CONOCOPHILLIPS INDONESIA INC. LTD.

Contract No. CS70-12398

NORTH BELUT PROJECT


WHP EPC

VENDOR DOCUMENTS
FOR
WELLHEAD CONTROL PANELS
PO No : A-84508-9787-4W-2200
TAG No : 32-QJP-001 & 32-QJP-101

PERFORMANCE TESTING AND


ACCEPTANCE TEST PROCEDURE

Document No.
ID-F-NB-P-JP-002-H05-0001

PT. NIPPON STEEL CONSTRUCTION INDONESIA

VENDOR NISCONI COPI RETURN


REV ISSUE
Reviewed Approved Issue Date Reviewed Approved Issued Date STATUS DATE
For
D MOS MAN 25-Juni-07
Comments
For
0 MOS MAN 26-Dec.-07
Construction
NORTH BELUT PROJECT
WHP EPC
PT. NISCONI PT. IBP
TITLE DOCUMENT NUMBER REV DATE PAGE
PERFORMACE TESTING AND
ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 2 of 35
ACCEPTANCE TEST PROCEDURE

REV REVISION NOTES


D Issue For Approval
0 Approved For Construction
NORTH BELUT PROJECT
WHP EPC
PT. NISCONI PT. IBP
TITLE DOCUMENT NUMBER REV DATE PAGE
PERFORMACE TESTING AND
ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 3 of 35
ACCEPTANCE TEST PROCEDURE

TABLE OF CONTENTS

1 GENERAL 4

2 VISUAL INSPECTION TEST 4

2.1 Body Inspection 4

2.2 Internal View Inspection 4

3 FUNCTIONAL TEST 5

3.1 Preparation before Test 5

3.2 WHCP Function and Leak Test 5


3.2.1 Start & Stop Motor Pump on Manual Condition (Without PLC Simulator) 5
3.2.2 Start & Stop Motor Pump on Remote Condition (With PLC Simulator) 5
- Pump 30-QJP-101-2A 6
- Pump 30-QJP-101-2B 6
- Pump 30-QJP-101-1A 6
- Pump 30-QJP-101-2B 7
- Hand Pump for Medium Pressure Supply 7
- Hand Pump for High Pressure Supply 7

4 CLEANLINESS TEST 8

5 RECORDING OF INSPECTION AND TEST DATA 8

FORM 1 - VISUAL INSPECTION 9

FORM 2 - HPU PERFORMANCE TEST 10

FORM 3 – FUNCTION TEST 11

FORM 4 – PUNCH LIST DURING FAT 34


NORTH BELUT PROJECT
WHP EPC
PT. NISCONI PT. IBP
TITLE DOCUMENT NUMBER REV DATE PAGE
PERFORMACE TESTING AND
ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 4 of 35
ACCEPTANCE TEST PROCEDURE

1 GENERAL

The purpose of this document is to define the procedure of Factory Acceptance


Test for Wellhead Control Panel and Hydraulic Power Unit

The verification and tests specified hereafter is considered being compliance to


be carried out on the unit and its equipment.

The document to be handed over shall include at least:

No. Documents Document Number Company Doc. Num.


1 General Arrangement Drawing 837005-IN-WHCP-006 ID-F-NB-P-JP-002-B01-0001
2 Schematic Diagram 837005-IN-WHCP-009 ID-F-NB-P-JP-002-C03-0101
3 Instrument Data Sheets 837005-IN-WHCP-010 ID-F-NB-P-JP-002-C15-0001
4 Block Wiring Diagram 837005-IN-WHCP-011 ID-F-NB-P-JP-002-C19-0001
5 Name Plate Format Drawings 837005-IN-WHCP-013 ID-F-NB-P-JP-002-D01-0101
6 Detailed Fabrication Drawings 837005-IN-WHCP-014 ID-F-NB-P-JP-002-D04-0001
7 Electrical Connection Diagram 837005-IN-WHCP-015 ID-F-NB-P-JP-002-D06-0101
Instrument/Electrical Panel Detail
8 837005-IN-WHCP-016 ID-F-NB-P-JP-002-E01-0101
Drawings
9 Calculation notes 837005-IN-WHCP-018 ID-F-NB-P-JP-002-F04-0001
10 Cause and Effect Chart 837005-IN-WHCP-029 ID-F-NB-P-JP-002-C16-0001

