Académique Documents
Professionnel Documents
Culture Documents
Prepared by CHICO
Table of Contents
I. Introduction ................................................................................................................................... 3
II. Methodology............................................................................................................................... 3
III. Collection and analysis of data ...................................................................................................... 4
III.1 Catchment description ............................................................................................................. 4
III.2. Demarcation of Catchment area ............................................................................................ 5
III.3. Choice of return period ........................................................................................................... 6
IV. Hydrological components ............................................................................................................... 7
Rainfall data ................................................................................................................................... 7
Land use ......................................................................................................................................... 8
V. Calculations of peak discharge ..................................................................................................... 8
V.1. Time of concentration ............................................................................................................... 9
V.2. Runoff coefficient..................................................................................................................... 10
V.3. Calculation of Intensity ........................................................................................................... 10
V.4. Estimation of peak discharge for different return periods .................................................. 11
VI. Hydraulic study ....................................................................................................................... 13
VI.1. Calculation of hydraulic parameters.................................................................................... 13
VI.2. Bridge design .......................................................................................................................... 13
VI.3. Protection ................................................................................................................................ 20
VII. Findings after conducting verification study ........................................................................ 21
APPENDIXES ..................................................................................................................................... 22
i
Hydrological Study of Construction project of Road RUKOMO-BASE |
ii
Hydrological Study of Construction project of Road RUKOMO-BASE |
I. Introduction
The strategy of the Ministry of Infrastructure is supporting the overall objectives of Vision 2020
by putting the action on the upgrading of transport infrastructure, particularly roads, by
programming a number of rehabilitation actions, modernization and maintenance. In this
context, the proposed development of the road Rukomo-Base is part of the Government of
Rwanda's policy of improving the transport offer to promote integration areas in the national
economic space and boost trade inter-regions, retained ultimate objective being the increase in
income of the population, combating and reducing poverty and improving living conditions.
The project of construction of road Rukomo-Base have been subjected to the preliminary study
done in 2010. Actually, the project is in progress, and the data which are being used are from
that study. It is in this regard that the verification study has been proposed in order to increase
the accuracy in designing and installation of hydraulic structure.
The objective consists essentially in the elaboration of the hydrological and hydraulic studies
of road BASE-RUKOMO within the framework of verification of the previous technical study
in particular for the two bridges located at Pk 34+386 and Pk 37+193 respectively.
II. Methodology
The basic sequence for the hydraulic analysis of a bridge consists mainly of the following:
Determine watershed hydrology
Visit the site and obtain flood history from bridge inspection files, and local residents.
Investigate upstream and downstream for conditions affecting stream stability such as
significant hydraulic features.
Complete a water surface profile analysis through the bridge reach. This analysis should
include the analysis of the natural situation without any bridge and an analysis of the
existing floodplain situation.
Bridge opening should be analyzed and then compared with the existing and natural
conditions to choose the optimum bridge channel width for the design flow.
The adopted methodological approach articulates around the activities enumerated below:
1. Inventory and bibliographical research with the various ministerial departments and non-
state board concerning the domain of the evaluation or the use of water resources.
2. Collection of Data and information
3. Identification of the current situation of the area
3
Hydrological Study of Construction project of Road RUKOMO-BASE |
4. Identification of the characteristic parameters of the water regime of the catchment area of
every sector based on the hydro-climatic data as well as the existing historic information.
5. Calculation of the peak discharge
6. Hydraulic analysis of the natural situation, Hydraulic analysis of the existing bridge, and
hydraulic analysis of the proposed bridge
7. Elaboration and presentation of the report.
4
Hydrological Study of Construction project of Road RUKOMO-BASE |
5
Hydrological Study of Construction project of Road RUKOMO-BASE |
The whole of catchment area concerning with the construction project of the road BASE-
RUKOMO has the varied slopes. This card rich in topographic information with recognitions
on land as visualized by Google Earth and by the available various cartographic documents
permits to really delimit the pouring basins of dependence of the road networks to study as well
as their physiographic parameters (surface of the basin, length of the-cut-offs, slope, etc.) in
particular the catchment areas concerned with two bridges.
