel placed horizontally on the foun-
dation and partially embedded in grout. Usually the grout covers all but the top half
inch or so of the rail. The rails have holes for the anchor bolts to pass through, and
when the machine is mounted, the rails are sandwiched between the machine and
the foundation. Usually, large shims called chocks are located between the machine
and the rail. Refer to Figure 300-8.
Rails and soleplates (described later) are more popular than direct grouting for
equipment that is too large for a baseplate. Besides the advantage of allowing
completion of grout work without the machine being on site, this method of
mounting permits better cooling because it allows air to circulate more freely under
the casing. Rails impose higher unit loading on the grout than machines that are
directly grouted (but not as much as soleplates). The longer the rail the more diffi-
cult it is to mount true (straight, flat, and not twisted). Keep length to a minimum
without exceeding the compressive strength limits of the grout.
Soleplates
Soleplates are mounted on the foundation in a similar manner to rails. The differ-
ence is that there is a soleplate for each machine foot and therefore they will be
square or nearly square in shape. The unit loading on the grout will naturally be the
highest with soleplates and so it becomes increasingly important that the compres-
sive strength of the grout is adequate. (See Figure 300-9.) For this reason it is
conventional to use epoxy grout with soleplates.
As with rails, there is generally a chock between the machine foot and the soleplate.
The chocks may vary in thickness to compensate for errors in elevation of the sole-
plates. Thin shims are also frequently used in conjunction with the chocks. Typi-
cally, machines are aligned using shims of various thickness and then, when the
alignment is complete, the shim packs are replaced with single (stainless steel)
shims of a minimum 0.125-inch thickness.
The ends of all rail and soleplate corners should be rounded to a 2-inch radius to
prevent the creation of stress risers in the grout.
Figure 300-9 lists the typical total compression on the grout for various mounting
techniques. Note that the load is the combined force of the static load (weight),
anchor-bolt load, and dynamic load (vibration).
Epoxy Chocks
As mentioned previously, when rails or soleplates are used, the machine is usually
mounted on steel chocks which rest on the rails or soleplates. For epoxy chocks, no
rails or soleplates are used—the epoxy grout on the foundation has specially formed
“chocks” of liquid epoxy grout for each machine foot. The epoxy chocks are
roughly the same dimensions as steel chocks but they have the advantage of not
requiring a machined surface on the underside of the machine to be in contact with
the chock. In some cases, chocks (steel or epoxy) offer the advantage of permitting
air circulation under the machine frame which may decrease operating temperature.
In the past, epoxy chocks have been used primarily for diesel engines in marine
applications. In our industry, they are probably more suitable for rotating equip-
ment than for reciprocating engines and compressors because of the difference in
unbalanced forces. Marine diesels fall somewhere between our rotating and recipro-
cating machines in terms of the loading imposed on the chocks. Because the oil
industry in general has little experience with epoxy chocks, we are reluctant to
endorse their use before a sufficient experience base has been built. The main
concerns are abrasion resistance and high unit loading.
Ideally, anchor bolts are always tight, so there is no relative movement between the
machine and the chock, and therefore no mechanism for abrasion. Realistically,
however, anchor bolts are often allowed to come loose and then the superior abra-
sion resistance of steel adds an extra margin of protection against wear and subse-
quent distortion of the machine frame or casing due to uneven support. Whether or
not the unit loading will be higher with epoxy chocks compared to, say, steel chocks
and soleplates depends of course on the area of the soleplate versus the area of the
portion of the machine frame or casing in contact with the epoxy chock.
342 Grouting
Also see MAC-MS-3907, Grouting of Machinery, in the Specifications Section.
Grouting Methods
Pouring (Cementitious and Epoxy). This is the most common method of placing
grout although it may involve pumping and pushing the grout into place as well.
The consistency of cementitious grout should be adjusted to suit the application. It
is best to start with a thick consistency (often referred to as “flowable”) and only
Common Questions
Removal of Wedges or Backing Off Jack Screws. Prior to grouting a mounting
plate, it is leveled and positioned at the correct elevation on steel blocks. Jack
screws, or wedges, and the bolts are tightened. After the grout has been placed and
firmed-up enough to support the weight of the equipment, the wedges must be
removed, or the jack screws must be backed off, so that the weight is transferred to
the grout. Occasionally the question arises as to the necessity of this step.
If the wedges are not removed, or if the jack screws are not backed off, the grout
does not bear the entire load. Over time, the steel portion of the load-bearing area
will wear away or corrode, causing the anchor bolts to lose tension. As the machine
vibrates during normal use, abrasion between the loose mounting plate and the foun-
dation can cause cracking at sharp edges and further deterioration of the grout.
