Académique Documents
Professionnel Documents
Culture Documents
JOURNAL
* PAVEMENT
* TRAFFIC ENGINEERING
Published on behalf of the Indian Roads Congress at Jamnagar House, Shahjahan Road, New Delhi-110 011 and
Printed at Aravali Printers & Publishers Pvt. Ltd., W-30 Okhla Phase-II, New Delhi-110 020.
Editor Shri Vishnu Shankar Prasad, Secretary General, Indian Roads Congress, Jamnagar House,
Shahjahan Road, New Delhi-110 011.
14000
Members of the IRC Highway research Board
(2012-2014)
Members
PAVEMENT Page
Rigid Pavement Response to Environment and Traffic Loading Investigated 1
through Instrumentation
Binod Kumar, Renu Mathur & S. Gangopadhyay
Automated Detection and Measurement of Potholes from Road Surface Video Clips 9
Huidrom Lokeshwor, Lalit K. Das & S.K. Sud
TRAFFIC ENGINEERING
Modeling Occurrence and Severity of Road Crashes on Selected Multi Lane 27
Carriageways in India
S. Padma, S. Velmurugan, E. Madhu, J. Sitaramanjaneyulu, S. Gangopadhyay
& A Revathi
ABSTRACT
The response of concrete pavement slabs to environmental and traffic loadings has been captured through instrumented test sections laid
at Allahabad by-pass on NH-2; Kota, Rajasthan, on NH-76 and Siliguri, West Bengal, on NH-31. The sensors, embedded into the concrete
pavement slabs during construction, included Vibrating Wire (VW) type temperature sensors and strain gauges, and resistance type dynamic
strain gauges. VW temperature sensors measured temperature within the concrete slabs at various depths. VW strain gauges measured the
strain induced at different depths due to the temperature. Resistance type dynamic strain gauges measured the strains induced within the
concrete due to vehicle axle loads under dynamic conditions. Concrete slab behaviour during hardening phase and afterwards was studied.
Theoretical curling stresses were compared with measured stresses. Tests were conducted under road traffic to measure the dynamic strains
induced at non-tied and tied edges with different axle loads.
1 INTRODUCTION response to environmental and vehicle loads may be
characterized more accurately by measuring temperature and
Rigid pavement design is largely based on past experience strains through various sensors and instruments embedded
and empirical data. Theoretically temperature stresses and into the concrete slabs. Keeping this in view, instrumented
wheel load stresses at mid slab edge in concrete pavements concrete pavement sections were constructed near Silliguri
are calculated using Westergaard’s classical approach which (NH-31), Allahabad (NH-2), and Kota (NH-76) on three
is based on various assumptions. Temperature gradient different National Highways. This Paper presents the
across the depth of the concrete pavement slab causes the findings related to the response of instrumented concrete
slab to curl and deform resulting in the bending stresses. pavement slabs under real field conditions.
Westergaard1 presented an analysis of curling stresses in
concrete slab based upon the plate theory, and Bradbury2 2 DESCRIPTION OF INSTRUMENTS
developed a simple chart and equations to calculate curling
The response of concrete pavement slabs to environmental
stress. The analysis is based on the assumption that the
and traffic loading was studied through sensors embedded
temperature distribution is linear throughout the depth of the
into the concrete pavement slabs during construction. The
slab. This is an approximation, because studies have shown
sensors which were embedded into concrete slabs included
that the actual distribution is nonlinear3,4.
Vibrating Wire (VW) type temperature sensors and strain
The load stresses induced in the concrete pavement gauges, and resistance type dynamic strain gauges. VW
slabs can be determined using formulae developed by temperature sensors measured temperature within the
Westergaard. These formulae were developed for single concrete slabs at various depths. VW strain gauges measured
wheel load. Pickett and Ray charts can be used for multiple the strain induced at different depths due to temperature
wheel loads of any configuration. The present guidelines of variation. Resistance type strain gauges were used to measure
IRC:58, 2nd revised for design of rigid pavements, are based the strains induced within the concrete due to vehicle axle
on the determination of temperature and load stresses as per loads under dynamic conditions. The data from the VW type
Westergaard and Pickett-Ray formulae respectively. sensors and resistance type strain gauges was captured by
using static and dynamic data loggers.
The real field conditions with regard to the subgrade
3 DESCRIPTION OF TEST SECTIONS
support, presence of granular and dry lean concrete subbases
under the slabs, dowel bars at transverse joints and tie bars Instrumented concrete pavement test sections were
at longitudinal joints between slabs of different lanes and constructed at three locations – near Silliguri on NH-31 in
at tied shoulders etc. are quite different from theoretical West Bengal, Allahabad by-pass on NH-2 in U. P., and near
assumptions. Thus, the actual response of concrete pavement Kota on NH-76 in Rajasthan. The instrumented test section
slabs subjected to environmental and traffic loading may be near Silliguri is approximately 60 km from the city at chainage
different from what is obtained theoretically. The pavement 508.341 on NH-31. Thickness of concrete pavement slabs is
The views expressed in the Paper are personal views of the author. For any quary, the author may be contacted at e-mail
}
* Scientist, Rigid Pavements Division
** Head, Rigid Pavements Division Central Road Research Institute, New Delhi
*** Director
gauges measure the dynamic strains induced in the concrete different channels of multiplexers which were attached to
due to traffic movement. The measured compressive strains in datalogger. The data stored in the memory of datalogger was
the top fibers and tensile strains in the bottom fibers were used downloaded into a laptop computer from time-to-time. The
for estimating load stresses induced in the concrete slabs. The static data was collected at an interval of 30 min.
design of concrete pavement is based on the edge stresses at
the middle of the slab. Therefore, the dynamic strain gauges
have been installed in such a way so that the compressive and
tensile strains could be measured at the critical mid slab edge.
Strain gauges were embedded near the top and bottom at the
mid slab along the longitudinal tied joint edge and longitudinal
untied edge towards median (Photo 3).
a rise in temperature. At the same time the exterior of the slabs. Axial and curling displacements are induced in
concrete mass loses some heat so that a temperature gradient the slabs due to diurnal and seasonal fluctuations in
is established. The set time of the concrete was taken as temperature. Temperature changes cause a change in length
the time when strain begins to develop with changes in while temperature differential between the top and bottom
temperature. The temperature and strain of concrete during of concrete slab causes the pavement slab to curl. The
hardening, at different depths, were monitored and following curling upward or downward of slab depend on the sign
observations were made. and magnitude of temperature gradient. The temperature
at slab sub-base interface varies little in comparison to the
●● At Silliguri, the maximum temperature rise due to temperature variation at slab surface. Thus, a temperature
evolution of heat of hydration in the initial hours gradient exists daily in the slab as it tends to warm during
of hardening of concrete was observed to be 53 daylight hours and cool at night.
ºC at a depth of 200 mm from the top, after nearly
13 hours of placing the concrete. The concrete 6.2.1 Through thickness temperature variation: Variation
pouring temperature was 33 ºC and the ambient of temperature at different depths in the concrete pavement
temperature during laying in the evening was 38.6 ºC. slab was recorded. The maximum fluctuation in the
The temperature at top and bottom was observed to temperature was observed at the top. The range of variation
be 44.1ºC and 52.1ºC respectively at the same time. in temperature due to variation in ambient temperature go
The time of final set of concrete was observed to be on decreasing with the depth of the slab and is minimum
6.30 hours after placement. At the time of set, the near the bottom of the slab. Fig. 1 shows the temperature
temperature of top concrete surface was 10.6ºC less variation near the top and bottom of the slab with the
than the temperature at the bottom of the slab. Thus, variation in ambient temperature. The pattern of rise and
the concrete slab was observed to have set under a fall of temperature near top is similar to the pattern of
negative temperature differential of 10.6 ºC. variation in ambient temperature. The time of maximum and
minimum temperature at the top coincides with the time of
●● At Allahabad, the rise in temperature due to heat peak and least ambient temperature. However, this does not
evolved during hydration reaction of cement was happen in case of bottom temperature where the maximum
observed to be 54 ºC at a depth of 178 mm from and minimum temperatures are recorded a few hours later.
the top, after 19 hours of placing the concrete. The
concrete pouring temperature was 33 ºC. The concrete
was laid in the evening at an ambient temperature of
35 ºC. A negative temperature differential of 10.9 ºC
was observed at the time of setting of concrete.
calculation of curling stresses as per Westergaard that the reduction of edge load stresses due to the
analysis and IRC:58-2002, which is based upon presence of tie bars at longitudinal joint between lanes
positive temperature differentials, do not take into and between outer lane and tied shoulders should be
account the negative temperature differentials under considered while calculating the edge load stresses.
which slabs have been observed to have finally set.
It is recommended that it should be considered while ●● Comparison of strains developed at the mid slab edge
calculating the curling stresses. when wheel loads were placed just over the free edge
with the strains that developed when wheel loads were
●● Concrete slabs remain under positive and negative placed 25 cm inside the free edge revealed significant
temperature differentials for almost 12 hours reduction of strains in later case. Strain reduction was
each during day time and night time respectively. found to be in the range of 22 per cent to 40 per cent
The maximum positive and negative temperature for different loads with an average reduction of 31.4
differentials were observed between 1PM and 3 per cent
PM in the afternoon and 4 AM and 6 AM in the
early morning respectively. Maximum positive ●● The conclusions drawn above are based on the
temperature differential was recorded as 17.1 ºC for limited study carried out at three locations only. It is
30 cm thick slab at Kota, 18.9 ºC for 31 cm thick recommended that further study should be taken up to
slab at Siliguri and 19.2 ºC for 32 cm thick slab at cover different climatic zones of India as envisaged
Allahabad. These values are slightly higher than the in IRC:58; different sub-base types, slab thicknesses,
values recommended by IRC:58. and slab sizes.
●● istribution of positive temperature differential
D 9 ACKNOWLEDGEMENT
during 12 hours of day time indicates that its average
value between 12 Noon to 4 PM is 90 per cent of the Ministry of Shipping, Road Transport and Highways, Govt. of
maximum value that happens at some point of time India, New Delhi is acknowledged for sponsoring this study.
in the afternoon. Between 10 AM to 12 Noon and Sh. Dinesh Ganvir, Scientist; Sh. Pankaj Goel, Technical
4 PM to 6 PM, the average temperature differential Officer; Sh. Ashok Pant, Senior Technical Assistant, Rigid
was around 62 per cent of the maximum. During first Pavements Division, CRRI, New Delhi are thankfully
2 hours in the morning (8 AM to 10 AM) and last 2 acknowledged for their assistance during field work.
hours in the evening (6 PM to 8 PM), it was about REFERENCES
25per cent of the maximum. Present design methods
1. Westergaard, H. M. “Analysis of Stresses in Concrete Roads
assume a constant value of positive temperature
caused by Variation of Temperature”, Public Roads, Vol. 8, No. 3,
differential for calculating curling stresses which is May, 1927, pp 54-60.
not justified. It is recommended that different values 2. Bradbury, Royall D. “Reinforced Concrete Pavements”, Wire
of temperature differential should be used for stress Reinforcement Institute, Washington, D. C., 1938.
calculation during different time of the day.
