Tabla de contenido

I. INTRODUCCIÓN............................................................................................................. 2
II. OBJETIVOS..................................................................................................................... 6
III. ANTECEDENTES........................................................................................................ 7
Antecedentes Históricos. .................................................................................................... 7
IV. DESARROLLO ...........................................................................................................12
1. FORMULACIÓN DEL PROYECTO............................................................................12
a) Descripción del proyecto ........................................................................................12
b) Perfil del proyecto ...................................................................................................13
c) Objetivos del proyecto. ...........................................................................................13
d) Metodología ............................................................................................................14
2. ALCANCE DE OBRA..................................................................................................19
a) Localización ............................................................................................................19
b) Trazo y nivelación global ........................................................................................21
c) Diseño de terracería (corte, relleno, descapote) ....................................................21
3. PLANIFICACIÓN ...........................................................................................................40
3.1 Criterios para la selección de la maquinaria ...............................................................40
5. PRESUPUESTO.........................................................................................................80
V. CONCLUSIÓN................................................................................................................86
VI. RECOMENDACIONES ..............................................................................................87
VII. REFERENCIAS ..........................................................................................................88
VIII. ANEXOS .....................................................................................................................89
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

I. INTRODUCCIÓN
Para obtener éxito en el funcionamiento de las construcciones, es fundamental
tener como base un movimiento de tierra que cumpla con los estándares de la
construcción; es necesario recalcar que el objetivo de tener una adecuada ejecución
en las etapas del movimiento de tierra proporcionará un entorno propicio en el
desarrollo de las actividades a realizar a lo largo de un proyecto de obras públicas.

Dentro del proceso de elaboración de cualquier construcción, el movimiento de tierra


es la etapa que implica una mayor trasformación del entorno, por lo que debe
ejecutarse con las previsiones correspondientes para reducir al máximo las
alteraciones de los medios.

Antes de proseguir, se debe tener claro el significado textual de movimiento de tierra


para comprender de que están compuestas y porque es indispensable al iniciar una
construcción. Maurice y Clays (1995) exponen:

Es un conjunto de operaciones que se efectúan de forma manual o mecánica sobre


el terreno. Así mismo, consiste en una serie de realizaciones, entre los que se
encuentran las excavaciones y los vaciados, que se llevan a cabo en un terreno
determinado antes de comenzar la ejecución de una obra.

Sin embargo, el movimiento de tierra depende directamente de la topografía que


presenta el terreno donde se construirá, por lo que se debe concluir que las dos
actividades que comprenden básicamente un movimiento de tierra son: excavación
y el terraplenado.

Para ampliar la formación como estudiante de ingeniería y tomar consciencia de la


importancia que tiene la participación de la maquinaria pesada, así como la
topografía y estudios de suelo en obras de ingeniería civil. Se presenta un estudio
propuesto denominado “Colegio el Doral” con el fin de comprender y llevar a cabo
con las especificaciones previamente planificadas así como diseño arquitectónico,
diseño de terracería y construcción. A partir de ahí, ampliar conocimientos y
disponer eficazmente para enfrentar situaciones como futuros ingenieros.

2
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Sin embargo, ante todo se debe de considerar factores notables en cualquier


construcción. La planificación de un movimiento de tierra es de vital importancia
para obtener buenos rendimientos. Así como también cumplir con los plazos
propuestos con la intensión de evitar demoras no deseadas y no menos importante
reducir los costos evitando así desviaciones en esta unidad de obra.

Existen diversos factores que son conocidos previamente al inicio del movimiento
de tierra y que deben ser valorados a la hora de dimensionar los medios para
optimizar la productividad de los equipos, esto se expone específicamente en el
diseño de terracería. Considerando los aspectos antes mencionado, se discurre una
exhaustiva valoración de maquinaria; seleccionando así las más factibles y
rentables en este proyecto.

Actualmente la utilización de las mismas, se encuentra altamente demandada, esto


debido al aumento de trabajo en el campo de la construcción en Nicaragua. Las
cuales poseen equipos y herramientas que juegan un papel fundamental, utilizadas
en diversas operaciones. De tal forma que cada una cumple diversas
funcionalidades las cuales ejecutan directamente determinada operación.

Así bien, existen normas generales de maquinaria que se ha de utilizar. De acuerdo


a Rogers (2000) Deben de ser apropiadas en función de los siguientes aspectos:
“Ubicación de la obra, Topología de la obra, Envergadura de la obra, Material que
se ha de excavar y Condicionantes adicionales” (p. 132). & uno no menos
trascendental, factores climatológicos que influyen de forma muy negativa en los
movimientos de tierra.

Así mismo, las funciones de estos equipos difieren en dependencia de su capacidad


y finalidad. Uno de los aspectos más importantes sobre las maquinarias es conocer
el rendimiento y su posible mantenimiento que posee cada equipo y la forma de
organizarlo en el ataque, gasto de combustible, refracción, control de acarreo según
kilometraje y control de hora/metro de cada uno de ellos. En cuanto a los
rendimientos que posee diferente equipo dependerá del análisis hecho sobre las
condiciones de tal equipo que por lo general cada uno de ellos posee diferentes
especificaciones.

3
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Por esta razón, existen proveedores de venta y alquiler. Como empresa de venta
consideran formar un costo, que de ello dependerá obtener ganancias, de manera
que sea factible tanto para ellos como para el cliente que explotará el equipo.
Mientras que las maquinarias rentables tratan de reducir los costos, cuya estrategia
es brindar una mejor cotización a sus clientes, es aquí donde entran los
requerimientos más significativos en base a sus condiciones y posibles propuestas
que incluyen como empresa rentable.

No obstante, es necesario conocer los tipos de requerimientos que son necesarios


para las obras. Con el fin de comprar los mejores precios y las mejores maquinarias
que se pueden encontrar en el mercado, puesto que de ello también es decisivo e
imprescindible para el correcto desarrollo de sus proyectos.

Estos aspectos son empleados en dependencia de algunos factores a como es la


ubicación de terreno y la economía del proyecto. Por otro lado, se debe de cotizar
en diferentes empresas que provean todos los equipos necesarios a utilizar, para
así tener opción de elegir los precios más accesibles y rentables existentes en el
mercado.

Posteriormente en el proceso de movimiento de tierra se hace una valoración de


elevaciones promedios o bien respecto a niveles de calle; de este modo, se conoce
si es necesario rellenar o cortar material.

De esta manera, se detalla paso a paso todo lo relacionado a la planificación del


proyecto propuesto antes mencionado, cuya proposición es idealizada para
incentivar a una buena ejecución de obras públicas y privadas en el país, partiendo
de las necesidades y economía del departamento o localidad. Este proyecto se
realiza debido al incremento de la población que se vive hoy en día y surge la
necesidad de infraestructura pública como escuelas, hospitales, súper mercados,
entre otros.

Se debe agregar que se expresará todo lo relacionado a la maquinaria,


rendimientos, características, costos y dificultades que se presentan no solo en
dicho proyecto sino en el diario vivir como en proyectos actuales y futuros. A

4
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

continuación se detalla todo el proceso correspondiente del proyecto propuesto


“Colegio El Doral” considerando varios factores que proporcionan un excelente
desempeño. De esta forma, será un refuerzo para los estudiantes conocer y adquirir
experiencias en cuanto al funcionamiento de los equipos en estudios y el
compromiso que requiere llevar un proyecto a cabo.

5
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

II. OBJETIVOS
 Objetivo general:
1. Planificar la etapa de movimiento de tierra para el proyecto “Colegio El Doral”
en el municipio de Mateare, departamento de Managua.

 Objetivos específicos:
2. Definir niveles de rasante estratégicos para la compensación de volúmenes de
corte y relleno en el proyecto “Colegio el Doral”.
3. Establecer criterios técnicos y rentables para la selección de maquinaria
pesada que se utilizará en la etapa de movimiento de tierras del proyecto
“Colegio el Doral”.
4. Estimar un presupuesto general en el cual se expongan las actividades por
costo unitario y costo global de la etapa de movimiento de tierra del proyecto a
ejecutar.
5. Interpretar los volúmenes, costos y alcance de obras definidos en la etapa de
movimiento de tierras del proyecto “colegio el Doral”.

6
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

III. ANTECEDENTES
Los movimientos de tierra son actividades constructivas muy frecuentes en la
ejecución de la infraestructura vial, el desarrollo urbano, social e industrial de un
país. Estas actividades son de la competencia de los profesionales de la
construcción y en especial de los ingenieros civiles.

Es de suma importancia estar al tanto de los aspectos que han sido tomados al
momento de decidir construir escuelas o centros de estudio en una comunidad, ya
sea localización, presupuesto municipal y necesidad proveniente de la población
existente y venidera. Actualmente esta propuesta nace debido a la necesidad que
tiene el país dado su creciente poblacional en los últimos años que ha aumentado
en un 50% aproximadamente con un total de 49,360 habitantes. La implementación
de este proyecto permitirá a niños y jóvenes tener una mejor educación y por ende
un excelente desarrollo en el país. Según la constitución política “El derecho a la
educación es un derecho fundamental de todos los seres humanos que les permite
adquirir conocimientos y alcanzar así una vida social plena”.

Antecedentes Históricos.
En la realización de construcción, el hombre se integró a un centro de estudio para
su posible conocimiento en edificaciones de forma vertical como horizontal.
Asimismo, en el proceso de construcción tuvo la exigencia de remover y rellenar
dichos terreno. De esta forma el hombre tomó acciones que le permitiera variar o
modificar la tierra con ayuda de la topografía de un área respectiva con el fin de
adaptarla a un proyecto de construcción previamente elaborado. De esta forma el
ser humano, tuvo la necesidad de realizarlo mediante el empleo de maquinaria
especialmente diseñada para realizar esta función.

Cabe recalcar que en el trascurso del tiempo se ejecutaban proyectos donde se


consideró el tipo de movimiento de tierra que se iba a implementar. Es por esto, que
existen dos tipos de métodos.

1- Movimiento de tierra manualmente: Método conocido como el más simple


que básicamente en cavar y lanzar. Generalmente se utiliza en los suelos
cohesivos donde se podrá excavar y cortar bloques de tierra. Estos bloques

7
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

se podrán pasar manualmente de una persona a otra haciendo una cadena


humana.
Respecto a los demás tipos de suelos, se podrá cavar y lanzar la tierra
directamente. En la práctica, la distancia de lanzado se limitará a 3 m.
2- Movimiento de tierra con maquinaria. En este método se orienta para su
elección, es decir; conocer la distancia de trasporte, condiciones de trabajo y
maquinaria recomendada o necesaria.

Por otro lado, al realizar los movimientos de tierra en la obra, y de trasportar las
tierras extraídas, se ejecutara la construcción de los cimientos sobre los que se
asentara dicha edificación. En este sentido, Andrés Gonzales (1997) dijo “El
movimiento de tierra es de suma importancia, puesto que ayuda a fundar los
cimientos que sostendrán dicha construcción”. Para la elección de los métodos de
movimiento de tierra, se considerarán varios factores tales como:

1- Condiciones locales.
2- Vías de trasporte y sus posibilidades de utilización.
3- Condiciones estacionales o distancia media de trasporte.
4- Volumen de tierra.
5- Disponibilidad y costo de la mano de obra.

La recopilación tiene como objetivo ofrecer un acercamiento a los temas que centran
la atención de los investigadores del área y detectar la existencia de algunas líneas
de investigación comunes.

En este sentido, Andrés considera que el movimiento de tierra ha pasado a ser un


complemento necesario para iniciar una construcción que se llevara a cabo de no
ser así, no será posible. Así mismo, esto ha proporcionado cambio tanto para
solucionar problemas como trasformar al país.

Para elaborar los antecedentes de este estudio, se consultó en internet las distintas
páginas web, la biblioteca “La Yanca” entre otros no menos importante. Los
primeros indicios de investigación sobre los medios, como antecedente a
construcciones de centros de estudios que conllevan a su posible movimientos de

8
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

tierra, se encuentran una investigación titulada “ESCUELA NACIONALES DE


EDUCACION FISICA” (2012) ubicado en el complejo IND (Managua). Se procedió
a realizar la primera etapa de la construcción de 12 aulas cuya área es de 900 𝑚2
edificada en dos niveles.

Esta investigación se enfoca en brindarles una educación y entretenimiento a


jóvenes con deseo de superación convirtiéndolos en profesores de educación física.
No obstante, dicho lugar tenía pendientes muy altas, lo cual se procedió a realizar
los movimientos de tierra, utilizando maquinaria pesada, a pesar que es un lugar
muy pequeño no fue necesario ir a un banco, sino que se utilizó la misma tierra para
su posible relleno.

Otra investigación titulada “Escuela Taller La Esperanza”. Ubicado en el distrito


numérico II de Managua en el extremo noroeste de la cuidad y a orillas del lago
Xolotlan. Dicha investigación contiene una notabilidad en el ámbito de información
en Nicaragua lo cual se consideró muchos aspectos. Ubicado en el Barrio
Acahualinca conocido popularmente como la chureca, cuyo lugar es uno de los
barrios más grande. Por lo tanto, el desarrollo integral del barrio Acahualinca
(PDIBA) fue necesario la construcción de una escuela, debido a que es un barrio
con menor calidad de acceso a servicios básicos y educativos.

Descripción del problema de investigación.

Por la ubicación propuesta, fue necesario realizar ciertos criterios sumamente


importantes para llevarse a cabo.

Situación Ambiental.

Posee una dimensión superficial de unas 40 hectáreas y una profundidad media de


30m. El vertedero recibe unas 1300 toneladas diarias de residuos sólidos urbanos.
Debido a su ubicación y a sus dimensiones crecientes y a su falta de tratamiento
adecuado, se presentó problemas en relación al medio ambiente. Los afluentes
lixiviados se infiltran en los acuíferos y contaminan sus aguas, así como las del lago.
Así como también otros problemas que afectan la atmosfera y sus posibles
calentamientos globales.

9
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Situación Social.

En el distrito numérico II de Managua, posee una población aproximada de 18 000


personas, la situación socioeconómica en los barrios colindantes con “La Chureca”
es de extrema pobreza, marginalidad y exclusión social. La mayor parte de las casas
están construidas con materiales de desechos, básicamente chapas de cinc y acero.
Por otro lado, los habitantes carecen en gran medida de los servicios urbanos
básicos.