Removal of Equipment from Mounting Plate Prior to Grouting. Should the
machinery be removed from the mounting plate before it is grouted or should it be
left in place? Although there is no easy answer to this question, consider the
following guidelines:
1. Be aware that this question can and does arise. Contractors may bid a job
assuming that all the machines will remain on the mounting plates while the
Company’s expectation is that they will be removed. If the point is not covered
in the contract, there is potential for a disagreement about extra charges.
2. Many mounting plates have holes into which grout is poured which may be
inaccessible unless the machinery is removed. Sometimes these holes are only
necessary to prevent air from being trapped or to confirm that grout has reached
that area.
3. Grouting is a messy job. If the machine is left in place, will it suffer from expo-
sure to all the materials commonly used for grouting, such as sand, gravel, dust,
water, epoxy liquids, and cement?
4. If the equipment is removed, will the mounting plate spring out of dimensional
tolerance and be grouted in the wrong way? In other words, how much does the
weight of the equipment cause the mounting plate to flex?
5. Is there a suitable surface on which to place a level when positioning the
mounting plate? Often, one of the pads onto which the machine will be
mounted is the best place for a level. This may necessitate the removal of at
least one machine.
6. Is there a large enough crane available to safely move the equipment?
If, after considering the items above, you are still not sure what to do, leave the
machines in place. This is the typical practice, although not always the best.
Dynamic Forces
Rotating machines generally exert much smaller dynamic forces than reciprocating
machines. Nevertheless, these forces should be accounted for to avoid a potentially
serious vibration problem during operation.
A fault in the design of a concrete foundation is extremely difficult to correct after
the concrete has been placed. There is no easy way to add mass, alter the stiff-
nesses, or adjust the damping to change the natural frequency of a concrete founda-
tion in an effort to move the system away from a condition of resonance. In a few
extraordinary cases, it has been necessary to break out an existing foundation and
pour a redesigned foundation to solve a serious vibration problem. Obviously, such
instances are exceedingly expensive and time consuming.
While guidelines have been developed over the years for the allowable vibration of
the foundation itself, criteria for defining the forces to be used in foundation design
have been lacking.
A misunderstanding between the foundation designer and the machine manufac-
turer regarding the unbalanced forces to be allowed for in the design has contrib-
uted to many foundation vibration problems. These problems have commonly been
caused by not designing for the actual dynamic forces but rather for some lower
value due to communication problems between the foundation designer and the
machine manufacturer.
Depending on how the question about unbalanced force is asked, the manufacturer
might respond with the rotor’s residual unbalance from the dynamic balancing
machine. This balancing machine tolerance is an extremely small number that might
be only 1/20th of the actual force at rated speed. At other times arbitrary values are
assumed for foundation design, yet they may not be representative of actual
machine operation.
The dynamic force generated by the rotor is typically related to its running speed
and the amplitude of vibration. Because of the complexity of the subject, it is
impossible to accurately predict the behavior of a rotor system with one or two
simple equations.
Vibration Limit. Fortunately, however, standards have been developed for allow-
able limits of vibration for new machinery. One of the most widely used standards is
the API limit for dynamic and rotary machines:
where:
Av = peak-to-peak amplitude (displacement) of vibration in mils (0.001
inch)
N = rated speed in RPM
Note Below 3000 RPM the limit is 2 mils.
Vibration Limit Converted to Dynamic Force. The following equation may be
used for calculating the force used in the foundation design. This equation is based
on a vibration three times the amplitude calculated from Equation 300-1. A safety
factor of three is recommended because that is about the maximum vibration level at
which you would ever allow a machine to continue to operate.
F = 4.3 x 10-8(N2)(WR)(Av)
(Eq. 300-2)
where:
F = Dynamic force, lb
N = RPM
WR = Weight of rotor, lb
Av = Vibration level, mils, from Equation 300-1
The force calculated is a rotating vector, and it should be assumed that it is acting
perpendicularly at the center of the rotor. It should also be assumed that there will
be a 50% reaction at each bearing from the unbalanced rotating force. The reactions
at the machine’s hold-down bolts can then be resolved.
The latter reactions are transmitted to the foundation via soleplates or baseplates and
anchor bolts. Figure 300-10 illustrates the forces for a typical centrifugal
compressor and turbine driver. Note that Equation 300-2 can also be applied to other
rotating machinery.
Occasionally the foundation designer may want to add an additional factor above
the dynamic force determined by Equation 300-2, although Equation 300-2 is quite
conservative. Five times the API vibration limit has been used as a design criterion
in some cases where there were special concerns about the design. (This would
provide a safety factor of 1.67 beyond Equation 300-2.) To make the calculation,
substitute 7.1 for 4.3 in Equation 300-2.
Other Considerations
The question often arises about whether the foundation would survive if a large
chunk of metal, such as a piece of an impeller or turbine blade(s) were thrown off
the rotor while running at full speed. A second question might be whether the foun-
dation should be designed to accommodate such an occurrence.