2 VISUAL INSPECTION TEST

The visual inspection test consists of (Form 1):

2.1 Body Inspection


• General aspect
• Size (Dimensional Check)
• Labeling
• Front Side
• Left Side
• Right Side
• Rear Side

2.2 Internal View Inspection


• General Aspect
• Equipment Conformity (Data sheet and test reports)
• Equipment Location
• Tubing work
• Wiring & Termination
• Labeling
• Cleanliness
• Accessibility
NORTH BELUT PROJECT
WHP EPC
PT. NISCONI PT. IBP
TITLE DOCUMENT NUMBER REV DATE PAGE
PERFORMACE TESTING AND
ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 5 of 35
ACCEPTANCE TEST PROCEDURE

3 FUNCTIONAL TEST

3.1 Preparation before Test

Pressurized the initial Pressure in Hydraulic Accumulator with Nitrogen gas (90% of
minimum operating pressure) and the results shall be recorded.

Required several preparation & check items to be done, before running the Wellhead
Control Panel as follows:
• Fill the hydraulic tank with “Tellus 32” until 75% of the full tank.
• Tighten all the tubing and pipe connection.
• Plug the output to all Wing Valve, SSV, and SCSSV bulkheads.
• Open all valve
• Close the ball valve in return line.
• Connect Pressure Transmitters to Junction Box.
• Connect SOV to Junction Box.
• Connect Push Button to Junction Box.
• Connect all Junction Box to PLC simulator.
• Install power and control cable to each motor.
• Show oil cleanliness to NAS 1638 class 6.

3.2 WHCP Function and Leak Test

The Function test will be perform for each module of well and all part of instruments. For
the leak test will be perform and record. Duration for the leak test is 12 hours.

3.2.1 Start & Stop Motor Pump on Manual Condition (Without PLC Simulator)

The purposes of this test are to ensure Motor can be run by Local control station on
Wellhead Control Panel and to ensure a relief valves setting pressure are working
properly.

Without PLC simulator motor can be run until the pressure reach set point of relief valve
(3,300 psig for MP & 6,050 psig for HP), because if we used PLC simulator motor will be
stop at 3,000 psig (MP) & 5,500 psig (HP) according to set point of start & stop for motor.
The test result will be reported (Form 2 A).

3.2.2 Start & Stop Motor Pump on Remote Condition (With PLC Simulator)

The purposes of this test are to ensure the whole system will work properly after WHCP
are connected to PSD system. The PSD system represent by PLC Simulator.

For pressurize the system we sequence to start & stop the motor pump. Depend which
motor pump need to be used.
NORTH BELUT PROJECT
WHP EPC
PT. NISCONI PT. IBP
TITLE DOCUMENT NUMBER REV DATE PAGE
PERFORMACE TESTING AND
ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 6 of 35
ACCEPTANCE TEST PROCEDURE

- Pump 30-QJP-001-2A

Working Step:
1. Open the line of pump 30-QJP-001-2A (AC-4, AC-5, AC-6, AC-8,CD-13)
2. Open isolation valve to accumulator CA5 & CA6, and close the return line
3. Start the motor and automatically stop when the pressure of the hydraulic
already reach 3000 Psig (Check on PI-1020A and PT-1014)
4. Check the running time duration of the motor to reach the desired operating
pressure.
5. If the pressure lines drop before 30 minutes, check the fitting and tubing
connections, which leakage may occur, repeat step 4 to 7.

- Pump 30-QJP-001-2B

Working Step:
1. Close valve AC-3
2. Open the return/bleed line of accumulator CA-5 & CA6
3. Check on PI-1020B, the pressure should back to initial pressure.
4. Close return/bleed line of accumulator CA-5 & CA-6
5. Close the line to Pump 30-QJP-001-2A (AC-4), open valve AC-3
6. Open the line of pump 30-QJP-001-2B (AC-9, AC-10, AC-11, CD-14)
7. Start the motor and automatically stop when the pressure of the hydraulic
already reaches 3000 Psig (Check on PI-1020B and PT-1014).
6. Check the running time duration of the motor to reach the desired operating
pressure.

