MASTER SCHEDULE OF WORK PT.

PARAMA SAKA
Rincian Kegiatan : AIR CONDITIONING Rukan Taman Meruya Plaza Blok B.29 Jakarta Barat
Proyek : BEKKAN BY ESINA
Waktu Pelaksanaan : 70 ( Tujuh Puluh ) Hari Kalender

SEPTEMBER OKTOBER
NO DESCRIPTION Start Finish Duration KETERANGAN
(Days) 1-7 8-14 15-21 22-28 29-5 6-12 13-19 20-26 27-2 3-10
1 2 3 4 5 6 7 8 9 10

A PEKERJAAN PERSIAPAN 04-Sep-19 19-Oct-19 46


B Pekerjaan Exhaust & Air Fan
1 Pabrikasi Ducting Exhaust Fan Fresh Air Fan di Work shop 13-Sep-19 27-Sep-19 15
2 Pabrikasi Support Ducting Exhaust & Fresh Air Fan 13-Sep-19 15-Sep-19 3
3 Pemasangan Support Ducting Exhaust & Fresh Air Fan 16-Sep-19 20-Sep-19 5
4 Pemasangan Ducting Exhaust 21-Sep-19 24-Sep-19 4
5 Pemasangan Ducting Fresh Air Fan 27-Sep-19 03-Oct-19 7
6 Pemasangan Volume Dumper 04-Oct-19 05-Oct-19 2
7 Penarikan Kabel Power Exhaust Fan Dan Fresh Air Fan 11-Oct-19 12-Oct-19 2
8 Pemasangan Unit Exhaust Fan dan Fresh Air Fan 13-Oct-19 14-Oct-19 2

C Pekerjaan Air Conditioning


1 Pabrikasi & Pemasangan Support Ducting PU 18-Sep-19 20-Sep-19 3
2 Pabrikasi Ducting PU 25-Sep-19 02-Oct-19 8
3 Pemasangan Instalasi Ducting PU 03-Oct-19 10-Oct-19 8
4 Pabrikasi dan pemasangan rack pipa Refrigersnt 17-Sep-19 23-Sep-19 4
5 Instalasi Pipa drain AC 21-Sep-19 23-Sep-19 3
6 Instalasi Pipa Refrigerant 24-Sep-19 01-Oct-19 8
7 Test tekan pipa reffrigerant 02-Oct-19 04-Oct-19 3
8 Instalasi kabel Power 05-Oct-19 08-Oct-19 4
9 Pemasangan Unit AC 09-Oct-19 20-Oct-19 12
10 Pemasangan Supply Air Grille dan Return Grille 21-Oct-19 23-Oct-19 3
11 Perapihan pekerjaan 24-Oct-19 25-Oct-19 2

D Testing Commissioning 26-Oct-19 01-Nov-19 7

Dibuat oleh
PT. PARAMA SAKA

`
SUGIYONO
Project Manager