Vous êtes sur la page 1sur 7

TRANSPORTATION RESEARCH RECORD 1579 Paper No.

971108 11

Field Analysis of Operation and Design of


Single-Point Urban Interchanges
PAUL W. DOROTHY, THOMAS L. MALECK, AND LAURA AYLSWORTH-BONZELET

Michigan is considering the much needed rehabilitation and upgrading to progress traffic on the crossroad, and the impact of continuous
of many of the freeway interchanges located in urban environments. The frontage roads on the overall operation. The field review also con-
single-point urban interchange (SPUI) has been suggested as an alter- centrated on collecting observations about the geometric design, sig-
native to designs presently used, in particular the Michigan urban dia-
nal operation, pedestrian control, pavement markings, and land use
mond interchange. To evaluate the appropriateness of the SPUI, a
literature review was conducted, along with an e-mail and telephone sur- and landscaping of SPUIs.
vey of other state departments of transportation experience with the
SPUI. Then, a field review of selected SPUIs was conducted to collect
observations about the geometric design, signal operation, pedestrian LITERATURE REVIEW FOR SPUI DESIGN
control, pavement markings, and land use and landscaping of SPUIs. A
SPUI with the crossroad going over the freeway was found to be a pre-
ferred design. In addition, the smaller designs were observed to function Much of the published literature on the design and operation of
the best. However, the use of continuous frontage roads is believed to single-point interchanges was generated from research efforts by
counteract the advantages of the design. Currently, progression of the Bonneson and Messer (1) at the Texas Transportation Institute
crossroad is not a problem, although the impact of the SPUI on inter- (TTI). The objective of that study was to evaluate the design of a
sections downstream must be considered. Additionally, the need for SPUI compared with that of other interchange geometric configura-
pavement markings in large SPUIs is paramount. However, these pave-
tions. The preliminary results indicated a concern for pedestrians
ment markings overlap and cause driver confusion. Several other obser-
vations were also made: most SPUIs reviewed were not able to and the lack of a protected pedestrian phase. Also, a concern that
adequately provide for pedestrians, controlled access near the SPUI is with the addition of continuous frontage roads the capacity of
suggested, and landscaping dramatically increases the aesthetics of the the interchange would be reduced was expressed. Moreover, it
interchange. The SPUI is a good design and has a place. However, some was found that SPUIs appear to have a relatively large number of
of the newer and enhanced designs with the resulting increase in size rear-end accidents.
may be counterproductive.
The final report from the TTI project endorsed the SPUI as a safe
and efficient design alternative to a tight urban diamond interchange
As Michigan marks its 100th year of automobile manufacturing, it (TUDI) in restricted urban conditions. However, there was still a
should also be noted that the freeways in the Detroit area have been concern for pedestrian safety, and it was determined that SPUIs cost
in service since 1942. The first 11 km (7 mi) were constructed in more than TUDIs. It was concluded that “motorist’s driving skills
1942 to get workers from Detroit to the World War II bomber plant at SPUIs are expected to improve with time” (2). It was also stated
at Willow Run. On December 19, 1960, Michigan claimed to have that “the tight urban interchange is a viable alternative to all other
the longest freeway [322 km (200 mi)] in the nation. Many of these interchange forms” (2). Although the capacity analyses determined
early interchanges preceded the Interstate system and, thus, Inter- that a simple SPUI is slightly more efficient than a TUDI, the advan-
state design standards. The Michigan Department of Transportation tage diminishes as the SPUI becomes larger. It was concluded that
(MDOT) is considering the much needed rehabilitation and upgrad- the SPUI with a four-phase signal operation “clearly does not have
ing of many of these and other interchanges located in the urban as efficient lane capacities” (2).
environments. MDOT and Michigan State University have under- Other authors have also stated a concern for pedestrian safety
taken a joint effort to evaluate the appropriateness of an urban inter- with SPUIs. In addition, a concern for vehicle traffic violations was
change geometric configuration, the single-point urban interchange expressed. Due to the SPUI’s unusual design, several authors have
(SPUI) (Figure 1), as an alternative design to those presently used expressed a need for excellent sight lines and a heavy reliance on
by MDOT. In particular, the Michigan urban diamond interchange guide signs, pavement markings, and lane use signing. A concern
(MUDI) (Figure 2) will be considered. for the impacts resulting from a skewed intersection was also found
There are no SPUIs in Michigan, and most of the known SPUIs in the literature. Fowler (3) concluded that as the directional split of
are located in southern states. As a result, the first step was to deter- the cross-street through volumes increases, the performance of a
mine what literature already existed on the subject. Then, e-mail and TUDI improves with respect to that of a SPUI.
telephone surveys of other state departments of transportation Leisch et al. (4) stated in two publications that a SPUI is an effec-
(DOTs) on their experience with SPUIs were conducted. Next, a tive design. However, it was also stated that it has little potential for
field review was conducted in six states. In Michigan, three areas of expansion and that any possible advantage diminishes as the clear-
concern were raised before the field reviews commenced. These ance intervals increase. No conclusive observation of safety differ-
areas are a need to rely heavily on traffic lane markings, the ability ences between the two configurations was found, and it was stated
that the potential exists for higher accident rates with a SPUI. In
Department of Civil and Environmental Engineering, Michigan State addition, an analysis of the accident rates for three SPUIs was
University, A349 Engineering Building, East Lansing, Mich. 48824. compared to the accident rate for three compressed diamond
12 Paper No. 971108 TRANSPORTATION RESEARCH RECORD 1579