3. Richardson, J. M. and Armghani, J. M. “Stress Caused by
●● Measured curling stresses were found to be Temperature Gradient in Portland Cement Concrete Pavements”,
Transportation Research Record 1121, TRB, National Research
considerably less than the theoretically calculated Council, Washington D. C., 1987, pp. 7-13.
stresses as per IRC:58 by using modified Westergaard
4. ouzid Choubane and Mang Tia, “Non-Linear Temperature
B
equation. It was estimated that measured stresses
Gradient Effect on Maximum Warping Stresses in Rigid
are approximately 50per cent to 65per cent of the Pavements”, Transportation Researech Record 1370, TRB,
theoretical stresses depending upon the value of the National Research Council, Washington D. C., 1991, pp. 11-19.
modulus of subgrade reaction, k. 5. Teller, L. W. and Sutherland, E. C. “The Structural Design of
Concrete Pavements”, Public Roads, Vol.16, No.9, November
●● Load testing of tied edge and non-tied free edge of
1935.
concrete slabs indicated considerable contribution of
tie bars in reducing load induced strains and hence 6. I RC:58-2002. Guidelines for the Design of Plain Jointed Rigid
Pavement Highways. Indian Roads Congress, New Delhi, 2002.
load stresses at mid slab edge. Average reduction in
load induced strains and hence edge load stresses due 7. AASHTO, 1993. Guide for Design of Pavement Structures.
American Association of State Highway and Transportation
to the presence of tie bars was observed to be of the Officials.
order of 25per cent. Present thickness design methods
of concrete pavements do not take into account the 8. PCA, 1984. Thickness Design for Concrete Highways and Street
Pavements. Portland Cement Association.
stress reducing effect of tie bars. It is recommended
ABSTRACT
The assessment of potholes is an essential part of a road maintenance management system for developing repair and maintenance strategies.
Nowadays, road condition assessment is gradually being automated by using various imaging systems. However, the processing of the
collected raw visual data is still being done manually or semi-automatically in India. Existing methods of data processing are very costly,
time consuming and mostly focused on the detection and classification of cracks only. This paper presents an efficient and accurate algorithm
for automated detection and measurement of potholes out of a large volume of road surface video clips of Indian Highways. In the proposed
algorithm, potholes are detected and their features are measured automatically out of a video clip in one go, using various image processing
techniques supported by user defined decision logic. This algorithmis implemented in a Windows environment with the help of Visual Studio
2008 and OpenCV, an open source computer vision library and tested on nine different road video clips. The results show that this algorithm
can detect and measure potholes automatically with accuracy upto 94 per cent. The information extracted using the proposed algorithm can
be used for determining maintenance levels of Indian roads and taking further appropriate actions for repair and maintenance.
The views expressed in the Paper are personal views of the author. For any quary, the author may be contacted at e-mail
* Technical Officer, Central Road Research Institute (CSIR-CRRI), Delhi, Email: hlokeshwor@gmail.com
** Ex-Head, IDD Centre, Indian Institute of Technology (IITD), Delhi, Email: lalitdas@gmail.com
*** Chief Design Engineer, IDD Centre, Indian Institute of Technology (IITD), Delhi, Email: sksud123@hotmail.com
detection in pavement images using histogram shape-based results obtained are also compared with that of two semi-
thresholding technique. However, quantification of potholes, automated toolkits. One is the NSV Toolkit while another
which is an essential task for road maintenance management, one is ImageJSoftware17, open source medical image analysis
was not done. Since the 3D image - based methods cost software developed by National Institute of Health, USA.
very high, the vibration-based methods lack accuracy and The information extracted using the proposed algorithm
reliability9 and the existing 2D image-based methods rely on can be used for determining maintenance levels for Indian
selected individual images, the development of automated roads and taking further appropriate actions for repair and
potholes detection and measurement algorithm out of a maintenance related issues, such as, allocating budgets
video clip still remains as a challenge.The key challenges or awarding contracts for repairing the critical roads in a
before the researchers is the segmentation of potholes out of short duration of time1, 11. The results obtained are up to 94
a large noisy road video data collected in different sunlight per cent accurate.
intensities with different images of objects (manholes,
animals, vehicles or their parts), different shadows of In the next section, a brief description of road video data
various objects (vehicles, manholes, animals, trees or poles) collection systems used in this research programme is given.
and different road markings (white, yellow or black). After that the proposed algorithm for automated potholes
detection and measurement is described. Later, test results
This paper proposesan efficient and accurate algorithm are presented and compared with that of two existing semi-
for automated detection and measurement of potholes out automated toolkits. Finally, conclusions and future works
of a road surface video clip.Here, a pothole is defined as are given.
a series of interconnected small distinct (dark or bright)
regions appearing against the background of a road 2 POTHOLES DETECTION AND
surface image with a minimum standard deviation of 10.0, MEASUREMENT METHOD
minimum circularity of 0.20 and minimum average width of
The overall objective of this research is to test whether a large
60 mm. Standard deviation (std) is a measure of variation or
database of road surface video clips of Indian highways that
dispersion of pixels intensities representing a pothole in a road
have been captured by existing imaging systems without any
image from their mean value. The value of std is computed
artificial lighting systems, can be utilized for the purpose of
using the Equn.1. Circularity is a shape factor which describes
speedy and accurate assessment of Indian roads condition.
the circular shape of a pothole numerically and its value is
With regard to this objective, the NSV and an omni present
1 for an ideal circle and between 0 & 1 for all other shapes.
passenger van have been chosen as road survey vehicles to
The value of circis computed from area (A) and perimeter (P)
capture the video clips of Indian Highways. The database
covering the pothole, using Equn.2 while the average width
of collected video clips captured is processed offline using
(w) of the pothole is computed using Equn.3.
the proposed algorithm. The result is two different types
In the proposed algorithm, a frame is extracted from an of video frames category viz. frames with potholes and
input road video clip and selected its blue channel from frames without potholes. Here, a video frame belongs to
default 24-bit RGB format using OpenCV for applying frames with potholes category if the frame contains at least
image processing techniques more efficiently. The blue one pothole, otherwise the video frame belongs to frames
channel image is subjected to Median filtering, followed by without potholes category.The potholes in the former
a clipping technique for noise removal. Then, the clipped category are tagged with a different color and measurement
image is applied to an adaptive thresholding, followed by a information is reported in a printable format. The results are
chain of morphological operations for image binarization. compared with the current methods practiced in the field for
Later, the binary image is applied to a connected component the evaluation of the proposed method.
labeling using contour tracing technique and Freeman chain
2.1 Road Video Data Collection Systems
coding supported by user defined logic for the potholes
detection and their measurement. The results show that the First imaging system used in this study is the pavement
proposed algorithm can detect potholes automatically out of video imaging module in the NSV while the second one is
a video clip based on three features of a pothole. The first just a Kodak easyshare digital camera held manually in a
feature is the statistical visual texture as given by standard running Tata Magic Passenger Van.The NSV continuously
deviation of the pixels intensities covering the pothole captures road surface video clips using two monochrome
from their mean valuewhile the second feature is the shape FireWirebased cameras in distance mode (every interval of
of pothole as given by circularity and the third feature is 3 metres). The two progressive scan digital cameras are fitted
the dimension of pothole as given by average width. The in the back of a Tata Sumo and are synchronized with the
triggers provided by a distance measuring instrument(DMI) potholes out of a video clip is listed below:
fitted to the rear wheel of the vehicle. One video frame 1. Input a road video clip of road surface;
covers 3m length by 2.5 m width of the road with a
resolution of 1280X960 pixels. Each square pixel covers 2. Extract the first frame;
2.5mm×2.5 mm. 3. Convert its default 24-bit depth format into 8-bit depth
format by selecting its blue channel (section 2.2.1);
Using a Kodak easyshare digital camera, the road visual
data of State Highway No.1 in Manipur state of India, are 4. Apply median filtering for image enhancement (section
recorded as video clips in continuous mode (time mode) by 2.2.2);
sitting in the rear sit of a running Tata Magic passenger van. 5. Apply clipping technique to remove unwanted features
This digital camera records video clips with a resolution of such as white road markings and white spots (section
640 x 480 in 24-bit RGB color format. One video frame 2.2.3);
covers approximately 2.5m width by 2.0m length of the
6. Apply adaptive thresholding to convert clipped enhanced
road surface with each pixel covering 4mm X 4mm. Use
image into binary image with black pixels representing
of video clips recorded using such an economical common
objects of interest (2.2.4);
digital camera without any extra costs of DMI, vehicle, data
acquisition system and laptop or personal computer is also 7. Apply morphological erosion to add black pixels to
being tested in this research study for automated potholes bridge the gaps in binary image (section 2.2.5);
detection and measurement. This method may be useful for 8. Apply morphological dilation to remove isolated black
developing repair and maintenance strategies with minimum pixels or their small cluster (section 2.2.6);
cost at regional or project levels.
9. Apply morphological erosion again to add black pixels
2.2 Potholes Detection and Measurement Algorithm to the binary image;
10. Apply connected component labeling and chain coding
The automated potholes detection and measurement algorithm
techniques (section 2.2.7) to count the number of objects
proposed in this study is developed for automated detection of
or region of interest and estimate each objects area (A)
frames with potholes as well as measurement of potholes from
and perimeter (P);
a noisy road video clip stored in a hard drive. This algorithm is
able to group all the frames of a video into two main categories 11. Filter out all the objects whose A<177cm2 (Non-Critical
viz. Frames with Potholes and Frames without Potholes, Objects) in the binary image;
based on user defined decision logic. Using this algorithm, 12. Determine std, circ and w of each remaining objects
a video frame is grouped into the frames without potholes (objects whose A >=177cm2);
category if total area of objects in the image computed using
13. Classify each object into two types: (a) Potholes, if std>=
this algorithm is less than 177cm2 or the objects do not satisfy
10.0 &circ>= 0.20 & w>= 60mm; (b) Non-Potholes, if
three criteria mentioned in our potholes definition (section
otherwise (section 2.2.8);
1). The remaining video frames are grouped into frames with
potholes category. A video frame is considered to the frames 14. Store the corresponding extracted frame along with the
with potholes category if total area of objects is greater or extracted information in a folder;
equal to 177cm2 and there is at least one object that satisfy 15. Repeat steps 3 to 14 for all remaining video frames;
the three criteria mentioned in our potholes definition. The
16. End.
authors choose 177cm2 to be the minimum cut off limit, since
it is the minimum area of a pothole that affects the motion of Various image processing techniques applied in the proposed
a car wheel and measures roughness significantly3. The area algorithm are discussed in the Sections 2.2.1 to 2.2.7.
of 177cm2 which is used in the decision logic can be modified
as per the actual requirement in context of road repair and 2.2.1 8-Bit Depth Format Conversion
maintenance.However, the authors have been found that The original video frame extracted from a video clip is in the
177cm2 as the most significant threshold value to identify RGB 24-bit depth (24-bit per pixel) format. Each channel (Red,
potholes out of a noisy road video clip and this threshold Green and Blue) is represented by 8-bit array and their pixel value
value has been determined by experimenting on 120 road ranges from 0(black) to 255(white). Thus, the blue channel image
images with potholes. which contains more detail information is selected. This makes
The algorithm which is developed for the automated the frame compatible with our image processing techniques and
detection of frames with potholes as well as measurement of saves memory space and processing time.
