TCE.GP/9506A/130 0
CO C 27
January,2010
ISSUE
R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited
TCE.GP/9506A/130 0
CO C 27 CONTENTS
B4 TCE.GP/9506A/130 0 CO C 27 R0 MECHANICAL 1
REQUIREMENTS
(CHAPTER -9)
B5 SPEC NO: TCE.GP/9506A/130 0 R0 ELECTRICAL 2
CO C 27 REQUIREMETS (CHAPTER
-10)
B6 SPEC NO: TCE.GP/9506A/130 0 R0 INSTRUMENTATION AND 2
CO C 27 CONTROL DESIGN
REQUIREMENTS
(CHAPTER -11)
B7 SPEC NO: TCE.GP/9506A/130 0 R0 CIVIL REQUIREMENTS 2
CO C 27 (CHAPTER -12)
B8 SPEC NO: TCE.GP/9506A/130 0 R0 CODES AND STANDARDS 1
CO C 27 (CHAPTER -13)
B9 SPEC NO: TCE.GP/9506A/130 0 R0 DESIGN AND 2
CO C 27 CONSTRUCTION
REQUIREMENTS
(CHAPTER -14)
B10 SPEC NO: TCE.GP/9506A/130 0 R0 MISCELLANEOUS 1
CO C 27 SERVICES (CHAPTER -15)
ISSUE
R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited
TCE.GP/9506A/130 0
CO C 27 CONTENTS
1 TCE.9506A-130-GA-1154 P0 LAYOUT OF 1
AUGMENTAION OF BOD
PLANT
ISSUE
R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited
TCE.GP/9506A/130 0
CO C 27 CONTENTS
ISSUE
R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: A1
TCE.GP/9506A/130 0
CO C 27 INTRODUCTION Chapter 1
Sheet 1of 1
1.0 Introduction
The existing Biological Treatment plant had been commissioned in 1991-92 and
the design basis was treatment of the effluent generated from the existing by
product plant and the adjoining Benzol Plant. Later the Benzol Plant was taken
out from operation/dismantled. Currently the Biological Treatment Plant is taking
its load only from the existing By-product plant. The design capacity of the
existing Coke Oven ETP was 125 m3/hr.
Approximately 105 m3 / hr of effluent will be generated in the new BPP plant for
battery #10 & #11. To treat this additional effluent ,it is proposed to augment the
capacity of the existing BOD plant from 125 m3/hr to 230 m3/hr . The existing
plant area is approximately (L*B: 216m*63M).The augmentation of the existing
BOD plant is to be accommodated in the adjoining area. The quality of the
effluent will be almost same as the existing one. However the new plant effluents
have BOD Approx.2000 & COD approx.5000.It implies that for new BPP effluent
BOD goes down and COD goes high. Moreover it is desired that treated effluent
water quality released from coke oven effluent plant shall be colour-less. Existing
plant discharging the effluent has brown colour which shall not be allowable for
the new augmented plant.
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: A2
TCE.GP/9506A/130 0
CO C 27 SCOPE OF ENQUIRY Chapter 2
Sheet 1of 1
This specification shall form a part of tender documents and shall be read in
conjunction with the same. The Effluent Treatment Plant shall be complete in
all respects. Any equipment not covered in the specification but essential for
proper design and operation shall be included in the tender.
The Bidder shall study the specification and satisfy himself thoroughly
regarding the workability of the equipment and shall take full responsibility for
the guaranteed operation of the equipment regarding performance guarantee
of the equipment and smooth reliable working.
The entire scope of work shall be covered by bidder in accordance with the
schedule attached with this specification. The bidder shall take the above into
account and quote for his best and earliest delivery schedule.
ISSUE
R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: A3
TCE.GP/9506A/130 0
CO C 27 DEFINITION OF TERMS Chapter 3
Sheet 1of 5
3.1 “PURCHASER” shall mean the client Tata Steel Limited (TSL) on whose behalf
the enquiry is issued by the CONSULTANT and shall include his successors and
assigns, as well as his authorized officers/ representatives.
3.2 “OWNER” shall mean Tata Steel Limited (TSL) on whose work site / plant the
entire project will be executed.
