Date : August 19, 2019

Project : 6/F CYBER ONE BLDG.


Location : 11 Eastwood Ave. Eastwood City Cyberpark, Quezon City

Subject : Cost Proposal Breakdown


Attention :

ITEM NO. ITEM / DESCRIPTION LOCATION QTY UNIT UNIT COST AMOUNT
II CIVIL / ARCHITECTURE WORKS
Demolition Works
a. Dismantling of existing fixed ceiling including hangers and supports 342.41 sqm
b. Dismantling of existing wall including door (7 set flush door) 1.00 lot
c Dismantling/ Opening of CHB wall (1.2m x 2.6m) 1.00 lot
Note: Hauling location for verification
Ceiling
installation of 600x600(mm) acoustic tile including metal framing,
a. Enclosed Rooms 250.30 sqm
hanger and support (ref.: fine fissured)
b. Surface preparation including sanding of rough surface and cleaning 49.70 lot
Painting works with one coat primer and two coats of top coat (slab
c. Hallway 49.70 sqm
soffit/beam)
Painting works with one coat primer and two coats of top coat
d. 1.00 lot
(exposed pipes)
Wall
installation of 12mm thk gypsum board on both side of metal
a. 339.80 sqm
framings
b. installation of insulation, 50mm thk x 50kg/m3 339.80 sqm
Painting works with one coat of primer and two coats of top coat
c. 577.65 sqm
(washable paint)
d. Installation of Metal skirting, H=50mm Perimeter 244.50 lm
e Support for glass wall and wooden doors. 1.00 lot
Miscellaneous
a. Curtain cove using marineply board in paint finish Perimeter 33.90 lm