Foundations usually will survive such accidents, although some repairs to anchor
bolts, hold-down bolts, or bearing pedestals may be necessary. Generally, such
occurrences are not taken into account in the design. The forces involved are
extremely high, and it is impossible to predict their magnitude. It is suggested that
bolting and structures be checked for adequacy at 10 times rated torque. This value
is often used on turbine-generator foundations, because a short circuit can cause an
instantaneous torque increase to that level. Similarly, a compressor rotor might
cause such a torque increase in the event of a severe rub.
It is recommended that the natural frequency of the foundation system be at least
30% above or below the frequency of any machine operating speed.
As a rule of thumb, the weight of a rotating-machinery foundation should be no less
than three times the weight of the machinery it supports.
Forces arising from differential gas pressure acting on the piston and piston rod
have no effect on the unbalanced forces and moments transmitted to the foundation.
The magnitude of these forces and moments can sometimes be extremely large, and
they must be accounted for in the foundation design. No “rule of thumb” exists for
predicting the magnitude since machine designs vary widely in terms of the number
and sizes of cylinders and crankshaft configuration. Data Sheet CMP-DS-875 (in
the Standard Drawings and Forms Section) may be sent to the vendor with the
Company’s quotation request. The vendor then provides preliminary values so that
the forces and moments of the various machines proposed can be evaluated. Prelim-
inary foundation design can begin with this information and be refined as the actual
forces are furnished by the vendor.
Other Considerations
Any natural frequency of the foundation should be at least 30% above or below the
primary and secondary frequencies. For instance, on a 450 RPM unit, ideally any
natural frequency should not be anywhere in the range of 315 to 1170 cycles per
minute (cpm). Sometimes it is impractical to keep natural frequencies out of a range
that wide. Accordingly, it may be possible to place a natural frequency between the
primary and secondary frequencies. A natural frequency in the range of
585-630 cpm would satisfy the criterion of 30% separation margin in the above
example.
For reciprocating units, as a rule of thumb, the weight of the foundation should be a
minimum of five times the combined weight of the frame, cylinders, and driver.
Plugging of the drain pipe nipple can be another problem. A half section (cut down
the length with the upper half removed) would be sufficient and can be cleaned
more easily. Some users prefer a 2-inch nipple mounted vertically and piped to the
drain. If for some reason a piping connection is necessary, cleanout provisions
should be included.
Jacking Bolts
When machinery shafts are aligned, it is usually necessary to move one or more
machines. Vertical moves are fairly straightforward. The machine is jacked up and
shims are installed between the machine foot and the base. Horizontal moves,
however, are more difficult, especially on heavy machines, because there is no easy
way to slide hundreds of pounds of steel a few thousandths of an inch and stop at a
precise point.
Jacking bolts consist of threaded pieces of steel plate welded to the baseplate so that
a bolt can be screwed in and tightened against the machine pushing it slowly in the
desired direction. When used in conjunction with dial indicators, they enable the
machinist to make precise horizontal moves.
Some equipment specifications recommend jacking bolts (sometimes called align-
ment positioning screws). Company pump specifications recommend them on
machines weighing more than 60 pounds. They are great time savers and well worth
installing on existing equipment not presently fitted with them.
After an alignment job is completed, the screws should be backed off before
running the machine.
Vibration Problems
The Company has encountered vibration problems associated with skid-mounted
reciprocating compressors on platforms. The problems were caused by lack of skid
rigidity and a failure to investigate potential vibration problems in the module struc-
ture. Typically, only the direct supporting members are investigated. These prob-
lems can be mitigated by requiring:
• Offshore platform design contractors to analyze the major structure for poten-
tial vibration problems induced by machinery
• The equipment vendor to meet basic skid rigidity and vibration requirements
The Civil and Structural Manual provides skid design requirements.
Transportation
Equipment for offshore platforms can experience large transportation forces, both
during transportation from the vendor to the platform fabrication site and from the
fabrication site to the offshore installation location. Lateral loading of 50% of the
weight of the machine is a typical factor applied to the design of machinery in order
to withstand the effects of transportation forces. It is important that both the vendor
and platform designer be aware of these requirements. The Civil and Structural
Manual also addresses this requirement.
360 Repairs
Note Although Specification MAC-MS-3907 Grouting of Machinery is written
primarily for new installations, some parts of it will be useful and applicable to
grout repairs. It is available in the Specification Section and can be accessed on the
Technical Standards website at http://techstds.rrc.chevron.com/tech_standards/.
diameter, is inserted into the hole along with small diameter copper injection and
vent tubes. The entrance is then plugged, and the equipment is regrouted. After
equipment regrouting, the annular space around the reinforcing steel is filled, the
vent tube plugged, and the crack pressure injected from the inside out.
a. Remove the nut. Clean the threads of both the nut and anchor bolt with motorized wire wheels or chase
them with appropriate dies and taps.
b. Visually inspect the threads of both parts. Replace any nuts that do not look good. Run a sharp die down
any anchor bolt that a good nut will not run freely on.
c. Apply plenty of antiseize to the threads of both parts and also on the mating surfaces. Note that friction
is a major factor, and good lubrication is essential to achieving correct torque.
d. Apply a torque of 110% of the recommended value to all anchor bolts that are not broken.