6
Hydrological Study of Construction project of Road RUKOMO-BASE |
The collected data are the daily and monthly data. This hydrological study is interested with the
annual maximum daily rainfall which is used to determine the peak discharge for road
construction project, or flood control (or mitigation) projects. For this study, the rainfall data to
be used are the daily rainfall data provided by the Rwanda Meteorology Services for a period
of 35 years (from 1980 to 2015). So considering the location of the project, the data are from
the rain gauge stations installed in GICUMBI and RULINDO Districts.
The annual average rainfall is around 1400 mm and the maximum daily rainfall is 90.4 mm
which has been observed at MUGAMBAZI Station (see appendix A). Therefore, the maximum
daily rainfall observed at the nearest stations to the road construction project is 78,7 mm for 10
years. The extreme daily rainfall are used to assess the risk of extreme floods and for different
return periods.
The value of the daily rainfall data shows different frequencies such once every two years (1/2),
once every ten years (1/10), once every twenty years (1/20), once every fifty years (1/50) and
once every hundred years (1/100). According to the size of available data, the use of such data
requires the statistical analysis to identify the type of distribution. To do that some laws are
usually applied in particular:
Law of Gauss
Law of Dalton
Law of Weibull
Law of Gumbel
Law of Fuller
Therefore, the law of Gumbel (used for the extremes) adapts itself relatively well to this
adjustment of these annual maximum daily rainfall as indicates the previous studies.
7
Hydrological Study of Construction project of Road RUKOMO-BASE |
Land use
From the cartographical document and GIS data, and descent on ground, the majority of land
is covered by the forestry and plant. The river concerned with the bridges is surrounded with
tea plantation.
The primary purposes of road drainage systems are to minimise water depths occurring on road
surfaces during heavy storms and to prevent seepage causing damage to the pavement
construction. Since runoff occurs rapidly from roads, the most critical storm conditions for the
design of surface water drainage systems are normally associated with heavy rainfall events
typically lasting between 2 and 15 minutes (FHWA, 2005).
There exist different formulas to calculate or estimate the peak discharge; therefore the
appropriate formulas are Rational Method for the small basins (catchment areas less than 5
km²), and CIEH (Comité Interafricain d’Etudes Hydrauliques) method which is applicable for
the catchment areas less or equal to 2,500 km2 (250,000 ha) (Tirogo, 2008; Albergel et al.,
1991).
Rational method
𝑸 = 𝑲𝑪𝑰𝑨
8
Hydrological Study of Construction project of Road RUKOMO-BASE |
C: Runoff coefficient
I: Rainfall intensity in mm/hr depending on the time of concentration (tc) and return
period (T)
A: Catchment area in ha
CIEH Method
The CIEH formula used for central Africa (longitude > 10°) is as follows:
Where:
It is defined as the time from the beginning of runoff to the time at which the entire watershed
is contributing runoff that reaches the watershed outlet or “travel time from the hydraulically
most remote point in a watershed to the outlet”.
Considering that the almost catchment is in rural area, the time of concentration can be
calculated by PASSINI or Kirpich Formula:
PASSINI Formula:
𝒕𝒄 = 𝟎. 𝟏𝟒 × (𝑨 × 𝑳)𝟏⁄𝟑 × 𝑺−𝟎.𝟓
9
Hydrological Study of Construction project of Road RUKOMO-BASE |
S: slope (m/m)
Watershed runoff coefficients depend upon the land use, soil type and slope of the watershed.
Runoff coefficients are needed to calculate storm water runoff rate using the Rational Method.
Table 1: Runoff coefficient
For this study, the runoff coefficient has been estimated to be 0.25 due to the type of soil, slope
and crop.