2.2.2 Median Filtering images, collected without any artificial lighting systems due to
varied conditions. Other techniques of segmentation, such as
The blue channel image needs to be enhanced or smoothened histogram based thresholding and edge detection techniques
before they can be used for analysis. For this, median are not able to give reliable results due to the highly textured
filtering12,13 is applied to the gray scale (8-bit depth) image. or uneven nature of road surface, which resulted in highly
There may be many reasons for doing smoothening but noisy road images18. However, adaptive thresholding based
it is done here mainly to reduce noise or camera artifacts on weighted mean is found to be very useful for images
developed during road image acquisition. This filter that are characterized by strong illumination or reflectance
replaces each pixel by the median or middle pixel in a gradient as a result of variation of illumination. Besides,
square neighborhood around the centre pixel. The size of the this technique is also able to remove uniformly distributed
neighborhood used for filtering is 5X5 pixel. Other technique shadows or image parts of some unwanted features present
like simple blurring that replaces each pixel by an average in the images while saving computation time.
pixel value can be sensitive to noisy images, especially
images with large isolated outliner points, sometimes called 2.2.5 Morphological Erosion Operation
“shot noise”. Large differences in even a small number of
points can cause a noticeable movement in the average value. By applying adaptive thresholding, the grayscale image is
However, median filtering is able to ignore the outliners by converted into a binary image with black pixels representing
selecting the middle points. objects which may be a distress or noise while white pixels
representing the background. Further processing of this
2.2.3 Clipping Values binary image is required for removing noise, mapping
the actual area of the objects as measured on the road and
Besides noises or camera artifacts, there are still unwanted extracting their visual properties. For this purpose, a series of
features present in the road frames, such as, road markings morphological operations is applied followed by connected
or white spots. These unwanted features need to be removed component labeling and chain coding techniques. Then, the
before segmentation. For this, all the pixel intensity values shape and size of objects are measured from the binarized
above the average value of the enhanced image are clipped image while the visual texture of each object is calculated
to its average value. This is because most of the values of from the original image by mapping the co-ordinates of
pixels representing these road markings or white spots are objects on the binarized image.
found to be above the average value of the image and an
average value of an image represents the most occurring Morphological operations, such as, erosion, dilation etc., can
pixel value. If clipping values technique is not applied then be used for different purposes like removing noise, isolating
some of these features will be falsely detected as potholes. individual elements, joining disparate elements and finding
intensity bumps or holes or gradients in an image12. Erosion
2.2.4 Adaptive Thresholding operation is used in the proposed method to join the disparate
elements or bridge the gaps between black pixels (object
It is not wise to apply many layers of preprocessing steps
pixels). Basically, this operator adds more black pixels to
since it will slow automation of image processing and also
a binary image. The action of this operator is equivalent
waste some valuable information. The main objective at this
to computing a local minimum over the area of the kernel.
stage is only to determine which pixel belongs to object or
As the kernel is scanned over the image, it computes the
region of interest. To achieve this segmentation,an adaptive
minimum pixel value overlapped by the kernel and replaces
thresholding technique based on the weighted mean12, 14 is
the image pixel under the anchor point of the kernel with
applied. This is a modified threshold technique in which the
that minimum value. This operator is iterated a limited
threshold level is itself variable. The threshold level is set
number of times using a square 3X3 kernel with the anchor
on a pixel by pixel basis by computing a weighted mean of
at its centre, just before the dilation operation (discussed in
a neighborhood region around each pixel location minus a
Section 2.2.6), as well as just after the dilation, so that more
constant. All the pixels in the region are weighted equally.
detail and useful information is retained in the image.
By trial and error method, the optimal neighborhood region
2.2.6 Morphological Dilation Operation
and the best constant value are determined for a frame
resolution of 1280 X 960 which covers an area of 3m X 2.5m After the erosion operation has been applied, isolated
as well as for a frame resolution of 640 X 480 which covers black pixels or their small clusters which constitute noise
2.5m X 2m. Global thresholding is not applied here since are developed in the binary image.This noise needs to be
getting an optimum threshold is very difficult for large set of removed. For this, dilation operation12is applied, which is
basically addition of white pixels to a binary image. The Where, ne and no are number of even and odd Freeman chain elements respectively;
action of the dilation operator is equivalent to computing D(m) = {P + √ (P2 – 16*A)} / 4; if (P2 – 16*A) > 0;
a local maximum over the area of the kernel. As the kernel = P / 4; if (P2 – 16*A) <= 0; (6)
is scanned over the image, it computes the maximum pixel
value overlapped by the kernel and replaces the image pixel 2.2.8 Decision Logic for Potholes Identification
under the anchor point of the kernel with that maximum The extracted information such as std, circ and w are
value. By iterating this operation a limited number of times compared with user defined decision logic for the automated
using same kernel used in erosion, some of the isolated black identification of potholes out of short listed COs. This
pixels or their small clusters are removed away without decision logic has been developed by experimenting on
affecting the larger black regions. To map the actual shape 120 numbers of video images having potholes.The images
and size of the segmented object with physical road, total with potholes used for the experiments have been selected
number of iterations that has been eroded throughout the randomly to determine the deciding range of values or
processing must be dilated back. significant thresholds for std, circ and w.
2.2.7 Connected Component Labeling and Chain Coding In this decision logic, a CO is classified using Eq. (7).
After applying all the above image processing techniques, an
image containing probable objects of interests is obtained.
To simplify the process as well as save time, all the objects
whose area are less than 177cm2 (minimum cut off limit)
are filtered out and called them non-critical objects (NCOs). In the developed logic, the average width of 60 mm is the
The authors choose 177cm2 to be the minimum cut off limit minimum limit of average width that has been computed
since it is the minimum area of a pothole that affects the from area and perimeter of a pothole in a video image, using
motion of a car wheel and measures roughness significantly3. the developed algorithm. This computed average width
Then, some information are extracted from the remaining may be sometimes more or less than that of actual width
bigger objects, which are called as critical objects (COs). of a pothole in a road surface due to the presence of noise,
This minimum size of critical objects of our interest can developed automatically during the course of various image
be decided in accordance with the actual requirements of a processing stages.This dimension has been used in the
concerned authority. For extracting the required information, proposed method for automated identification of potholes
a connected component labeling algorithm using contour in a noisy road video image. However, this method has not
tracing technique15 is applied. Unlike traditional two-pass attempted to measure the actual width of a pothole.
algorithms, labeling is done here in a single pass over
The procedure for automated detection and measurement of
the image, while contour points are revisited more than
cracks is illustrated in Fig.1 to 2. Here, images in column
once but not more than a limited value. This technique is
(a) are original images; column (b) are binary images B
applied here since the computational speed is faster than after median filtering, clipping and adaptive thresholding;
other traditional connected component labeling techniques. column (c) are binary images BE after erosion; column (d)
Using this technique and the 8-connected Freeman chain are binary images BED after dilation; column (e) are binary
coding technique16, the number of COs present in each images BEDE after erosion; column (f) are detected potholes
image has been counted, and their area (A), perimeter (P), with a minimum size of 177cm2 in binary image BEDE
circ, maximum dimension (D) and average width (w) are whereblack color represents non-critical objects (NCO), gray
estimated from the binary image using Equn. (1-6), while std color represents critical objects (CO) with dark gray color
of pixels intensities from their mean value (µ) is computed represents non-potholes (NP),bright gray color represents
from the original image by mapping the corresponding critical potholes (P) and brightest gray color represents
pixels co-ordinates of the CO (binary image). biggest critical object (BCO); and column (g) are extracted
information reporting all the required measurements with
POTHOLE_REPORT represents information of detected
potholes using Eqn.7, NON-POTHOLE_REPORT
represents information of detected non-potholes using Eqn.7;
BIGGEST_CO_REPORT represents extracted properties
A (m2) = (Number of pixels in CO) * pixel size (m2); (4) of the biggest critical object (BCO) based on which the
decision logic has been developed. This BCO report is just
P (m) = {π/8 (1+ √2) (ne+ ne)} * pixel length (m); (5) to illustrate the effectiveness of the logic.
Fig. 2 (g)
Fig.1 Procedure to detect and measure potholes using the proposed For testing the performance of the proposed algorithm,
method in video image with potholes nine numbers of video clips has been selected randomly
from a database of video clips collected using two different
imaging systems (discussed in Section 2.1). These video
clips have all the varieties of features that occur on a road
e.g. road markings, shadows / images of trees, and vehicle
ortheir parts, distress like potholes, cracks, water bleeding,
patching.The detailed analysis reports whichhave been
obtained by implementing the proposed algorithm in a
Windows environment (BENQ Joybook mini-Laptop with
Intel Atom CPU 1.60 GHz, 1 GB RAM and OS XP SP3) is
listed below in Table 1 to 2 and Graph 1 to 2.
Fig. 2 (a) Fig. 2 (b)
Table 1 Comparisons of evaluation done using the proposed method and NSV Toolkit
Video clips TNF Proposed method NSV Toolkit Error (per Time saving
cent) (min)
No. of No. of Time No. of No. of FPt No. of No. of Time
FNPour FPour taken FNPt Falses Falses in taken
(min) in FNPour FPour (min)
NSV.1 57 53 4 3 54 3 0 1 102 1.7 102-3 = 99
NSV.2 300 294 6 19 300 0 0 6 525 2.0 525-19 = 506
NSV.3 200 116 84 13 200 0 0 84 398 42.0 398-13 = 385
NSV.4 300 292 8 16 286 4 8 2 594 3.3 594-16 = 578
NSV.5 200 170 30 10 164 36 9 3 396 6.0 396-10 = 386
Color.1 225 32 193 7 46 179 0 8 431 3.5 431-7 = 424
Color.2 370 231 139 9 233 137 3 5 701 2.2 701-9 = 692
Color.3 432 377 55 11 374 58 4 1 840 1.2 840-11 = 829
Color.4 182 30 152 5 34 148 0 4 355 2.2 355-5 = 350
Note:- Tnf = Total Number Of Video Frames; Fp = Frames With Potholes, Fnp = Frames Without Potholes;
Error(Per Cent) = {(No. False Detections In Fpour + No. False Detections In Fnpour)/ Tnf}*100;
their locations, number of occurrences, areas, and extent 6. .Li, M. Yao, X. Yao, B. Xu (2010), A Real-Time 3D Scanning
Q
(relative area) can be measured automatically while saving System For Pavement Distortion Inspection, Meas. Sci. Technol.