- Pump 30-QJP-001-1A

Working Step:
1. Valve AC-2 open position
2. Open the line of pump 30-QJP-001-1A (AC-12, AC-13, AC-14, AC-16, CD-15)
3. Open isolation valve to accumulator CA-11 & CA-12, and close the return
line
4. Start the motor and automatically stop the motor if the pressure of the
hydraulic already reach 5500 Psig (Check on PI-1021A and PT-1015)
5. Check the running time duration of the motor to reach the desired operating
pressure.
6. While all motor in stop condition, wait for 30 minutes. If the line pressure keeps
in the working pressure, mean the Hydraulic Unit working properly.
7. If the pressure line drops before 30 minutes, check the fitting and tubing
connections, which leakage may occur, repeat step 4 to 7.
NORTH BELUT PROJECT
WHP EPC
PT. NISCONI PT. IBP
TITLE DOCUMENT NUMBER REV DATE PAGE
PERFORMACE TESTING AND
ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 7 of 35
ACCEPTANCE TEST PROCEDURE

- Pump 30-QJP-001-1B

Working Step:
1. Close valve AC-2
2. Open the return/bleed line of accumulator CA-11, CA-12
3. Check on PI-1021A, the pressure should back to initial pressure.
4. Close return/bleed line of accumulator CA-11, CA-12
5. Close the line to pump 30-QJP-001-1A (AC-12)
6. Open the line of pump 30-QJP-001-1B (AC-17, AC-18, AC-19)
7. Start the motor and automatically stop the motor if the pressures of the
hydraulic already reach 5500 Psig (Check on PI-1021B and PT-1015).
8. Check the running time duration of the motor to reach the desired operating
pressure.

- Hand Pump for Medium Pressure Supply

Working Step :
1. Close valve AC-3
2. Open return line of accumulator CA-5 and CA-6
3. Check the pressure on PI-1020A and PI-1020B, the pressure should back to
initial pressure
4. Close the return line of accumulator CA-5 and CA-6.
5. Close valves AC-9, AC-8, and CD-14.
6. Open Valves AC-3, AC-4, AC-5, AC-6, AC-7, AG-1, CD-13.
7. Open valve AB-11 and start the hand pump until the pressure on PI-1020A
reach 3300 psi

- Hand Pump for High Pressure Supply

Working Step :
1. Close valve AC-2
2. Open return line of accumulator CA-11 and CA-12
3. Check the pressure on PI-1021A and PI-1021B, the pressure should back to
initial pressure
4. Close the return line of accumulator CA-11 and CA-12.
5. Close valves AC-17, AC-16, and CD-16.
6. Open Valves AC-2, AC-12, AC-13, AC-14, AC-15, Af-1, CD-15.
7. Open valve AB-12 and start the hand pump until the pressure on PI-1021A
reach 6050 psi

For the detailed instruction WHCP Function test fill the WHCP function test Form (Form 3)
NORTH BELUT PROJECT
WHP EPC
PT. NISCONI PT. IBP
TITLE DOCUMENT NUMBER REV DATE PAGE
PERFORMACE TESTING AND
ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 8 of 35
ACCEPTANCE TEST PROCEDURE

4 CLEANLINESS TEST

Cleaning test shall be done to check particle contamination level of hydraulic oil
after circulating in the HPU unit. System Cleanliness standard will refer to NAS 1638
class 6 (AEROSPACE INDUSTRIES ASSOCIATION OF AMERICA, INC.).

5 RECORDING OF INSPECTION AND TEST DATA

The result of the checks and measurement done during Factory Acceptance Test
shall be recorded on the following test forms:

• FORM 1 – VISUAL INSPECTION


• FORM 2 – HPU PERFORMANCE TEST AND LEAK TEST
• FORM 3 – WHCP FUNCTION TEST
• FORM 4 – PUNC LIST DURING FAT
NORTH BELUT PROJECT
WHP EPC
PT. NISCONI PT. IBP
TITLE DOCUMENT NUMBER REV DATE PAGE
PERFORMACE TESTING AND
ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 9 of 35
ACCEPTANCE TEST PROCEDURE

FORM 1 - VISUAL INSPECTION

A. BODY INSPECTION

CONFORMITY
Aspect To be Checked Yes No N/A
General Aspect
Size (Dimensional Check)
Front Side
Rear Side
Right Side
Left Side

B. INTERNAL VIEW INSPECTION

CONFORMITY
Aspect To be Checked Yes No N/A
Equipment Conformity
Equipment Location
Labeling
Cleanliness
Tubing Works
Wiring and Terminations