Where I: rainfall intensity depending upon the time of concentration and return period
(mm/hr)
a and b Montana coefficients. a = 572.45 and b= 0.647 corresponding to the time of
concentration 2≤ t ≥ 15 min for a return period of 10 years.
10
Hydrological Study of Construction project of Road RUKOMO-BASE |
By using MONTANA’S formulas, rainfall intensities for different sub catchment areas as
enumerated before were calculated by using the Montana’s coefficients.
11
Hydrological Study of Construction project of Road RUKOMO-BASE |
The peak discharge was calculated for each catchment corresponding with each bridge.
Area
Length of Talweg
Intensity [I]
[S]
method_ Q10
Rational
Method Q10
CIEH
red
Q10_Conside
h
Pk [ha] [-] [m] [m/m] [min] [min] [mm/h] [m3/s] [m3/s] [m3/s] [m3/s] [m3/s] [m3/s]
34+860 13772.00 0.25 735.20 0.04 161.89 11 21 - 108.502 108.502 121.522 138.882 150.818
37+193 16268.00 0.25 1252.3 0.040 191.18 16 19 - 133.118 133.118 150.755 172.291 187.098
12
Hydrological Study of Construction project of Road RUKOMO-BASE |
The selection of the most appropriate and economical type of structure to use in a specific
situation will depend on the hydraulic parameters of the site.
Data collection is vital and requires the gathering of all necessary information for hydraulic
analysis. This should include such information as topography and other physical features, land
use and culture, any existing flood studies of the stream, historical flood data, basin
characteristics, precipitation data, geotechnical data, historical high-water marks, existing
structures, channel characteristics and environmental data (Zevenbergen, et al., 2012).
In general, given a particular design discharge at a given crossing, the shorter a bridge the more
backwater it will create. The smaller bridge will also have higher velocities through the bridge
13
Hydrological Study of Construction project of Road RUKOMO-BASE |
opening and an increased potential for scour at the bridge foundation. A longer bridge at this
same crossing will generate a smaller amount of backwater and will have lower velocities and
potential for scour. Policy considerations and economics require an understanding of the
impacts that the bridge could have on the flow of water in the floodplain and impacts it might
have on adjacent properties.
The bridge waterway width is directly associated with the bridge length, from abutment to
abutment. Hydraulic capacity should be a primary consideration in setting the bridge length.
This is verified by the Manning’s formula.
𝟐/𝟑
𝑸 = 𝑲 ∗ 𝑨𝒘 ∗ 𝑹𝒉 ∗ 𝑺𝟎.𝟓
Where Q: Discharge (m3/s),
K: roughness Coefficient
Aw: Wetted area, expressed in (m²),
Pw: Wetted perimiter (m)
Rh: hydraulic radius = Sw/Pw, exprimé en (m),
S: Slope of the natural flow, expressed in (m/m).
Freeboard
For a high debris stream: the freeboard should be of 4 feet or more
For low to moderate debris stream the freeboard is calculated as follow:
𝑭𝒓𝒆𝒆𝒃𝒐𝒂𝒓𝒅 = 𝟎. 𝟏𝑸𝟎.𝟑 + 𝟎. 𝟎𝟎𝟖 × 𝑽𝟐
Where: Q: design discharge
V: mean velocity of the design flow through the bridge.
The previous study has proposed two bridges with the following dimensions:
14
Hydrological Study of Construction project of Road RUKOMO-BASE |
River Return Min Ch W.S. Crit E.G. E.G. Vel Flow Top Froude
Reach Station period Q Total El Elev W.S. Elev Slope Chnl Area Width number
(m3/s) (m) (m) (m) (m) (m/m) (m/s) (m2) (m)
20 years 121.52 0.04 3.47 3.47 5.14 0.016763 5.71 21.38 6.5 1
Upstream 50 years 138.88 0.04 3.79 3.79 5.6 0.016827 5.96 23.42 6.5 1
100
years 150.82 0.04 3.99 3.99 5.91 0.016934 6.13 24.74 6.5 1
34+860
15
Hydrological Study of Construction project of Road RUKOMO-BASE |
The analysis from Table 4 showed that the maximum water depth is 3.99 m, and the velocity of 6.13 m/s which is largely above the maximum
recommended that is 4.91 m/s, hence the velocity is higher than the maximum required. Furthermore, during the interview with the local residents,
they said that during the heavy rainy season the flood overflows the existing bridge and some areas of tea plantation where the water depth
exceeds the height of tea plant. This led to verify the capacity of the proposed bridge design whether the peak discharge will be evacuated through
its opening.