21
considerable time, money and manpower resources.This
algorithm can be readily applied in professional practice and 7. . Hou, K.C.P Wang, Challenges, W. Gong, Experimentation of
Z
effectively to meet the challenges faced by Indian highway 3D Pavement Imaging Through Sereovision, Proc. of Int. Conf. on
Transportation Engineering (ICTE 2007), pp. 376-381.
professionals both for road maintenance management and
evaluation of the current health condition of the national 8. .X. Yu, X. Yu, Vibration –Based System For Pavement Condition
B
highways. The method is worthy of field implementation and Evaluation, Proc. of the 9th Int. Conf. on Applications of Advanced
Technology in Transportation (AATT), pp. 183-189.
only field testing will demonstrate its novelty and innovative
character. There is potential in developing an automated road 9. . Koch, L.Brilakis (2011), Pothole Detection in Asphalt Pavement
C
surface imaging system which is optimally designed for the Images, Advanced Engineering Informatics, Elsevier, Volume
25, Issue 3, August, pp. 507-515.
described method to get even far better results.
10. .Sharma (2006), Keeping a Hawk’s Eye on Roads, 12 Dec, 0053
N
5 ACKNOWLEDGMENTS hrs IST, TNN, Available at http://timesofindia.indiatimes.com/
article show/780093.cms.
The authors gratefully acknowledge the support of this
research by MORTH and CSIR-CRRI, particularly Professor 11. ommittee (2007), The Report of the Working Group on Roads
C
(2007-2012) for 11th Five Year Plan, MORTH, Govt. of India,
S.K. Brahmachari, Director General (CSIR), Professor April, p. 30, http://planningcommission.nic.in/aboutus/committee/
Gangopadhyay, Director (CSIR-CRRI) and D.C. Sharma, wkgrp11/wg11.road.pdf.
Head, Instrumentation Division (CSIR-CRRI). Furthermore,
12. . Bradski, A. Kaehler (2008), Learning OpencV, O’Reilly Media
G
the authors would like to acknowledge the support of IIT Inc., Sebastopol, CA, First Edition.
Delhi and thank Professor K.K.Biswas for his illuminating
13. .C. Gonzalez, R.E. Woods (2008), Digital Image Processing,
R
lectures in the field of Digital Image Analysis which the first Pearson Educational International, Upper Saddle River, Third
author had the honour to attend. Edition.
14. .K. Jain (1986), Fundamentals of Digital Image Processing,
A
REFERENCES
Englewood Cliffs, NJ, Prentice-Hall, p. 408.
1. MORT&H (2004), Guidelines for Maintenance Management of 15. . Chang, C. Chen, C. Chun (2004), A linear-Time Component
F
Primary, Secondary, and Urban Roads, Indian Roads Congress, Labeling Algorithm Using Contour Tracing Technique, Computer
New Delhi, May, p.3. Vision and Image Understanding, Volume 93, Issue 2, February,
2. R.Robinson, U.Danielson, M.Sneith ( 1998 ), Road Maintenance Elsevier, pp. 206-220.
Management, Palgrave, New York, pp. 3-4. 16. .Yang, F.Albertgtsen, T.Lonnestad, P. Grottum (1994), Method
L
3. .D.O. Paterson (1987), Road Deterioration and Maintenance
W to Estimate Areas and Perimeters of Blob-Like Objects: a
Effects, The Highway Design and Maintenance Standards Series, Comparision, MVA’94 IAPR Workshop on Machine Applications,
The Johns Hopkins University Press, Baltimore and London, pp. Dec. 13-15, Kawasaki.
230-231. 17. . Rasband (2011), ImageJ 1.44P, National Institute of Health,
W
4. .H.McGhee (2004), Automated Pavement Distress Collection
K USA, http://imagej.nih.gov/ij. Last view on 01-06- 2011.
Techniques, NCHRP Synthesis 334, Transportation Research 18. .Qingquan, L. Xianglong (2008), A Model for Segmentation
L
Board, WashingtonD.C. and Distress Statistic of Massive Pavement Images Based
on Multi-Scale Strategies, The International Archives of the
5. .R.Bennett, a.Chamorro, C.Chen, H.D.Sominihac,G.W.Flintsch
C Photogrammetry, Remote Sensing and Spatial Information
(2007), Data Collection For Road Management, East Asia Pacific Sciences, Vol. XXXVII.Part B5. Beijing 2008.
Transport Unit, The World Bank, Washington D.C., Version 2.0,
February.
abstract
Reinforced cement concrete pavement with reinforcement at top and bottom is designed for village roads in alluvial regions.
The concrete grade used in pavement is M 20. Design curves for village roads are presented. It is observed that for low volume
traffic roads, M20 grade is found to be suitable. Proposed RCC pavement is suitable for sub-grade having low modulus of
reaction. The proposed RCC pavement comes out to be economical in comparison to conventional rigid pavement.
1 Introduction result in better and long performing roads at a much lesser
cost.
Village roads in general have low volume of traffic, consisting
mostly of rural transport vehicles, like, agricultural tractors/ Rigid pavement comes out to be a better alternative to
trailers, light goods vehicles, buses, animal drawn vehicles, flexible pavement where the soil strength is poor, aggregate
motorized two-wheelers and cycles. Some of the village are costly and the drainage conditions are bad but they
roads may also have light and medium trucks carrying demand a high degree of professional expertise at the design
sugarcane, timber, quarry material, etc. Due to shifting of stage, construction and maintenance besides high initial
industries towards villages there is an increase in volume cost. The guidelines have been developed by Indian Roads
of traffic on village roads. It necessitates providing the Congress (IRC) for the design and construction of cement
cost effective solution of connectivity to the villages. As of concrete pavements for village roads in year 2004, named as
now, flexible pavements are in use for village connectivity IRC: SP: 62-20047. For low traffic volume roads, i.e. village
program because of low initial construction cost. But, high roads and streets, a rural road manual has been introduced by
cost of maintenance, sensitivity to water logging and lack IRC where cement concrete roads are preferred in populated
of institutional set up for the maintenance, the village roads areas/streets to meet the problems of maintenance due to
deteriorate very fast, especially in alluvial regions. As most poor drainage, etc. M 30 grade concrete is being used in
of northern parts of India belong to alluvial region having the cement concrete road. The state of Punjab has already
soft soil and poor drainage conditions, lot of expenditure is adopted cement concrete pavement in villages. In year 2008,
being incurred every year to maintain the flexible pavements state of Uttar Pradesh opted for the construction of rigid
in their congenial condition. This necessitates the use of pavement for village roads/streets in Ambedkar villages. In
cement concrete road, a better option from climatic and near future the states of northern India that fall in alluvial
environmental considerations. The planners and engineers regions, facing the problem of poor sub-grade and water
are bound to think about the option of rigid pavement as a logging will be forced to adopt rigid pavements.
substitute of flexible pavement for village roads.
Rigid pavements consist of a number of joints to reduce the
Different options have been tried for village roads depending temperature stresses and are one of the principal causes of
upon the soil and climatic considerations. Visser and Hall1,2 discomfort and inconvenience to the users and traffic. IRC:
developed a concept of cell-filled pavement termed as flexible 101-19888 specifies technique of continuously reinforced
concrete pavement for village roads. Pandey3,4 investigated concrete pavement which reduces the need of expansion
cell filled concrete for village roads. Sahu et al.5 investigated and contraction joints. This permits longer slab lengths with
the structural behavior of cell-filled concrete pavement. improved riding quality and reduced maintenance cost than
Sinha et al.6 presented the concept of white topping as a that for the plain cement concrete pavement (PCP). The
rehabilitation measure by strengthening of deteriorated conventional Continuously Reinforced Concrete Pavement
bituminous pavements and observed that white topping will (CRCP) requires per centage of steel 0.7 to 1.0 per cent
The views expressed in the Paper are personal views of the author. For any quary, the author may be contacted at e-mail
* Chief Engineer Head Quarter 1, UPPWD, Lucknow
** Professor, Civil Engineering Department,
*** Professor, Applied Mechanics Department
} MNNIT, Allahabad
The proposed type of pavement has been designed for single Radius of relative stiffness,
wheel load placed on edges and reinforcement provided
at 40 mm below the top and above the bottom of the slab,
The design of reinforced cement concrete pavement for
respectively. Reinforcement is calculated for CRCP based
village roads in alluvial regions of Uttar Pradesh with lean
on consideration of frictional stresses. Stresses due to wheel
concrete as base is done. Two cases are considered; (i) 30
load and temperature variation are obtained on the basis of
kN single wheel load and pavement width 3.0 m and, (ii) 51
provisions of IRC: SP: 62-2004. An equivalent section of
kN single wheel load and pavement width 3.75 m. Design
RCC pavement in terms of concrete is obtained by replacing
parameters are:
the steel area by equivalent concrete area which equals
modular ratio times the steel area. The design steps are
similar to PCP as given below. It is observed that critical Tyre pressure = 0.50 N/mm2 for 30 kN
condition occurs at edges. single wheel load
Temperature gradient = 12.5 oC for pavement modified k value is taken as 16.6 kg/cm2/cm and 5.6 kg/cm2/
width 3.0 m cm, respectively (IRC: 58-20029). In case of RCC pavement
over existing base of WBM/BOE/GSB, the modulus of sub-
= 13.1 oC for pavement grade reaction k based on field observations of Benkelman
width 3.75 m beam deflection is taken as 8 kg/cm2/cm. The design
parameters are summarized in Table 1.
Modulus of Elasticity = 30,000 N/mm2
(EPQC) The stresses in the RCC pavement with reinforcement at
top and bottom are calculated at edge, corner and interior
Poisson’s ratio = 0.15 of the pavements and the results are shown in Tables 2-3.
Maximum joint = 50 m The stresses in RCC pavement on WBM/BOE/GSB are
spacing (L) calculated and shown in Tables 4-5. It can be seen that the
RCC pavement with M 20 grade concrete is sustainable for
Design life = 20 years village roads. The critical condition occurs when wheel is
placed at edges during the day time just in noon/afternoon.
Coefficient of thermal = 10.0*10-6/0c The cost comparisons of the proposed RCC pavements
expansion shown in Figs. 1-4 are made with plain concrete pavement
(PCP) and tabulated in Table 6-9. It is seen that savings for
The amount of reinforcement is calculated using the
proposed RCC pavement are meager, but the performance
following relations: will be better than the PCP since the former will take care of
Area of steel (cm2), the temperature stresses and cracks will be arrested.
