Construction of Green field No Airport at Orvakal, Kurnool [Dist]

List of clarifications required :

S. No Location Drawing ref Nature of clarification GM Sir comments

Window position between grid C2 & C3, as per


architectural drawing at Mezzanine floor is shown in As discussed and guided by JE, we have
ATC Building the middle, but the structural drawing shows duct in casted the slab as per the architectural
I & Tower: WD/ AEC/AR- 02 the middle and windows on both sides. drawing. OK

Window W1 size: width of window W1 is shown 1500 As discussed and confirmed by JE, we have
& 1800 mm both in the same floor plan. casted the slab with 1500mm width for W1
- OK

Cut outs for services along grid B1 to B2 are shown


only in architectural drawing. The cutouts are not As discussed and confirmed by JE, we have
shown in the structural drawing provided and casted the slab as per
architectural drawing - OK

Architectural drawings / structural drawings of all the As discussed with JE, we have casted the
floors doesn’t have any sunken slabs at toilets areas Mezzanine floor slab without sunken slab at
toilets area - OK
False ceilings in all the floors- Services drawings are
showing false ceilings in all the floors but GFC
Reflected flase ceiling drawings are not available in
the revised set of drawings. Will be clarified by architect
From 1st floor to terrace- structural staircase working
drawing is not complete. Will be clarified by architect
Third floor plan- in the drawing between staircase and
lift shaft shear walls brickwall hatching is shown, but
text mentioned is structural glazing. Please clarify
ATC Tower WD/ATC/DT- 05 which one to follow Will be clarified by architect

Plan at 4th floor level- plan and sections are not


Slab concrete has to be done as per
matching. Need more clarity on working details at
structural drawing. Architectural
that level
elements will be clarified as early as
possible
Section X-X of tower, wall from 4th floor level to roof-
outer wall shown is 115mm thick, but as it is the
external wall, this need to be made 230mm thick.
Please confirm the same Will be clarified by architect

4th floor plan- 600mm wide slab projection / 1000 Slab concrete has to be done as per
mm wide corridor both are shown in the plan. Please structural drawing. Architectural
clarify the same. elements will be clarified as early as
possible
Roof truss fabrication drawing is not available

Structural column & wall junction:


230mm thick outer wall- junction of wall & structural 8mm / 10mm reinforcement steel of
column, because of two different materials there will min 300mm long to be welded to the
always be crack. Please suggest us to arrest water steel column at random locations to
seapage into the building during rains increase bonding strength; vertical
groove in plaster to be made at the
2 PTB WD/PTB/AR-01 junction of wall & structural column.

Terrace roof plan- slopes as shown in the drawing for


rain water disposal in different directions can not be
made in sheeting. Please suggest accordingly Slopes should be as per approved
WD/PTB/AR-02 sheeting drawing
75mm thick aerocon partition wall in the grid A5 - F5,
plan shows 3.30m height. But the section Y-Y of
building is showing full height. Please confirm
To make it full height
As aerocon partiton is full height,
Structural columns- SC 5 & SC 6: these are 150 mm
intermediate sections for aerocon has
x 150 mm square columns are going up to roof level.
to be provided as per standards. These
As they are very small, they need to be given a
sections will be functioning as bracings
horizantal bracing in the middle. Please suggest us
for structural columns.
2mm thick polycorbonate sheet for skylight: due to
the materials self property, polycorbonate sheet can
not be bent due to chance of breaking. Hence as
shown in the drawing, skylight can be provided in one
line. Please confirm Will be clarified by architect
Toilet- T2 : out of 3 no of urinals, 1 no of urinal is
shown with different height. Do we have to fix it same
as per drawing. To be executed as per drawing
False ceiling sections drawing: Vertical of
polycarbonate sheet opening is shown as GI metal
ceiling, but the polycarbonate sheet fixing detail
shows ACP for the vertical in the opening area. Please Polycarbonate sheet detail drawing to
WD/PTB/FC- 02 confirm. follow
Glass Vs ACP corner closing details are required Will be clarified by architect
Toilet slab structural drawing is not available. Please
provide the same. Will be clarified by architect
Gypsum false ceiling at both ends [Apron side & city
side]- connection with structural glazing may not be
possible. Please suggest Will be clarified by architect

UG Sump &
Details of puddle flanges is required
3 Pump room
In the upper level slab above pump room- staricase
cutout location to be shown. Section through pump
room will give more clarity. Please provide the Start point of staircase from Ground to
WD/STR/UGWT-02 required detail. lower level is from the beam face.
Staircase structural drawing is not matching with the Staircase to be casted as per the actual
details shown in the architectural drawing [1st flight, heights keeping raiser height as
WD/STR/UGWT-05 no of steps] 150mm & tread 300mm.
Section A-A is showing roof projection of 300mm wide
in gird from A2- D2. This is not mentioned in the
structural drawing of upper level slab [drg no: Slab projects to be provided as per
WD/UGWT/AR-01 WD/STR/UGWT-02]. archtectural drawings.