Escuela La Esperanza.

Atiende a los niños/as del sector de la Chureca apoyándoles, ya que se encuentra


ubicada directamente en la misma. Brinda educación formal en preescolar y primaria
en turnos matutino y vespertino.

Cuenta con una población de alrededor 237 estudiantes, 8 maestros, de los cuales
solamente dos han estudiado en la universidad; tiene dos turnos y cuenta con los
tres niveles de educación preescolar y con primaria completa. (Datos del 2006)

La Chureca hoy en día 2017, según Organización Internacional del Trabajo (OIT)
asegura que ha cambiado completamente. “Se han implementado muchos
proyectos en este sitio, trayendo muchos beneficios para la gente que vivía en sus
alrededores” indico Guerrero. Este proyecto permitió brindarles oportunidades de
trabajo en condiciones dignas, la preparación de jóvenes en la escuela Taller de
Acahualinca “ESPERANZA” en oficios de la construcción que les representara una
herramienta para ofertarse dentro del mercado laboral nacional y el fortalecimiento
de la organización comunitaria.

Esta investigación se enfoca en la construcción de un centro de estudio en la cuidad


de Managua. En la biblioteca “La Yanca” no se encontró ningún tema relacionado
al movimiento de tierra y maquinaria pesada; por lo tanto es un tema novedoso y
abarca un sector importante dentro de la población dado que brinda un servicio
indispensable en la comunidad.

Sin embargo, la información reflejada sirve como referencia lo importante que son
las instalaciones de centros de estudios que de una u otra manera ayuda al

10
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

desarrollo del país. Esto se debe al crecimiento que tiene el país y su alta demanda
en el ámbito laboral.

11
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

IV. DESARROLLO
El proceso de movimiento de tierra abarca diversas sub- etapas que poseen un
orden cronológico dependiendo de las características del terreno y el presupuesto
del proyecto.

Se ha desarrollado un esquema gradual que se divide de la siguiente manera:


primeramente la formulación del proyecto “Colegio El Doral” en el cual se describe
el proyecto con su respectivo perfil, objetivos y metodología empleada para la
realización.

Así bien, se desarrolla el alcance de obra del proyecto, el cual hace referencia al
diseño de terracería con su respectiva memoria de cálculo, apoyándose en el trazo
y nivelación (topografía), se especifica la localización del banco de materiales, y
botadero más cercanos al proyecto.

Consecutivamente se expone la planificación, esta sub- etapa incluye los criterios


que se tomarán para elegir a la maquinaria así como: especificaciones técnicas,
factibilidad en la movilidad y el tiempo que tomará está sub- etapa.

Por otra parte, se refleja el rendimiento de cada uno de los equipos en su campo de
trabajo y finalmente se ha realizado un presupuesto general, en el que se detalla el
costo unitario y costo total por actividad, primeramente de las etapas preliminares y
las etapas propiamente del movimiento de tierra: excavación, terraplén y desalojo.

1. FORMULACIÓN DEL PROYECTO


a) Descripción del proyecto
El proyecto que se va a realizar tiene una complejidad moderada e implica un
esfuerzo estimado de 30 días, debido a resolución de problemáticas identificando
costos, beneficios y beneficiarios directos e indirectos. Los defectos que se
produzcan en el mismo pueden causar graves daños a los trabajadores y pueden
exponer la vida de las demás personas, por lo que existen fuertes restricciones al
acceso de la obra. La construcción del proyecto estará formada por un mínimo de
12 puestos y un máximo de quince.

12
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

b) Perfil del proyecto.

Para la realización del proyecto se ha tenido en cuenta un condicionante que ha


sido la adaptación al desnivel. Así como su posible distribución para el acceso de
vehículos y peatones, es por eso que se presenta en este caso como beneficiarios
directos a la población.

Factibilidad

El proyecto “colegio el Doral”, comprende en su primera etapa de movimiento de


tierra la determinación de niveles respecto al relieve natural de la localidad.
Garantizando la asignación de niveles de terracería óptimos para la construcción de
dicha edificación, tomado en cuenta los volúmenes de corte y relleno, al mismo
modo que la compensación de estos volúmenes, reflejando el drenaje natural del
agua ya existente en el terreno y los nuevos niveles de calle respecto a las
elevaciones ya presentes.

Ejecución

La ejecución del proyecto se divide en las siguientes sub-etapas: primeramente el


corte de material para obtener el nivel de terracería diseñado, la compensación del
volumen de relleno con el volumen cortado, del mismo modo la capa de material
selecto para un mejoramiento de suelo, subsiguientemente se tiene la perfilación y
compactación de terracerías.

c) Objetivos del proyecto.


El centro educativo “EL DORAL” tiene como objetivo construir un espacio para el
aprendizaje y transmisión de valores fundamentales para tener una vida digna,
responsable y ser reconocido por la sociedad, así como también tener una misión
en difundir los valores de la solidaridad, la responsabilidad cívica y los derechos
humanos universales.
De este modo, dicho centro promueve la toma de conciencia acerca de la
importancia que tienen estos valores para el desarrollo armónico y pacífico de las
relaciones tanto entre personas como entre naciones, estimulando, a la vez, una
interpretación más clara de los hechos actuales y pasados.

13
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Cabe destacar que la fase de este proyecto es plenamente física y mecánica, al


iniciar el proyecto no habrá ningún tipo de problema de accesibilidad durante el
proceso de construcción del centro de estudio ya que el solar cuenta con suficiente
superficie para que todas las acciones del proceso constructivo se lleven a cabo con
normalidad. En referencia al transporte y descarga de materiales en la obra tampoco
habrá ningún imprevisto puesto que la calle a la que da la parcela posee una
amplitud la cual permite que camiones y demás vehículos puedan maniobrar sin
dificultad para llevar a cabo sus funciones.

d) Metodología.

El proyecto propuesto “Colegio El Doral”.

Para desarrollar un proyecto se consideran varios aspectos fundamentales, los


cuáles serán esenciales antes de iniciar la construcción del mismo.

Primero que todo se hizo un análisis de la situación actual del sector (Residencial
Ciudad El Doral- Kilometro 18.1 Carretera Nueva León) que se llevará a cabo la
construcción. La primera etapa es el movimiento de tierra la cual requiere de una
serie de procedimientos previos a su ejecución tales como el estudio del suelo,
ubicación geográfica, la topografía y la población en general.

Por otro lado, se procedió a realizar una descripción de las maquinarias,


rentabilidad, y renta horaria de cada uno de los equipos a utilizar para realizar una
planificación que evite pérdidas de tiempo y pérdidas monetarias.

Para lograr una construcción apropiada desde el inicio hasta el final, se debe de
tener en cuenta ciertos criterios. Lo cual se procedió a seguir un estudio de tareas
que son importantes enumerar y resaltar las interacciones entre ellas en función al
trabajo propuesto.

• Análisis del proyecto y su inversión.

De acuerdo al análisis llevado a cado, se concluyó que es necesaria la construcción


de un centro de estudio, debido a alto incremento de la población en el municipio de

14
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Mateare y zonas aledañas como son las construcciones urbanísticas de Ciudad El


Doral, Vistas de Momotombo y Valles de Sandino. Dicho proyecto se considera
factible para la comunidad. Asimismo, se valoró de acuerdo al estudio la necesidad
no solo de este centro de estudio, sino de más construcciones tales como: Centro
de salud, parques, bancos etc.

Para la ejecución de cualquier obra civil es importante realizar un presupuesto en


donde se desglose cada una de las actividades a realizar y el precio de cada una
de ellas. El movimiento de tierra para El Colegio El Doral está estimado un valor
aproximado de 94,580.89 dólares, en donde se incluye procesos de descapote,
corte, relleno, traslado de material, limpieza entre otros.

• Organización de la obra:

La Organización de la obra tiene cierta complejidad, por lo tanto requiere de una


clasificación estricta por dos motivos:

Para una mejor gestión

Para que la empresa pueda en todo momento conocer la situación de cada


diligencia. Sin embargo, en esta construcción se estará rentando maquinaria de dos
empresas “Master Construction y Agroindustrial Mantica, S.A (AIMSA). Cabe
destacar que es frecuente que los equipos cambien de obra, es por ello que se
necesita de una buena organización tanto administrativa como en maquinaria.

• Seguimiento:

Una adecuada construcción depende de un seguimiento constante que permita al


responsable de la obra conocer en todo momento la situación y etapa en que se
encuentra y así poder tomar o proponer medidas correctoras. Además, todo trabajo
previo debe ser controlado y para ello es preciso establecer unos parámetros a
controlar y en su caso modificar.

En consecuencia, antes de realizar este análisis se debe de obtener primeramente


dichos arreglos para realizar cualquier construcción.

a) Ser titular de un derecho que le faculte para construir en el solar.

15
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

b) Contratar al Proyectista, la Dirección de obra y la de Ejecución y el Project


Manager en su caso.

c) Gestionar y obtener las preceptivas licencias y autorizaciones administrativas, así


como suscribir el acta de recepción de la obra.

d) Contratar los seguros previstos.

e) Gestionar la documentación de obra ejecutada, o cualquier otro documento


exigible por las Administraciones competentes.

En el desarrollo del trabajo llevado a cabo, se realizaron por partes todo lo mostrado
a continuación.

El elegir el terreno donde se propone una construcción, es una de las decisiones


más importantes ya que se debe de considerar varios aspectos transcendentales
tales como:

Lugar de trabajo:

Colegio “El Doral” estará ubicada en Residencial Ciudad El Doral, Kilometro 18.1
Carretera Nueva León.

Banco de préstamo.

Está ubicado kilómetro 12 carretera a Nueva León, en el municipio de Cuidad


Sandino llamando Mina Sandino. En dicho banco de préstamo solo se explota lo
que es material selecto y escoria volcánica (Hormigón). Cabe destacar que no
proporciona material arenoso ni de ningún otro tipo.

Botadero.

El botadero está ubicado en kilómetro 20 Carretera Nueva a León.

Plantel.

Como en todo proyecto, se tiene destinado un plantel donde se guardan las


maquinaria ya sea propias de la empresa o rentable. En este caso, el plantel de la
maquinaria destinada al proyecto “Colegio El Doral” se estará resguardando en el

16
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

en el mismo sitio (Kilometro 18.1 Carretera Nueva León), en un área aproximada de


2,000 m2, esta área se encuentra fuera del área de construcción, no se aplican
costos adicionales ya que el terreno pertenece al mismo dueño.

Procedimiento.

Una vez seleccionado el lugar, se procedió al levantamiento topográfico del terreno


obteniendo un área de 9200 m2. Una vez, que se realizó el levantamiento se
calcularon las curvas de nivel por medio del programa AUTOCAD CIVIL 3D.

A través del programa, también se realizaron las terrazas del centro de estudio
ocupando solamente 8563.52 m^2, el cual está compuesto por canchas, pabellones,
sala de profesores, casetas de guarda de seguridad, y calles alternas que conectan
a los parqueos.

Una vez ubicadas las terrazas en plano se procedió a diseñar una rasante que de
una u otra forma lograra compensar corte con relleno. A pesar que la cantidad de
relleno se puede solventar con el material cortado se requiere colocar una capa de
20 cm de material selecto para lograr mayor estabilidad y resistencia en el suelo.
Los métodos utilizados para calcular los volúmenes de corte y relleno fueron: la hoja
de cálculo Excel, utilizando secciones y perfiles de cada terraza para trazar la sub
rasante; se utilizó la programación de Volume Dashboard del programa CIVIL 3D.
Por ello, se seleccionó el banco de préstamo “Mina Sandino” más cercana con una
distancia de 7 km al proyecto con el objetivo de que resulte factible. De igual forma
se optó por no invertir dinero en un plantel, teniendo espacio y posible seguridad en
el proyecto que se ejecutará, proporcionado una rápida accesibilidad al equipo y
disminuir el gasto en lo más mínimo.

De acuerdo a la rentabilidad de los equipos, solo se estará utilizando 7 equipos tales


como Retroexcavadora, vibro compactadora, motoniveladora, mini cargador de la
empresa (AIMSA). Mientras que las 3 maquinarias restantes son Volquete, cisterna
y tractor oruga de la empresa (Master Constructor).

17
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Se estarán adquiriendo así, debido a la accesibilidad en cuanto al costo y lo que


incluye cada empresa a la hora de su rentabilidad, tomando siempre
consideraciones pertinentes que disminuyan los costos de movilización.

18
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

2. ALCANCE DE OBRA
a) Localización
 Localización del Proyecto Colegio El Doral

El proyecto esta propuesto para realizarse en el Residencial Ciudad El Doral


kilómetro 18.1 Carretera Nueva León. En la ilustración 1 se puede observar la
ubicación del proyecto, este se representa por el cuadro blanco ubicado al costado
de la avenida principal del residencial. El acceso hacia el colegio se localiza dentro
de la urbanización. La construcción cuenta con 9200.40 m2 de los cuales 7623. 35
m2 serán destinados para la construcción de diferentes áreas tales como salones
de clase, cancha, salón de maestros, parqueos y áreas verdes.

Ilustración 1: Colegio El Doral

 Localización del Proyecto Colegio El Doral al banco de materiales Mina


Sandino

El banco de materiales se localiza a 6.5 km de la zona de construcción.

Mina Sandino se sitúa en el kilómetro 12 carretera nueva a león, cuenta con un área
de aproximadamente 20 manzanas. En esta mina anteriormente sustraía arena pero
por falta de concesión la explotación se ha detenido, hoy en día solo sustraen
material selecto para compactación y realizan colados para la obtención de bloques.

19
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Su explotación se realiza de manera industrial con la ayuda de maquinaria pesada,


la cual recolecta el material y colocado en forma de montañas para su próxima
distribución. Se estima que el volumen mínimo de explotación se encuentra entre
200-300 m3.

Ilustración 2: Ruta Colegio El Doral-Banco de Materiales Mina Sandino

 Localización Colegio El Doral a Botadero

El botadero se localiza a 2.97 km del proyecto. Este lugar es utilizado por la


constructora del Residencial para desechar los materiales sobrantes de corte en los
movimientos de tierra que se realizan.

20
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

b) Trazo y nivelación global


El éxito de un proyecto radica en la planificación previa de factores útiles a lo largo
de este, la etapa de movimiento de tierra es la actividad principal para
construcciones de edificios, por lo tanto la corrección y supervisión de los niveles de
terracería son vitales para proceder a excavar o rellenar.