The proposed RCC pavements were constructed at three places
Spacing of reinforcing bars on each face (cm),
to observe their performance. First, Lucknow-Nagram road
Number of bars on each face, to Sarthua link road 3.0 m width and of 15 cm thickness was
constructed in the year 2004 for PMGSY with reinforcement at
Equivalent thickness of the RCC top and bottom. Sub-grade of 1:3:6 PCC was of 10 cm thickness.
pavement (cm), Second, Pratapgarh-Jathwara-Lal Gopalganj road 7.0 m width
and of 20 cm thickness was constructed in the year 2007 with
reinforcement at top and bottom. Sub-grade was provided with
Frictional stresses (kg/cm2), WBM/BOE. The third, Sakutiya-Byodhan-Khurd Road 3.0
m width and of 20 cm thickness was constructed in year 2009
Total stresses in the concrete at the with reinforcement at top and bottom. Sub-grade was provided
pavement edges, with WBM/BOE. The performances of these RCC pavements
The stresses are calculated in the equivalent section. The were observed and it has been found that there are no visible
modulus of sub-grade reaction k based on field observation cracks on the surface of the pavements and there are no signs of
of CBR value is taken as 4.2 kg/cm2/cm and 2.1 kg/cm2/ distress. The RCC pavements observed for their performance
cm. The pavement is laid over lean concrete and hence the are shown in Figs. 5(a to c).
Table 3 Stresses at Different Locations in RCC Pavement (Axle load: 102 kN).
Modulus of Sub- Stress (N/mm2) Total Stress (N/mm2)
S. Effective k Over 10 cm Temperature Temperature
Location grade Reaction, k
No. LC (kg/cm2/cm) Load Friction
(kg/cm2/cm) tºc 0.7 tºc tºc 0.7 tºc
1. Edge 4.2 16.6 1.93 1.35 2.72 -0.9 3.75 3.15
2. Interior 4.2 16.6 2.27 1.59 1.66 -0.9 3.03 2.35
3. Corner 4.2 16.6 10.4 0.28 2.50 -0.9 2.03 1.88
4. Edge 2.1 5.6 1.93 1.35 3.14 -0.9 4.17 3.59
5. Interior 2.1 5.6 2.27 1.59 1.89 -0.9 3.26 2.58
6. Corner 2.1 5.6 0.35 0.24 2.9 -0.9 2.35 2.24
Table 6 Per km. Cost Comparison of PCP and Reinforced Concrete Pavement (Pavement width 3.0 m Wheel Load 30kN). (Using
M 30 Concrete in PCP and M 20 in RCC Pavement as PQC and Base as LC)
Fig. 1 Cross Section of RCC Pavement over BOE/GSB/WBM Base for Fig. 2 Cross Section of RCC Pavement over BOE/GSB/WBM Base for
Dead End Road (Joint Spacing: 50) through village Road (Joint Spacing: 50m)
Fig. 3 Cross Section of RCC Pavement over LC Base for Dead End Fig. 4 Cross Section of RCC Pavement over LC Base for Through Village
Village Road (Joint Spacing: 50m) Road (Joint Spacing: 50 m).
Table7 Per km. Cost comparison of PCP and Reinforced Concrete Pavement (Pavement width 3.0m Wheel Load
30kN). (Using M30 Concrete in PCP and M20 in RCC Pavement as PQC and Base as BOE/GSB/WBM)
S. Plain Concrete Pavement Composite Cement Concrete Pavement
No. Rate Rate
Item Measurement Qty. Amount Measurement Qty. Amount
(Rs.) (Rs.)
M 30 Grade 4913 per
1. 1x1000x3.0x0.15 450 m 3
2210850.00
Cement Concrete m3
M 20 Cement 4555 per
2. 1x1000x3.0x0.125 375 m3 1708125.00
Concrete m3
1000 3000 per 1000 3000 per
3. Number of Joints 226 No. 678000.00 21 No. 63000.00
4.44 Joint 50 Joint
Reinforcement
10 mm in
Longitudinal - - - -
2x20x13×50x0.62 16120 45 per
4. Direction 990756.00
2x20x126×3.0x0.39 5896.80 kg
8 mm in - - - -
22016.8 kg
Transverse
Direction
Total: 2888850.00 2761881.00
Saving = 4.40 per cent
Table 8 Per km. Cost Comparison of PCP and Reinforced Concrete Pavement (Pavement width 3.75 m Wheel Load 51kN).
(Using M30 Concrete in PCP and M20 in RCC pavement as PQC and Base as LC)
S. Plain Concrete Pavement Composite Cement Concrete Pavement
No. Item Measurement Qty. Rate (Rs.) Amount Measurement Qty. Rate (Rs.) Amount
M 30 Grade
1. 1x1000x3.75x0.2 450 m 3
4913 per m 3684750.00
3
Cement Concrete
M 20 Cement
2. 1x1000x3.75x0.175 656.25 m3 4555 per m3 2989218.75
Concrete
1000 4000 per 1000 4000 per
3. Number of Joints 226 No. 904000.00 21 No. 84000.00
4.44 Joint 50 Joint
M 10 Concrete as
4. 1x1000x3.75x0.1 375 3744 1404000.00 1x1000x3.75x0.1 375 m3 3744 1404000.00
base
Reinforcement
10 mm in 26040
Longitudinal - - - - 2x20x13×50x0.62
5. Direction 7371.80 45 per kg 1503495.00
2x20x126×3.0x0.39
8 mm in Transverse 33411.0 kg
Direction - - - -
Total: 5992750.00 5980714.00
Saving = 0.20 per cent
Table 9 Per km. Cost Comparison of PCP and reinforced Concrete Pavement (Pavement width 3.75m Wheel Load
51kN). (Using M30 Concrete in PCP and M20 in RCC Pavement as PQC and Base as BOE/GSB/WBM)
Plain Concrete Pavement Composite Cement Concrete Pavement
S. No. Item Rate
Measurement Qty. Amount Measurement Qty. Rate (Rs.) Amount
(Rs.)
M 30 Grade 4913 per
1. 1x1000x3.75x0.2 750 m3 3684750.00
Cement Concrete m3
M 20 Cement 4555 per
2. 1x1000x3.75x0.175 656.25 m3 2989218.75
Concrete m3
1000 4000 per 1000 3000 per
3. Number of Joints 226 No. 904000.00 21 No. 84000.00
4.44 Joint 50 Joint
Reinforcement
10 mm in
Longitudinal 2x20x21×50x0.62
4. Direction - - - - 26040 45 per kg 1503495.00
2x20x126×3.75x0.39
8 mm in Transverse 7371.00
Direction - - - - 33411.0 kg
Total: 4588750.00 4576714.00
Saving = 0.26 per cent
Fig. 6 Stresses in RCC Rigid Pavement for Rural Dead End Roads in Fig. 7 Stresses in RCC Rigid Pavement for Rural Dead End Roads in
Alluvial Region (Zone I). Alluvial Region (Zone II).
Fig. 8 Stresses in RCC Rigid Pavement for Rural Dead End Roads in Fig. 9 Stresses in RCC Rigid Pavement (for Rural Dead End Roads in
Alluvial Region (Zone I). Alluvial Region (Zone II).
Fig. 10 Stresses in RCC Rigid Pavement for Rural Dead End Roads in Fig. 11 Stresses in RCC Rigid Pavement for Rural Dead End Roads in
Alluvial Region (Zone I). Alluvial Region (Zone II).
Fig. 12 Stresses in RCC Rigid Pavement for Rural Through Roads in Fig. 13 Stresses in RCC Rigid Pavement for Rural Through Roads in
Alluvial Region (Zone I). Alluvial Region (Zone II).
Fig. 14 Stresses in RCC Rigid Pavement for Rural Through Roads in Fig. 15 Stresses in RCC Rigid Pavement for Rural Through Roads in
Alluvial Region (Zone I). Alluvial Region (Zone II).
Fig. 16 Stresses in RCC Rigid Pavement for Rural Through Roads in Fig. 17 Stresses in RCC Rigid Pavement for Rural Through Roads in
Alluvial Region (Zone I). Alluvial Region (Zone II).
6 CONCLUDING REMARKS 2. Visser, T., and Hall, S. (2003), “Innovative and Cost Effective
Solutions for Roads in Rural Areas and Difficult Terrain”,
Reinforced cement concrete pavement with reinforcement Transportation Research Record 1652, J. Transportation Research
Board, 1819A/2003, 169-173.
placed at top and bottom are designed for village roads. For
low volume traffic roads, M 20 grade concrete is found to 3. Pandey, B.B., (2006), “ Low Cost Concrete Roads for Villages”,
Grameen sampark, National Rural Road Development Agency,
be more appropriate because of its easy implementation Ministry of Rural Development, Government of India, Vol. II, No.
in the field for village roads. Proposed RCC pavement is 1 &2, June 2006,14-15.
suitable for sub-grade having very low modulus of reaction. 4. Pandey, B.B., (2007), “Durable Pavements for Villages with Sand-
RCC pavement for dead end roads (CBR = 5, k = 4.2 kg/ Cement”, Grameen Sampark, National Rural Road Development
cm2/cm, modified k = 16.6 kg/cm2/cm, joint spacing = 50 Agency, Ministry of Rural development, Government of India,
m) is economical by 4.0 per cent in comparison to PCP May 2007, 23-24.
pavement as specified by IRC. The temperature and moisture 5. Sahu, U.C., Reddy, K.S., and Pandey, B.B. (2006), “Structural
Evaluation of Concrete Filled Cell Pavement”, Int. J. Pavement
variations may also cause tension at top and bottom of
Engineering & Asphalt Technology, U.K., 7 (1), 27-27.
slab. Reinforcement at middle specified in CRCP is not so
6. Sinha,V.K., Kumar.S., and Jain.R. K. (2007), “ WhiteTopping-A
effective since cracks appear first at top and bottom face and Cot-Effctive rehabilitation Alternative for Preserving Bituminous
then move towards inner region. Flexural use of steel is not Pavements on Long-Term Basis” Indian Roads Congress. Vol.
possible if it is placed at neutral axis. By providing steel 68-3
at both faces of pavement, the spacing of contraction joint 7. IRC:SP:62-2004 (2004), “Guidelines for the Design and
can be increased that further improves the riding comfort. Construction of Cement Concrete Pavements for Rural Roads”,
The advantage of long length of panel also increases the The Indian Roads Congress, 2004.
frictional stresses which are compressive in nature and 8. IRC: 101-1988 (1988), “Guidelines for Design of Continuously
Reinforced Concrete Pavement with Elastic Joints”, The Indian
ultimately reduce the critical tensile stress. The proposed
Roads Congress, 1988.
RCC pavements are constructed and their performance in
9. IRC: 58-2002 (2002), “Guidelines for Design of Plain Jointed
the field have been observed and found to be satisfactory.
Rigid Pavements for Highways”, The Indian Road Congress
2002.
REFERENCES:
1. Visser, T., and Hall, S. (1999), “Flexible Portland Cement Concrete
Pavement for Village Roads”, Transportation Research Record
1652, Transportation Research Board, Washington D.C., 121-127.