3.4 “BIDDER” shall mean the firm / party who quotes against an enquiry.
3.7 “MANUFACTURER‟ refers to a person or firm who is the producer and furnisher
of material or designer and fabricator of equipment to either the OWNER /
PURCHASER or the VENDOR / CONTRACTOR or both under the “Contract”
3.8 “OTHERS” shall mean other successful BIDDERS whose Bids have been
accepted by the OWNER/PURCHASER and to whom the orders have been
placed by the OWNER/PURCHASER and shall include their heirs, legal
representatives, and successors and permitted assigns.
3.10 “PROJECT” shall mean the project specified in the “Project Information-
General”, Section -B of the “Specification”.
3.11 “Site” shall mean the actual place of the proposed “Project”as detailed in the
“Specification” or other place where work has to be executed under the Contract.
3.13 “Specification” shall mean collectively all the terms and stipulations contained in
those portions of the 'Contract‟ known as General Conditions, the Specifications
and such Amendments, Revisions, Deletions or Additions, as may be made in
the Agreement and all written Agreements made or to be made pertaining to the
method and manner of performing the work or to the quantities and qualities of
the materials to be furnished under this “Contract”.
3.14 “BID” shall mean the proposal / document that the BIDDER submits in response
to bid invitation by PURCHASER / CONSULTANT.
3.15 Plant and/or Equipment:- The terms “Plant/or Equipment” shall mean all plant,
machinery, equipment, utilities, services, facilities, building, structures, material,
store and other items of all kinds, requirement for work in accordance with the
contract/order as part of the project from commencement of work up to its final
acceptance by the purchaser.
3.16 Work:- The term “work” shall means all or any part of the material,equipments,
drawings, documents, supervision of erection, testing, start-up, commissioning
and performance tests or complete erection service and other services required
for the design, supply , execution, completion and guarantee of the work which
is either specifically required by the contract/ order or is required in connection
with such services and such material or which is within the scope of the contract/
order and not specifically exchanged by the contract/order from the materials
and services which the contractor in obliged to furnished under the contract/
order or implied from contract specification, drawing, documents and schedules,
here to annexed or incidental thereto.
3.17 “Contract” or “Purchase Order” shall mean the order and associated
specifications executed by the PURCHASER and the VENDOR including other
documents agreed between the parties or implied to form a part of the
“Contract”.
3.18 “Contract Price‟ shall mean, if there is a formal agreement, the prices referred to
in the agreement or if there is no formal agreement, the price agreed to be the
value of the “Contract”.
3.19 “Date of Contract” shall mean the calendar date on which the OWNER
/PURCHASER and VENDOR / CONTRACTOR / FABRICATOR have signed the
“Contract”. “Effective Date of Contract‟ shall mean the calendar date on which
the OWNER / PURCHASER have issued to the VENDOR the “Letter of Intent‟
or as otherwise mutually agreed to between the OWNER /PURCHASER and the
VENDOR.
3.20 “Contract Period” shall mean the period during which the “Contract” shall be
executed as agreed between “VENDOR/CONTRACTOR / FABRICATOR and
OWNER / PURCHASER”.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: A3
TCE.GP/9506A/130 0
CO C 27 DEFINITION OF TERMS Chapter 3
Sheet 3of 5
3.21 “Guarantee Period” shall mean the period during which the “Plant” or
“Equipment” shall give the same performance guarantee by the VENDOR in the
“Schedule of Guarantee” or as in the “Specification”.
3.23 “Writing” shall include any manuscript, typewritten or printed statement, under or
over signature and / or seal as the case may be.
3.24 “Notice in Writing” or “Written Notice” shall mean a notice in written, typed or
printed characters sent (unless delivered personally or otherwise proved to have
been received) by registered post or courier service to the last known private or
business address or registered office of the addressee and shall be deemed to
have been received when in the ordinary course of post it would have been
delivered.
3.30 “Trial Operation‟ shall mean the integrated operation of the plant system
/Equipment covered under the contract for a specified period at specified load
for proving trouble-free operation of the plant / system / Equipment covered
under the Contract.
