Practitioner Exam Questions

® 8
PRINCE2 Practitioner Resource Book

Using the Project Syllabus


Scenario and the additional information
Area Question provided
Number for this
Part question Marks
in the
Scenario Booklet, answer the following 5 questions about the Project Product 2 Description.
Quality Theme 3 C 5
Remember to select 2 answers to each question.

1 Which 2 statements apply to the Composition section?


A Amend entry 2 to 'Selected paper'.
B Delete entry 3 because this is NOT a major product to be delivered by this project.

C Move entry 6 to Derivation because this product already exists.


D Delete entry 7 because these will be produced by the photographer.
E Add 'Calendars distributed to customers'.

2 Which 2 statements apply to the Derivation section?


A Move entry 9 to Composition because this is within the scope of the project.
B Delete entry 10 because this is NOT a source product for this project.
C Delete entry 11 as this is already correctly shown under Development Skills
required.
D Move entry 12 to Composition, because this is within the scope of this project.
E Add ’Professional photographer’.
3 Which 2 statements apply to the Development skills required section?
A Move entry 13 to Composition because the appointment of the photographer is within
the scope of this project.
B Move entry 13 to Derivation because this is a source of information for this project.
C Delete entry 14 because this skill is NOT required within this project.
D Delete entry 15 because this skill is NOT required within this project.
E Add 'Knowledge of Data Protection Legislation'.
4. Which 2 statements apply to the Customer's quality expectations section?
A Delete entry 16 because this should be shown on the Product Description for the
photos.
B Delete entry 17 because this is beyond the scope of this project.
C Delete entry 18 because standards should NOT be shown here.
D Delete entry 19 because this should appear in the Product Description for the calendar
and not the Project Product Description.
E Delete entry 20 because this is an expected benefit and should be recorded in the
Business Case.