ABSTRACT
The causative factors for road crashes are well known and they can be classified into three groups namely vehicle, road and driver. However,
the apportionment of these factors which leads to road crashes is a very difficult task. This requires exhaustive representation of road
crash severity considering each and every causative parameter. Whatever savings that are gained from the high speed corridors in terms of
enhanced speed and increased capacity are getting lost due to the road crashes and it is estimated that about 3 per cent of GDP in India is
lost due to road crashes. Considering these issues, it is proposed to study the trend of these road crashes and quantify loss to economy in
the present study. In order to do that the road crash data was collected from National Highway Authority of India (NHAI) for the selected
high speed corridors for the last two years. The road crashes are modeled to predict road crash occurrence as well as severity using Binary
Logit Model and Multinomial Logit Model. For this, the influencing parameters such as road characteristics, geometry, weather conditions
etc. are considered.
The views expressed in the Paper are personal views of the author. For any quary, the author may be contacted at e-mail
}
* Scientist and corresponding author, Traffic and Transport Planning Area
** Scientist, Traffic and Transport Planning Area Central Road Research Institute (C.R.R.I.),
*** Scientist, Pavement Evaluation Division New Delhi-110020, INDIA
**** Director
***** Post Graduate Student, College of Engineering, Anna University, Guindy, Chennai-600025, INDIA
each and every causative parameter. In this study, an attempt combinations of varying causative factors were considered.
has been made to understand the role of causative factors To understand the nature of road crash within the dataset,
and therefore an investigation into the relationship between critical analysis of the causative variables was carried out.
the causative factors and the occurrence as well as severity
of road crashes has been investigated.
NH-1 NH -5
NH-7 NH-45 Fig. 2 Variation of Occurrence and Severity of Road Crashes with respect
NH-8 NH-2 to the Weather Conditions
NH-68 NH-76
NH-79 NH-46
NH-28 NH-37
NH-36 NH-54
NH-6 NH-3
NH-47 NH-22
NH-79A NH-45C
NH-5A NH-13
Fig. 3 Variation of Occurrence and Severity of Road Crashes with respect
NH-17 to the Intersection Type
the ith case or the propensity towards the ith case experience Table 3 Prediction Accuracy of Binary Logit Model
and road crash. during Validation
Predicted Samples
Zi = b0+b1 xi1+b2 x i2+...+ bpxip equn. 2
Per centage
Where, Probability 0 1
Accuracy
xij – is the jth predictor for ith case
0 24686 57 99.80 per cent
bj - is the jth coefficient Observed
Samples 1 295 127 30.1 per cent
p – is the number of predictors
Overall Per 98.8 per 69.0 per
For the development of the road crash occurrence prediction 98.60 per cent
centage cent cent
model, the independent variables considered include time,
causes, road features, road condition, intersection type and
2.2 Modeling Road Crash Severity
weather condition. Since the dependent variable is either
(i.e. non-occurrence of road crash) or 1 (i.e. occurrence of The road crash severity is classified into three categories
road crash) and all the independent variables are divided
namely; fatal, grievous and minor as discussed earlier. The
into categories by appropriately assigning codes and since
dependent variable considered in the model is road crash
dependent variable is having two choices and independent
variables are not continuous variables, a binary Logit model severity which is discrete in nature. The modeling involves
has been developed by establishing relationship between the prediction of road crash severity between the dependent
these variables. The calibration of the road crash occurrence variable namely the severity of road crash (i.e. based on
prediction model is carried for the 70 per cent of sample fatal, grievous, minor) and independent factors, such as
using the software called the SPSS (Statistical Packages for nature of road crash, causes of road crash, road feature, road
Social Studies). The R2 value of the developed model was condition, intersection type, weather condition. All these
found to be 0.537 (Nagelkerke), 0.518 (Macfadden) and independent variables are also discrete in nature as discussed
0.074 (Cox and Snell) indicate that the developed model in the previous section. The easiest and most widely used
can be used to predict with reasonable degree of accuracy. discrete choice model for Modeling road crash severity is
The prediction accuracy of the calibrated sample is given Multinomial Logit Model (MNL). Its popularity is due to
in Table 2. From this table, it can be observed that overall
the fact that the formula for the choice probabilities takes a
prediction accuracy is about 98.9 per cent which implies that
closed form and is readily interpretable. The basic limitation
the model is able to predict the road crash occurrence with
a reasonable degree of accuracy. The parameter coefficients of the MNL model is that it has the property termed as the
obtained from the calibration process were then used for independence from irrelevant alternatives (IIA). The IIA
validating the model and during the validation process; the property implies that the relative probability of choosing
remaining 30 per cent data has been used. The prediction between any two alternatives is independent of all other
accuracy table of the validated sample is shown in Table 3. A alternatives. Correlation among unobserved factors across
close look at the above table shows that the validated sample alternatives makes the MNL model ineffective under these
has an overall prediction accuracy of 98.6 per cent. conditions. In addition, the MNL model does not account
for the ordinal nature of discrete data and thus the ordering
Table 2 Prediction Accuracy of Binary Logit Model
information for road crash severity (ranked for e.g. fatal,
during Calibration
grievous, minor) is lost.
Predicted Samples
The MNL model for road crash severity prediction has
Probability 0 1 Per centage been modeled using SPSS software as was done in road
Accuracy crash occurrence prediction model. As done in the case
0 57906 93 99.80 per of road crash occurrence prediction model, the road crash
Observed cent severity prediction model was also calibrated by considering
Samples 1 568 268 32.10 per 70 per cent of the dataset and the remaining 30 per cent
cent of the data was used for validation purpose. The statistical
Overall Per 99.40 per 0.60 per 98.90 per output generated from the MNL model by using SPSS is
centage cent cent cent presented in Tables 4 and 5.
Table 4 Multinomial Logit Model Output for Road crash The probabilities were then used to estimate the accuracy of
Severity Prediction the model in terms of road crash severity for the validation
Model Fitting sample. The relationship of individual variables with the
Likelihood Ratio Tests dependent variable is highlighted in Table 6.
Model Criteria
Table 6 Likelihood Ratio Tests for Multinomial
-2 Log Likelihood Chi-Square df Sig.
Logit Model
Intercept
1.709E3 Model Fitting
Only Likelihood Ratio Tests
Criteria
Final 1.552E3 157.146 52 .000 -2 Log
Effect
Likelihood Chi-
df Sig.
of Reduced Square
Table 5 Multinomial Logit Model Output of Goodness of fit for
Model
Road Crash Severity Prediction Intercept 1.552E3 .000 0 .
Chi-Square df Sig time 1.567E3 15.668 8 .047
Nature of acc 1.573E3 21.397 8 .006
Pearson 985.003 864 .003
causes 1.597E3 45.706 6 .000
Deviance 985.407 864 .002 Road feature 1.565E3 13.933 6 .030
From Table 4, it can be inferred that the presence of a Road condition 1.573E3 21.232 6 .002
relationship between the dependent and independent variables intersection 1.567E3 15.232 12 .229
weather 1.572E3 20.249 6 .003
exists. The significance value for the model is 0.000 which is
less than 0.05 indicating that the null hypothesis which states The statistical significance of the relationship between the
that there is no difference between the model having the set of independent variables and the dependent variable is based
independent variables and the model having no independent on the statistical significance of the chi-square statistic in the
variable is rejected. The existence of a relationship between likelihood ratio test. The probability of chi square statistic for
the independent variable and the dependent variable is hence the independent variable time was 0.047 which is lesser than
established. From Table 5, it can be concluded that goodness the level of significance of 0.05. Hence the null hypothesis
of fit of the model is reasonable as the significance values that all the ‘b’ coefficients associated with the independent
of Pearson and Deviance are lesser than 0.05 indicating that variable ‘time’ is equal to zero is rejected. The existence of a
the proposed model fits the present data set with reasonable relationship between the independent variable ‘time’ and the
degree of accuracy. The reference category for calibration was dependent variable ‘severity of road crash’ was established.
chosen to be ‘minor injuries’ as they form the largest category Similarly the probability of chi square statistic for the
amongst Road Crash severity. The “estimated parameters” independent variables “nature of road crash”, “causes”,
are the log odds used to predict the dependent variable. The “road feature”, “road condition”, and “weather” are lesser
parameter estimates associated with the explanatory variables than the level of significance of 0.05. From this it can be
are the estimators of the change in Logit model for unit change inferred that the null hypothesis that all the ‘b’ coefficients
in the dependent variable. The log of odds of various groups associated with these independent variables are equal to zero
was calculated as follows: gets rejected. The existence of a relationship between these
Zik =bko + bk1xi1 + bk2xi2 + ...+ bkpxip equn. 3 independent variables and the dependent variable of road
crash severity was thus proven. However, the probability of
Where, chi square statistic for the independent variable “intersection
xij - is the jth predictor for ith case type” is more than the level of significance. Hence the
model indicates that either this independent variable should
bkj - is the jth coefficient for the kth unobserved variable
be rejected or else should be refined to be included in the
p - is the number of predictors model. The significance of the independent variables can
also be tested by comparing the difference in -2LL of the
e
Zik overall model with the reduced model. This difference
πik =
e
Zi1 +eZi2 +eZik equn. 4 is assessed by the chi square value, that is, for significant
Where, variables the larger the chi square values, the greater is the
loss to the model fit if that parameter is dropped. Based on
πik – is the probability the ith case falls in category k
the developed model, prediction table (as shown in Table
Zik – is the value of kth unobserved continuous variable for 7) has been formulated based on the parameter estimates
the ith case derived from the calibration sample.
Table 7 Level of Road Crash Severity Prediction during their thanks to all the team members of the study in C.R.R.I
Calibration including Shri Sher Singh, Shri, Rajan Verma and Shri S.K.
Predicted Samples Ummat.
Severity Fatal Grievous Minor Per centage REFERENCES
Accuracy 1. Geedipally.R.S, Patil.S & Lord D, Examining Methods for
Fatal 10 23 298 3.0 per cent Estimating Crash Counts According to Their Collision Type, TRB
Observed
Grievous 1 94 554 14.5 per cent 89TH Annual Meeting, paper 10-2572, 2010.
Samples
Minor 6 63 1064 93.9 per cent 2. Holdridge.M.J, Shankar.N.V & Ulfarsson.F.G,(2005) The Crash
Overall Per 0.8 per 8.5 per 90.7 per 53.3 per cent Severity Impacts of Fixed Roadside Objects, Journal of Safety
centage cent cent cent Research Vol 36, 139-147.
3. Jonsson.T, Ivan.N.J & Zhang.C (2007), Crash Prediction Models
From Table 7, it can be noted that an overall prediction for Intersections on Rural Multilane Highway, Transportation
accuracy of 55.3per cent with 3per cent prediction accuracy Research Record: Journal of the Transportation Research Board
for fatal road crashes, 14.5per cent prediction accuracy for Vol 2019, 91-98.
grievous road crashes and 93.9per cent prediction accuracy 4. Khorashadi.A, Niemeier.D, Shankar.V & Mannering.F,(2005)
for minor injuries. The remaining 30per cent of the dataset was Differences in Rural and Urban Driver-Injury Severities Involving
Large Trucks : An explanatory Analysis. Journal of Accident
used for validation. The validation was done with coefficients Analysis and Prevention Vol 37, 910-921.
obtained by the parameter estimated. The probabilities were 5. Lee.J and Mannering.F (2002) Impact of Roadside Features on
then used to estimate the accuracy of the model in terms of the Frequency and Severity of Run-Off-Roadway Accidents: An
road crash severity for the validation sample. The prediction Empirical Analysis, Journal of Accident Analysis and Prevention
Vol 34, 149-161.
table for the validated sample is presented in Table 8.