TEST DATE: ACCEPTED REJECTED PUNCH LIST


/ /

PT INDOKOMAS PT NISCONI INDONESIA CONOCOPHILLIPS IND INC.LTD

NAME & NAME & NAME &


SIGNATURE SIGNATURE SIGNATURE
NORTH BELUT PROJECT
WHP EPC
PT. NISCONI PT. IBP
TITLE DOCUMENT NUMBER REV DATE PAGE
PERFORMACE TESTING AND
ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 10 of 35
ACCEPTANCE TEST PROCEDURE

FORM 2 - HPU PERFORMANCE TEST

A. PUMP MOTOR PERFORMANCE

Electrical Motor Power Consumption (0 – 6,050 & 3,300 PSI)


Running Stop
Tag Number Time Remarks
Ampere Voltage Ampere Voltage
30-QDE-101-1A
30-QDE-101-1B
30-QDE-101-2A
30-QDE-101-2B
Electrical Motor Power Consumption (5,300 PSI – 5,500 PSI)
Running Stop
Tag Number Time Remarks
Ampere Voltage Ampere Voltage
30-QDE-101-1A
30-QDE-101-1B
Electrical Motor Power Consumption (2,800 PSI – 3,000 PSI)
30-QDE-101-2A
30-QDE-101-2B

B. PRESSURE RELIEF VALVE FUNCTION TEST

Tag Number Set at (Psig) Result Remarks


FA1 6050
FA2 6050
FA3 6050
FB1 3300
FB2 3300

C. LEAK TEST

Recorded

TEST DATE: ACCEPTED REJECTED PUNCH LIST


/ /

PT INDOKOMAS : PT NISCONI INDONESIA CONOCOPHILLIPS IND INC.LTD

NAME & NAME & NAME &


SIGNATURE SIGNATURE SIGNATURE
FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL

NORMAL / REMOTE OPERATION (CONTROLLED BY PLC)

☼ HYDRAULIC POWER UNIT SECTION & COMMON MODULE


Medium Pressure
Start Motor (30-QDE-001-2A) & Pump (30-QJP-001-2A) or WHCP
Motor (30-QDE-001-2B) & Pump (30-QJP-001-2B) Pressure gauge MP pump-2A discharge pressure (PI 1020A) or MP pump-2B (PI 1020B) indicate 3,000 psi
LCD Pressure Transmitter (PT 1014) indicate the pressure

HMI
Display Motor MP1 or MP2 is Turn from Green (Run) to Red (Stop)

Pull the manual reset at SOV (HY 1071) WHCP


Pressure gauge MP hydraulic header pressure (PI 1091) will indicate 3,000 psi
LCD Pressure Transmitter (PT 1013) indicate the pressure

HMI
Display SOV HY 1071 is Green

High Pressure
Start Motor (30-QDE-001-1A) & Pump (30-QJP-001-1A) or WHCP
Motor (30-QDE-001-1B) & Pump (30-QJP-001-1B) Pressure gauge MP pump-1A discharge pressure (PI 1021A) or MP pump-1B (PI 1021B) indicate 5,500 psi
LCD Pressure Transmitter (PT 1015) indicate the pressure

HMI
Display Motor HP1 or HP2 is Turn from Green (Run) to Red (Stop)

Pull the manual reset at SOV (HY 1070) WHCP


Pressure gauge MP hydraulic header pressure (PI 1090) will indicate 5,500 psi
LCD Pressure Transmitter (PT 1012) will indicate the pressure

HMI
Display SOV HY 1070 is Green

Push PB "Close All Wing Valve" WHCP


All Pressure gauge Wing Valve hydraulic pressure will gradually drop to 0 psi

HMI
Display for all SOV is Red

Push PB "Close All SSV Valve" WHCP


All Pressure gauge Wing Valve hydraulic pressure will gradually drop to 0 psi
All Pressure gauge SSV Valve hydraulic pressure will gradually drop to 0 psi

Form 3 (Function Test) Page 11


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL

HMI
Display for all SOV SDY "C" is Red
Display for all SOV SDY "B" is Red

Push PB "Close All SCSSV Valve" WHCP


All Pressure gauge Wing Valve hydraulic pressure will gradually drop to 0 psi
All Pressure gauge SSV Valve hydraulic pressure will gradually drop to 0 psi
All Pressure gauge SCSSV Valve hydraulic pressure will gradually drop to 0 psi

