Vous êtes sur la page 1sur 2

CONSTRUCTION OF PROPOSED Doc.

No: LHP/MS/013
RESIDENTIAL PROJECT AT 104 CHITHRA Revision:0
LANE, COLOMBO 5
FOR Date: 30//03/2017
ASIA BROADCASTING (PVT) LTD

METHOD STATEMENT OF SCREED CONCRETING FOR PILE CAPS,


FOOTINGS, BASE OF LIFT WELLS AND WALL FOUNDATIONS
OBJECTIVES: To formulate guide lines for placing, compacting and finishing of concrete work.

REFERANCE: Drawings

Tech. specifications and BS1881

Inspection and test plan

QA check list

EQUIPMENTS: Batching plant / Concrete mixer

Agitator trucks / Wheel barrows

Crane and skip buckets or pump car

Poker vibrators / Tampers

No Procedure Responsibility Checked by Records


1 Set out the pile cap allowing reasonable Foreman AE
working space & erect foam work 15mm thick
plywood & GI pipes including necessary brazing
to prevent collapsing of soil to working area.
2 Placing of 150mm thick layer of quarry dust or Foreman AE
quarry muck around pile cap
3 Establish bottom level of the pile cap around Foreman AE
the area add or remove quarry dust or quarry
muck and prepare the surface to the level
4 Fix and arranged the working platforms, guard Safety Officer AE
rails, ramps maintaining the safety requirement
to before proceeding concrete work
5 Request for inspection AE SM
6 Once obtaining the approval order ready mix Forman TO/AE
concrete or arrange the site mix according to
the grade & type as per specification.
7 Casting of cubes for testing AE SM
8 Pour & laid concrete well rammed/vibrate by Foreman AE
using a steel or wooden tamper/poker vibrator.
9 Coordinate with plant for avoid delays if use TO AE
ready-mix concrete.
9 Level the top surface using wooden floats & Forman AE
Trowel.
10 Ensure the HSE during the entire process Safety officer SM

OUTPUT RECORDS:

1 Laboratory test report


2 Ready mix dispatch
3 Pre inspection for concreting

Prepared by Approved by
Signature
Name Haritha Jayasinghe Rohith Thirimavithana
Designation AE SM
Date 31-03-2017 31-03-2017

Vous aimerez peut-être aussi