referred to as a Michigan Urban Diamond Interchange (MUDI). The


MUDI has parallel one-way frontage roads, with additional bridges
over the freeway located approximately 213 m (700 ft) to the left
and right of the structure for the crossroad. Left turns from the cross-
road onto the freeway are accommodated via a right turn onto the
first frontage road and a U-turn over the freeway via the extra
bridges, and a vehicle reaches the entrance ramp via the other
frontage road.
The capacity of a freeway interchanging traffic with an urban arte-
rial is normally limited by its ability to accommodate left-turning
traffic onto and from the freeway. Both the SPUI and the MUDI are
promoted as high-capacity interchanges that require a minimum of
right-of-way.
FIGURE 1 Typical SPUI configuration. In urban areas, access to property abutting the freeway is often
of such importance as to require parallel frontage roads. In addi-
tion, intelligent transportation system strategies, such as ramp
interchanges (CDIs) by the Utah DOT (UDOT) (5). UDOT found metering, function better with continuous frontage roads. However,
that the SPUI had an accident rate that was one-third to one-half that the intersections of the frontage roads with the crossroad usually
of a CDI. However, the sample size available is too narrow, which require the use of traffic signals. These closely spaced traffic sig-
could bias these results. nals may have a significant negative impact on the operation and
capacity of the crossroad. This impact may also be influenced by
MICHIGAN URBAN DIAMOND the cross section (divided multilane versus nondivided multilane)
INTERCHANGE DESIGN of the crossroad.

In Michigan, freeway interchanges in urban areas are usually some


type of a partial cloverleaf or a highly modified diamond often
AASHTO E-MAIL SURVEY

A survey was submitted by e-mail to each of the other 49 state


DOTs. The survey requested fundamental information on the
design and operation of SPUIs. Although the survey was as suc-
cinct as possible (i.e., it had only 11 questions), only 14 state DOTs
responded. The responding state DOTs were those of Arkansas,
California, Indiana, Iowa, Missouri, New Mexico, New York,
North Dakota, Oklahoma, Pennsylvania, Texas, Vermont, West
Virginia, and Wyoming. Of these, only California, Indiana, Mis-
souri, and New Mexico have operating SPUIs. In addition, New
York is designing its first SPUI. None of the responding states with
existing SPUIs reported having frontage roads as part of the design.
As expected, the state DOTs did not necessarily respond to each
question.
Generally, the respondents reported that the major advantages of
a SPUI configuration with respect to other geometric configura-
tions are that it requires the same or less right-of-way, has fewer
delays and lower user costs, is adaptable to frontage roads, requires
fewer signals, costs less, has fewer conflict points, allows for
U-turn movements, and has superior aesthetics. Another advantage
is that it is easier to coordinate the traffic signals of a SPUI with
the surrounding system. The responding states stated that the major
disadvantages of a SPUI configuration with respect to other inter-
change designs are that it is not an optimal solution if adequate
right-of-way is available, it costs more, it has long or special bridge
structures, signals are difficult to mount, it has long clearance inter-
vals, it has unbalanced traffic flows from the off ramps, it is tough
on pedestrians, it should not be considered where the right-of-way
allows for the construction of a partial-cloverleaf interchange, it
has less capacity than a partial-cloverleaf interchange, the down-
stream intersections may control the flow, left-turn storage capac-
ity on the crossroad is critical, and sight distance will always be a
FIGURE 2 Typical MUDI configuration. concern.
Dorothy et al. Paper No. 971108 13

