Académique Documents
Professionnel Documents
Culture Documents
Dohn Kissinger
PMP, PMI-SP, MCTS, MCITP
Profit Solutions
Critical Path
Phase Actuals
(weeks)
Project definition
System analysis
System design
System construction
System installation __
Project definition
System analysis
System design
System construction
System implementation
Project buffer
0 10 20 30 40 50
Time (weeks)
© Copyright 2010 Profit Solutions (800) 9-PROFIT Page 12
What if we have resource contention?
Critical Path
Task C
Project 3
3 days
Task C
A B C A B C A B C
Project 3
1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day
3 days
Task C
A B C A B C A B C
Project 3
1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day
3 days
Becomes Plan Analysis Design Build & Test Deploy Project Buffer
this
this
Pacing/drum resource
rdkissinger@att.net
(916) 939-3801
(800) 9-PROFIT
© Copyright 2010 Profit Solutions (800) 9-PROFIT Page 24