6. Leveson.N (2004) A New Accident Model for Engineering Safer
Table 8 Level of Road Crash Severity Prediction Systems, Safety Science, Vol.42, No.4, 237-270.
during Validation
7. Malyshkina.V.N, Mannering. L.F, (2008), Markov Switching
Predicted Samples Multinomial Logit Model: An Application to Accident Injury
Severity Fatal Grievous Minor Per centage Severities, Accident Analysis and Prevention.
Accuracy 8. Padma, S., Velmurugan, S., Errampalli, M. and Shukla, A. 2010.
Fatal 7 56 56 5.9 per cent Modeling Accident Severity Using Multinomial Logit Model.
Observed Proc. International Conference on Infrastructure, Sustainable
Grievous 3 111 179 37.9 per cent
Samples Transportation and Urban Planning, CISTUP@CiSTUP 2010,
Minor 10 214 268 54.5 per cent IISc, Bangalore.
Overall Per 0.8 per 8.5 per 90.7per 42.7 per cent 9. Padma, S., Errampalli, M., Shah, P. M., Shukla, A. and
centage cent cent cent Gangopadhyay, S., 2011. A Study of Road Crashes Along the High
From Table 8, it can be seen that an overall prediction Speed Corridors of India. Journal of Road Transport, Vol. 3, IRT,
Chennai, 1-14.
accuracy of 42.7 per cent with 5.9 per cent prediction
10. Park.J, On.C, (2009) Relating Freeway Traffic Accidents to
accuracy for fatal, 37.9 per cent prediction accuracy for
Inductive Loop Detector Data Using Logistic Regression, 4th
grievous and 54.5 per cent prediction accuracy for minor IRTAD Conference, Seoul, Korea. 223-231.
injuries. Though the overall prediction accuracy is about 11. Pai.W.C, Saleh.W, (2008), Modeling Motorcyclist Injury Severity
43 per cent, the fatal road crash prediction rate is very less Resulting from Sideswipe Collisions at T Junctions in United
which is about 6per cent. From all these calibration and Kingdom: New insights into effect of Maneuvers, International
validation results, it can be concluded that the developed Journal Of Crash Worthiness, Vol13, No 1, 89-98.
model would be able to predict the minor road crashes with 12. Shankar.V, Mannering.F and Barfield.W (1995) Effect of Roadway
quite reasonable accuracy, but the fatal road crash prediction Geometrics and Environmental Factors on Rural Freeway Accident
Frequencies. Journal of Accident Analysis and Prevention Vol27-
rate is quite poor. It is recommended from the results of the No.3, 371-389.
study that the improvement in the model can be done by
13. Shaw-Pin Miaou (1994) The Relationship between Truck
considering other soft computing tools like fuzzy logic for Accidents and Geometric Design of Road Sections. Journal of
modeling the road crash severity. Accident Analysis and Prevention Vol 26, 471-489.
ACKNOWLEDGEMENTS 14. Wang.X, Kockelman.M.K, Occupant Injury Severity using a
Heteroscedastic Ordered Logit Model: Distinguishing the Effects
The authors are grateful to the Director, Central Road of Vehicle Weight and Type, Transport Research Record: Journal
Research Institute (C.R.R.I.), New Delhi-110020 for kindly of Transport Research Board, Vol 1908, 2005, 195-204.
giving permission to publish the Paper from the studies 15. Zang.H, PhD Dissertation, Identifying and Quantifying Factors
carried out by this institute. They also would like to extend Affecting Traffic Crash Severity in Louisiana, May 2010.
ABSTRACT
Design of traffic signal coordination in the conventional method makes use of only traffic related parameters. A design
procedure which can incorporate user perception also in addition to traffic related parameters can lead to a better design. In
this study an attempt was made to design two phase coordinated traffic signal incorporating quantitative as well as qualitative
parameters using fuzzy logic approach. Fuzzy rules were formulated by relating the important quantitative parameters
like average stream speed, volume to capacity ratio and average control delay and quality of progression was taken as the
qualitative parameter. The design procedure was implemented on a real corridor consisting of three intersections. Measures
of effectiveness such as band width, efficiency, attainability, average control delay per vehicle per cycle length were used to
determine the efficacy of the design procedure. It gave an efficiency of 64 per cent and an attainability of 92 per cent while
improving the average stream speed from existing 14 kph to 32 kph. The average control delay per vehicle per cycle length
on major stream was reduced by 69 per cent and on the minor stream was reduced by 70 per cent.
The views expressed in the Paper are personal views of the author. For any quary, the author may be contacted at e-mail
* Assistant Professor, Department of Civil Engineering, College of Engineering Trivandrum, Thiruvananthapuram 695016, INDIA.
Email:ashu.cet@gmail.com
** Ex-Post Graduate Student, Department of Civil Engineering, College of Engineering Trivandrum, Thiruvananthapuram 695016, INDIA
in his study has presented a distributed approach to traffic and per centage of stopped vehicles, etc. Solving such an
signal control, where the signal timing parameters at a given optimization problem mathematically will be difficult. Fuzzy
intersection were adjusted as functions of the local traffic control has proved to be successful in problem areas where
condition and of the signal timing parameters at adjacent exact mathematical modeling is difficult or impossible. Thus,
intersections. A set of 40 fuzzy decision rules were used traffic signal control is a suitable task for fuzzy control.
for adjusting the signal timing parameters. Chand and Chui
(1993) presented an approach to self-organizing traffic signal 3 DESCRIPTION OF STUDY STRETCH
control based on a fully distributed system of cooperative In the present study, a corridor along National Highway-
local controllers. This fully distributed architecture provided 47 passing through Thiruvananthapuram city (in the
for a fault-tolerant, responsive traffic control system, while southern part of India), with three isolated intersections was
the underlying fuzzy rule-based algorithm provides for a selected. Fig. 1 gives the schematic sketch of the selected
flexible and easily extensible control law. Niittymäki and corridor along with the traffic volume. The major road is
Pursula (1998) also studied the application of fuzzy control in 4-lane divided carriageway and minor legs are single lane
traffic signal control. They conducted a theoretical analysis of approaches. The major stream through traffic (one direction)
fuzzy traffic signal control and fuzzy rules were generalized during the morning peak was observed in the range of 720
using linguistic variables. The study validated fuzzy control
principles and membership functions were also calibrated
and a fuzzy adaptive signal controller was developed. Their
study revealed that the incorporation of fuzzy parameters to
traffic control problems enlarges usefulness of the approach
and makes it possible to implement the results in an adaptive
traffic control. Niittymäki and Turunen (2003) used the
principles of fuzzy logic in traffic signal control and found
it to be superior in complex transportation problems with
multi objective decisions.
vph-900 vph, while the minor stream traffic ( straight and preferences and/or experience. The triangular membership
right turn) was 350 vph, 400 vph and 200 vph at intersections function is the most frequently used function and the most
1, 2 and 3 respectively. The range of traffic composition on practical one. In this study triangular membership functions
the corridor was observed as buses 6per cent -10per cent, were used for all parameters because of its simplicity.
two wheelers 50 per cent - 55per cent, cars 20per cent - 23 Linguistic expressions, like, low, medium, high, very high
per cent and motorized three wheelers 10 per cent - 15 per were used for quantitative input parameters like, average
cent. All the intersections at present are controlled by fixed stream speed and volume to capacity ratio and terms like,
time signal. It was observed that the signals were switched poor, unfavourable, random arrival, favourable, highly
off during the peak hours and the entire traffic was controlled favourable and excellent were used for expressing quality
manually. These points to the inefficiency of the signals of progression. Delay which is taken as the output parameter
was expressed in terms of low, medium, high. Ranges of
installed there in handling peak demand. The existing time-
quantitative parameters (delay and average stream speed) as
space diagram is shown in Fig. 2. The bandwidth is about 11
well as the qualitative parameter needed for developing fuzzy
s towards south and 15 s towards north, which is very less.
rules were determined on the basis of a questionnaire survey
The average control delay experienced by a through vehicle
conducted from among the users of the selected corridor. 150
along this corridor was found to be in the range of 20 -25 users of the selected corridor were interviewed. Through the
seconds. The average stream speed along this corridor is as questionnaire survey, users’ response regarding the delay he/
low as 14 kph and the variation in speed of different types of she experiences at present while traveling through the study
vehicles is about 10 per cent to 15 per cent. stretch, the acceptable delay, acceptable average stream
speed and acceptable quality of progression were obtained.
These responses were to be related to the traffic volume
during his/her period of travel, so that the volume to capacity
value corresponding to his/her time of travel was obtained.
For this hourly traffic volume was collected from 7 am to
6 pm on a typical working day and based on the time of
travel (which is recorded in the questionnaire) the responses
of the user regarding delay experienced and acceptable,
average stream speed and acceptable quality of progression
were linked to the actual traffic volume (vph) and thus the
Fig. 2 Existing time-space diagram corresponding volume to capacity ratio. An expert opinion
survey was conducted for fixing the ranges of member ship
4 DESIGN OF TRAFFIC SIGNAL function for volume to capacity. As per IRC: SP:41-1994,
COORDINATION USING FUZZY LOGIC intersection capacity should be equal to the capacity of the
APPROACH approach roads. In the present study the major road approach
In this study an attempt was made to develop fuzzy rules is 4 lane divided arterial road. The value of capacity was
to effectively design a two traffic signal coordination taken as 2600 pcu /hr/ direction as per IRC: 106-1990. The
acceptable average speed and average delay obtained from
incorporating both quantitative and qualitative parameters.
questionnaire survey are shown in Fig. 3 and 4 respectively.