3.31 “Performance Tests” shall mean such tests as are prescribed in the specification
to be done by the CONTRACTOR before the plant is taken over under
guarantee by the OWNER / PURCHASER.
3.32 “Virtual Completion‟ shall mean that all work is completed as directed and the
site is cleared to the satisfaction of the OWNER / PURCHASER or the
CONSULTANT.
3.33 “Commercial Use” shall mean that use of the equipment or work which the
contract contemplates or that for which equipment or work is commercially
capable.
3.34 “Minor Modification” as applied to equipment erection contracts only, shall mean
the modification work required to be done on the Equipment and works, which
need a maximum of 38 man-hours per item of work. In the case of civil
contracts, it shall be works, which need a maximum of 8 man-hours per item of
work.
3.35 “Major Modification” as applied to equipment erection contracts only, shall mean
the modification work required to be done on the equipment and works needing
more than 38 man-hours per item of work, where such work is required to be
done for no fault of the VENDOR / CONTRACTOR. In the case of civil contracts,
it shall be works needing more than 8 man-hours per item of work.
3.36 Words importing persons shall include Firms, Companies Corporations and
other Bodies whether incorporated or not.
3.37 Words importing the singular only shall also include the plural and vice-versa
where the context requires.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: A3
TCE.GP/9506A/130 0
CO C 27 DEFINITION OF TERMS Chapter 3
Sheet 5of 5
(c) Drawings submitted by the VENDOR with his proposal provided such
drawings are acceptable to the OWNER / PURCHASER or the
CONSULTANT.
(e) Engineering data and drawings submitted by the VENDOR during the
progress of the work provided such drawings are acceptable to the
CONSULTANT.
3.39 FOB Part of shipment : The term “FOB part of shipments” shall apply according
to the International Rules for the interpretation of Trade Terms (INCOTERMS
2000).
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: A4
TCE.GP/9506A/130 0
CO C 27 LOCATION DETAILS Chapter 4
Sheet 1of 2
4.9 Major access road in the vicinity : National Highway NH-44 which branches
off from the National Highway NH-6
connecting Kolkata with Mumbai
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: A5
TCE.GP/9506A/130 0
CO C 27 INSTRUCTION TO BIDDERS Chapter 5
Sheet 1of 4
5.1 It is not the intent to completely specify herein all details of design and
construction of the equipment. However, the equipment shall conform in all
respects to high standards of engineering, design and workmanship and shall
be capable of performing in continuous commercial operation up to the
successful bidder’s guarantees in a manner acceptable to the TSL-TSL who
shall interpret the meaning of drawings and specifications and shall have the
power to reject any work or material which in his judgment are not in full
accordance with it.
5.2 The extent of supply under the contract includes all items shown in the drawings,
notwithstanding the fact that such items may have been omitted from the
specifications or schedules. Similarly the extent of supply also includes all
items mentioned in the specification and/or schedules, notwithstanding the fact
that such items may have been omitted in the drawings.
5.3 The successful bidder shall carry out all necessary co-ordination with regard to
sub- contracted equipment. Purchaser shall communicate only with the
successful bidder for all matters pertaining to this contract.
5.4 The total price quoted for this contract shall be firm lump sum all-inclusive basis
and shall cover all items and services necessary for the successful completion
of the contract. Even if all components of a system included in this
specification are not explicitly identified and/or listed herein, these shall be
supplied under this contract to ensure completeness of the system and
facilitate proper operation and easy maintenance of the system. Changes in
quoted lumpsum price shall be permissible only in case of addition/ deletion of
scope. Separate Unit rates shall be quoted for spares.
5.5 This contract specification shall be read along with the attached signed contract
technical specification between TSL and TCE, and General Technical
Specification (GTS) and the attached drawings and documents.
5.6 In case of any conflict between clauses order of preference for governing clause
shall be the latest single line diagrams of TSL & TCE, signed contract
technical specification between TSL & TCE,GTS of TSL/TCE and this
specification.
5.7 The Successful bidder shall take prior approval from TSL/TCE& purchaser, if any
modifications, is required in GTS/Contract technical Specification after contract
finalisation and in this regard, Successful bidder’s technology shall be
followed.