The responses received from the different states varied widely. two of the state traffic engineers reported that they progressed the
With respect to delay, one state reported that delay decreased and traffic on the crossroad arterial. Most of the states reported that they
another reported no noticeable increase in delay. Accident rates rely solely on traffic-actuated signalization. One state engineer
were reported to be similar to those for diamond interchanges or reported that it is difficult to progress the crossroad traffic because
there was no noticeable increase in accidents. One state reported that the SPUI requires too long of a cycle length. Another engineer
signing was more difficult, and two other states reported that they responded that the older and smaller designs were much easier to
used conventional signing. One state reported that it used conven- operate.
tional pavement markings, another state reported that pavement The comments of the Minnesota DOT were of special interest
markings may be a problem, and a third state reported that there since that state has a climate similar to that of Michigan. The district
is a need for extensive pavement markings. Reports indicated that traffic engineer in Duluth believed that a SPUI was easier to oper-
a SPUI cost $2 million to $4 million more than a conventional ate than a conventional diamond interchange. In addition, he
diamond, $8 million to $12 million to convert from an existing dia- reported that pedestrians did not have a problem, and he knew of no
mond, and the same as a conventional diamond. Finally, the right- wintertime difficulties.
of-way requirements were reported to be similar to those for a tight
diamond, to depend on the use of retaining walls, and to be less than
those for a conventional diamond. FIELD REVIEW
The limited number of responses to the survey restricted its use-
fulness for comparison to the conditions found in Michigan. On the basis of the information gathered through the e-mail and tele-
Although maintenance of a SPUI was not a problem for one state phone surveys, sites were selected in several states for inclusion in
and was “little” problem for another state, snow plowing was not the field review. These sites were located in Indiana, Illinois,
considered, because none of the responding states with SPUIs is con- Minnesota, Florida, Missouri, and Arizona. Without exception,
sidered to be in a climate where snow plowing would be a problem. the various state DOTs and county road commissions were very
In addition, Michigan tries to progress traffic on most of its cross- cooperative and their representatives were a pleasure to meet with.
roads. However, only one state responded that it had a crossroad with During a typical field review, the engineers and technicians
good progression. The other states did not address this issue. responsible for the operation of the SPUI being studied were inter-
viewed. These interviews included a visit to the site where the actual
operation of the SPUI was discussed. If possible, plan view draw-
ings, signing plans, aerial photographs, signal timings, traffic vol-
TELEPHONE SURVEY umes, in-house studies, and economic data pertaining to the SPUI
in question were collected. In the field, extensive photographs and
The preliminary review of the literature and the response to the videos of the interchange were taken.
e-mail survey, although helpful, had significant inconsistencies and On the basis of the field review conducted between January and
lacked information in key areas. A telephone survey was subse- May 1996, subjective observations can be made about the design
quently conducted with some of the state DOTs that responded to and operation of a SPUI. These observations can best be presented
the e-mail survey and with several additional state DOTs. The state by grouping them into several topic areas including geometric
DOTs called in the telephone survey were Indiana, Illinois, Min- design, signal operation, pedestrian control, pavement markings,
nesota, Florida, Arizona, Missouri, and Texas. The objective of the and land use and landscaping.
phone survey, in addition to collecting more information, was to
locate the most appropriate sites for a field review. Specifically, it
was desired to observe the operation of SPUIs with frontage roads, Geometric Design
the progression of traffic on the crossroad, and the operation of
SPUIs under winter conditions. The geometric features of the SPUIs varied greatly from state to
The individuals having the greatest knowledge of the operations state. The difference in designs was much greater than anticipated,
of the SPUIs were sought. Thus, most of the phone conversations and this difference may explain some of the inconsistencies in the
were with the district traffic engineers. Of the seven state DOTs tele- responses to our e-mail and telephone surveys.
phoned, four gave strong favorable recommendations on the posi- The most significant observed difference in design is between a
tive aspects of a SPUI. One state DOT could not recall its operation SPUI with the crossroad going over the freeway and a SPUI with the
and had ambivalent impressions. The remaining two state DOTs had freeway going over the crossroad. The SPUIs with the crossroad
very unfavorable opinions. going over the freeway were found to be a preferred design (Figure 3).
Of the favorable comments, one engineer responded that the oper- The resulting single-point intersection looks and operates more like
ation was “wonderful,” and another responded that the SPUI was his a conventional signalized intersection. Because of this, driver con-
preferred design. However, one of the state engineers responded that fusion is greatly reduced. Conversely, significant driver confusion
the SPUI did not have a single advantage with respect to the design was observed at interchanges that used a design with the crossroad
and operation of a conventional tight diamond. Also on a negative going under the freeway. At times, vehicles became trapped in the
note, another state traffic engineer responded that when the state’s intersection due to driver confusion, creating a dangerous situation
first SPUI was open to traffic, it was like a “zoo,” with the first (Figure 4). An engineer in one state that had recently opened a new
6 months of operation being “total chaos.” SPUI of this design referred to “mass confusion when opened.” In
When attempting to narrow the search for appropriate field addition, routing the freeway over the crossroad exposes the free-
review sites, it was discovered that only two of the states had any way and major traffic volume to differential icing in cold-weather
experience operating SPUIs with frontage roads. Surprisingly, only climates.
14 Paper No. 971108 TRANSPORTATION RESEARCH RECORD 1579