HMI
Display for all SOV SDY "C" is Red
Display for all SOV SDY "B" is Red
Display for all SOV SDY "A" is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 12


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL

☼ WELL CONTROL SECTION

♦ Well 32QAY-001
Push PB "Open All Valves" (32 HS 1030A) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002A) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001A) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003A) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001A) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001A is Green
Display SOV SDY 1002A is Green
Display SOV SDY 1003A is Green

Push PB " Close All Valves" (32 HS 1032A) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003A) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002A) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001A) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001A) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001A is Red
Display SOV SDY 1002A is Red
Display SOV SDY 1003A is Red

Push PB " Normal Close" (32 HS 1031A) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003A) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002A) will gradually drop to 0 psi

HMI
Display SOV SDY 1003A is Red
Display SOV SDY 1002A is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 13


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL

Form 3 (Function Test) Page 14


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-002
Push PB "Open All Valves" (32 HS 1030B) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002B) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001B) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003B) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001B) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001B is Green
Display SOV SDY 1002B is Green
Display SOV SDY 1003B is Green

Push PB " Close All Valves" (32 HS 1032B) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003B) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002B) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001B) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001B) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001B is Red
Display SOV SDY 1002B is Red
Display SOV SDY 1003B is Red

Push PB " Normal Close" (32 HS 1031B) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003B) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002B) will gradually drop to 0 psi

HMI
Display SOV SDY 1003B is Red
Display SOV SDY 1002B is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 15


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-004
Push PB "Open All Valves" (32 HS 1030D) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002D) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001D) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003D) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001D) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001D is Green
Display SOV SDY 1002D is Green
Display SOV SDY 1003D is Green

Push PB " Close All Valves" (32 HS 1032D) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003D) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002D) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001D) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001D) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001D is Red
Display SOV SDY 1002D is Red
Display SOV SDY 1003D is Red

Push PB " Normal Close" (32 HS 1031D) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003D) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002D) will gradually drop to 0 psi

HMI
Display SOV SDY 1003D is Red
Display SOV SDY 1002D is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 16


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-005
Push PB "Open All Valves" (32 HS 1030E) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002E) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001E) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003E) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001E) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001E is Green
Display SOV SDY 1002E is Green
Display SOV SDY 1003E is Green

Push PB " Close All Valves" (32 HS 1032E) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003E) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002E) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001E) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001E) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001E is Red
Display SOV SDY 1002E is Red
Display SOV SDY 1003E is Red

Push PB " Normal Close" (32 HS 1031E) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003E) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002E) will gradually drop to 0 psi

HMI
Display SOV SDY 1003E is Red
Display SOV SDY 1002E is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 17


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-008
Push PB "Open All Valves" (32 HS 1030H) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002H) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001H) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003H) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001H) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001H is Green
Display SOV SDY 1002H is Green
Display SOV SDY 1003H is Green

Push PB " Close All Valves" (32 HS 1032H) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003H) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002H) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001H) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001H) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001H is Red
Display SOV SDY 1002H is Red
Display SOV SDY 1003H is Red

Push PB " Normal Close" (32 HS 1031H) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003H) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002H) will gradually drop to 0 psi

HMI
Display SOV SDY 1003H is Red
Display SOV SDY 1002H is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 18


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-009
Push PB "Open All Valves" (32 HS 1030I) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002I) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001I) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003I) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001I) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001I is Green
Display SOV SDY 1002I is Green
Display SOV SDY 1003I is Green

Push PB " Close All Valves" (32 HS 1032I) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003I) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002I) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001I) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001I) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001I is Red
Display SOV SDY 1002I is Red
Display SOV SDY 1003I is Red

Push PB " Normal Close" (32 HS 1031I) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003I) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002I) will gradually drop to 0 psi

HMI
Display SOV SDY 1003I is Red
Display SOV SDY 1002I is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 19


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-011
Push PB "Open All Valves" (32 HS 1030K) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002K) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001K) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003K) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001K) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001K is Green
Display SOV SDY 1002K is Green
Display SOV SDY 1003K is Green

Push PB " Close All Valves" (32 HS 1032K) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003K) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002K) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001K) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001K) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001K is Red
Display SOV SDY 1002K is Red
Display SOV SDY 1003K is Red