5.8 The make of all electrical items shall be selected from the preferred vendors list
of TSL/TCE which form part of the contract document amongst TSL & TCE.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: A5
TCE.GP/9506A/130 0
CO C 27 INSTRUCTION TO BIDDERS Chapter 5
Sheet 2of 4
5.9 The PURCHASER considers information / data called for in this specification
as material to evaluate the BIDS and determine whether or not a Bid meets
the specification, that omission of any of it could make such decision
impossible and cause the bid to be considered non-responsive. All information
asked for must be available in the bid when it is opened. Omitted data will not
be requested by the PURCHASER or accepted by the PURCHASER if offered
by the BIDDER after Bid opening. If the omission of information renders a Bid
non-responsive, such a Bid will be rejected. The same restrictions apply to
errors in data submitted in a Bid.
5.10 BID shall be submitted strictly as per the format outline in the schedules to
enable the PURCHASER / ENGINEER to evaluate the BID expeditiously.
5.11 Any and all the exceptions or deviations or objections which the BIDDER may
have to any of the clauses in this specification both technical, commercial and
General conditions of contract for supply shall be clearly outlined in the
respective schedule of deviations failing which the offer will be DEEMED TO
CONFORM FULLY WITH TECHNICAL SPECIFICATION AND GENERAL
TERMS AND CONDITIONS in all ways. All deviations shall be strictly
indicated under Section F3 and F5 only. Deviations indicated elsewhere /
reference to catalogues etc. will not be considered / accepted.
5.14 Prices as quoted in Section-F shall be exclusive of type test charges. Charges
for conducting type tests shall be indicated separately as called for in Section-
F.
5.15 Any clarifications required on the BID / ENQUIRY shall be sought before date
of Bid opening. Seeking clarifications will not entitle any BIDDER for extension
of Bid due date.
5.16 Prices quoted by the BIDDER for all items shall be FIRM.
5.17 All unit prices quoted shall be valid until the date of successful commissioning
of the equipment. Unit rates quoted shall form basis of addition or deletion of
equipment at any stage.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: A5
TCE.GP/9506A/130 0
CO C 27 INSTRUCTION TO BIDDERS Chapter 5
Sheet 3of 4
5.18 BIDDERS shall submit quality assurance plan along with the BID. This quality
assurance plan shall form part of the PURCHASE ORDER to enable the
PURCHASER/OWNER to assure the quality of components at various stages
of manufacture.
5.19 This being a turnkey specification, all expenses for commissioning including
transportation, boarding and lodging of VENDOR's personnel is included in the
basic scope of the VENDOR.
5.20 VENDOR shall give MINIMUM 15 days prior notice for inspection of all
equipment included in this specification to enable PURCHASER / his
authorized representative to carry out inspection. PURCHASER reserves the
right to waive inspection at any stage. Inspection will be carried out only on
receipt of Vendor's internal test report of the equipment offered and scrutiny of
the same. In event, on receipt of inspection call, the PURCHASER's
representative reaches the manufacturer's works and finds the material not
ready for inspection / incomplete / has short supply, the inspector will return to
his base station and all expenses incurred by the inspector including to and
from travelling expenses from his base station to place of inspection, boarding
and lodging charges etc. shall be reimbursed by the VENDOR.
5.22 VENDOR shall keep his testing instruments duly calibrated against standard
meters not earlier than 6 months form the date of testing. Calibration
certificates shall be made available during inspection.
.
5.23 BIDDER shall indicate separately price for supply of ‘Start-up and Essential
spares’ listed in the specification. Cost of these spares will be considered for
evaluation. BIDDER shall also indicate separately price for supply of
‘Recommended Spares’ for two years operation and maintenance of the
equipment.
5.24 As and when the need arises, the VENDOR shall depute his representative /
engineer for discussions with the PURCHASER / CONSULTANT at a venue to
be decided by PRUCHASER till the successful commissioning of the
equipment and completion of the project to finalize outstanding issues.
a) Cover -1 containing:
I) Technical and commercial deviations.
ii) Technical data.
iii) Un-priced price schedule.
iv) All schedules filled up as per Section-F2 to F6.