FIGURE 3 SPUI in Minnesota with crossroad going over the


freeway, with all signal heads located on a single overhead
tubular beam.

Another significant difference in design is related to the physical


FIGURE 5 U-turn lane accommodates large trucks.
size of the interchange. Some of the newer SPUI designs include the
provision of a dedicated U-turn lane to permit a U-turn maneuver
from the exit ramp back onto the entrance ramp (Figure 5). These
dedicated structures were located under the tail spans, requiring the
tail spans to be much longer than normal. Although the smaller The impact of continuous frontage roads on the overall operation
designs can provide for most U-turns, this dedicated lane is neces- of a SPUI was a key area of interest. It was explicitly desired to
sary to accommodate large trucks and to increase the speed of the observe the operation of a SPUI with parallel frontage roads whose
maneuver. Even at interchanges where this maneuver was prohib- intersections with the crossroad are signalized and accommodate
ited, it was still observed to occur regularly. However, the smaller significant through traffic. Two of the states visited were anticipated
designs were observed to function better than the larger designs. In to have these types of frontage roads on the basis of the responses
addition, the right-of-way requirements are obviously much less from the e-mail and telephone surveys. However, these frontage
with the smaller design. roads did not satisfy Michigan’s requirements. One of the state’s
The designs of the structures varied from state to state. They are frontage roads are what would be considered ramps with private
generally much longer than those of conventional diamond inter- driveways. The other state had a two-way frontage road that was not
changes. For example, some of the spans were greater than 146 m observed to generate the through traffic desired. Several of the
(480 ft) in length. Often, there are three spans of nearly equal district traffic engineers expressed strong opinions that providing
lengths. Some of the structures were very noisy, and the resulting for continuous frontage roads with a SPUI is a poor design and
booms could be heard for kilometers. This noise was the source of counteracts the advantages of a SPUI.
almost constant complaints from nearby residents. Because of the The geometry of the exit ramps often flared from one lane to three
large widths and lengths, the roads under the structures were dark. lanes at the ramp terminus. Of these three lanes, two were for left-
Lighting was often provided under the structures during the day, and turning traffic and one was for right-turning traffic. The right- and
visibility at locations where light-colored bridge paints (e.g., sand left-turning lanes are separated by a large channelized island. The
or concrete) were used was noticeably better than that where dark- dual left-turning traffic on the off-ramp often backs up during peak
colored bridge paints were used. These undesirable characteristics periods. This blocks right-turning traffic from exiting and locks up
were not evident when the crossroad went over the freeway. the ramp (Figure 6). In the case in which the freeway goes over the
crossroad, sight distance is a concern.
The geometry of the on-ramps normally consisted of two left-turn
lanes, under signal control, and a free-flow right-turn lane. These
lanes merge down to one lane before entering the freeway. This
geometry causes a racetrack effect on the on-ramp as vehicles vie
for position to merge. This effect, along with the short distance
allowed for the merge to occur, results in a sideswipe crash problem.
However, in at least one state, the crash reporting system is struc-
tured in such a way that these sideswipe crashes are not referenced
to the interchange. Thus, it is difficult to get a clear picture of the
crash experience of the interchange.
Most of the SPUI designs, regardless of state, added several
additional lanes to the basic laneage of the crossroad at the inter-
change. A typical design would have a six-lane crossroad being
widened to nine lanes at the interchange. The additional lanes are
typically a right-turn bay and provision for dual left-turn lanes for
the on-ramp. In addition to the auxiliary lanes, most of the cross-
FIGURE 4 Confused driver (car with lights on) stopped in roads had raised, concrete medians ranging in width from 1.2 m
middle of SPUI while traffic proceeds on either side. (4 ft) to 3.6 m (12 ft).
Dorothy et al. Paper No. 971108 15