River Return Min Ch W.S. Crit E.G. E.G. Vel Flow Top Froude
Reach Station period Q Total El Elev W.S. Elev Slope Chnl Area Width number
(m3/s) (m) (m) (m) (m) (m/m) (m/s) (m2) (m)
20 years 150.76 0.04 3.99 3.99 5.91 0.016929 6.13 24.74 6.5 1
Upstream 50 years 172.29 0.04 4.35 4.35 6.44 0.017133 6.41 27.05 6.5 1
100 years 187.1 0.04 4.58 4.58 6.8 0.017267 6.59 28.59 6.5 1
37+193
16
Hydrological Study of Construction project of Road RUKOMO-BASE |
The analysis of the table 5 showed that the velocity and water surface change according to the cross section. Therefore, the velocities for this reach
are higher than the recommended velocity.
Then, the verification of the preliminary design of two bridges was done. For this, the Manning’s formula was used to verify the capacity of bridges
(openings). The related results are depicted in Table 6.
17
Hydrological Study of Construction project of Road RUKOMO-BASE |
The analysis of Table 6 showed that by keeping the same dimensions of the preliminary study the velocity through the bridge are acceptable as
well as the maximum velocity recommended is 16 ft/s equivalent to 4.91 m/s in metric system, and minimum is 0.92 m/s (AASHTO, 1982).
Considering the freeboard, the maximum required total depth is 1.753 m. Hence, the proposed design size is largely enough may transport the
exceptional flow rate. The proposed bridge allows to overcome the flooding problems which blocks the traffic.
Therefore, a hydraulic modeling for bridge by using HEC-RAS was performed, and the related results are presented in table 7 and 8 for Pk 34+860
and Pk 37+193 respectively.
Table 8: Hydraulic modeling of Bridge 2 (20 x 2.5) located at Pk 34+860
River Return Min Ch W.S. Crit E.G. E.G. Vel Flow Top Froude
Reach Station period Q Total El Elev W.S. Elev Slope Chnl Area Width number
(m3/s) (m) (m) (m) (m) (m/m) (m/s) (m2) (m)
20 years 121.52 0.04 1.09 1.09 1.6 0.002291 3.18 38.2 37.4 1.01
Upstream 50 years 138.88 0.04 1.18 1.18 1.75 0.002239 3.33 41.76 37.4 1.01
100
years 150.82 0.04 1.25 1.25 1.84 0.002207 3.42 44.12 37.4 1.01
34+860
20 years 121.52 0 1.05 1.05 1.56 0.002293 3.18 38.19 37.4 1.01
Downstream 50 years 138.88 0 1.14 1.14 1.71 0.002237 3.33 41.77 37.4 1
100
years 150.82 0 1.21 1.21 1.8 0.002208 3.42 44.11 37.4 1.01
Considering to the results provided in table 7, it was noticed that the maximum water surface level is 1.25 m and the maximum velocity is 3.42 m/s
which are acceptable. The maximum water depth to evacuate the peak discharge for 100 years of return period is 1.8 m (including the freeboard).
Hence, the proposed opening is greatly enough.