5.27 Besides hard copies, Bidders shall also furnish all the above information on a
compact disc in pdf format. Filled up Data Sheets shall be in pdf format.
a) Cover-2 containing:
i) Schedule of prices
5.28 The successful BIDDER shall submit bar chart indicating schedules of
drawing submission, manufacture, delivery, construction etc. immediately on
placement of LOI / PO (whichever is earlier) to enable PURCHASER to
monitor work progress.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B1
TCE.GP/9506A/130 0
CO C 27 PROJECT BACKGROUND Chapter 6
Sheet 1of 1
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B2
TCE.GP/9506A/130 0
CO C 27 SCOPE OF AUGMENTAION JOB Chapter 7
Sheet 1of 1
7.1 Bidder shall inspect the existing effluent treatment plant of the coke oven
battery and by product plant and submit the scheme for augmentation of existing
Coke Oven ETP so that it can effectively treat the effluent/waste water volume of 230
m3/hr (125 m3/hr as per existing plant design + additional 105 m 3/hr for the new facility
to be installed) within the discharge standards when the new coke oven battery and
the associated by product plant will be in operation along with the existing one. Bidder
shall visit and study the facilities minutely and offer all possible solutions. The
scheme shall be submitted to PURCHASER/CONSULTANT for approval.
7.2 Bidder shall ensure that augmentation of existing Effluent Treatment plant shall
not affect the performance of existing plant.
7.4 The augmentation shall have facility for tertiary treatment so that the discharge
water from the augmented plant should be colourless and can be reused within the
works.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B3
TCE.GP/9506A/130 0
CO C 27 SCOPE OF SERVICES OF VENDOR/CONTRACTOR Chapter 8
Sheet 1of 2
8.1.2 Supply of all technical literature, drawings & documents, general arrangement
drawing, assembly & sub-assembly drawings & erection drawings of Effluent
Treatment Plant.
8.1.3 Submission of design calculations, data sheets, suction & discharge line
sizing calculations for various pumps for approval of Purchaser/Consultant &
finalizing the same as per approval of Purchaser/Consultant.
8.1.5 Supply of commissioning spares & consumables till completion i.e first tap of
hot metal.
8.1.6 Bidder shall submit an itemized price-list of two years operation & maintenance
spares.
8.1.7 Supply of special tools, tackles for construction, erection operation, repair &
maintenance of all pumps.
8.1.8 All necessary connections for hook-up with Purchaser’s system at battery
limits.
8.1.10 First fill of fuel, lubricating oil & other consumables till completion i.e first tap of
hot metal.
8.1.13 All associated civil works such as excavation, dewatering, foundation and
backfilling by compacting backfill to 90% standard proctor density. The scope
shall also include disposal of surplus excavated soil outside the plant area.
Area for disposal of excavated material shall be identified by the Contractor.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B3
TCE.GP/9506A/130 0
CO C 27 SCOPE OF SERVICES OF VENDOR/CONTRACTOR Chapter 8
Sheet 2of 2
8.1.14 Cold water RCC basin with supporting structures, extended channel from each
compartment of basin provided with stop log, screens and suitable handling
facilities for the same.
8.1.15 Painting of all steel surfaces conforming to General Specification for Painting
8.1.16 Carrying out performance test of the Effluent Treatment Plant including supply
of
all test instruments which are calibrated to National level and same can be
taken
back by Vendor after testing and completion of performance guarantee.
8.1.18 Earthing of all the equipment in Effluent Treatment Plant area. Formation of
earthing grid in the Effluent Treatment Plant and connecting it to the main
earthing grid through test electrodes/test links.
8.1.19 Cable glands and lugs of appropriate sizes for cable terminations on the
motors.
8.1.20 Local Push button (LPB) stations, junction boxes (JB’s), cable trays, earthing
and lightning protection conductor & earth electrodes.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B4
TCE.GP/9506A/130 0
CO C 27 MECHANICAL REQUIREMENTS Chapter 9
Sheet 1of 4
All equipment shall be designed to operate satisfactorily and meet all the
requirements specified in Data sheet-A. The equipment shall be designed,
manufactured in accordance with best engineering practices and shall have been
proven to be suitable for intended purpose.Vendor's design of the ETP shall be based
on design influent water analysis indicated in the specification.