ESS
[Electrical
4 Sub station]
115mm thick brick wall partition between POL, Store
& Office room - height of the wall from floor level is
TD/ESS/D- 01 not shwon To take it up to full height
False ceiling is shown in sectional views of toilet. But
GFC false ceiling drawing is not availabe in the set of
drawings Will be clarified by architect
Please confirm whether false ceiling is requied in
Office, Store & POL rooms. If yes GFC false ceiling
detail drawing is requied. Will be clarified by architect
Structural column & wall junction:
8mm / 10mm reinforcement steel of
min 300mm long to be welded to the
External wall: joint of structural column, due to
steel column at random locations to
different materials there will always be gap because
increase bonding strength; vertical
of which there is a chance of rainwater seapage into
groove in plaster to be made at the
the building.
junction of wall & structural column.

Roof sheeting @ +6.30m lvl is shown with 2mm thick


polycarbonate sheet. Please confirm whether to
5 Watch Tower WD/FWT/AR-02 proceed same as per drawing. To change it to Galvolume sheet

RITES/AP/KURNO Beam plan: this detail to impliment at what level,


OHT [Over OL/ST-01/OHT- 02 because plan at +15.00 m level is seperately shown 15.00 m lvl plan and beam plan is
6 head Tank] & 03 same.
Staircase sections details are not provided in the
drawing Will be clarified by architect
Construction of Greenfields No frills airport at Orvakal, Kurnool Dist.

Details required from all services:

S.No. Package Clarification required Arch / Consultant reply

Main LT Panel to main feeder


Cable sizes required from Main LT panel to pillar 3.5C x 120sq mm; Main
Main feeder pillars and from main feeder feeder pillar to sub feeder pillar
I Electrical works: pillars to Sub feeder pillars 2C x 6 sq mm

Main LT Panel to main feeder


pillar 3.5C x 120sq mm; Main
feeder pillar to sub feeder pillar
2C x 25 sq mm for SFP 1,2&4
Cable sizes required for street lights of
and 2C x 35 sq mm for SFP 3.
peripheral areas

Pole earthing details required for both Earth pit for every 5 poles (pipe
approach area and peripheral areas earthing)
[individual earthing for each pole or looping]
Each feeder pillar cable size required for solar
3.5C x 25 sq mm for FP 4.
supply and EB supply
In peripheral areas sub feeder pillar locations
required and number of light points in each Architect will provide drawing.
circuit
Cable size for High mast pole & location of
4C x 6 sq mm
High mast pole is required
PTB lightning arrestors drawing and routing is Architect will provide PTB
required. lightning arrester drawing.
If in case it is necessory.
ATC Tower and OHT lightning arrestors Because, ATC Tower and OHT
drawing and routing is required are taller than ATC Building
Details of body earthing & neutral earthing,
location, type of earthing and number of earth Clarification not given.
pits is required.
Server room DB location and circuit details are
Surface mounted fixing at server.
required

Electrical requirement for Security room near Need to take supply from nearest
main gate is not provided. If yes please let us feeder pillar.
know from which panel it is to be tapped.
Height of Light poles at car parking 4 mts or 9 4M pole. Supply from nearest
mts, please confirm feeder pillar.
3 phase power is required for flag post. Taping Supply from nearest feeder pillar
location is required. with 4 x 6 sq mm
Cable size and routing for solar power and
Clarification not given.
syncronization details are requied.

Peripheral road light foundations- as instructed


by APADL foundations are shifted towards
compound wall to have better lighting on
4M pole with single arm is
compound wall. But peripheral road also needs
enough.
lighting, hence we propose to have 9.00m
high pole with double side arm with 60 watts
LED light fitting on both sides. Please confirm
the same
Ceiling fans in retails rooms etc are provided.
Technically not possible. How to place ceiling Provide wall mounted fan.
fan.

Ceiling fans- for the present height of terminal Provide 1600mm vanes and 1ft
building air throw with 1200mm normal ceiling hanging rod from FCL.
fan is not adequate. Need suggession on this
Conduiting of Distribution Boards in ATC
Building are exposing.
Construction of Greenfields No frills airport at Orvakal, Kurnool Dist.