depending on where one looked. In addition, the signal heads, when


mounted on posts, were vulnerable to damage from motorists
running into them.
The physical size of the interchange also affected the signal oper-
ation. If the intersection area is very large, longer clearance times
are required for traffic to clear the intersection before allowing the
next phase. Additionally, the green signal arrow for left-turning traf-
fic was often canted to give the motorist a sense of direction in these
large intersection areas. Still, driver confusion resulted from the
large distances needed to clear the intersection (Figure 4). Three
common mistakes were observed. The first results when the lead car
does not start on green because the driver is confused as to which
signal indication to follow. The second results when a motorist
entering the intersection from the exit ramp on a green light must
drive through a red indication meant for the crossroad. Vehicles
were observed to stop in the middle of the interchange and wait for
FIGURE 6 Dual left-turning traffic on the off-ramp is backed
up, blocking right-turning traffic. a green indication. The third results when a motorist starts into the
intersection and simply gets lost because of the large size of the
interchange.
Signal Operation

The operation and placement of traffic signals were of special inter- Pedestrian Control
est. Each state’s practice differed significantly. The cycle lengths
varied from 80 to 180 sec. The reviewed SPUIs that had longer cycle The ability to accommodate pedestrian movements varied greatly
lengths usually had fully actuated signal phases for all movements, from site to site. Many of the locations simply had no pedestrian
which was not what was expected. movements to accommodate. When pedestrians were present, it was
Of special interest was the ability to progress traffic on the cross- not difficult for them to move parallel to the crossroad and cross the
road. Two of the SPUIs reviewed had a crossroad arterial that was ramp movements. However, with all movements going through the
part of a pretimed progressed strategy. Although the interchange center of the interchange and a signal operation using fully traffic-
was operating well below capacity, it was obvious that progression actuated phases, there is always traffic moving through the inter-
would not be a problem. These interchanges were of the smaller section. This makes it hard for pedestrians to cross the crossroad. In
design, which results in shorter clearance times and allows for a addition, the width of the crossroad, often six to eight lanes, makes
shorter cycle. However, the impact of the SPUI on intersections it difficult for pedestrians to cross the crossroad. Often, pedestrians
downstream must be considered. Comments were made to the effect would become trapped on the concrete channelization of the cross-
that the SPUI dumps traffic on the downstream nodes, causing road when attempting to cross. Some sites actually prohibited pedes-
delays. This was hard to judge in the field because none of the SPUIs trians from crossing. However, this prohibition was often violated
reviewed were operating near their capacities. because, typically, the only other opportunity to cross was at the next
Most of the SPUIs reviewed had a three-phase signal operation. intersection, which was usually 400 m (a quarter of a mile) away.
The three phases were usually left-turn entrance ramp movements,
left-turn exit ramp movements, and crossroad through movements.
One state provided for a right-turn exit ramp green arrow during the Pavement Markings
left-turn entrance ramp phase. Usually, the exiting right turn was
accommodated via a free-flow, channelized merge with the cross- With the potential for snow covering faced by Michigan, the need
road traffic. However, a skewed intersection affected the operation to rely heavily on traffic lane markings was a concern that was
of the signal phasing. At these locations, there are four signal focused on. For the most part the larger SPUIs have supplemental
phases: first exit ramp movement, opposing exit ramp movement, lane markings to assist the motorist with the left-turn movement.
left-turn entrance ramp movements, and crossroad through move- The need for these pavement markings is paramount. However,
ments. In addition, the skew causes the clearance times to increase. even in the best-case scenario, these pavement markings overlap,
The placement of the traffic signal heads also varied greatly from creating driver confusion (Figure 7). In a skewed configuration, this
state to state and by geometric design. In the case of a SPUI in which overlap is taken to the extreme, and it can be confusing even to a
the crossroad goes over the freeway, all of the signal heads are driver familiar with the interchange. However, the need for supple-
located on a single overhead tubular beam (Figure 3). Thus, the mental lane lines for the turning movement was not evident for
three-phase operation was analogous to a traditional at-grade inter- the locations where the crossroad went over the freeway or the
section with a three-phase signal. This design typically took little interchange was small.
right-of-way. This SPUI design was observed to function very well, At one location lights were placed in the pavement to help illu-
although the traffic volumes were not heavy. In the case of a SPUI minate the turning path. When left-turning traffic was given a green
in which the freeway goes over the crossroad, the signal heads are light, these “runway” lights would light up green along the path to
mounted on the structure. However, some states have post-mounted be taken by the motorist (Figure 8). However, the design of these
signals located on traffic islands. In one interchange alone there lights is such that they are a maintenance problem because they can
were 24 signal heads. With this proliferation of signal heads, it was become filled with dirt, which obscures the lens. They also raise sev-
possible to see green, amber, and red indicators at the same time eral tort liability issues. For example, if the runaway lights are not
16 Paper No. 971108 TRANSPORTATION RESEARCH RECORD 1579