The required water quality to be guaranteed at the outlet of ETP shall be guaranteed
at values as indicated in the specification.
The following documents shall be furnished by bidder along with bid (Mandatory).
ISSUE
R0
ISSUE
R0 ISSUE
R0
ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B5
TCE.GP/9506A/130 0
CO C 27 ELECTRICAL REQUIREMETS Chapter 10
Sheet 1of 2
- MCC/PDB/LCS as required
- All power and control cabling for the MCC/PDB downstream feeders.
- VFD/VVVF/Soft Starter
- HT/LT Motors & junction boxes
- All HT motors (<=1000 kW) suitable control circuit taking care of process
/safety interlocks local remote selection
- Equipment earthing
- Any other equipment as required to make the installation complete in all
respects.
10.2 Exclusions
10.3.1 Bidder to include LV power cables, control cables and cable accessories
between MCC/PDB and different consumers under this scope including
routing, supply of trays and accessories in the scope of supply.
10.3.2 Where applicable, Bidder to supply DC distribution boards for their package
related DC loads. Purchaser will provide power supply to the DCDB.
10.3.3 Main earthing grid including the risers and electronic earthing will be provided
by the purchaser.
10.3.4 For the Electrical rooms / substation building dedicated for the package, ISSUE
Bidder to include the detail engineering of the electrical control room, electrical
R0
equipment layout, cable Tray layout, above equipment earthing layout and
ISSUE
R0 ISSUE
R0
ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B5
TCE.GP/9506A/130 0
CO C 27 ELECTRICAL REQUIREMETS Chapter 10
Sheet 2of 2
lighting layout in the scope of supply. However, Bidder to furnish all required
civil feedback data for design and construction of building by Purchaser.
10.3.5 In the event of order Bidder shall submit all GA, SLD, Control schematics,
layouts, cable schedule, data sheets, ICS etc. for the equipments supplied /
installed by them. For the motors to be supplied by them Bidder shall furnish
following:
- Motor data sheet for all motors indicating rating, full load current, starting
current, starting time (no load & coupled with load at 100% & 80%
voltage), stall time, thermal time constants (heating & cooling), no. Of
starts etc., Motor GD2 , Load GD2, Coupling GD2
- Thermal curves
- torque speed characteristic curves for both motors and loads.
10.3.6 Any item or equipment not specifically mentioned but essential for proper
installation, operation, maintenance and safety of plant, equipment and
personnel shall be included by the Successful bidder in his scope of work.
10.3.7 Bidder to note and confirm that approval of drawings and documents from
TSL/TCE as well as from Statutory Authority e.g. CEI of the state etc. will
lie in Bidder's Scope.
10.3.8 The make of all electrical items shall be selected from the preferred vendors
list of TSL which form part of the contract document amongst TCE & TSL.
ISSUE
R0
ISSUE
R0 ISSUE
R0
ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B6
TCE.GP/9506A/130 0
CO C 27 INSTRUMENTATION AND CONTROL DESIGN Chapter 11
REQUIREMENTS Sheet 1of 2
11.1 General
All the instruments shall be from the latest product ranges of reputed
manufacturers.
The control system for the ETP system will be supplied by the client. Bidder ISSUE
shall submit the control logic diagrams (based on the approved R0
operational & control philosophy for the plant) to be implemented in the
ISSUE
R0 ISSUE
R0
ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B6
TCE.GP/9506A/130 0
CO C 27 INSTRUMENTATION AND CONTROL DESIGN Chapter 11
REQUIREMENTS Sheet 2of 2
control systems. This is also bidder’s responsibility to implement the logic in the
control system.
The bidder shall supply the following spares for the instruments & accessories
to be supplied by them: a) Commissioning Spares, b) List of 2 years operational
spares (only list to be furnished).
The installation, cabling up to RIOs through JB , tubing, testing & commissioning
of their own instruments shall be under the bidder’s scope.