Push PB " Normal Close" (32 HS 1031K) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003K) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002K) will gradually drop to 0 psi

HMI
Display SOV SDY 1003K is Red
Display SOV SDY 1002K is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 20


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-012
Push PB "Open All Valves" (32 HS 1030L) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002L) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001L) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003L) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001L) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001L is Green
Display SOV SDY 1002L is Green
Display SOV SDY 1003L is Green

Push PB " Close All Valves" (32 HS 1032L) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003L) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002L) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001L) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001L) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001L is Red
Display SOV SDY 1002L is Red
Display SOV SDY 1003L is Red

Push PB " Normal Close" (32 HS 1031L) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003L) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002L) will gradually drop to 0 psi

HMI
Display SOV SDY 1003L is Red
Display SOV SDY 1002L is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 21


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-013
Push PB "Open All Valves" (32 HS 1030M) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002M) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001M) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003M) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001M) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001M is Green
Display SOV SDY 1002M is Green
Display SOV SDY 1003M is Green

Push PB " Close All Valves" (32 HS 1032M) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003M) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002M) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001M) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001M) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001M is Red
Display SOV SDY 1002M is Red
Display SOV SDY 1003M is Red

Push PB " Normal Close" (32 HS 1031M) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003M) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002M) will gradually drop to 0 psi

HMI
Display SOV SDY 1003M is Red
Display SOV SDY 1002M is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 22


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-014
Push PB "Open All Valves" (32 HS 1030N) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002N) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001N) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003N) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001N) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001N is Green
Display SOV SDY 1002N is Green
Display SOV SDY 1003N is Green

Push PB " Close All Valves" (32 HS 1032N) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003N) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002N) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001N) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001N) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001N is Red
Display SOV SDY 1002N is Red
Display SOV SDY 1003N is Red

Push PB " Normal Close" (32 HS 1031N) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003N) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002N) will gradually drop to 0 psi

HMI
Display SOV SDY 1003N is Red
Display SOV SDY 1002N is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 23


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-016
Push PB "Open All Valves" (32 HS 1030P) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002P) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001P) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003P) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001P) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001P is Green
Display SOV SDY 1002P is Green
Display SOV SDY 1003P is Green

Push PB " Close All Valves" (32 HS 1032P) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003P) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002P) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001P) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001P) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001P is Red
Display SOV SDY 1002P is Red
Display SOV SDY 1003P is Red

Push PB " Normal Close" (32 HS 1031P) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003P) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002P) will gradually drop to 0 psi

HMI
Display SOV SDY 1003P is Red
Display SOV SDY 1002P is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 24


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-017
Push PB "Open All Valves" (32 HS 1030Q) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002Q) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001Q) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003Q) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001Q) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001Q is Green
Display SOV SDY 1002Q is Green
Display SOV SDY 1003Q is Green

Push PB " Close All Valves" (32 HS 1032Q) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003Q) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002Q) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001Q) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001Q) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001Q is Red
Display SOV SDY 1002Q is Red
Display SOV SDY 1003Q is Red

Push PB " Normal Close" (32 HS 1031Q) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003Q) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002Q) will gradually drop to 0 psi

HMI
Display SOV SDY 1003Q is Red
Display SOV SDY 1002Q is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 25


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-020
Push PB "Open All Valves" (32 HS 1030T) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002T) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001T) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003T) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001T) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001T is Green
Display SOV SDY 1002T is Green
Display SOV SDY 1003T is Green

Push PB " Close All Valves" (32 HS 1032T) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003T) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002T) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001T) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001T) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001T is Red
Display SOV SDY 1002T is Red
Display SOV SDY 1003T is Red

Push PB " Normal Close" (32 HS 1031T) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003T) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002T) will gradually drop to 0 psi

HMI
Display SOV SDY 1003T is Red
Display SOV SDY 1002T is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 26


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-021
Push PB "Open All Valves" (32 HS 1030U) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002U) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001U) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003U) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001U) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001U is Green
Display SOV SDY 1002U is Green
Display SOV SDY 1003U is Green

Push PB " Close All Valves" (32 HS 1032U) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003U) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002U) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001U) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001U) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001U is Red
Display SOV SDY 1002U is Red
Display SOV SDY 1003U is Red