For example:
e. Replace any bolt that will not hold that much torque.
a. Bolts that fail to hold the test torques but do not break:
• Chip sufficient grout and concrete away to determine the reason for the looseness.
• If the problem is due to a poor anchor in the concrete, the new concrete must be allowed to cure
sufficiently before load is put on the bolt.
• Chip sufficient grout and concrete away to expose a portion of the anchor bolt.
• Bridge the chipped-away part of the foundation with a thick bar with a hole drilled through it. (The
new section of anchor bolt goes through the hole.) The bar spans the chipped-out hole and rests on
solid grout on either side. This is a temporary tool used to facilitate testing the strength of the bolt in
the concrete.
• Repeat the above steps 1c and 1d to be sure the rest of the bolt is solid in the foundation and that
the threaded coupling is strong enough.
c. Installing sleeves:
• Put sleeves around all anchor bolts that are exposed for repair. Sleeves should be about 6 to 8
inches long and about an inch larger than the O.D. of the bolt or threaded coupling.
Pack the sleeves with some soft waterproof material that will keep out grout and water. The sleeve
must stay filled with this material because if water ever gets in and freezes, it will crack the
foundation.
d. Grouting: Patch in the areas around the sleeves with a good grade of epoxy grout.
e. Torquing:
• Put a dial indicator on the machine foot prior to torquing each nut to check for soft foot. Use shims
as necessary to prevent crankcase distortion.
• After all nuts have been torqued, go around again to be sure they are all tight.
f. Re-torquing:
• Run the machine for about an hour. Re-torque all the anchor bolts.
Note: Sleeves help the anchor bolts stay tight. The ones that do not have sleeves may need frequent checking. Re-check all of them
periodically and determine how often it is necessary to re-torque.
Pressure Grouting
Pressure grouting was described above in connection with grouting methods and
foundation repairs. The techniques are very similar when repairing grout. For minor
repairs where it is only necessary to fill small areas under a machine frame or
mounting plate, injection sites may be drilled through the metal and threaded for
grease fittings. Solvent (to remove oil) is then injected, followed by one or more
applications of epoxy liquid. Care must be taken to ensure that the equipment is not
lifted or distorted during the injection. It is important to check alignment before and
after the epoxy is injected.
Generally, the holes are drilled about 2 feet apart, and pressure grouting proceeds in
both directions from the center. As soon as clear epoxy escapes from the adjacent hole,
a grease fitting is installed and injection is started at the next location. This procedure is
continued until clear (oil free) epoxy is forced from all sides of the equipment.
Partial Regrouting
When the top portion of the foundation (grout and a few inches of the concrete) is
badly deteriorated and time does not permit a complete removal of the equipment, a
partial regrout is probably the best type of repair. The grout- and oil-soaked concrete
are chipped down to expose clean dry concrete from the edge of the foundation to a
point partway under the machine case. The area under the case should be equivalent
to that used for a rail or soleplate mounting so that the newly poured grout will bear
approximately the same load as a rail or soleplate mounted machine. If foundation
cracking is discovered, repairs should be made as described in Section 361 before
proceeding further. Otherwise, the effectiveness of the regrout will be limited.
After the old grout has been chipped away, holes spaced about 18 inches apart are
drilled into the remaining grout for the installation of injection tubes. Quarter-inch
copper tubing is inserted into the holes and putty is used to seal around the tube at
the entrance to the hole. Then the anchor bolts are isolated with sleeves and soft
material to prevent them from coming in contact with the grout. Forms are
constructed and the grout is poured just as it would be with a new installation. After
curing for about 24 hours, liquid epoxy is injected through the tubes into the area
between the old grout and the machine case. The liquid also fills any cracks in the
grout or foundation that intersect the holes.
364 Regrouting
The difference between partial and complete regrouting is that the latter implies
removal of the machinery from the foundation. This is necessary when damage to
the grout and concrete is so severe that it cannot be adequately prepared without
removing the machine.
Every effort should be made to remove all traces of oil-soaked concrete. In cases
where this is not practical, it may be necessary to use a thick layer of epoxy grout
over the entire foundation. The grout manufacturer should be consulted on the
maximum thickness per pour and also the grout’s ability to adhere to itself. This use
of extra epoxy to compensate for oil-soaked concrete should not be confused with
the remedy for cracked foundations. Where cracking exists, the foundation should
first be repaired as described in Section 361.