Minutes of meeting on 12th March 2019


S.No. Package Clarification required

Location of indoor units, outdoor units, copper


I HVAC:
pipe routing, drain pipe routing is required

BOQ specification is not matching with


II CCTV: technical specifications mentioned for
execution of work
Cable routing for cameras from server room

III ACCESS CONTROL: Cable routing from server room


Locations where access control need to be
provided
BMS integration details

Server, Data &


IV Cable routing from server room to all locations
Voice system:
Locations & number of data & voice points at
specified locations
Any redendant points required at specified
locations
Present server room shown provided in PTB,
may not be suffecient to provide all the
equipment

Cable routing from server room to speakers


V PA System:
locations is required
Speakers location in all the buildings

VI Fire alarm system: Cable routing


Details pertaining to BMS integration
Hooters location
Speakers, smoke / heat detectors & Manual
call point locations
Location of fire alarm control panel,
addressable repair pannel is required

Approval of structural glazing & ACP claddig


VII ATC tower
detailed drawing

Fixing arrangement of signaling lamp over and


above ATC tower
Storage tank for treated water for domestic
UG Sump &
VIII usage, can we use the domestic tank shown in
Pumproom:
the drawing?
Pumps foundation details

STP treated water distribution- whether this


Plumbing &
IX STP treated water is used for gardening or for
sanitary works
flushing ?
Distance betweeb terminal building and OHT is
almost above 200 meters. We feel that gravity
feed will not give suffecient pressure.
Rainwater disposal routing from ATC tower
roof is required.

GFC Reflected false ceiling drawings for ATC


X Interior works: building, ATC tower, ESS are required for
execution
Furniture layout drawing showing sizes of
furniture in all the buildings
Images of check in counter, Gate counter, X
-ray roller bench, passenger bauggage trolley
are required to give more clarity for
procurement
Loose furniture- Detailed drawings of storages,
conference table, officers tables, staff table,
centre / coffee table, study table with chair for
guest room, bed for rest room are required
for better clarity
Location of portable security cabin & portable
toilet is required
Portable toilet & Portable security cabin
locations required
Inside PTB: MS setions above spider glazing
are visible from inside, please suggest how to
hide them
To execute gypsum false ceiling inside PTB,
MS sections behind ACP cladding need to be
closed and plain surface needs to be created.
Please suggest the solution for this

Door opening provision to be made at Apron


entry [north east corner] for baggage carriage
Infront of PTB building details for hiding of
rainwater downtake pipes is required
External painting- specification shows only
texture finish to external walls. How ever to
have better protection against water seapage-
XI Painting works:
it is better to have water resistant painting of
sufficient coats over and above texture
painting.

Revised drawings is required for construction


XII Watch towers:
of watch towers.

As per the specification- particle board with


laminate finish is given for all the doors.. But
looking at the durability, there are many
posibilities for particle board to get damage
XIII Doors specification
when comes in contact with water directly /
indirectly. Hence we propose Bison board with
laminate finish in place of particle board.
Please confirm

External signages- content on the signages is


XIV Signages:
required
Need more clarity on Over Head granty
Internal signages- Rate for SS plate signages
are mentioned in Kgs, but it has to be in
numbers

Coordingated layout showing all services


XV Drawings:
fittings on reflected false ceiling is required
airport at Orvakal, Kurnool Dist.

Arch / Consultant reply

Loations of High wall split AC units will be


confirmed airport operations team Once
locations are finalized, consultant will suggest
the routing & outdoor unit loations

BOQ is analog based system, where as technical


specifications shows IP based system
Consultant will share the routing

Consultant will share the routing

Consultant will share the routing

Consultant will share the routing

After discussing the design development,


architect has suggested few changes in the
structural glazing detailing. We have noted the
content. We will share the updated drawings to
architect duly implementing the suggested
points for final approval.
Consultant will suggest the design
It is confirmed to use domestic water tank as
treated water tank
Consultant will share the routing

Not confirmed

As per consultant,, the gravity feed will have


required pressure at water outlets

As per stroam water drain diagram provided


earlier

Architect will share the required drawings

Location will be confirmed by Airport operations


team
Architect will share the details pertainingn to
this

Architect will share the details pertainingn to


this

Location has been shown by architect. Working


details related to this will be shared by the
architect.
Architect will share the details pertainingn to
this
As confirmed by the architect, work shall be
executed as per BOQ

As of now the design finalization is in process.


Once it is freezed, architect will share the
drawing for execution. However as we
[contractor] have completed the excavation,
Rod bending & tieng works for 4 no of watch
towers, we have requested APADCL to consider
the quantities of workdone. APADCL has
confirmed the same.

Architect has confirmed to proceed as per BOQ,,


but as particle board is very brittle we are still
requesting to consider the suggested revision to
have better durability of doors.

APADCL will update us the locations, content of


signage and numbers

Architect / Consultant will share the drawing

Vous aimerez peut-être aussi