18
Hydrological Study of Construction project of Road RUKOMO-BASE |
River Return Min Ch W.S. Crit E.G. E.G. Vel Flow Top Froude
Reach Station period Q Total El Elev W.S. Elev Slope Chnl Area Width number
(m3/s) (m) (m) (m) (m) (m/m) (m/s) (m2) (m)
20 years 150 0.04 1.24 1.24 1.83 0.002209 3.41 43.96 37.4 1.01
Upstream 50 years 172.29 0.04 1.35 1.35 2.01 0.002159 3.57 48.22 37.4 1
100
years 187.1 0.04 1.43 1.43 2.12 0.00213 3.67 50.94 37.4 1
34+386
20 years 150 0 1.2 1.2 1.79 0.00221 3.41 43.95 37.4 1.01
Downstream 50 years 172.29 0 1.32 1.32 1.97 0.002157 3.57 48.23 37.4 1
100
years 187.1 0 1.39 1.39 2.08 0.002131 3.67 50.93 37.4 1.01
The analysis of table 8, showed that the bridge with an opening of 2 (20 x 2.5) is greatly enough for different peak discharge in particular 20 years,
50 years, and 100 years, because the maximum total depth (water depth plus the freeboard) is 2.08 m.
19
Hydrological Study of Construction project of Road RUKOMO-BASE |
VI.3. Protection
The failure of many highway hydraulic structures can be traced to unchecked erosion. Erosive
forces which are at work in the natural drainage network are often increased by the construction
of a highway. Interception and concentration of overland flow and constriction of natural
waterways inevitably result in increased erosion potential.
Scour is the result of the erosive action of flowing water, excavating and carrying away material
from the bed and banks of streams. Different materials scour at different rates. Loose granular
soils are rapidly eroded by flowing water, while cohesive or cemented soils are more scour-
resistant. Under constant flow conditions, scour will reach maximum depth in sand- and gravel-
bed material in hours; cohesive bed material in days; glacial till, sandstones, and shale in
months; limestone in years, and dense granite in centuries. Under flow conditions typical of
actual bridge crossings, several floods may be needed to attain maximum scour.
A factor in scour at highway crossings and encroachments is whether it is clear-water or live-
bed scour. Clear-water scour occurs where there is no transport of bed material upstream of the
crossing or encroachment or the material being transported in the upstream reach is transported
through the downstream reach at less than the capacity of the flow.
20
Hydrological Study of Construction project of Road RUKOMO-BASE |
obstructions. Local scour can also be either clear-water or live-bed scour. Live-bed local scour
is cyclic in nature; that is, the scour hole that develops during the rising stage refills during the
falling stage.
Countermeasures of scour
There are a number of energy dissipator designs which utilize blocks, sills, or other roughness
elements to impose exaggerated resistance to flow. Roughness elements provide the designer
with a versatile tool in that they may be utilized in forcing and stabilizing the hydraulic jump
and shortening the hydraulic jump basin. A key parameter that determines the magnitude of
changes in water level and flow velocity around structures is the Froude number, F, which is
𝑽
defined as: 𝑭=
√𝒈×𝒅
Where: V: velocity
g: acceleration of gravitation (9.81 m/s2).
Steep channel flow, and flow through constrictions is often in a transitional flow state between
subcritical and supercritical. Experimental work conducted by the U.S. Army Corps of
Engineers (HEC14, 2006) indicates that this transition zone occurs between Froude numbers of
0.89 and 1.13. When flow conditions are within this range, an extremely unstable condition
exists in which the inertia and gravity forces are unbalanced. This causes excessive wave action,
hydraulic jumps, localized changes in water-surface slope, and extreme flow turbulence. Non-
uniform, unsteady, and near supercritical flow conditions create stresses on the channel
boundary that are significantly different from those induced by uniform, steady, subcritical
flow. These stresses are difficult to assess quantitatively.
The estimation of amount of local and total scour involves different parameters in particular the
slope of naturel streambed, the bed material size (particle size), and the eventual height between
invert bridge and the streambed.
21
Hydrological Study of Construction project of Road RUKOMO-BASE |
APPENDIXES
22