Este proyecto en su particular cuenta con una cuadrilla de topógrafos que están al
tanto delos niveles de terracería anteriormente diseñados. Dicha cuadrilla está
conformada por el topógrafo de cabecera y dos asistentes.

Se conoce que la topografía del terreno oscila entre las cotas 68 y 65.25, y las
curvas de nivel están reflejada a cada 0.25 metros.

c) Diseño de terracería (corte, relleno, descapote)


La determinación de los niveles de rasante para cada terraza se realizó a partir de
la generación de perfiles y secciones transversales. Cada sección muestra el relieve
del terreno y por ende al trazar la rasante propuesta se logra observar el área de
corte y de relleno de cada terraza.

Para lograr una compensación entre volúmenes de corte y relleno se crearon diez
terrazas las cuales incluyen las calles internas propuestas en plano, tomando en
cuenta que según las pruebas de suelo realizadas anteriormente se conoce que es
un suelo A-2-4 (gravas y arenas arcillosas limosas, con calidad de sub rasante de
excelente a bueno) Cada terraza cuenta con un nivel de rasante distinto. Se debe
mencionar que la diferencia de nivel desde el punto más alto del terreno hasta el
punto más bajo es de alrededor de 3m por lo que se debía lograr un equilibrio entre
el corte y el relleno a realizar en sitio.

Los niveles por cada terraza se muestran a continuación:

Terraza Pabellones:

El nivel establecido para este sector es 66, dicha elevación fue necesaria debido a
que el nivel de calle es de 65.82. Para evitar inundaciones en los pabellones que
servirán como aulas de clase se toma la decisión de dejar la terraza 20 cm por
encima del nivel de calle.

21
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Terraza Parqueo 1:

En el área del parqueo 1 se aplicó una pendiente de 1% lo que significa que la parte
más del terreno presenta un nivel de 66.90 y el nivel más bajo el 66.23. Esta
pendiente fue estimada con el propósito que las corrientes de agua no se queden
concentradas en dicho sector y que fluyan hacia los desaguaderos.

Terraza Cancha:

Las consideraciones tomadas en para las terrazas previas también fueron tomadas
en cuenta en esta. El nivel que se estableció es de 67.38 y de igual forma queda
por encima del nivel de calle.

Terraza Área Verde:

En el área verde se trató de minimizar el impacto de corte y relleno el nivel


proyectado es de 67.80 y este se asemeja al nivel de terreno natural. Con la
nivelación lo que se pretende es crear un espacio con poco impacto ambiental pero
que a su vez pueda ser utilizado como área de recreación.

Terraza Parqueo 3:

El parqueo 3 se localiza en el lado este del plano. De igual forma que el parqueo 1
se le aplicó una pendiente del 1% con niveles de 66 y 66.23, logrando así quedar
niveles encima de la calle.

Terraza Caseta:

La caseta es un área pequeña la cual está destinada para la construcción de un


lugar que albergue a la seguridad del lugar. El nivel predeterminado es de 67.90.

Terraza Salón de Maestros:

Esta terraza cuenta con un nivel 66.20 lo cual equilibra la cantidad de corte y relleno
a realizar.

22
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Terraza Parqueo 2:

El parqueo 2 se ubica en el lado norte, de igual manera que en los dos parqueos
anteriores se estableció una pendiente pero esta vez del 0.5% con niveles de 66 y
65.70. Dicha pendiente contribuirá a la circulación del agua.

Terraza Calle Secundaria:

Esta terraza comprende la calle que une los pabellones con el parqueo N°2. Debido
a la forma del terreno natural se decidió aplicar una pendiente del 0.5% y niveles de
66 y 65.67 esto con la finalidad de verter las aguas en un solo sector para luego de
un estudio hidráulica proponer la mejor solución de colocar un sistema de captación
de aguas pluviales y dirigirlas a un pozo de infiltración.

Terraza Calle Interna:

Esta calle conecta a casi todas las terrazas por ende en considerada la calle
principal del sitio. Debido a que por la distribución de la terrazas y de los niveles
cierta cantidad de agua es vertida sobre esta, por esta razón se decidió establecer
una pendiente del 2.8% con niveles de 67.70 y 65.82 para evitar estancamiento de
agua y que fluya de manera rápida.

Una vez explicados los niveles de cada terraza se muestran seguidamente las
tablas generadas de movimiento de tierra. En ellas se presenta las áreas de corte y
relleno. Es importante mencionar que por cada terraza las secciones generadas se
encontraban cada 10 metros. Los perfiles y secciones se muestran en los anexos.

23
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

a) Calculo de volúmenes

Se muestra los volúmenes de corte y relleno en su estado natural haciendo uso de


la formula = (Área 1+Área 2)*Semidistancia. Por ultima se multiplica el volumen de
relleno en su estado natural por el factor de abundamiento que en este caso
particular se consideró un factor del 1.15%

Para explicar de una mejor manera la aplicación de la formula ya mencionada se


tomara como ejemplo la hoja de movimiento de tierra de Terraza Pabellones:

𝑉𝑐𝑜𝑟𝑡𝑒 = (𝐴1 + 𝐴2 ) ∗ 𝑆𝑒𝑚𝑖𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑖𝑎

La obtención de las áreas de corte fue a partir de secciones de cada terraza y el


trazo de una rasante. Toda el área que se encontraba por encima de la rasante era
área de corte.

1) 𝑉𝑐𝑜𝑟𝑡𝑒 = (25.79 + 20.41) ∗ 5

𝑉𝑐𝑜𝑟𝑡𝑒 = 231 𝑚3

2) 𝑉𝑐𝑜𝑟𝑡𝑒 = (20.41 + 14.13) ∗ 5

𝑉𝑐𝑜𝑟𝑡𝑒 = 172.70𝑚3

3) 𝑉𝑐𝑜𝑟𝑡𝑒 = (14.13 + 9.19) ∗ 5

𝑉𝑐𝑜𝑟𝑡𝑒 = 116.60𝑚3

4) 𝑉𝑐𝑜𝑟𝑡𝑒 = (9.19 + 5.49) ∗ 5

𝑉𝑐𝑜𝑟𝑡𝑒 = 73.40𝑚3

5) 𝑉𝑐𝑜𝑟𝑡𝑒 = (5.49 + 4.44) ∗ 5

𝑉𝑐𝑜𝑟𝑡𝑒 = 49.65𝑚3

24
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

6) 𝑉𝑐𝑜𝑟𝑡𝑒 = (4.44 + 2.30) ∗ 5

𝑉𝑐𝑜𝑟𝑡𝑒 = 33.70𝑚3

7) 𝑉𝑐𝑜𝑟𝑡𝑒 = (2.30 + 0.14) ∗ 5

𝑉𝑐𝑜𝑟𝑡𝑒 = 12.20𝑚3

8) 𝑉𝑐𝑜𝑟𝑡𝑒 = (0.14 + 0.03) ∗ 5

𝑉𝑐𝑜𝑟𝑡𝑒 = 0.85𝑚3 El cálculo de volumen de corte se aplica de la misma forma. Es la


sumatoria de las áreas de relleno multiplicado por la semidistancia.

1) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = (0 + 0) ∗ 5

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 0𝑚3

2) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = (0 + 0.63) ∗ 5

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 3.5𝑚3

3) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = (0.63 + 3.19) ∗ 5

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 19.10𝑚3

4) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = (3.19 + 6.48) ∗ 5

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 48.35 𝑚3

5) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = (6.48 + 10.47) ∗ 5

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 84.75 𝑚3

6) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = (10.47 + 12.31) ∗ 5

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 113.90 𝑚3

7) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = (12.31 + 8.58) ∗ 5

𝑉𝑟𝑒𝑙𝑙𝑙𝑒𝑛𝑜 = 104.45 𝑚3

8) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = (8.58 + 9.13) ∗ 5

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 88.55 𝑚3

25
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Estos volúmenes obtenidos son en su estado natural. El factor de abundamiento


aplicado es del 1.15% por lo tanto cada uno de los volúmenes de relleno se
multiplican por dicho factor.

1)𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 0𝑚3 ∗ 1.15

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 0𝑚3

2) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 3.5𝑚3 ∗ 1.15

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 3.62𝑚3

3) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 19.10𝑚3 ∗ 1.15

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 21.97 𝑚3

4) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 48.35 𝑚3 ∗ 1.15

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 55.60 𝑚3

5) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 84.75 𝑚3 ∗ 1.15

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 97.46 𝑚3

6) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 113.90 𝑚3 ∗ 1.15

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 130.99 𝑚3

7) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 104.45 𝑚3 ∗ 1.15

𝑉𝑟𝑒𝑙𝑙𝑙𝑒𝑛𝑜 = 120.12 𝑚3

8) 𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 88.55 𝑚3 ∗ 1.15

𝑉𝑟𝑒𝑙𝑙𝑒𝑛𝑜 = 101.83 𝑚3

Todos los volúmenes calculados tanto de corte, relleno y relleno abultado se suman
para obtener la cantidad de material de corte y relleno se necesita para tener una
terraza nivelada.

26
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HOJA DE MOVIMIENTO DE TIERRAS

TERRAZA PABELLONES
AREAS VOLUMENES VOLUMENES ACUMULADOS
RELLENO
SEMI - RELLENO
ESTACION CORTE ( m2 ) RELLENO (m2 ) CORTE ( m3 ) RELLENO (m3 ) ABUNDADO CORTE (m3 )
DISTANCIA ABUNDADO (m3 )
1.15%(m3 )

0+000.00 25.79 0.00

5.00 231.00 0.00 0.00

0+010.00 20.41 0.00 231.00 0.00

5.00 172.70 3.15 3.62

0+020.00 14.13 0.63 403.70 3.62

5.00 116.60 19.10 21.97

0+030.00 9.19 3.19 520.30 25.59

5.00 73.40 48.35 55.60

0+040.00 5.49 6.48 593.70 81.19

5.00 49.65 84.75 97.46

0+050.00 4.44 10.47 643.35 178.65

5.00 33.70 113.90 130.99

0+060.00 2.30 12.31 677.05 309.64

5.00 12.20 104.45 120.12

0+070.00 0.14 8.58 689.25 429.76

27
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

5.00 0.85 88.55 101.83

0+080.00 0.03 9.13 690.10 531.59

TOTALES DE ESTA
HOJA 81.92 50.79 690.10 462.25 531.59

TOTALES ANTERIORES 0.00 0.00 0.00 0.00 0.00


TOTALES
ACUMULADOS 81.92 50.79 690.10 462.25 531.59

28
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HOJA DE MOVIMIENTO DE TIERRAS


TERRAZA PARQUEO 1

AREAS VOLUMENES VOLUMENES ACUMULADOS DIFERENCIAS


RELLENO ORDENADAS
SEMI - RELLENO
ESTACION CORTE ( m2 ) RELLENO (m2 ) CORTE ( m3 ) RELLENO (m3 ) ABUNDADO CORTE (m3 ) PARA CURVA
DISTANCIA ABUNDADO (m3 )
1.15%(m3 ) MASA

0+000.00 2.72 0.68 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0+000.00 3.03 0.64 0.00 0.00 0.00
0.00 0.00 0.00 0.00

0+000.00 3.03 0.65 0.00 0.00 0.00

5.00 50.65 3.80 4.37


0+010.00 7.10 0.11 50.65 4.37 46.28
5.00 78.30 0.55 0.63
0+020.00 8.56 0.00 128.95 5.00 123.95
5.00 65.95 13.55 15.58
0+030.00 4.63 2.71 194.90 20.58 174.32
4.91 167.04 13.31 15.31
0+039.81 29.39 361.94 35.89 326.05

TOTALES DE ESTA
HOJA 58.46 4.79 361.94 31.21 35.89
TOTALES ANTERIORES 2.30 12.31 0.00 0.00 0.00
TOTALES
ACUMULADOS 60.76 17.10 361.94 31.21 35.89

29
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HOJA DE MOVIMIENTO DE TIERRAS


TERRAZA CANCHA

VOLUMENES
AREAS VOLUMENES
ACUMULADOS
RELLENO RELLENO
SEMI - CORTE ( m2 CORTE ( m3 CORTE
ESTACION RELLENO (m )
2
RELLENO (m )
3
ABUNDADO ABUNDADO
DISTANCIA ) ) (m3 )
1.15%(m3 ) (m3 )

0+000.00 0.00 42.44 0.00 0.00

5.00 0.00 389.45 447.87

0+010.00 0.00 35.45 0.00 447.87

5.00 0.00 327.85 377.03

0+020.00 0.00 30.12 0.00 824.90

0.04 0.00 2.77 3.19

0+020.09 0.00 39.06 0.00 828.09

TOTALES DE ESTA
HOJA 0.00 147.07 0.00 720.07 828.09
TOTALES ANTERIORES 0.00 0.00 0.00 0.00 0.00
TOTALES
ACUMULADOS 0.00 147.07 0.00 720.07 828.09

30
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HOJA DE MOVIMIENTO DE TIERRAS


TERRAZA AREA VERDE

AREAS VOLUMENES VOLUMENES ACUMULADOS

RELLENO
SEMI - RELLENO
ESTACION CORTE ( m2 ) RELLENO (m2 ) CORTE ( m3 ) RELLENO (m3 ) ABUNDADO CORTE (m3 )
DISTANCIA ABUNDADO (m3 )
1.15%(m3 )

3.12 7.44 0.00 0.00


0.00 0.00 0.00 0.00
0+000.00 3.12 7.45 0.00 0.00
5.00 27.25 72.00 82.80
0+010.00 2.33 6.95 27.25 82.80
5.00 23.45 83.90 96.49
0+020.00 2.36 9.83 50.70 179.29
4.07 9.89 117.34 134.94

0+028.13 0.07 19.00 60.59 314.23

TOTALES DE ESTA
11.00 50.67 60.59 273.24 314.23
HOJA
TOTALES ANTERIORES 60.76 17.10 361.94 31.21 35.89
TOTALES
71.76 67.77 422.53 304.45 350.12
ACUMULADOS

31
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HOJA DE MOVIMIENTO DE TIERRAS


