Vous êtes sur la page 1sur 11

Khorais Road Project - Riyadh

Saudi Diyar Consultants

HVAC System
Fan Coil Units
Project :
Date : Ambient Temp, °F:

a- General :

1- Unit No :
2- Location :
3- Served area :
4- Serial Number :
5- Model Number :
6- Type :
7- Voltage :
8- Amperage :
WATER
9- Inlet Temperature , ° F:
10- Outlet Temperature, ° F :
11- Inlet Pressure, psi :
12- Outlet pressure, psi :
Design Actual
13- Water flow, gpm :
AIR
14- Leaving air temperature db/wb, ° F : /
15- Entering air temperature db/wb, ° F : /
Design Actual
16- Airflow, cfm :
Electric Heater
17- Heater , Kw :
18- Stages :
Design Actual
19- Supply air, cfm
20- Return air, cfm
21- Fresh air, cfm

NOTES :
Name Signature

10/29/2019
General 1
03:39:12
Khorais Road Project - Riyadh
Saudi Diyar Consultants

b- Check List :

1 - Unit is installed with anti vibration mounts ok not ok


2 - Alignment and Levelling good bad
3 - Condensate drain pipe connected to nearest FD ok not ok
4 - Condensate drain pipe shall have a P-Trap found not found
5 - Chilled water pipes installation good bad
6 - Chilled water pipes insulation good bad
7 - FDI installation on main ChW return pipe found not found
8 - Pipes identifications ok not ok
9 - Valves tagging ok not ok
### - 2-way valve installation found not found
11 - Connection to BMS found not found
### - Strainer installation found not found
### - General cleaning ok not ok
### - Duct vibration or ratling found not found
### - Die electric union installation (copper to steel) found not found
### - Electric heater installation found not found
### - Ducts installations good bad
### - Ducts insulation good bad
### - Ducts identification found not found
### - Canvas installation at main supply and return ducts found not found
### - Fresh air duct installation found not found
### - Volume damper installation at FA duct with filter found not found
### - Filter cleaning good bad

NOTES :

Name Signature Date

10/29/2019
Checklist 2
03:39:12
Khorais Road Project - Riyadh
Saudi Diyar Consultants

c- Electrical Checklist

FCU is connected to MCC panel No. :


Voltage :
Amperage :

1 - Control panel installation good bad


2 - Indication lamps found not found
3 - Phase failure unit protection found not found
4 - Overload protection found not found
5 - Wires are tightly connected good bad

c- Control Checklist

FCU is connected to DDC panel No. :


Thermostat setting:

Min, ° F Max, ° F
occupied
not occupied
RH %

1 - 2-way valve connection to DDC panel ok not ok


2 - Fan flow switch connection to DDC panel ok not ok
3 - Thermostat installation and connection to DDC ok not ok
4 - Heater connection to DDC panel ok not ok
5 - Sequence of operation programming ok not ok
6 - Interlocking with fire alarm system ok not ok

NOTES :

Name Signature Date

10/29/2019
Electrical&Control 3
03:39:12
Khorais Road Project - Riyadh
Saudi Diyar Consultants

d- Air Balancing

Velocity Reading

UNIT No. : Section: Main Supply Location:


Width, in Av. FPM 0.0 SCFM 0.0 Design CFM
Duct

Depth, in Reading No. 1 ACFM 0.0 Actual CFM


Area, ft² 0.0 Corr, Factor 0.90 Deviation % 100.00
INPUT DATA
CALCULATED

XY 1 2 3 4 5 6 7 8 9
1
2
3
4
5
6
7
8
9
10

Measured data
INPUT DATA
CALCULATED

NOTES :

Name Signature Date

10/29/2019
Supply 4
03:39:12
Khorais Road Project - Riyadh
Saudi Diyar Consultants

1
0
100.00

10/29/2019
Supply 5
03:39:12
Khorais Road Project - Riyadh
Saudi Diyar Consultants

d- Air Balancing

Velocity Reading

UNIT No. : Section: Main Return Location:


Width, in Av. FPM 0.0 SCFM 0.0 Design CFM
Duct

Depth, in Reading No. 1 ACFM 0.0 Actual CFM


Area, ft² 0.0 Corr, Factor 0.90 Deviation % 100.00
INPUT DATA
CALCULATED

XY 1 2 3 4 5 6 7 8 9
1
2
3
4
5
6
7
8
9
10

Measured data
INPUT DATA
CALCULATED

NOTES :

Name Signature Date

10/29/2019
Return 6
03:39:12
Khorais Road Project - Riyadh
Saudi Diyar Consultants

1
0
100.00

10/29/2019
Return 7
03:39:12
Khorais Road Project - Riyadh
Saudi Diyar Consultants

d- Air Balancing

Velocity Reading

UNIT No. : Section: Fresh Air Duct Location:


Width, in Av. FPM 0.0 SCFM 0.0 Design CFM
Duct

Depth, in Reading No. 1 ACFM 0.0 Actual CFM


Area, ft² 0.0 Corr, Factor 0.90 Deviation % 100.00
INPUT DATA
CALCULATED

XY 1 2 3 4 5 6 7 8 9
1
2
3
4
5
6
7
8
9
10

Measured data
INPUT DATA
CALCULATED

NOTES :

Name Signature Date

10/29/2019
Fresh air 8
03:39:12
Khorais Road Project - Riyadh
Saudi Diyar Consultants

1
0
100.00

10/29/2019
Fresh air 9
03:39:12
Khorais Road Project - Riyadh
Saudi Diyar Consultants

d- Air Balancing

Velocity Reading

UNIT No. : Served Area: Location:


Length, ft Av. FPM 0.0 SCFM 0.0 Design CFM
Area factor Reading No. 1 ACFM 0.0 Actual CFM
Type Corr, Factor 0.90 Deviation % 100.00
INPUT DATA
CALCULATED

Measured data, FPM

NOTES :

Name Signature Date

10/29/2019
Air Outlet 10
03:39:12
Khorais Road Project - Riyadh
Saudi Diyar Consultants

1
0
100.00

10/29/2019
Air Outlet 11
03:39:12

Vous aimerez peut-être aussi