Push PB " Normal Close" (32 HS 1031U) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003U) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002U) will gradually drop to 0 psi

HMI
Display SOV SDY 1003U is Red
Display SOV SDY 1002U is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 27


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-023
Push PB "Open All Valves" (32 HS 1030W) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002W) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001W) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003W) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001W) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001W is Green
Display SOV SDY 1002W is Green
Display SOV SDY 1003W is Green

Push PB " Close All Valves" (32 HS 1032W) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003W) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002W) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001W) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001W) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001W is Red
Display SOV SDY 1002W is Red
Display SOV SDY 1003W is Red

Push PB " Normal Close" (32 HS 1031W) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003W) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002W) will gradually drop to 0 psi

HMI
Display SOV SDY 1003W is Red
Display SOV SDY 1002W is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 28


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
♦ Well 32QAY-024
Push PB "Open All Valves" (32 HS 1030X) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002X) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001X) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003X) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001X) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001X is Green
Display SOV SDY 1002X is Green
Display SOV SDY 1003X is Green

Push PB " Close All Valves" (32 HS 1032X) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003X) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002X) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001X) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001X) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001X is Red
Display SOV SDY 1002X is Red
Display SOV SDY 1003X is Red

Push PB " Normal Close" (32 HS 1031X) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003X) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002X) will gradually drop to 0 psi

HMI
Display SOV SDY 1003X is Red
Display SOV SDY 1002X is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 29


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL

♦ Well 32QAY-025
Push PB "Open All Valves" (32 HS 1030Y) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002Y) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001Y) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003Y) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001Y) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001Y is Green
Display SOV SDY 1002Y is Green
Display SOV SDY 1003Y is Green

Push PB " Close All Valves" (32 HS 1032Y) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003Y) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002Y) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001Y) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001Y) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001Y is Red
Display SOV SDY 1002Y is Red
Display SOV SDY 1003Y is Red

Push PB " Normal Close" (32 HS 1031Y) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003Y) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002Y) will gradually drop to 0 psi

HMI
Display SOV SDY 1003Y is Red
Display SOV SDY 1002Y is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 30


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL

♦ Well 32QAY-026
Push PB "Open All Valves" (32 HS 1030Z) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002Z) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001Z) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003Z) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001Z) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001Z is Green
Display SOV SDY 1002Z is Green
Display SOV SDY 1003Z is Green

Push PB " Close All Valves" (32 HS 1032Z) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003Z) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002Z) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001Z) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001Z) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001Z is Red
Display SOV SDY 1002Z is Red
Display SOV SDY 1003Z is Red

Push PB " Normal Close" (32 HS 1031Z) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003Z) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002Z) will gradually drop to 0 psi

HMI
Display SOV SDY 1003Z is Red
Display SOV SDY 1002Z is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 31


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL

♦ Well 32QAY-028
Push PB "Open All Valves" (32 HS 1030AB) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002AB) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001AB) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003AB) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001AB) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001AB is Green
Display SOV SDY 1002AB is Green
Display SOV SDY 1003AB is Green

Push PB " Close All Valves" (32 HS 1032AB) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003AB) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002AB) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001AB) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001AB) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001AB is Red
Display SOV SDY 1002AB is Red
Display SOV SDY 1003AB is Red

Push PB " Normal Close" (32 HS 1031AB) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003AB) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002AB) will gradually drop to 0 psi

HMI
Display SOV SDY 1003AB is Red
Display SOV SDY 1002AB is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 32


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL

♦ Well 32QAY-029
Push PB "Open All Valves" (32 HS 1030AC) to Open the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge SSV Valve hydraulic pressure (32-PI-1002AC) will indicate 3,000 psi
Opening Sequence are; Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001AC) will indicate 5,500 psi
1st SSV valve Pressure gauge Wing Valve hydraulic pressure (32-PI-1003AC) will indicate 3,000 psi
2nd SCSSV valve LCD Pressure Transmitter (PT 1001AC) will indicate the pressure
3rd Wing valve
HMI
Display SOV SDY 1001AC is Green
Display SOV SDY 1002AC is Green
Display SOV SDY 1003AC is Green