Quantitative parameters considered were volume to capacity
It shows that majority of the users of the corridor preferred
ratio, average stream speed and delay. The qualitative
an average speed in the range of 35 kph to 45 kph and an
parameter considered was quality of progression. Volume
average delay of 15 s/ veh / cycle length to 30 s/ veh / cycle
to capacity ratio, average stream speed and quality of
length. Fig. 5, 6 and 7 show the membership functions
progression were the input parameters and delay was taken
selected for the quantitative parameters.
as the output parameter.
equn. 1
where,
Fig. 4 Acceptable delay preferred by the users
RP = platoon ratio
The qualitative parameter, quality of progression was taken preferred that about 60 per cent -85 per cent of the total
as an indication of the proportion of the total traffic (P ) that approaching traffic should be able to effectively utilize green
can effectively utilize green time and move without delay and clear the corridor without delay. A rough estimate of g/C is
through the corridor. The value of this parameter ( P) was also required initially to estimate the value of RP In the present study
a C of 65 s and of g 45 s as obtained for the same corridor in a preferred by majority of the users, the score given to each of
separate study done by the authors (Manjusha and Ashalatha, the levels expressed as linguistic variables (out of 12) was
2008) was used. Using the average value of P preferred by also averaged out. The average values are given in Table 2.
majority of users and a C value of 65 s and g value of 45 s,
Table 1 Preferred order and scores assigned
the preferred platoon ratio RP was found out as per equation
(1). The preferred value of P as revealed by the questionnaire Parameters Score ( out of 12)
Average stream speed 12
survey was later used as one of the input parameters to the
rule base viewer in MATLAB 7.0.1 version. Acceptable delay 11
Quality of progression 8
4.2 Formulation of Fuzzy Rules Using Scoring Volume to capacity ratio 6
Technique
Table 2 Score for the linguistic variable for each
Fuzzy rules, which describe relationships in a linguistic parameter
sense, are written as antecedent consequent pairs of IF-
Factor/ weight Term Score
THEN statements. Once the ranges of quantitative as well Average stream Low 3
as qualitative parameters were determined, fuzzy rules were Medium 6
speed ( 12/12)
formulated using scoring technique. For this a survey of the High 9
users’ of the corridor was required. 150 users’ of the corridor Very High 12
were surveyed. Care was taken to ensure that those who were Delay ( 11 /12) Low 12
Medium 6
surveyed were frequent travellers through the selected corridor High 0
and could understand the functioning of signal coordination Volume to capacity Low 12
when briefed upon. The survey was conducted in two stages; ratio ( 6 /12) Medium 9
the score stage and numeric level indication stage. The factors High 6
Very High 3
considered under score stage were volume to capacity ratio, Quality of progres- Poor 0
average stream speed, quality of progression and delay. In the Unfavorable 2
sion ( 8 / 12)
score stage participants were asked to assign scores to (rate) Random 4
the various factors in the questionnaire. The factor score Favourable 6
Highly favourable 8
(out of 12) represents the degree to which the participants Excellent 12
rate the important quantitative and qualitative parameters
which is needed for designing the signal coordination. In the Based on the priority preferred by majority of the users and
numeric level identification stage, each participant was asked scores obtained for each parameter as well for each linguistic
to indicate an average value for each of the levels (expressed variable, the fuzzy rules were formulated.
as linguistic variables) mentioned under each parameter. A sample rule formulation is given below.
Modeling of fuzzy rule base adopted in the present study is
based on the assumption that the linguistic variable for the If the average stream speed is “high”, volume to capacity
output parameter, delay can be determined from the sum of is “low” and quality of progression is “random”, then the
the products of the attribute scores and the perceived level linguistic variable to be assigned to delay can be worked out
scores of the input parameters. Formulation of fuzzy rules as follows (using the values from Table 1 and Table 2).
using scoring technique is explained here with the help of an
illustration. Score obtained for average stream speed = 12/12
Score obtained for “high” average stream speed = (12/12) *9
In the questionnaire survey each user was asked to prioritize
the parameters of traffic signal coordination. Out of the Score obtained for volume to capacity ratio = 6/12
various combinations of the orders of priorities obtained from Score obtained for “low” volume to capacity = (6/12)*12
the survey, the one which was preferred by the maximum Score obtained for quality of progression = 8/12
number of users was selected. As per the present study the
Score obtained for “random” quality of
combination - average stream speed, acceptable delay, quality
of progression and volume to capacity (in the decreasing progression = (8/12) *4
order of priority) was preferred by majority of the users. The Score obtained for delay = (12/12)* 9 + (6/12)*
scores (out of 12) for the corresponding parameter were also 12 + (8/12)* 4 = 17
assigned by the user. The average value of scores for each This value is greater than 12; hence for this combination
of these parameters was then found out. The average values of input parameters, the linguistic variable for the output
are given in Table 1. For the combination of the parameters parameter delay is “low” (as per Table 3).
Using this scoring technique 96 fuzzy rules were formulated the range of 720 vph to 1080 vph this range was adopted
with various combinations of the parameters. The rules were for comparison. The various measures of effectiveness like
cross checked using neuro fuzzy technique. bandwidth, efficiency and attainability were determined for
Fuzzy logic is a rule based system. The input to the fuzzy this range. Table 4 gives the design parameters as well as
system is a scalar value that is fuzzified. The set of rules the measures of effectiveness obtained for a through traffic
is applied to the fuzzified input. The output of each rule is volume of 720-1080 vph.
fuzzy. These fuzzy outputs need to be converted into a scalar Table 3 Details of traffic signal coordination at different
quantity so that the nature of the action to be performed can flow values
be determined by the system. This process of converting a
fuzzy output into a scalar quantity is called defuzzification. Sl. Flow values Cycle Offset Speed Efficiency Attainability
There are many defuzzification techniques available. Centriod No. (vph) lengths (s) (s) (kph) (per cent) (per cent)
1 <360 70 22 35-40 66 94
defuzzification technique was used in the present study. 2 360 - 720 75 22 35-40 65 94
3 720 - 1080 80 24 30-35 64 92
4.3 Selection of Common Cycle Length 4 1080 - 1440 85 30 30-35 62 91
To determine the common cycle length to be adopted for 5 1440 - 1800 90 34 20-25 60 86
6 1800 -2400 90 40 20-25 60 86
coordination the following procedure was adopted. For
a given value of volume to capacity ratio and quality of Table 4 Design parameters and measures of effectiveness
progression as preferred by the maximum number of users Cycle Offset (s) Average v/c ratio at Bandwidth Efficiency Attainability
length (s) stream Intersection (s) (%) (%)
(60per cent - 85per cent), in the fuzzy logic tool box the speed No.
average stream speed was varied within the logical limits (kph)
I II III
(25 kph-35 kph) till a minimum delay was obtained. An
80 24 30-35 0.34 0.38 0.37 51 64 92
interface was developed between fuzzy logic tool box and
the MATLAB program which calculated the cycle length
Fig. 11 shows the time-space diagram obtained using fuzzy
as per Webster’s delay model (Webster, 1961). The cycle
logic approach for a through traffic volume in the range of
length was determined using the MATLAB program based
720 vph/hr-1080 vph/hr. Field control delay during the peak
on the minimum delay obtained through the fuzzy logic
hour was determined using HCM (2000) procedure. This
rule viewer. Once the cycle length was obtained, the green
is compared with the average control delay obtained for a
time was apportioned among the two phases based on the
through traffic range of 720 vph/hr-1080 vph/hr when signals
ratio of approach flow to saturation flow. Saturation flow
rate was determined using U.K. method. Fig. 10 shows the are coordinated using fuzzy logic approach. A comparison
procedure adopted for designing a two phase traffic signal of the delay values is given in Table 5.
co-ordination using fuzzy logic. Table 5 Comparison of average control delay
Condition un- Average control delay to (s/veh/cycle length)
der which delay Major traffic flow Minor traffic flow
is determined Intersection Intersection
1 2 3 1 2 3
Existing condi-
16 22 20 27 29 26
tion
After design us-
6 6 10 8
ing fuzzy logic
6 RESULTS AND DISCUSSION Fuzzy logic can also take into consideration dynamic traffic
flow condition. According to the changing traffic flow, the
To ascertain whether the proposed methodology of traffic cycle length can be varied. In order to implement this fuzzy
signal coordination is efficient various measures of system in field, fuzzy controller unit together with a system
of sensors are required. The sensors should be installed at Engineering, Thiruvananthapuram, Kerala, India, 259-262.
appropriate locations so that the approaching traffic can be 8. Matlab 7 (2004), “Getting Started Guide.” The MathWorks, Inc.
sensed and based on the software designed the cycle length 9. Niittymäki, J. and Pursula, M. (1998), “Signal Control Using
and phasing can be displayed. Electronic speed display Fuzzy Logic.” Transportation Research, 116 B (19), 11-22.
units should be provided indicating the speed at which 10. Niittymäki J. and Turunen E. (2003), “Traffic Signal Control
vehicles should traverse the section to utilize the benefits of on Similarity Logic Reasoning.” Fuzzy Sets and Systems 133,
coordination. 109-131.
11. Pappis, C. P. and Mamdani, E. H. (1977), “A Fuzzy Logic
Thus the present study gives a new approach towards signal Controller for a Traffic Junction.” IEEE Transactions on Systems,
coordination where by both traffic as well as users’ demand Man Cybernetics, SMC-7 (10), 707-717.
and preferences can also be incorporated in the design. 12. Singh, I. and Morgan, D. J. (2003), “Importance of Offset in Signal
Coordination.” Indian Highways, 31(12), 7-52.
REFERENCES 13. Suhas, B. K. (2005), “Time and Space Allocation to Maximize
Heterogeneous Traffic Flow Through Signalized Intersections.”
1. Chui, S. (1992), “Adaptive Traffic Signal Control Using Fuzzy
Unpublished, M.Tech. Thesis, Indian Institute of Technology
Logic.”
Madras, Chennai, India.
2. Intelligent Vehicles Symposium, Proceedings of the IEEE
14. Sunkari, S. R., Engelbrecht, R. J. and Balke, K.N. (2004),
Intelligent Vehicle Symposium, 98-107.
“Evaluation of Advance Coordination Features in Traffic Signal
3. Chui, S. and Chand, S. (1993), “Self Organizing Traffic Control Controllers.” Project Report of Texas Transportation Institute, The
Via Fuzzy Logic.” Decision and Control, Proceedings of the 32nd Texas A&M University System, Texas.
IEEE Conference, 2, 1897-1902.
15. Todd, K. (1988), “Effect of Arterial Platoon Progression on
4. HCM (2000), “Highway Capacity Manual.” SR 209, Transportation Capacity.” Traffic Engineering + Control, 29 (9), 468-475.
Research Board, National Research Council, Washington D.C.
16. Tian, Z. and Urbanik, T. (2007), “System Partition Technique to
5. Indian Roads Congress, (1994), “Guidelines for the Design of at Improve Signal Coordination and Traffic Progression.” Journal of
Grade Intersections in Rural Area and Urban Areas”. IRC SP 41, Transportation Engineering, ASCE 133(2), 119-128.
New- Delhi.
17. Webster, F. W. (1961), “Traffic Signal Settings.” Dept. of Scientific
6. Indian Roads Congress, (1990), “Guidelines for Capacity of Urban and Industrial Research, Road Research Laboratory, Road
Roads in Plain Areas”. IRC: 106, New- Delhi. Research Technical Paper No. 39, H.M.S.O., London.
7. Manjusha, M. and Ashalatha, R. (2008), “Design of Traffic Signal 18. McShane, W.R., Roess, R. P. and Prassas, E.S. (1990), “Traffic
Using Modified Conventional Method.” Proceedings of the Engineering.” Prentice- Hall Publications, New Jersey, Second
Ninth National Conference on Technological Trends, College of Edition, USA.