TERRAZA PARQUEO 3

AREAS VOLUMENES VOLUMENES ACUMULADOS


RELLENO
SEMI - RELLENO
ESTACION CORTE ( m2 ) RELLENO (m2 ) CORTE ( m3 ) RELLENO (m3 ) ABUNDADO CORTE (m3 )
DISTANCIA ABUNDADO (m3 )
1.15%(m3 )

0+000.00 3.06 9.90 0.00 0.00


0.00 0.00 0.00 0.00
0+000.00 3.06 9.89 0.00 0.00
5.00 27.70 91.10 104.77
0+010.00 2.48 8.33 27.70 104.77
5.00 31.10 76.55 88.03
0+020.00 3.74 6.98 58.80 192.80
5.00 57.35 53.85 61.93
0+030.00 7.73 3.79 116.15 254.73
5.00 87.25 32.15 36.97
0+040.00 9.72 2.64 203.40 291.70
5.00 112.90 18.45 21.22
0+050.00 12.86 1.05 316.30 312.92
5.00 149.75 5.40 6.21
0+060.00 17.09 0.03 466.05 319.13
3.60 133.67 0.11 0.13
0+067.19 20.04 0.00 599.72 319.26

TOTALES DE ESTA
79.78 42.61 599.72 277.61 319.26
HOJA

TOTALES ANTERIORES 0.00 0.00 0.00 0.00 0.00


TOTALES
79.78 42.61 599.72 277.61 319.26
ACUMULADOS

32
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HOJA DE MOVIMIENTO DE TIERRAS


TERRAZA CASETA

AREAS VOLUMENES VOLUMENES ACUMULADOS


RELLENO
SEMI - RELLENO
ESTACION CORTE ( m2 ) RELLENO (m2 ) CORTE ( m3 ) RELLENO (m3 ) ABUNDADO CORTE (m3 )
DISTANCIA ABUNDADO (m3 )
1.15%(m3 )

0+000.00 9.63 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0+000.00 9.64 0.00 0.00 0.00
5.00 118.55 0.00 0.00
0+010.00 14.07 0.00 118.55 0.00
2.40 80.16 36.67 42.17
0+014.80 19.33 15.28 198.71 42.17

TOTALES DE ESTA
52.67 15.28 198.71 36.67 42.17
HOJA
TOTALES ANTERIORES 9.72 2.64 0.00 0.00 0.00
TOTALES
62.39 17.92 198.71 36.67 42.17
ACUMULADOS

33
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HOJA DE MOVIMIENTO DE TIERRAS


TERRAZA SALON DE MAESTROS

VOLUMENES
AREAS VOLUMENES
ACUMULADOS
RELLENO
SEMI - RELLENO RELLENO
ESTACION CORTE ( m )
2
CORTE ( m )
3
RELLENO (m )
3
ABUNDADO CORTE (m3 )
DISTANCIA (m2 ) ABUNDADO (m3 )
1.15%(m3 )

0+000.00 5.88 2.67 0.00 0.00

0.00 0.00 0.00 0.00

0+000.00 1.90 6.48 0.00 0.00

5.00 44.95 52.30 60.15

0+010.00 7.09 3.98 44.95 60.15

0.57 8.33 4.29 6.44

0+011.13 7.52 3.54 53.28 66.59

TOTALES DE ESTA
22.39 16.67 53.28 56.59 66.59
HOJA
TOTALES ANTERIORES 9.72 2.64 0.00 0.00 0.00
TOTALES
32.11 19.31 53.28 56.59 66.59
ACUMULADOS

34
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HOJA DE MOVIMIENTO DE TIERRAS


TERRAZA PARQUEO 2

AREAS VOLUMENES VOLUMENES ACUMULADOS


RELLENO
SEMI - RELLENO
ESTACION CORTE ( m2 ) RELLENO (m2 ) CORTE ( m3 ) RELLENO (m3 ) ABUNDADO CORTE (m3 )
DISTANCIA ABUNDADO (m3 )
1.15%(m3 )

0+000.00 7.75 1.20 0.00 0.00


0.00 0.00 0.00 0.00
0+000.00 7.56 1.20 0.00 0.00
5.00 71.50 14.30 16.45
0+010.00 6.74 1.66 71.50 16.45
5.00 45.20 23.55 27.08
0+020.00 2.30 3.05 116.70 43.53
5.00 16.45 31.85 36.63
0+030.00 0.99 3.32 133.15 80.16
5.00 4.95 50.90 58.54
0+040.00 0.00 6.86 138.10 138.70
5.00 0.00 83.20 95.68
0+050.00 0.00 9.78 138.10 234.38
5.00 0.00 48.90 56.24
0+060.00 0.00 0.00 138.10 290.62
0.47 0.00 0.00 0.00
0+060.94 138.10 290.62
TOTALES DE ESTA
25.34 27.07 138.10 252.70 290.62
HOJA

TOTALES ANTERIORES 0.00 0.00 0.00 0.00 0.00


TOTALES
25.34 27.07 138.10 252.70 290.62
ACUMULADOS

35
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HOJA DE MOVIMIENTO DE TIERRAS


TERRAZA CALLE SECUNDARIA

AREAS VOLUMENES VOLUMENES ACUMULADOS


RELLENO
SEMI - RELLENO
ESTACION CORTE ( m2 ) RELLENO (m2 ) CORTE ( m3 ) RELLENO (m3 ) ABUNDADO CORTE (m3 )
DISTANCIA ABUNDADO (m3 )
1.15%(m3 )

0+000.00 12.03 0.85 0.00 0.00


0.00 0.00 0.00 0.00
0+000.00 12.05 0.84 0.00 0.00
5.00 120.15 11.00 12.65
0+010.00 11.98 1.36 120.15 12.65
5.00 83.70 19.25 22.14
0+020.00 4.76 2.49 203.85 34.79
5.00 36.10 26.30 30.25
0+030.00 2.46 2.77 239.95 65.04
5.00 12.30 52.55 60.43
0+040.00 0.00 7.74 252.25 125.47
5.00 0.00 103.65 119.20
0+050.00 0.00 12.99 252.25 244.67
5.00 0.00 75.10 86.37
0+060.00 0.00 2.03 252.25 331.04
0.47 0.00 0.95 1.09
0+060.93 0.00 0.00 252.25 332.13
TOTALES DE ESTA
43.28 31.07 252.25 288.80 332.13
HOJA

25.34 27.07 138.10 252.70 290.62


TOTALES ANTERIORES
TOTALES
68.62 58.14 390.35 541.50 622.75
ACUMULADOS

36
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HOJA DE MOVIMIENTO DE TIERRAS


TERRAZA CALLE INTERNA
AREAS VOLUMENES VOLUMENES ACUMULADOS
RELLENO
SEMI - RELLENO
ESTACION CORTE ( m2 ) RELLENO (m2 ) CORTE ( m3 ) RELLENO (m3 ) ABUNDADO CORTE (m3 )
DISTANCIA ABUNDADO (m3 )
1.30%(m3 )

0+000.00 39.62 0.00 0.00 0.00


0.00 0.00 0.00 0.00
0+000.00 39.68 0.00 0.00 0.00
5.00 383.15 0.00 0.00
0+010.00 36.95 0.00 383.15 0.00
5.00 310.25 8.75 11.38
0+020.00 25.10 1.75 693.40 11.38
5.00 220.65 35.30 45.89
0+030.00 19.03 5.31 914.05 57.27
5.00 178.25 52.60 68.38
0+040.00 16.62 5.21 1,092.30 125.65
5.00 152.35 57.10 74.23
0+050.00 13.85 6.21 1,244.65 199.88
5.00 124.00 75.20 97.76
0+060.00 10.95 8.83 1,368.65 297.64
5.00 101.30 98.55 128.12
0+070.00 9.31 10.88 1,469.95 425.76
5.00 81.05 124.20 161.46
0+080.00 6.90 13.96 1,551.00 587.22
5.00 54.70 156.90 203.97
0+090.00 4.04 17.42 1,605.70 791.19
5.00 42.80 184.15 239.40
0+100.00 4.52 19.41 1,648.50 1,030.59
5.00 50.60 203.55 264.62
0+110.00 5.60 21.30 1,699.10 1,295.21

37
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

5.00 40.75 228.30 296.79


0+120.00 2.55 24.36 1,739.85 1,592.00
TOTALES DE ESTA
234.72 134.64 1,739.85 1,224.60 1,592.00
HOJA
TOTALES ANTERIORES 0.00 0.00 0.00 0.00 0.00
TOTALES
234.72 134.64 1,739.85 1,224.60 1,592.00
ACUMULADOS

La propuesta de niveles de cada terraza se basó principalmente en minimizar costos altos en el movimiento de tierra, por
ello se decide respetar las cuencas naturales del terreno y proponer pendientes que ayuden a dicho trabajo. Como se
menciona previamente las aguas serán recolectadas por medio de tragantes que luego las depositaran en pozos de
absorción.
Por otra parte el volumen de descapote depende directamente dela área a trabajar la cual es de 7623.35 m2, a esta área
se le aplicará un corte de 15cm lo que se convierte en un volumen de 1143.50 m3 con un abundamiento del 1.15% se
modifica en un volumen de 1315.03 m3. Para el traslado del material de desalojo se hará uso de dos camiones volquetes
de 12 m3 de capacidad.
Para el material selecto se requiere de un volumen de 1155.19 m3 lo cual se comprará en Mina Sandino ubicada en el
municipio de Ciudad Sandino. El material será utilizado para colocar una capa de 20 cm en cada una de las terrazas para
garantizar mayor resistencia al suelo.
A continuación se muestra el alcance de obra el cual expone los volúmenes precisos de corte y re

38
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

ALCANCE DE OBRA
Etapa Descripción Unidad Medida Cantidad
01 Descapote m3 1143.50
02 Desalojo Material Descapote m3 1315.03
03 Cálculo Terraza Pabellones (Corte) m3 690.10
04 Cálculo Terraza Pabellones (Relleno) m3 462.25
05 Cálculo Terraza Parqueo 1 (Corte) m3 361.94
06 Cálculo Terraza Parqueo 1 (Relleno) m3 31.21
07 Cálculo Terraza Cancha (Corte) m3 0
08 Cálculo Terraza Cancha (Relleno) m3 720.07
09 Cálculo Terraza Área Verde (Corte) m3 60.59
10 Cálculo Terraza Área Verde (Relleno) m3 273.24
11 Cálculo Terraza Parqueo 3 (Corte) m3 599.72
12 Cálculo Terraza Parqueo 3 (Relleno) m3 277.61
13 Cálculo Terraza Caseta (Corte) m3 198.71
14 Cálculo Terraza Caseta (Relleno) m3 36.67
15 Cálculo Terraza Salón de Maestros m3 53.28
(Corte)
16 Cálculo Terraza Salón de Maestros m3 56.59
(Relleno)
17 Cálculo Terraza Parqueo 2 (Corte) m3 138.10
18 Cálculo Terraza Parqueo 2 (Relleno) m3 252.70
19 Cálculo Terraza Calle Secundaria (Corte) m3 252.25
20 Cálculo Terraza Calle Secundaria m3 288.80
(Relleno)
21 Cálculo Terraza Calle Interna (Corte) m3 1739.85
22 Cálculo Terraza Calle Interna (Relleno) m3 1224.60
23 Material Selecto requerido para m3 1155.19
recubrimiento de 20 cm en terrazas.
24 Desalojo de material sobrante m3 541.42

39
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

3. PLANIFICACIÓN

3.1 Criterios para la selección de la maquinaria


La maquinaria utilizada en el movimiento de tierra hoy en día se encuentra
altamente demandada. Las cuales poseen equipos y herramientas que juegan un
papel fundamental, utilizadas en diversas operaciones. De tal forma que cada una
cumple diversas funcionalidades las cuales ejecutan directamente determinada
operación, es por esto que se ha decidido rentar las maquinarias de Agroindustrial
Mantica, S.A (AIMSA) y Master Construction, dichas empresas ofrecen diversos
servicios que benefician esta etapa del proyecto.

Agroindustrial Mantica, S.A (AIMSA)

AIMSA es una empresa que comenzó comercializando repuestos de maquinaria


agrícola en Managua, dicha empresa se ha concentrado en el marco de la
construcción, es decir, en venta y renta de maquinaria pesada desde 1991 por
medio de las marca italiana New Holland Construction. Durante 45 años, AIMSA ha
aportado al progreso de Nicaragua tanto como en la agricultura y la construcción,
conformado de un equipo de trabajo, talleres de servicio y stock de repuestos
guiados y especializados.

Aspectos Generales

AIMSA ofrece la renta y venta de maquinaria nueva y semi nueva, entre estos
equipos destacan: Retroexcavadoras, excavadoras, vibro compactadoras,
motoniveladoras, tractores de orugas, mini cargadores, siendo estos los más
demandados en el ámbito de la construcción. En lo particular AIMSA renta de 6 a 5
horas mínimas, no renta con 4 horas mínimas y estas pueden incluir operador y
asistencia mecánica esto difiere del cliente.

Al rentar el equipo con operador es política de la empresa llenar un informe diari o


en el cual incluye: la hora de entrada, el horómetro inicial y el horómetro final, horas
de trabajo, observaciones. Cada equipo utiliza combustible diésel y el rendimiento
del equipo depende de la experiencia del operador.

40
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Para AIMSA la vida útil del equipo llega alrededor de las 1500 horas, sin embargo
esto dependerá de la utilidad de la máquina y de su mantenimiento. Realizan el
primer chequeo mecánico a las 50 horas cuando el equipo es nuevo, el siguiente
mantenimiento es a las 100 horas, luego a las 250 horas y a las 500 horas. Después
de las 500 horas el próximo seria a las 1000 horas.

Mantenimiento

El mantenimiento que se le brinda a la maquinaria en AIMSA se divide en horas de


trabajo, a un equipo nuevo se hace el primer mantenimiento a las 50 horas
principalmente se hace cambio de filtro, el segundo se hace a las 100 horas cambio
de filtro y aceite, el tercer mantenimiento se da a las 200 horas con cambio de filtro,
aceite y niveles del sistema hidráulico y finalmente a las 500 horas este
mantenimiento dependerá de la explotación del equipo, se inspecciona lo
mencionado anteriormente y otros aspectos como el cambio neumáticos que
depende de la vida útil del equipo, cambio de mangueras. Del mismo modo se
engrasa el equipo una vez por semana para que este no presente dificultades al
trabajar.