Push PB " Close All Valves" (32 HS 1032AC) to close the well WHCP
Sequence for opening will be done at PLC logic Pressure gauge Wing Valve hydraulic pressure (32-PI-1003AC) will gradually drop to 0 psi
Closing Sequence are; Pressure gauge SSV Valve hydraulic pressure (32-PI-1002AC) will gradually drop to 0 psi
1st Wing valve Pressure gauge SCSSV Valve hydraulic pressure (32-PI-1001AC) will gradually drop to 0 psi
2nd SSV valve LCD Pressure Transmitter (PT 1001AC) will gradually drop to 0 psi
3rd SCSSV valve
HMI
Display SOV SDY 1001AC is Red
Display SOV SDY 1002AC is Red
Display SOV SDY 1003AC is Red

Push PB " Normal Close" (32 HS 1031AC) to close Wing & SSV WHCP
Pressure gauge Wing Valve hydraulic pressure (32-PI-1003AC) will gradually drop to 0 psi
Pressure gauge SSV Valve hydraulic pressure (32-PI-1002AC) will gradually drop to 0 psi

HMI
Display SOV SDY 1003AC is Red
Display SOV SDY 1002AC is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 33


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL

☼ WIRELINE BY PASS
Medium Pressure
Switch Selector (HS 1076) to bypass wireline WHCP
Turn off all SOV SDY "B" Common Section
Switch 3 way selector valve (EC) to bypass wireline Pressure gauge MP hydraulic wireline header (32 PI 1086) will indicate pressure

Wellhead Module
Pressure gauge SSV Valve hydraulic pressure for each module Tag below will indicate 3,000 psi
(32-PI-1002A)
(32-PI-1002B)
(32-PI-1002D)
(32-PI-1002E)
(32-PI-1002H)
(32-PI-1002I)
(32-PI-1002K)
(32-PI-1002L)
(32-PI-1002M)
(32-PI-1002N)
(32-PI-1002P)
(32-PI-1002Q)
(32-PI-1002T)
(32-PI-1002U)
(32-PI-1002W)
(32-PI-1002Y)
(32-PI-1002Z)
(32-PI-1002AB)
(32-PI-1002AC)

HMI
Display SOV HY 1076 is Green
Display for all SOV SDY "B" is Red

High Pressure
Switch Selector (HS 1075) to bypass wireline WHCP
Turn off all SOV SDY "C" Common Section
Switch 3 way selector (EB) valve to bypass wireline Pressure gauge MP hydraulic wireline header (32 PI 1085) will indicate pressure

Wellhead Module
Pressure gauge SCSSV Valve hydraulic pressure for each module Tag below will indicate 5,500 psi
(32-PI-1001A)
(32-PI-1001B)
(32-PI-1001D)

Form 3 (Function Test) Page 34


FORM 3 - FUNCTION TEST

VISUAL
INPUT OUTPUT
CONTROL
(32-PI-1001E)
(32-PI-1001H)
(32-PI-1001I)
(32-PI-1001K)
(32-PI-1001L)
(32-PI-1001M)
(32-PI-1001N)
(32-PI-1001P)
(32-PI-1001Q)
(32-PI-1001T)
(32-PI-1001U)
(32-PI-1001W)
(32-PI-1001Y)
(32-PI-1001Z)
(32-PI-1001AB)
(32-PI-1001AC)

HMI
Display SOV HY 1075 is Green
Display for all SOV SDY "A" is Red

TEST DATE : / / ACCEPTED REJECTED PUNCH LIST

PT INDOKOMAS BUANA PERKASA PT. NISCONI INDONESIA CONOCOPHILLIPS INDONESIA

NAME : NAME : NAME


SIGNATURE : SIGNATURE : SIGNATURE

Form 3 (Function Test) Page 35


NORTH BELUT PROJECT
WHP EPC
PT. NISCONI PT. IBP
TITLE DOCUMENT NUMBER REV DATE PAGE
PERFORMACE TESTING AND
ID-F-NBP-JP-002-H05-0001 0 26-Dec.-07 35 of 35
ACCEPTANCE TEST PROCEDURE

FORM 4 – PUNCH LIST DURING FAT

ACTION CLEARANCE
No. PUNCH LIST DESCRIPTION REMARKS
BY STATUS

TEST DATE: ACCEPTED REJECTED PUNCH LIST


/ /

PT INDOKOMAS : PT NISCONI INDONESIA CONOCOPHILLIPS IND INC.LTD

NAME & NAME & NAME &


SIGNATURE SIGNATURE SIGNATURE