driveway cuts in the median close to the interchange and a resultant


increase in conflicts in the interchange area. In one state, driveway
access was granted on the ramps themselves, greatly increasing the
complexity of their operation. Other states had complete access con-
trol to the abutting properties. A narrow median was often used on
the crossroad to limit access to properties except at specific loca-
tions. When allowed, access was typically handled at signalized
intersections. This strategy reduced conflict areas and should also
reduce the severity of the accidents that do occur.
Landscaping was present in only two of the states whose SPUIs
were reviewed, and both of these states had southern climates. In
one state, much of the original landscaping had been removed. The
high cost of maintenance and problems with transients were cited as
the reasons for its removal. In Arizona, however, great efforts had
been taken to landscape the interchanges. The effect of this land-
scaping was spectacular, especially when the crossroad went over
FIGURE 7 Pavement marking overlap creates driver confusion.
the freeway (Figure 9). The large island structures that result from
the separation of the left- and right-turn ramp movements in the
working at the time of an accident, can it be said that one of the traf- SPUI design provide an excellent space for landscaping. This land-
fic control devices was not working? Additionally, experience has scaping varied from small flowers, shrubs, and cacti to large palm
shown that there is a problem with motorcycles executing turning trees and flowering bushes.
maneuvers and hitting the slick surfaces of the lights when they are
wet, causing an accident.
Many of the SPUIs reviewed have channelized islands to help CONCLUSIONS
guide drivers as they negotiate through the single-point intersection.
Typically, directional signing was also present on the center island. To evaluate the SPUI as an alternative to designs currently in use in
The location of this signing makes it extremely vulnerable to dam- the state of Michigan, in particular, MUDI, several steps have been
age from motorists who stray onto the island. During the field review, taken. The preliminary review of the literature and the limited num-
it became obvious that motorists frequently strike these islands while ber of responses to the e-mail survey contained significant incon-
negotiating the intersection. Channelized islands are not popular in sistencies and lacked information in key areas. Thus, a telephone
Michigan because of their interference with snow plowing. survey was used to locate the most appropriate sites for a field
review. These sites were located in Indiana, Illinois, Minnesota,
Land Use and Landscaping Florida, Missouri, and Arizona. On the basis of this field review,
subjective observations can be made about the design and operation
The type of land use surrounding the SPUIs reviewed and the type of the SPUI. These observations were grouped into the areas of
of landscaping varied widely between states. In one case, the SPUI geometric design, signal operation, pedestrian control, pavement
had no development in either direction along the crossroad and was markings, and land use and landscaping of SPUIs.
located in an almost rural setting. For the remaining cases, the main The most significant geometric design difference in the SPUIs
difference in the type of land use surrounding the interchange was reviewed is between a SPUI with the crossroad going over the free-
based on access control to the crossroad. way and a SPUI with the freeway going over the crossroad. The
Some states did not control access to the crossroad or, in some SPUI with the crossroad going over the freeway was found to be a
cases, the interchange itself. This perpetuates a large number of preferred design. Another design difference was related to the