Se ha investigado acerca de la renta horario, costo, modelo y especificaciones


técnicas de los siguientes equipos:

Master Construction

Mantenimiento:

Cada 50 horas se chequean los niveles, se les chequea el filtro de aire y se les hace
un engrase a nivel de todas las maquinas

Cada 250 horas se le hace cambio de aceite al motor, estado de la correa de los
motores, en algunos casos como las excavadoras y los tractores de orugas se les
revisan el estado de los dientes o herramientas de cortes (se cambian los dientes y
las láminas de los lados de los cucharones se refuerzan con lámina especial
acerada.

41
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Cada 1000 horas se vuelve a cambiar el aceite del motor, se cambia el filtro de
transmisión, se chequea la parte eléctrica (luces, tablero, aceleración etc.)

Tiempo de Existir la Empresa: 8 años

Como Invierten en Ella: Esta empresa constructora se mantiene de proyectos y


trabaja tanto en obras horizontales como en obras verticales. Conforme agarran
proyectos y obtienen grandes ganancias se compran equipos nuevos y se
reemplazan aquellos equipos que están muy viejos.

Que Incluyen las Rentas: Incluye operador, el combustible lo pone el que renta el
equipo, 4 horas mínimas lo uses o no lo uses, todos los equipos trabajan con
horómetros.

a. Especificaciones técnicas
1. Retroexcavadora New Holland

Modelo: B95B

Precio por hora (no incluye IVA): $27

Horas mínimas por días: 5 a 6 horas

Forma de pago: al contado

Incluye: Asistencia mecánica.

No incluye: combustible, resguardo del equipo, operador, traslado, pinchadura.

Especificaciones técnicas:

• Motor con opciones de turbo, mecánico de inyección directa o electrónico


common rial.

• Nuevo sistema “venturi cone” el cual reduce las vibraciones en el tubo de


escape y aumenta la vida útil del silenciador.

• Las bombas dobles de engranaje ofrecen un flujo hidráulico de hasta 159


litros por minuto.

42
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

• El brazo tiene mayor alcance y altura de volcado.

• Potencia de 91 HP.

• Peso operativo de 7.261 kg.

• Profundidad de excavación 5.521 metros.

2. Vibro compactadora

Modelo: B95B

Precio por hora (no incluye IVA): $38

Horas mínimas por días: 4 horas

Forma de pago: al contado

Incluye: Asistencia mecánica.

No incluye: combustible, resguardo del equipo, operador, traslado, pinchadura.

3. Mini cargador New Holland

Modelo: L220

Precio por hora (no incluye IVA): $18

Horas mínimas por días: 5 a 6 horas

Forma de pago: al contado

Incluye: Asistencia mecánica, operador con viáticos de alimentación.

No incluye: combustible, resguardo del equipo, operador, traslado, pinchadura, ni


hospedaje de operador.

Especificaciones técnicas:

• Sistema hidráulico que cuenta con bombas hidráulicas en línea que produce
una operación suave y silenciosa.

• El motor New Holland ISM posee un sistema de inyección programado para


entregar la mayor potencia y torque con la cantidad justa de combustible.

43
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

• Potencia 60 HP.

• Peso operativo 2.930 kg.

• Alcance de descarga a altura máxima 905 kg.

3. Motoniveladora New Holland RG140.B

Especificaciones New Holland RG140.B

Modelo 6BTA 5.9

Motor

Nivel de emisiones Nivel 1

Refrigeración del motor: Líquido

Combustible: Diésel

Potencia 140 hp

Rendimiento

Peso máquina base14.371 kg

Peso máximo 15.486 kg 15.7

Velocidad de desplazamiento máximo Avance: 37.6 km/h

Retroceso: 25.7 km/h

4. Volquete

Renta: 35 dólares la hora

Precio Nuevo: 90,000 dólares

Precio Semi Nuevo: 50,000 dólares

Especificaciones: Marca Mack, Modelo Cd73, Capacidad 12 m3 de material, motor


inyección directa

Cambio de baterías: a las 850 o 1000 horas

44
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Cambio de llantas: a los 60,000 km

Precio de llantas: 8,000 dólares marca Firestone

5. Cisterna

Renta: 100 dólares el día

Precio Nuevo: 50,000 dólares

Precio Semi Nuevo: 25,000 dólares

Especificaciones: Marca International, modelo 8100, capacidad de la pipa 4,000


galones, doble eje, usa 2 baterías, tracción 6x4

Cambio de baterías: a las 850 o 1000 horas

Cambio de llantas: a los 60,000 km

Precio de llantas: 6,000 dólares

b. Movilidad

Primeramente se plantea que se rentaran siete equipos, de los cuales 3 de ellos se


trasladan por sí mismo y los cuatro restantes en camiones transportadores de
maquinaria. La movilización y desmovilización por equipos cuesta alrededor de 500
dólares.

Se tiene que la maquinaria rentada en Agroindustrial Mantica (AIMSA) son la vibro


compactadora, motoniveladora y mini cargador son transportadas en camión y
retroexcavadora por sí misma y recorren una distancia de 19 kilómetros hasta el
proyecto.

Mientras que la cisterna y el volquete se trasladan por sí mismo desde Master


Construction, así como el tractor sobre oruga transportado en camión recorren una
distancia total de 15 kilómetros.

45
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

c. Tiempo

El tiempo para realizar el traslado y plantee de maquinaria se comprende en los


primeros cinco días de entrega del terreno.

3.2 Renta horaria

CARGOS UNITARIOS POR MAQUINARIA.

 EMPRESA ( Agroindustrial Mantica, S.A) (AIMSA)

 RETROEXCAVADORA.
Marca Caterpillar
Modelo 446B
Potencia 110 HP
Carter 29 lt
Rendimiento 104.89 m3 /h
Precio Nuevo 78, 300 $
Factor de operación 0.85
C$64,000
Precio de Llantas C$ 16000 ∗ 4 = = $2098
$30.50

“CARGOS FIJOS”

Va=78,300 dólares – $2,098= $76202

Ve= 10 000 hr

Vr= (0.15) (76202)= 11430.3

46
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cargos por Depreciación


𝑉𝑎 − 𝑉𝑟
𝐷=
𝑉𝑒

76202 − 11430.3
𝐷=
10 000

𝐷 = $6.47

 Cargos por inversión.


𝑉𝑎 + 𝑉𝑟
𝐼= ∗𝑖
2𝐻𝑟

76202 + 11430.3
𝐼= ∗ 0.08
2(800)

𝐼 = $4.38

 Cargos por seguro.


S=0.03
𝑉𝑎 + 𝑉𝑟
𝑆= ∗𝑠
2𝐻𝑎

128219 + 19232
𝑆= ∗ 0.03
2(800)

𝑆 = $1.64

 Cargos por almacenaje.


K=0.07
𝐴 = 𝐾𝐷
𝐴 = 0.07 ∗ $6,47
𝐴 = $0.45

47
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cargos por mantenimiento.


Q=1
𝑀 = 𝑄𝐷
𝑀 = (1)($6.47)
𝑀 = $6.47

“CARGOS POR CONSUMO”


 Cargos por consumo de combustible.
e=0.2*110*0.85
e=18.7

𝐸 = 𝑒𝑃𝑐
𝐸 = 18.7lts/hr ∗ C$24.20/lts/$30.50
𝐸 = $14.84
 Cargos por consumo de lubricantes.
Precio del aceite 2500 la cubeta
19 𝑙𝑡𝑠 29 𝑙𝑡𝑠
=
𝐶$2500 𝑥
X= C$ 3,815.79
𝐶$3,815.79
$30.30
Pe=
29 𝑙𝑡𝑠
Pe= $4.34
29lts
𝑎= + 0.0035 ∗ 110 ∗ 0.85
100ℎ𝑟
𝑎 = 0.62 𝑙𝑡𝑠/ℎ𝑟
𝐿 = 𝑎𝑃𝑒
𝐿 = (0.62𝑙𝑡𝑠/ℎ𝑟 ∗ $4.34)
𝐿 = $2.69

48
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cargos por operación:


Salario operario: 870/día
𝑆𝑡
𝑂=
𝐻

$870
𝑂= /$30.50
6ℎ𝑟

𝑂 = $4.75

 Cargo unitario por maquinaria.


𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
HMD=D+I+S+A+M+E+L+O
HMD= (6.47+4.38+1.64+0.45+6.47+14.84+2.69+4.75) $/hr
HMD= 41.69+ 15%
HMD= 47.94 $/hr

RM=104.89m3/hr*0.85
RM=89.16m3/hr

𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
47.94 $/hr
𝐶𝑀:
89.16𝑚3 /hr
𝐶𝑀: 0.54

49
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 VIBROCOMPACTADORA
Marca Caterpillar Mixta
Modelo SD100
Potencia 170 HP
Carter 16 lt
Rendimiento 545.28 m3/h
Precio Nuevo 71,000 $
Factor de operación 0.85

C$32,000
Precio de Llantas C$ 16,000 ∗ 2 = $30.50
= $1050

“CARGOS FIJOS”
Va=71000 dólares- $1,050= $69950

Ve= 10 000 hr

Vr= (0.15) (69950)=10492.5

 Cargos por Depreciación


𝑉𝑎 − 𝑉𝑟
𝐷=
𝑉𝑒

69950 − 10492.5
𝐷=
10 000

𝐷 = $5.94

 Cargos por inversión.


𝑉𝑎 + 𝑉𝑟
𝐼= ∗𝑖
2𝐻𝑟

69950 + 10492.5
𝐼= ∗ 0.08
2(800)

𝐼 = $4.02

50
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cargos por seguro.


S=0.04
𝑉𝑎 + 𝑉𝑟
𝑆= ∗𝑠
2𝐻𝑎

69950 + 10492.5
𝑆= ∗ 0.04
2(800)

𝑆 = $2.01

 Cargos por almacenaje.


K=0.07
𝐴 = 𝐾𝐷
𝐴 = 0.07 ∗ $5.94
𝐴 = $0.41

 Cargos por mantenimiento.


Q=1
𝑀 = 𝑄𝐷
𝑀 = (1)($5.94)
𝑀 = $5.94

“CARGOS POR CONSUMO”


 Cargos por consumo de combustible.
e=0.2*170*0.85
e=28.9

𝐸 = 𝑒𝑃𝑐
𝐸 = 28.9lts/hr ∗ C$24.20/lts/$30.50
𝐸 = $22.93

51
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cargos por consumo de lubricantes.


Precio del aceite 2500 la cubeta
19 𝑙𝑡𝑠 17 𝑙𝑡𝑠
=
𝐶$2500 𝑥
X= C$ 2236.84
𝐶$2236.84
$30.50
Pe=
17 𝑙𝑡𝑠
Pe= $4.31
16lts
𝑎= + 0.0035 ∗ 170 ∗ 0.85
100ℎ𝑟
𝑎 = 0.66 𝑙𝑡𝑠/ℎ𝑟
𝐿 = 𝑎𝑃𝑒
𝐿 = (0.66𝑙𝑡𝑠/ℎ𝑟 ∗ $4.31)
𝐿 = $2.84

 Cargos por operación:


Salario operario: 870/día
𝑆𝑡
𝑂=
𝐻

$870
𝑂= /$30.50
6ℎ𝑟

𝑂 = $4.75

 Cargo unitario por maquinaria.


𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
HMD=D+I+S+A+M+E+L+O
HMD= (5.94+4.02+2.01+0.41+5.94+22.93+2.84+4.75) $/hr
HMD=48.84 + 15%
HMD=56.16 $/hr

52
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

RM=545.28m3/hr*0.85
RM=463.49m3/hr

𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
56.16 $/hr
𝐶𝑀:
463.49𝑚3 /hr
𝐶𝑀: 0.12 $/𝑚3

 MOTONIVELADORA.
Marca New Holland.
Modelo RG140B
Potencia 140 HP
Carter 29 lt
Rendimiento 730.95 m3/h
Precio Nuevo 135,000 $
Factor de operación 0.85
C$96,000
Precio de Llantas C$ 16,000 ∗ 6 = = $3148
$30.50

“CARGOS FIJOS”
Va=135000 dólares – $3,148= $131852

Ve= 10 000 hr

Vr= (0.15) (216,852)= 19777

 Cargos por Depreciación


𝑉𝑎 − 𝑉𝑟
𝐷=
𝑉𝑒

131852 − 19777
𝐷=
10 000

𝐷 = $11.20

53
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cargos por inversión.


𝑉𝑎 + 𝑉𝑟
𝐼= ∗𝑖
2𝐻𝑟

131852 + 19777
𝐼= ∗ 0.08
2(800)

𝐼 = $7.58

 Cargos por seguro.


S=0.03
𝑉𝑎 + 𝑉𝑟
𝑆= ∗𝑠
2𝐻𝑎

131852 − 19777
𝑆= ∗ 0.03
2(800)

𝑆 = $2.84

 Cargos por almacenaje.


K=0.07
𝐴 = 𝐾𝐷
𝐴 = 0.07 ∗ $11.20
𝐴 = $0.78
 Cargos por mantenimiento.
Q=1
𝑀 = 𝑄𝐷
𝑀 = (1)($11.20)
𝑀 = $11.20

54
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

“CARGOS POR CONSUMO”


 Cargos por consumo de combustible.
e=0.2*140*0.85
e=23.8 lt/hr

𝐸 = 𝑒𝑃𝑐
𝐸 = 23.8lts/hr ∗ C$24.20/lts/$30.50
𝐸 = $18.88
 Cargos por consumo de lubricantes.
Precio del aceite 2500 la cubeta
19 𝑙𝑡𝑠 29 𝑙𝑡𝑠
=
𝐶$2500 𝑥
X= C$ 3,815.79

𝐶$3,815.79
$30.30
Pe=
29 𝑙𝑡𝑠
Pe= $4.34

29lts
𝑎= + 0.0035 ∗ 140 ∗ 0.85
100ℎ𝑟
𝑎 = 0.71 𝑙𝑡𝑠/ℎ𝑟
𝐿 = 𝑎𝑃𝑒
𝐿 = (0.71𝑙𝑡𝑠/ℎ𝑟 ∗ $4.34)
𝐿 = $3.08

55
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cargos por operación:


Salario operario: 870/día
𝑆𝑡
𝑂=
𝐻

$870
𝑂= /$30.50
6ℎ𝑟

𝑂 = $4.75

 Cargo unitario por maquinaria.


𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
HMD=D+I+S+A+M+E+L+O
HMD= (11.20+7.58+2.84+0.78+11.20+18.88+0.71+4.75)$/hr
HMD=60.31+ 15%
HMD=69.35 $/hr
RM=730.95m3/hr*0.85
RM=621.31 m3/hr

𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
69.35 $/hr
𝐶𝑀:
621.31 𝑚3 /hr
𝐶𝑀: 0.11 $/𝑚3

56
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 MINI CARGADOR FRONTAL


Marca New Holland
Modelo L220
Potencia 60 HP
Carter 10 lt
Rendimiento 22.05 m3/h
Precio Nuevo 35, 000 $
Factor de operación 0.85
C$24,000
Precio de Llantas C$ 6000 ∗ 4 = = $787
$30.50

“CARGOS FIJOS”
Va=35,000 dólares- $787= $34213

 Cargos por Depreciación


𝑉𝑎 − 𝑉𝑟
𝐷=
𝑉𝑒

34213 − 5131.95
𝐷=
10 000

𝐷 = $2.90

 Cargos por inversión.


𝑉𝑎 + 𝑉𝑟
𝐼= ∗𝑖
2𝐻𝑟

34213 + 5131.95
𝐼= ∗ 0.08
2(800)

𝐼 = $1.45

57
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cargos por seguro.


S=0.03
𝑉𝑎 + 𝑉𝑟
𝑆= ∗𝑠
2𝐻𝑎

34213 + 5131.95
𝑆= ∗ 0.03
2(800)

𝑆 = $0.54

 Cargos por almacenaje.


K=0.07
𝐴 = 𝐾𝐷
𝐴 = 0.07 ∗ $2.90
𝐴 = $0.20

 Cargos por mantenimiento.


Q=1
𝑀 = 𝑄𝐷
𝑀 = (1)($2.90)
𝑀 = $2.90

“CARGOS POR CONSUMO”


 Cargos por consumo de combustible.
e=0.2*60*0.86
e: 10.32 lts/h

𝐸 = 𝑒𝑃𝑐
𝑙𝑡𝑟
10.32 ∗ C$24.20 𝑙𝑡𝑠
𝐸: ℎ𝑟
$30.50

58
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

𝐸 = $8.19
 Cargos por consumo de lubricantes.
Precio del aceite 2500 la cubeta
19 𝑙𝑡𝑠 10 𝑙𝑡𝑠
=
𝐶$2500 𝑥
X= C$ 1315.79

𝐶$1315.79
$30.50
Pe=
10 𝑙𝑡𝑠

Pe= $4.31
10lts
𝑎= + 0.0035 ∗ 60 ∗ 0.86
100ℎ𝑟
𝑎 = 0.28 𝑙𝑡𝑠/ℎ𝑟
𝐿 = 𝑎𝑃𝑒
𝐿 = (0.28𝑙𝑡𝑠/ℎ𝑟 ∗ $4.31)
𝐿 = $1.21

 Cargos por operación:


Salario operario: 870/día
𝑆𝑡
𝑂=
𝐻

$870
𝑂= /$30.50
6ℎ𝑟

𝑂 = 4.75$/ℎ𝑟𝑠

 Cargo unitario por maquinaria.


𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
HMD=D+I+S+A+M+E+L+O
HMD= (2.90+1.45+0.54+0.20+2.90+8.19+1.21+4.75) $/hr
HMD=22.90 + 15%

59
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HMD=26.33 $/hr
RM=22.05 m3/hr*0.86
RM= 18.74m3/hr
𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
26.33$/hr
𝐶𝑀:
18.74 𝑚3 /hr
𝐶𝑀: 1.4 $/𝑚3

 Empresa “Master Constructor”


 VOLQUETE
Marca Volvo
Modelo F12
Potencia 300 HP
Carter 26 lt
Botadero= 27.91 m3/h
Rendimiento
Banco de Materiales= 19.355 m3/h
Precio Nuevo 45, 000 $
Factor de operación 0.85
C$80,000
Precio de Llantas C$ 8000 ∗ 10 = = $2,623
$30.50

“CARGOS FIJOS”
Va=45,000 dólares- $2,623= $42377

Ve= 10, 000 horas

Vr= (0.15) (42377)= $6356.55

 Cargos por Depreciación


𝑉𝑎 − 𝑉𝑟
𝐷=
𝑉𝑒

42377 − 6356.55
𝐷=
10 000

60
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

𝐷 = $3.60

 Cargos por inversión.


𝑉𝑎 + 𝑉𝑟
𝐼= ∗𝑖
2𝐻𝑟

42377 + 6356.55
𝐼= ∗ 0.08
2(800)

𝐼 = $2.43

 Cargos por seguro.


S=0.03
𝑉𝑎 + 𝑉𝑟
𝑆= ∗𝑠
2𝐻𝑎

42377 + 6356.55
𝑆= ∗ 0.03
2(800)

𝑆 = $0.91

 Cargos por almacenaje.


K=0.07
𝐴 = 𝐾𝐷
𝐴 = 0.07 ∗ $ 3.60
𝐴 = $0.25
 Cargos por mantenimiento.
Q=1
𝑀 = 𝑄𝐷
𝑀 = (1)($3.60)
𝑀 = $3.60

61
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

“CARGOS POR CONSUMO”


 Cargos por consumo de combustible.
e=0.2*300*0.85
e: 51 lts/h

𝐸 = 𝑒𝑃𝑐
𝑙𝑡𝑟
51 ℎ𝑟 ∗ C$24.20 𝑙𝑡𝑠
𝐸:
$30.50
𝐸 = $40.46

 Cargos por consumo de lubricantes.


Precio del aceite 2500 la cubeta
19 𝑙𝑡𝑠 34 𝑙𝑡𝑠
=
𝐶$2500 𝑥
X= C$ 4473.68

𝐶$4473.68
$30.50
Pe= 34 𝑙𝑡𝑠

Pe= $4.31
34lts
𝑎= + 0.0035 ∗ 300 ∗ 0.85
100ℎ𝑟
𝑎 = 1.23 𝑙𝑡𝑠/ℎ𝑟
𝐿 = 𝑎𝑃𝑒
𝐿 = (1.23𝑡𝑠/ℎ𝑟 ∗ $4.31)
𝐿 = $5.31

62
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cargos por operación:


Salario operario: 870/día
𝑆𝑡
𝑂=
𝐻

870 C$
𝑂= /$30.50
6ℎ𝑟

𝑂 = $4.75

 Cargo unitario por maquinaria.


𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
HMD=D+I+S+A+M+E+L+O
HMD= (7.43+5.02+1.88+0.5+7.43+57+6.85+4.75) $/hr
HMD=61.31 + 15%
HMD=70.50 $/hr

- Al botadero
RM=27.91 m^3⁄h*0.85

RM=23.724 m3/hr

CM=HMD/RM

CM:(70.50$/hr)/(23.724m^3/hr)

CM=2.97 $/m3

- Al banco de préstamo.
RM=19.355 m3/hr*0.85
RM=16.45 m3/hr
CM=HMD/RM
CM:(70.50 $/hr)/(16.45 m^3/hr)
CM=4.29$/m3

63
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 CISTERNA.
Marca International
Modelo 8100
Potencia 104 HP
Carter 12.7 lt
Rendimiento 12.12 m3/h
Precio Nuevo 50,000 $
Factor de operación 0.85
C$36,000
Precio de Llantas C$ 6,000 ∗ 6 = = $1181
$30.50

“CARGOS FIJOS”
Va=50,000 dólares- $1,181= $48,819

Ve= 10, 000 horas

Vr= (0.15) (48,819)= $7,323

 Cargos por Depreciación


𝑉𝑎 − 𝑉𝑟
𝐷=
𝑉𝑒

48819 − 7323
𝐷=
10 000

𝐷 = $4.15

 Cargos por inversión.


𝑉𝑎 + 𝑉𝑟
𝐼= ∗𝑖
2𝐻𝑟

48819 + 7323
𝐼= ∗ 0.08
2(800)

𝐼 = $2.81

64
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cargos por seguro.


S=0.03
𝑉𝑎 + 𝑉𝑟
𝑆= ∗𝑠
2𝐻𝑎

48819 + 7323
𝑆= ∗ 0.03
2(800)

𝑆 = $1.05

 Cargos por almacenaje.


K=0.07
𝐴 = 𝐾𝐷
𝐴 = 0.07 ∗ $4.15
𝐴 = $0.29

 Cargos por mantenimiento.


Q=1
𝑀 = 𝑄𝐷
𝑀 = (1)($4.15)
𝑀 = $4.15

“CARGOS POR CONSUMO”


 Cargos por consumo de combustible.
e=0.2*104*0.86
e: 17.88 lts/h

𝐸 = 𝑒𝑃𝑐
𝑙𝑡𝑟
17.88 ℎ𝑟 ∗ C$24.20 𝑙𝑡𝑠
𝐸:
$30.50
𝐸 = $14.18

65
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cargos por consumo de lubricantes.


Precio del aceite 2500 la cubeta
19 𝑙𝑡𝑠 12.7 𝑙𝑡𝑠
=
𝐶$2500 𝑥
X= C$ 1671.05

𝐶$1675.05
$30.50
Pe=
12.7 𝑙𝑡𝑠

Pe= $4.32
12.7lts
𝑎= + 0.0035 ∗ 104 ∗ 0.86
100ℎ𝑟
𝑎 = 0.44 𝑙𝑡𝑠/ℎ𝑟
𝐿 = 𝑎𝑃𝑒
𝐿 = (0.44𝑙𝑡𝑠/ℎ𝑟 ∗ $4.32)
𝐿 = $1.9

 Cargos por operación:


Salario operario: 870/día
Salario ayudante: 265/día
𝑆𝑡
𝑂=
𝐻

$870 265
𝑂= + /$30.50
6ℎ𝑟 6ℎ𝑟

𝑂 = 6.20$/ℎ𝑟𝑠

 Cargo unitario por maquinaria.


𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
HMD=D+I+S+A+M+E+L+O
HMD= (4.15+2.81+1.05+0.29+4.15+14.18+1.9+6.20) $/hr
HMD=34.73 + 15%

66
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HMD=39.94 $/hr

RM=12.12m3/hr*0.85
RM=10.30 m3/hr
𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
39.94 $/hr
𝐶𝑀:
10.30 𝑚3 /hr
𝐶𝑀: 3.88 $/𝑚3
 Tractor Oruga
Marca Caterpillar.
Modelo D6KXL
Potencia 125 HP
Carter 66.2 lt
Rendimiento 195.22 m3/h
Precio Nuevo 150, 000 $
Factor de operación 0.85

- Cargos fijos
Va=150000 dólares
Ve= 10 000 hr
Vr= (0.15)(150000)= 22500

 Cargos por Depreciación


Va − Vr
D=
Ve

150,000$ − (22500)
D=
10, 000hr

D = 12.75$/hr

 Cargos por inversión.

67
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Va + Vr
I= ∗i
2Ha

150,000$ + (22500)
I= ∗ 0.08
2(800hr)

I = 6.37$/hr

 Cargos por seguro.

S=0.03
Va + Vr
S= ∗s
2Ha
150,000$ + (22500)
S= ∗ 0.03
2(800hr)
S = 2.39$/hr
 Cargos por almacenaje.
K=0.07
A = KD
A = 0.07 ∗ 12.75$
A = 0.89$/hr

 Cargos por mantenimiento.


Q=1
M = QD
M = (1.0)(12.75$)
M = 12.75$/hr
“CARGOS POR CONSUMO”
 Cargos por consumo de combustible.
e=0.2*125*0.86
e: 21.5 lts/h

𝐸 = 𝑒𝑃𝑐

68
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

𝑙𝑡𝑟
21.5 ∗ C$24.20 𝑙𝑡𝑠
𝐸: ℎ𝑟
$30.50
𝐸 = $17.06
 Cargos por consumo de lubricantes.
Precio del aceite 2500 la cubeta
19 𝑙𝑡𝑠 12.7 𝑙𝑡𝑠
=
𝐶$2500 𝑥
X= C$ 1671.05

𝐶$1675.05
$30.50
Pe= 12 .7 𝑙𝑡𝑠

Pe= $4.32
12.7lts
𝑎= + 0.0035 ∗ 125 ∗ 0.86
100ℎ𝑟
𝑎 = 0.50 𝑙𝑡𝑠/ℎ𝑟
𝐿 = 𝑎𝑃𝑒
𝐿 = (0.50𝑙𝑡𝑠/ℎ𝑟 ∗ $4.32)
𝐿 = $2.16

 Cargos por operación:


Salario operario: 870/día

𝑆𝑡
𝑂=
𝐻

$870
𝑂= /$30.50
6ℎ𝑟

𝑂 = 4.75$/ℎ𝑟𝑠

 Cargo unitario por maquinaria.


𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
HMD=D+I+S+A+M+E+L+O

69
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

HMD= (12.75+6.37+2,39+0.89+12.75+17.06+2.16+4.75) $/hr


HMD=59.12+ 15%
HMD=67.98 $/hr
RM=195.22m3/hr*0.85
RM=165.94 m3/hr

𝐻𝑀𝐷
𝐶𝑀 =
𝑅𝑀
67.98 $/hr
𝐶𝑀:
165.94 𝑚3 /hr
𝐶𝑀: 0.41 $/𝑚3

70
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

COMPARACIÓN DE MAQUINARIA

CUADRO COMPARATIVO
EMPRESA ( Agroindustrial Mantica, S.A)
EQUIPOS MARCA MODELO AIMSA CALCULADOS
Retroexcavadora New Holland. B90B 27 $/hora 47.94$/hora
Vibro compactadora New Holland. SD100 38 $/hora 56.16 $/hora
Motoniveladora New Holland. RG140B 55 $/hora 69.35 $/hora
Mini cargador New Holland L220 17 $/hora 26.33 $/hora

CUADRO COMPARATIVO
EMPRESA (Master constructor)
EQUIPOS MARCA Modelo MASTER CONSTRUCTION CALCULADOS
Volquete Volvo F12 35 $/hora 70.5 $/hora
Cisterna International 810 100 $/día 39.94$/hora
Tractor de Orugas Caterpillar D6KXL 60 $/hora 67.98$/hora

Con IVA
EQUIPOS MARCA MODELO AIMSA CALCULADOS
Retroexcavadora New Holland. B90B 31 $/hora 47.94$/hora
Vibro compactadora New Holland. SD100 44 $/hora 56.16 $/hora
Motoniveladora New Holland. RG140B 63 $/hora 69.35 $/hora
Mini cargador New Holland L220 20 $/hora 26.33 $/hora

71
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

CON IVA
EQUIPOS MARCA Modelo MASTER CONSTRUCTION CALCULADOS
Volquete Volvo F12 40 $/hora 70.5 $/hora
Cisterna International 810 115 $/día 39.94$/hora
Tractor de Orugas Caterpillar D6KXL 69 $/hora 67.98 $/hora

72
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

4. RENDIMIENTO

1. VIBROCOMPACTADORA
𝑉𝐶 ( 𝑚3 ) 3
Rendimiento = = 𝑚 ⁄ℎ
ℎ(ℎ𝑜𝑟𝑎 )

𝑉𝐶 = L*A*C

L= Longitud tramo compactado

A= Ancho tramo compactado

C= Espesor capa compactada

𝐴∗𝐶 ∗𝑉∗1000
Rendimiento =
𝑃

A= Ancho del rodillo en metros

C= Espesor capa en metros

V= velocidad en km/h

P= número de pasadas en una hora

A= 2130 mm = 2.13 m

C= 0.20 m

V = 6.4 km/h

P = 5 por hora

2.13 𝑚∗0.20𝑚 ∗6.4 𝑘𝑚/ℎ∗1000


Rendimiento =
5

3
Rendimiento = 545.28𝑚 ⁄ℎ

73
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

2. MOTONIVELADORA
T: Tiempo en horas utilizada

N: número de pasadas

L: longitud recorrida en km

V1,V2,V3: velocidad en km/h en cada pasada

𝑁∗𝐿 𝑁∗𝐿 𝑁∗𝐿


 T= + +
𝑉1∗𝐸 𝑉2∗𝐸 𝑉3∗𝐸

 Nivelación de 623 .746m² * 0.20m de espesor, mediante moto niveladora de


eficiencia de 0.79
 Se necesitan 6 pasadas para completar el nivelado.
La primera y la segunda se dieron a 4.6km/h

La tercera y la cuarta se dieron a 6.8 km/h

La quinta y la sexta se dieron a 9.3 km/h

2 ∗ 0.107𝑘𝑚 2 ∗ 0.107𝑘𝑚 2 ∗ 0.107𝑘𝑚


𝑇= + +
0.79 ∗ 4.6 𝑘𝑚⁄ℎ 0.79 ∗ 6.8 𝑘𝑚⁄ℎ 0.79 ∗ 9.3 𝑘𝑚⁄ℎ

T= 0.128h

𝑉𝑇
𝑅𝑀 =
𝑇

93.562𝑚3
𝑅𝑀 =
0.128ℎ
3
𝑅𝑀 = 730.95 𝑚 ⁄ℎ

74
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

3. VOLQUETE.
Se calculan dos rendimientos porque influye la distancia que hay del proyecto
al botadero y del proyecto al banco de préstamo.

Al botadero.

Distancia=2.97Km

Velocidad cargado=35km/h

Velocidad descargado=50km/h

Ciclo del cargador=1.5 minutos

𝑇𝑐𝑖𝑐𝑙𝑜𝑠 = 𝑇𝐶𝑎𝑟𝑔 + 𝑇𝑡𝑟𝑎𝑛𝑠𝑝 + 𝑇𝑑𝑒𝑠𝑐𝑎𝑟𝑔𝑎 + 𝑇𝑡𝑟𝑎𝑛𝑠. 𝑑𝑒𝑠𝑐𝑎𝑟 . + 𝑇𝑚𝑎𝑛𝑖𝑜𝑏𝑟𝑎

2.97𝐾𝑚 2.97𝐾𝑚
𝑇𝑐𝑖𝑐𝑙𝑜𝑠 = 0.1363ℎ. + + 0.066ℎ + + 0.083ℎ
35 𝐾𝑚⁄ℎ 50 𝐾𝑚⁄ℎ

𝑇𝑐𝑖𝑐𝑙𝑜𝑠 = 0.430ℎ

12𝑚3 3
𝑅𝑒𝑛𝑑𝑖𝑚𝑖𝑒𝑛𝑡𝑜 = = 27.91 𝑚 ⁄ℎ 𝑝𝑜𝑟 𝑐𝑎𝑑𝑎 𝑐𝑎𝑚𝑖𝑜𝑛.
0.430ℎ

Al banco de préstamo.

Distancia=6.90Km

Velocidad cargado=35km/h

Velocidad descargado=50km/h

𝑇𝑐𝑖𝑐𝑙𝑜𝑠 = 𝑇𝐶𝑎𝑟𝑔 + 𝑇𝑡𝑟𝑎𝑛𝑠𝑝 + 𝑇𝑑𝑒𝑠𝑐𝑎𝑟𝑔𝑎 + 𝑇𝑡𝑟𝑎𝑛𝑠. 𝑑𝑒𝑠𝑐𝑎𝑟 . + 𝑇𝑚𝑎𝑛𝑖𝑜𝑏𝑟𝑎

6.90𝐾𝑚 6.90𝐾𝑚
𝑇𝑐𝑖𝑐𝑙𝑜𝑠 = 0.1363ℎ. + + 0.066ℎ + + 0.083ℎ
35 𝐾𝑚⁄ℎ 50 𝐾𝑚⁄ℎ

75
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

𝑇𝑐𝑖𝑐𝑙𝑜𝑠 = 0.620ℎ

12𝑚3 3
𝑅𝑒𝑛𝑑𝑖𝑚𝑖𝑒𝑛𝑡𝑜 = = 19.355 𝑚 ⁄ℎ 𝑝𝑜𝑟 𝑐𝑎𝑑𝑎 𝑐𝑎𝑚𝑖𝑜𝑛
0.620ℎ

4. RETROEXCAVADORA:
3600
RENDIMIENTO: (𝑄 ∗ ∗ 𝐸)(1 + 𝐹𝐻)
𝑇

Q= Capacidad del cucharon

T= Tiempo del ciclo

E= Factor de rendimiento de la maquina

F.H= Factor de altura

Q= 1 m3

T= 25

E= 0.5865

(𝑎𝑙𝑡𝑢𝑟𝑎 𝑠𝑜𝑏𝑟𝑒 𝑒𝑙 𝑛𝑖𝑣𝑒𝑙 𝑑𝑒𝑙 𝑚𝑎𝑟 −1000 150−1000


FH= = = −0.085
10000 10000

3600
RENDIMIENTO = (1 ∗ ∗ 0.5865) (1 − 0.085) = 104.89
22

3
RENDIMIENTO: 104.89 𝑚 ⁄ℎ

5. TRACTOR DE ORUGAS.
𝐶 ∗ 𝐸 ∗ 60
RM =
𝑇∗𝐹
3
RM= rendimiento en 𝑚 ⁄ℎ𝑟 de suelo en banco

C= capacidad de la cuchilla en 𝑚3 suelto


F= coeficiente de abundamiento del suelo
E= coeficiente de eficacia del “dozer”

76
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

T= Duración del ciclo en minutos


60= número de minutos en una hora

C= 6.86𝑚3 (Hoja “SU” Semi-universal)


F= 1.20
E= 0.79
Distancia media de transporte = 45 m
Velocidad de recorrido = 3.7 km/h
Velocidad de regreso = 8.3 km/h
2 ∗ 10 𝑠 45 𝑚 ∗ 60 𝑚𝑖𝑛 45 𝑚 ∗ 60 𝑚𝑖𝑛
𝑇= + +
60 𝑠 3700 𝑚 8300 𝑚
𝑇 = 1.388 𝑚𝑖𝑛

6.86 𝑚3 ∗ 0.79 ∗ 60 𝑚𝑖𝑛⁄ℎ


RM =
1.388 𝑚𝑖𝑛 ∗ 1.20
3
RM = 195.22 𝑚 ⁄ℎ

6. MINI CARGADOR FRONTAL


Eficiencia (E)=0.79
Factor de esponjamiento (F 1)=1.20
Capacidad cucharon (Q)=0.5m3
Velocidad ida=4km/h
Velocidad vuelta=7km/h
Distancia a transportar=40m
El tiempo de ascenso-descarga-descenso=20segundos
Calculo del ciclo de trabajo
𝐶𝑚 = 𝑡𝑎𝑠𝑐 .𝑑𝑒𝑠𝑐 . 𝑑𝑒𝑠𝑐 . + 𝑡𝑟𝑒𝑔𝑟𝑒𝑠𝑜
1𝑚𝑖𝑛
𝑡𝑎𝑠𝑐 . 𝑑𝑒𝑠𝑐 . 𝑑𝑒𝑠𝑐 = 20𝑠𝑒𝑔 ∗ → 𝑡𝑓 = 0.33𝑚𝑖𝑛
60𝑠𝑒𝑔

77
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

0.040𝑘𝑚 0.040𝑘𝑚
𝑡𝑟𝑒𝑔𝑟𝑒𝑠𝑜 = +
4 𝑘𝑚⁄ℎ 7 𝑘𝑚⁄ℎ

𝑡𝑟𝑒𝑔𝑟𝑒𝑠𝑜 = 0.016ℎ ≈ 0.96𝑚𝑖𝑛

𝐶𝑚 = 0.33𝑚𝑖𝑛 + 0.96𝑚𝑖𝑛 = 1.29𝑚𝑖𝑛

Calculo del rendimiento


𝑄 ∗ 𝐸 ∗ 𝐹1 ∗ 60
𝑅𝑀 =
𝐶𝑚

0.5𝑚3 ∗ 0.79 ∗ 1.20 ∗ 60


𝑅𝑀 =
1.29
3
𝑅𝑀 = 22.05 𝑚 ⁄ℎ

7. CISTERNA.
Distancia a ENACAL aguadora de Managua: 4.50 Km

Velocidad cargado: 30 km/h

Velocidad descargada: 45 km/h

Tiempo para llenar el tanque: 1/2 h

Tiempo de descarga del tanque en proyecto: 1/8 h

Tiempo de imprevistos: 30 % del tiempo en ciclos

Capacidad de cisterna: 4000 Gal o 15.156 m3 de agua.

Riega 5 Gal ó 0.019 m3 por cada m²

𝑇𝑐𝑖𝑐𝑙𝑜𝑠 = 𝑇𝐶𝑎𝑟𝑔 + 𝑇𝑡𝑟𝑎𝑛𝑠𝑝 + 𝑇𝑑𝑒𝑠𝑐𝑎𝑟𝑔𝑎 + 𝑇𝑡𝑟𝑎𝑛𝑠. 𝑑𝑒𝑠𝑐𝑎𝑟 . + 𝑇𝑚𝑎𝑛𝑖𝑜𝑏𝑟𝑎

1 4.50 𝐾𝑚 1 4.50 𝐾𝑚
𝑇𝑐𝑖𝑐𝑙𝑜𝑠 = ℎ+ + ℎ+ + 0.083ℎ
2 30 𝐾𝑚⁄ℎ 8 45 𝐾𝑚⁄ℎ

𝑇𝑐𝑖𝑐𝑙𝑜𝑠 = 0.96ℎ

𝑇𝑛𝑒𝑡𝑜 𝑑𝑒 𝑐𝑖𝑐𝑙𝑜𝑠 = 𝑇𝑐𝑖𝑐𝑙𝑜𝑠 + 30% 𝑑𝑒 𝑇𝑐𝑖𝑐𝑙𝑜𝑠

78
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

30 × 0.958 ℎ
𝑇𝑛𝑒𝑡𝑜 𝑑𝑒 𝑐𝑖𝑐𝑙𝑜𝑠 = 0.96 ℎ +
100

𝑇𝑛𝑒𝑡𝑜 𝑑𝑒 𝑐𝑖𝑐𝑙𝑜𝑠 = 1.25 ℎ

15.156 𝑚3 3
𝑅𝑒𝑛𝑑𝑖𝑚𝑖𝑒𝑛𝑡𝑜 = = 12.12 𝑚 ⁄ℎ 𝑝𝑜𝑟 𝑐𝑎𝑑𝑎 𝑐𝑖𝑠𝑡𝑒𝑟𝑛𝑎
1.25 ℎ

79
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

5. PRESUPUESTO
Para finalizar con la etapa de movimiento de tierra en el proyecto “Colegio El Doral”
se ha realizado un presupuesto general que refleja las actividades a realizar a lo
largo del proyecto, a su vez se dividen en diversas sub- etapas con sus respectivos
costos unitarios y costos globales. Cabe destacar que este presupuesto fue
elaborado con el soporte de la empresa consultora PROCAD S.A y se expone lo
siguiente:

Etapas preliminares

Se comprende primeramente trazo y nivelación, es primordial el conocimiento


exacto de la topografía del terreno donde se construirá el futuro colegio “el Doral”,
en el campo laboral el modo de pago se determina por m2 y su precio unitario es de
0.33 dólares, el terreno que abarca este proyecto comprende 7,623.35 m 2, se
concluye que su precio total es de 2,515.71 dólares. (Esta suma de dinero es
referente a la cuadrilla de topógrafos)

En las construcciones temporales se comprende bodegas o planteles, las cuales


estarán ubicadas contiguo a lo que será el segundo acceso, con un área de 16 m 2.
Estas construcciones tienen un precio unitario aproximado de 26 dólares, y se refleja
un total de 1,664.00 dólares.

Finalmente la movilización y desmovilización de la maquinaria basados en costos


estándares en la ciudad de Managua cuesta 500 dólares por equipo, al ser cuatro
equipos transportados en camión se tiene un total de 2,000 dólares.

Movimiento de tierras

La etapa de movimiento de tierra se subdivide en las siguientes actividades:

Descapote

Preparación del terreno para la explanación y adecuación de la zona demarcada en


los planos que comprende un área de 8,563.52 m2 con un espesor de 0.15 metros,
dicha actividad posee un costo unitario de 1.60 dólares, dando como resultado un
costo total de 13,701.63 dólares consiste en limpiar y despejar el área de árboles,

80
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

arbustos, y todos los materiales extraños que obstaculicen las labores posteriores,
transportándolos al botadero destinado al inicio del proyecto que se encuentra a una
distancia de 2,7 kilómetros, su costo unitario por m3 actualmente se encuentra a
3.50 dólares, al tener un volumen de 1,477.21 m3 su costo total por desalojo
5,170.24 dólares.

