REQUEST FOR PROPOSAL 2
The Stateview Area Municipality is seeking proposals for the construction and
management of the new high school with a capacity of 1000 students, a new middle school with
a capacity of 1500 students. This also includes the construction of seat performing art center in
both schools with a capacity of 1000 seats for each school. The district would also require a
remodel of existing buildings in the district to improve security and safety and also a remodel of
the schools in the area to create a safe and flexible learning environment.
All the work needs to have some considerable completion by June 5, 2021, and a full
completion timeline of December 10, 2021. The total cost of the project, including all fees and
expenses, is $100,530,000. The voting by the organization is set to take place on May 30, 2019,
at the municipal hall. All federal requirements are followed and FAR part 52 is strictly adhered
to. All details necessary for this project, budget, schedule, schematic designs and program spaces
will be attached at this RFP’s end. The services needed will be for pre-construction and
Consider all phases of the project, based on architectural design, and develop detailed
Manage the budget and track cost estimates against the budget.
inspection, full-time supervision, prepare change orders and payment estimates, review
shop drawings, ultimate inspection, and provide reports of the complete project.
REQUEST FOR PROPOSAL 3
Assist the district with services like advertising of the request for bids, aid in securing
The construction manager is not expected to perform any division of the work on their
own nor will they be allowed to bid for the divisions of the work.
Engage in the design and document preparation of all team coordination meetings.
Proposed Schedule
The project schedule is to be adhered to ensure that the project is finished on time to
better serve the people. In order to ensure this, the schedule has been noted as follows;
There are detailed required in the proposal that are detrimental to the selection process.
All the details provided should comply with the Federal Acquisition Regulations in order to
COMPANY PROFILE
The company profile should include; the company name and address, the years of
experience with construction and management services, other services the company provides
besides the stated one, and include all the projects completed by the company.
PROFESSIONAL ORGANIZATION
This should include the number of employees in the organization and the project team to
be assigned to the proposed project. Provide an organizational chart of the people to be assigned
to the project. Each team member should have a specific role to do in the project, therefore,
describe their roles and provide their experience in this kind of project. Any changes of staff
during the project require written permission to the district and with good reason. The district
PROJECT EXPERIENCE
The company should list its experience in providing Construction and Management
services in the region for similar constructions. The company should also include a number of
references to support this claim. Before sending the proposal, the company should assess the
requirements and determine if this project is within their means. It should be noted that
compliance of the needs of the project is highly expected and failure to comply will be
The company needs to explain in detail how it will approach the management of cost
estimation and cost control, project scheduling, and bids procurement for the constriction. The
REQUEST FOR PROPOSAL 5
company will also need to explain how cooperation with other consultants (Architects, service
providers, etc.) will be conducted to avoid clashing and to smoothen the process of the project.
Project supervision and management is a crucial part of the project and the company will need to
explain how this will be conducted and by whom. Communication with the School District
during the project for updates and any other concerns is necessary. The company will need to
explain how this communication will take effect and who will be the point of contact to ease the
communication traffic.
WORKLOAD
projects that are similar to the proposed project. Provide the size of each project, location of the
projects and the anticipated completion date of each project. This is to ascertain the workload of
your company and if the company is in a position to tackle the proposed project comfortably
with no delays.
COMPENSATION PROPOSAL
The proposal sent should be based on the project spaces attached, the project summary
and the budget of the project, and the schedule of the project. Include the segregated percentage
of construction costs for pre-construction and construction development stage services for
construction and management based on the proposed development scope. It should follow the
following categories;
The percentage fee proposed for pre-construction facilities should include; planning and
director, tracking costs against the budget, design meetings, and clerical costs.
Construction services’ proposed percentage fee should include; senior project manager,
senior project manager, project manager, assistant project manager, safety officer project
drawings, prepare change orders, project completion reports, superintendent vehicle, and
clerical costs.
The predicted costs of some items should not be included in the proposal and these items
include and not limited to the following; safety equipment, first aid supplies, handrails
and toe boards, opening protection, fire extinguishers, temporary fencing, storage rental,
signs, bulletin boards, on-site equipment, printing, telephone expenses, temporary power
service, temporary water service, temporary heating service, heating energy charges,
temporary wiring, temporary lighting, periodic clean-up, trash dumpsters, dump permit
and fees, traffic control, temporary roads, roadway maintenance, and job trailer or trailer
utilities.
sites, project management, and office personnel, should also not be included in the
proposal. Employee expenses of the Construction Manager are included in the percentage
Items to be completed by other Consultants paid by the district include; Architecture and
Engineering, Special Testing, Site Surveys, Soil Explorations, Material Testing, and Permits for
Construction.
REQUEST FOR PROPOSAL 7
The proposal’s fee is to be presented to this RFP with the response. Kindly include
documentation of any qualifications or special conditions that may affect the company’s fee
proposal. The proposal shall be submitted no later than Tuesday, May 7, 2019, by end of
business hours. Kindly include 15 typed copies of each proposal which shall be labeled ‘Proposal
for Construction and Management Services’ and also a pdf copy send to
agnesliz@stateviewmunicpality.gov. The district will not refund any costs incurred in the
The information supplied when responding to this RFP, subsequently, becomes the
property of the district and shall not be returned to sender. The district reserves the right to ask
for more information from applicants to either qualify or disqualify them, to eliminate
irregularities in a proposal, to refuse a proposal in order to serve the best interest of the district
and select the proposal serves the district in the best way. This is not to say the lowest cost
proposal will be selected, but the one that serves the purpose of the district best. The district also
References
Porter-Roth, B. (2002). Request for proposal: A guide to effective RFP development. Boston,
MA: Addison-Wesley.