FIGURE 8 “Runway” lighting to help illuminate the turning


path. Note the buildup of debris. FIGURE 9 Typical landscaping of a SPUI in Phoenix, Ariz.
Dorothy et al. Paper No. 971108 17

physical size of the interchange. SPUIs without dedicated U-turn interchange was reviewed. This is also not an effective solution in
lanes appeared to accommodate U-turns as well as those with dedi- Michigan, due to the snow removal requirements.
cated U-turn lanes did. Thus, the smaller designs were observed to The major differences in land use between the different states
function better than the larger designs. In addition, the right-of-way can mostly be attributed to access control. Those states that did not
requirements are less with the smaller designs. Moreover, the design control access near the interchange had a large number of conflict
of structures was observed to be very important. In some cases, the areas in the interchange area. Those states that did control access
structures were very noisy, causing complaints from nearby residents. had a limited number of conflict areas. Where landscaping was
Because of the large size of these structures, the roadway under the provided, the aesthetics of the interchange were dramatically
structure is dark. These undesirable structural characteristics are not increased.
evident when the crossroad goes over the freeway. In addition, sev- On the basis of the work done to date, SPUI is a good design and
eral engineers expressed strong opinions that the use of continuous has a place. However, some of the newer and enhanced designs with
frontage roads with a SPUI counteracts the advantages of the design. the resulting increase in size may be counterproductive.
Furthermore, in the case in which the freeway goes over the cross-
road, sight distance is a concern. Finally, the geometry of the typical
on-ramps results in a sideswipe crash problem. ACKNOWLEDGMENTS
The signal operation strategy used by each state differed signifi-
cantly. Cycle lengths varied from 80 to 180 sec, with longer cycle The research project presented in this paper is funded by a grant
lengths usually having fully actuated signal phases for all move- from the Michigan Department of Transportation. Part of the fund-
ments. The interchanges reviewed were operating below capacity, ing is from the federal SPR-97653 program, specifically Federal
and at this level, progression of the crossroad traffic was not a prob- Project No. SPR-0010029.
lem. However, the impact of the SPUI on intersections downstream
must be considered. If the interchange area was very large, the clear-
ance times became quite long and there was significant driver con-
fusion. Finally, the best placement of traffic signal heads occurred REFERENCES
in designs in which the crossroad went over the freeway, allowing
the signal heads to be located on a single overhead tubular beam. 1. Bonneson, J. A., and C. J. Messer. A National Survey of Single-Point
Urban Interchanges. Texas Transportation Institute, College Station,
The ability to accommodate pedestrians varied greatly between
1989.
designs. Typically, it was not difficult for pedestrians to move 2. Messer, C. J., and J. A. Bonneson. NCHRP Report 345: Single Point
parallel to the crossroad and cross the ramp movements. However, Urban Interchange Design and Operations Analysis. TRB, National
due to the characteristics of the SPUI, there is always traffic Research Council, Washington, D.C., 1989.
moving through the intersection. This makes it extremely difficult 3. Fowler, B. C. An Operational Comparison of the Single-Point Urban and
Tight-Diamond Interchanges. ITE Journal, April 1993.
for pedestrians to cross the crossroad. 4. Leisch, J. P., T. Urbanik, and J. P. Oxley. A Comparison of Two Dia-
The need for pavement markings in large SPUIs is paramount. mond Interchange Forms in Urban Areas. ITE Journal, May, 1989.
However, these pavement markings can overlap and cause driver 5. Abbey, L., and G. S. Thurgood. Design and Operational Features of the
confusion. This resultant driver confusion is most pronounced when Single Point Urban Interchange. Utah Department of Transportation, Salt
Lake City, June 1991.
the crossroad is skewed. The use of “runway” lighting was not
observed to be an effective solution to this problem. Additionally, Publication of this paper sponsored by Committee on Operational Effects of
the use of channelized islands to help guide drivers through the Geometrics.

Vous aimerez peut-être aussi