Excavación

Debido a las grandes variaciones en el tipo y disposición de los materiales, es


indispensable analizar la estabilidad del terreno, según los estudios de suelos
realizados se tiene que es un suelo A-2-4, según el diseño de terracería se tiene
que el volumen de excavación total es de 12,693 m2, con un costo unitario de 3.10
dólares.

Retirada, acopio, mantenimiento

Una vez ya excavado y llegado a los niveles deseados según el diseño, se tiene
que el material sobrante por desalojar una vez restado el material a reutilizar se
tiene que es de 2838.37 m3, con un costo unitario de 2.00 dólares, se tiene un costo
total de 5,676.74 dólares.

Compra y traslado de material selecto

Según los cálculos realizados respecto al diseño de volúmenes, se ha solicitado


tener una capa de material selecto de un volumen de 1155.19 m3 lo cual se
comprará en Mina Sandino ubicada en el municipio de Ciudad Sandino a 7
kilómetros del proyecto. . El material será utilizado para colocar una capa de 20 cm
en cada una de las terrazas. Así bien el traslado y compra de este material tiene por
costo unitario 3.50 dólares, cabe destacar que este material será cortado por el
personal del proyecto haciendo uso de un tractor sobre orugas, y tiene como costo
global 4,043.17 dólares.

Terraplén

Primeramente se harán con material aprobado, es decir, relleno formado con suelos
propios, nivelación y compactación al 95% proctor del material selecto y comprende

81
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

un volumen de 3,623.74 m3 con un costo unitario de 7.50 dólares, dando como


resultado el costo total de terraplén de 27,178.05 dólares.

Se tiene como volumen total de desalojo o material sobrante de corte 541.45 m 3,


dando un costo total de desalojo de 1,847.97 dólares.

Finalmente se ha presupuestado el costo unitario de limpieza total del material por


m2, el cual es de 0.60 dólares, comprende el área total de trabajo 8563.52 m2 dando
un total de 5,138.11 dólares.

Así bien, este presupuesto se ha elaborado a partir de un cronograma de trabajo el


cual comprende las actividades que se realizarán simultánea e individualmente
durante 30 días. Y se desglosa de la siguiente manera:

Día 1: entrega de sitio, del dueño al contratista que realizará la obra.

Día 2: trazo y nivelación del terreno, es decir, toma de niveles topográficos basados
en el diseño de terracería anteriormente presentado. Simultáneamente se
encuentra las construcciones temporales abarcadas hasta el día 3.

Día 4: movilización de maquinaria, traslado de maquinaria individualmente y por


medio de camiones, tomará hasta el día 5 debido a la distancias entre el proyecto y
las empresas.

Día 6: se inicia concretamente con la etapa de movimiento de tierras, el descapote


del área total, se llevará a cabo en 3 días. Simultáneamente en el día 7 se inicia con
el desalojo del material orgánico, debido a la cantidad de volumen a desalojar esta
actividad comprende 6 días. Asimismo en el día 10 se inicia el corte o excavación
de las terrazas siguiendo concretamente el diseño acordado. No obstante el acopio
de materiales inicia el día 15, ambas actividades finalizan el día 19.

Exteriormente en el día 14 se corta, carga y traslada material desde Mina Sandino


a Ciudad Doral, esta actividad tomará alrededor de 10 días laborales, finalizando en
el día 23.

En el proyecto se plantea que el día 17 se inicia el relleno con material de sitio,


comprendidos hasta el día 24. Y el rellano con material de selecto en toda el área

82
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

se cronograma tres días, del día 25 al día 28. Finalmente el desalojo de material
sobrante se retira el día 29 y la limpieza final del terreno el día 30, culminando y
entregando este proyecto

83
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

ALCANCES DE OBRA – MOVIMIENTO DE TIERRAS


Precio
Precio
Nº Descripción Ud. Cantidad unitario
total ($)
($)
1 PRELIMINARES 6,489.96
1.1 Trazo y Nivelación m2 8,563.52 0.33 2,825.96
1.2 Construcciones Temporales area 8m x 8m m2 64.00 26.00 1,664.00
1.3 Movilizacion y Desmovilizacion Gl 1.00 2,000.00 2,000.00
2 MOVIMIENTO DE TIERRAS 75,495.98
Descapote, afectado por las obras, incluso tala de arbolado,
2.1 m2 8,563.52 1.60 13,701.63
arranque de troncos, medido sobre perfil de 0.15 m.
Desalojo de Mat. De descapote, fuera de la obra, para
2.2 distancias entre 2.5 a 3.0 km y por cualquier medio, sin incluir m3 1,477.21 3.50 5,170.24
costo de vertedero.
Excavación a cielo abierto, por medios mecánicos, en terreno
2.3 medio (suelo con golpeo en el ensayo SPT entre 10 y 30 golpes m3 4,094.54 3.10 12,693.07
/ 30 cm).

Retirada, acopio, mantenimiento. y posterior extendido de mat a


2.4 m3 2,838.37 2.00 5,676.74
reutilizar.

2.5 Compra y traslado de Material de banco a una distancia de 7km m3 1,155.19 3.50 4,043.17

Terraplén formado con suelos propios, incluso nivelación y


2.6 m3 3,623.74 7.50 27,178.05
compactación al 95% Poctor, medido sobre perfil.
Desalojo de Mat. Sobrante de Excav., fuera de la obra, para
2.7 distancias entre 2.5 a 3.0 km y por cualquier medio, sin incluir m3 541.42 3.50 1,894.97
costo de vertedero.
2.8 Limpieza Final m2 8,563.52 0.60 5,138.11
SUB-TOTAL 81,985.94
IVA (15%) 12,297.89
IMPUESTO MUNICIPAL 819.86
TOTAL 95,103.69

84
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Cronograma de Actividades

D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 D18 D19 D20 D21 D22 D23 D24 D25 D26 D27 D28 D29 D30
PRELIMINARES
ENTREGA DE SITIO
TRAZO Y NIV
CONSTRUCCIONES TEMP
MOVILIZACION
MOVIMIENTO TIERRAS
DESCAPOTE
DESALOJO DE MAT. ORGANICO
EXCAVACION
ACOPIO DE MATERIALES A REUTILIZAR
CARGA Y TRANSPORTE DE MAT SELECTO
TERRAPLEN CON MAT DE SITIO
TERRAPLEN CON MAT SELECTO
DESALOJO DE MAT SOBRANTE
LIMPIEZA FINAL

85
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

V. CONCLUSIÓN
La planificación previa que se realiza en todo proyecto, es fundamental para
la buena ejecución, ya que las decisiones a tomar a lo largo del proyecto son
basadas en la planificación de cada actividad y a su vez respetar el
presupuesto establecido.

ca y privada, así como necesidades sociales y de educación. Para la ejecución


de este proyecto se propusieron diversas actividades a realizar para el
cumplimiento de estas.

Se definió El proyecto “colegio El Doral” parte de una necesidad de


infraestructura públiniveles estratégicos para diseñar la rasante de las
terrazas que conforman el proyecto, para este diseño de terracería se tomó en
cuenta los cauces y pendientes naturales, así como la compensación de
volúmenes para reducir costos de desalojo, las elevaciones dadas en cada
una de las terrazas fueron evaluadas en perfiles para mayor exactitud. Del
mismo modo se consideró un mejoramiento de suelo, y se utilizó una capa de
material selecto proveniente de Mina Sandino.

En todo movimiento de tierra se requiere de maquinaria en buenas


condiciones según vida útil y vida económica; Agroindustrial Mantica (AIMSA)
y Master Construction cumplieron con los criterios impuestos por el
contratista, es decir, en rentabilidad y costos. Por otro lado, se han hechos
cálculos matemáticos respecto a la renta horaria y rendimiento de cada uno
de los equipos, estos ayudaron a tomar una mejor decisión respecto a la
maquinaria.

Como resultado del diseño de terracería y los costos de la maquinaria, se


logró estimar un presupuesto general, dando costos globales para cada una
de las actividades propuestas al inicio del proyecto. Sin más que agregar se
puede concluir que se ha valorado la situación topográfica y presupuestal a
lo largo la etapa de movimiento de tierra, y se ha planificado de acuerdo a las
condiciones presentes en la localidad y servicios cercanos.

86
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

VI. RECOMENDACIONES
 Se recomienda que antes de iniciar la etapa de excavación en el
movimiento de tierra hay que eliminar la primera capa vegetal del
terreno para asegurar la estabilidad del macizo.
 De igual modo se aconseja que la maquinaria para el movimiento
de tierra debe está en perfecto estados mecánicos para asegurar
eficiencia en el rendimiento de cada actividad.
 Realizar pruebas de suelos (sondeos, proctor estándar) para
conocer el tipo de suelo que se encuentra en el sitio, para realizar
compensaciones de volúmenes sin inconvenientes.
 Desarrollar una buena planificación previa del proyecto, tomando
criterios de especificaciones técnicas, costos y tiempo.

87
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

VII. REFERENCIAS
Bancos, I. (c.p). Cuido y protección del medio ambiente en escuela. Obtenida el 02 de
noviembre de 2017, de http://www.healthSALUD.escuElaNacionaldirect.nhs.uk/

Maurice, y Clays, E (1995). Método de movimiento terraplenado y excavación.


Rogers (2000). Maquinaria y especificaciones técnicas. Ed. Mc. Prat Bill
Interamericana S.A.
Tercero, (2012). Evaluación y gestión de riesgo asociado a la comunidad de
Managua. Recuperado el 02 de Noviembre 2017 de
http://www.eb.edu./recerca/entrevista%022012/seminaris11_PabloTercero.pdf

88
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

VIII. ANEXOS
Fotografías de la ubicación del proyecto “Colegio EL Doral”

Ilustración 1: Fotografía de entrada a Ciudad El Doral. Lugar donde se ubica el


proyecto

Ilustración 2: Terreno donde se realizará movimiento de tierra

89
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

A continuación se anexan las cotizaciones realizadas en la empresa Agroindustrial


Mantica S.A (AIMSA). Los equipos cotizados son:
 Retroexcavadora

Ilustración 3: Retroexcavadora B95B . Foto tomada por Gisele


Reyes

 Minicargador

 Motoniveladora

Ilustración 4: Minicargador New Holland

90
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Cisterna

 Volquete

91
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

 Vibro compactadora

 Tractor sobre oruga

92
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Anexo a

Ilustración 5: Cotización Retroexcavadora

93
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Anexo b

Ilustración 6: Cotización Minicargador

94
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Anexo c COTIZACIONo. 13102017

Ing. Gisele Reyes

Su oficina

Estimada Ingeniero:

Reciba un saludo cordial de nuestra empresa y éxito en sus funciones. Tengo a bien presentarle
muestra propuesta formal de Renta de Motoniveladora RG140 de la marca New Holland de los
cuales somos representantes exclusivos en Nicaragua.

CANT. / HORAS Precio por Hora


ITEMS DESCRIPCION Total USD $
No incluye IVA

1 MOTONIVELADORA NEW HOLLAND 160 hrs USD $55.00 USD 8,800.00

IVA $ $1,320.00

5 Horas Mínimas por día Total $ $ 10,120.00

Condiciones Comerciales:

Forma de pago : C ontado


Tiempo de entrega : Inmediata
Valides de la oferta : 15 días
C ortes para facturación : semanal

Incluye꞉ Asistencia mecánica y operador


No Incluye C ombustible, resguardo del equipo, pinchaduras, traslado, hospedaje del operador

Agradeciendo la atención prestada a esta oferta y en espera de poder servirles, me despido de usted.

Atentamente,

Ing. Yolanda Lopez


Asesora de Venta y Renta de
Maquinaria Industrial
gguitierrez@aimsacorp.com
De la Rotonda Universitaria 50mts Sur, Edificio AIMSA
Celular: 00 (505) 8741 2897

Oficina: 00 (505) 2270-2100

95
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Anexo d

Ilustración 7: Especificaciones técnicas de Retroexcavadora New Holland

96
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Anexo e

Ilustración 8: Especificaciones técnicas de Retroexcavadora New Holland

97
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Anexo f

Ilustración 9: Especificaciones técnicas de minicargador

98
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Anexo g

Ilustración 10: Especificaciones técnicas de minicargador

99
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Anexo h

Ilustración 11: Especificaciones técnicas de motoniveladora

100
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Anexo i

Ilustración 12: Especificaciones técnicas de motoniveladora

101
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Anexo j

Ilustración 13: Especificaciones técnicas de motoniveladora

102
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

Anexo k

Ilustración 14: Ejemplo de informe de recepción y entrega de equipos

103
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

I. IINTRODUCCIÓN
II. OBJETIVOS

III. ANTECEDENTES

IV. DESARROLLO

1. FORMULACIÓN DEL PROYECTO


a) Descripción del proyecto
b) Perfil del proyecto
c) Objetivos del proyecto
d) Metodología
2. ALCANCE DE OBRA
a) Localización
b) Trazo y nivelación global
c) Diseño de terracería (corte, relleno, descapote)
d) Calculo de volúmenes
3. PLANIFICACIÓN
2. Criterios para la selección de maquinaria
a) Especificaciones técnicas
b) Movilidad requerida por el equipo
c) Tiempo programado para hacer el trabajo
3. RENTA HORARIA
a) Selección de maquinaria
b) Determinación de horas mínimas
c) Costos por hora del equipo
4. CÁLCULO DE PRECIOS UNITARIOS
a) Equipos
b) Corte de material
c) Traslado de material
d) Relleno
e) Material selecto
5. PRESUPUESTO

104
“COLEGIO EL DORAL“ ETAPA DE MOVIMIENTO DE TIERRA 2017

a) Estructura de costo
b) Descripción
1. Actividades a realizar, las que se realizarán
simultáneamente o individualmente.
2. Definir el proyecto con todas sus actividades o partes
principales.
3. Establecer relaciones entre las actividades. Decidir cuál
debe comenzar antes y cuál debe seguir después. .
4. Definir costos y tiempo estimado para cada actividad.
c) Precios unitarios
d) Costo total
V. CONCLUSIÓN
VI. RECOMENDACIONES
VII. ANEXOS
VIII. PLANOS

105