ISSUE
R0
ISSUE
R0 ISSUE
R0
ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B7
TCE.GP/9506A/130 0
CO C 27 CIVIL REQUIREMENTS Chapter 12
Sheet 1of 2
This section of the specification covers design and construction of all civil work
for the Effluent Treatment Plant (ETP).
.
12.2 The design of different elements of ETP will be done as indicated below.
6mm (minimum) thick cement plaster (1:4) shall be provided on all exposed
concrete surface.
12.3 All M.S pipe inserts through R.C wall of basins and channels shall be provided
with puddle flange. In order to ensure water tightness pipes and other
embedment shall be cast monolithically. Both end of the pipe insert shall be
plugged during construction.
12.4 All construction joints in water retaining structures shall be provided with PVC
water stops.
12.6 The full area below the thickener shall be paved with PCC pre –cast paver block
of adequate thickness laid on minimum 150mm thick sand bedding.
12.7 Adequate road shall be provided around ETP for movement of trucks/dumpers
for disposal of sludge .
12.8 Suitable sludge handling facilities for ETP shall be envisaged. ISSUE
R0
ISSUE
R0 ISSUE
R0
ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B7
TCE.GP/9506A/130 0
CO C 27 CIVIL REQUIREMENTS Chapter 12
Sheet 2of 2
12.10 Area coming in to contact with acid/alkali vapors or fumes will be given
acid/alkali resistant tiles 20mm thick, joined with acid/alkali resistant cement
mortar. Bedding with comprise of potassium silicate mortar, conforming to IS:
4832 (part-1) and resin based mortar like epoxy for jointing. Total thickness of
flooring shall be 40 mm.
a. All material and workmanship shall confirm to the relevant parts of Technical
Specification which is an integral part of document and the same may be
referred.
b. During backfilling of any excavated area, top one (1) meter shall be
backfilled with granulated blast furnace slag/approved earth in layers of 250
mm with watering, compacting with vibro roller.
c. The scrap, if any generated during the course of excavation shall be
handed over to scrap and salvage department of Employer.
d. All other requirements which are not covered in the Technical Specification
shall be generally in conformity with the relevant Indian Standards
ISSUE
R0
ISSUE
R0 ISSUE
R0
ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B8
TCE.GP/9506A/130 0
CO C 27 CODES AND STANDARDS Chapter 13
Sheet 1of 1
13.1 All equipment, system and services covered under this specification shall
comply with all currently applicable statutes, regulations and safety codes.
Nothing in this specification shall be construed to relieve the VENDOR of
his Effluent Treatment Plant responsibility.
13.2 The standards not indicated in the specification are also acceptable, if
they are established to be equal or superior to the standards indicated in
the specification.
13.3 The metric units/SI units shall be used in all data/ drawings submitted
against this package.
13.4 The BIDDER shall furnish the English translations of all standards to which
the equipment and systems offered are conforming to, as and when
required by the OWNER.
13.5 In the event of any conflict between the codes and the standards referred to
elsewhere in the specification and the requirements of this specification,
more stringent of the two shall govern.
13.6 The latest issue of IS codes prevailing at the time of submission of final
offer shall be applicable. However, if there are any revisions during the
execution of the contract, the same shall be applicable and the cost
implication if any shall be mutually discussed.
13.7 All equipment shall comply with the statutory requirements of the
Government of India and the Government of Jrarkhand .
13.8 Bidder shall adhere to the various statutory regulations, such as State
Factory Rules, Indian Explosives Acts, State Electricity Rules, Static and Mobile
Pressure Vessels Codes / Unfired Rules, etc. Enforced / laid by the Govt. of
India and State Government of Jharkhand , NFPA-12 & 2001, FM approval &
UL listed during the design, fabrication/ manufacture, inspection, testing, painting,
transportation, storage, and erection and commissioning of plant and
equipment. Additionally all conditions as mentioned in the General Technical
Specification shall be fulfilled.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: B9
TCE.GP/9506A/130 0
CO C 27 DESIGN AND CONSTRUCTION REQUIREMENTS Chapter 14
Sheet 1of 2
The capacity and design requirements of the Coke Oven ETP shall be as
specified in Data Sheet-A.
4. The augmentation should have facility for tertiary treatment so that the
discharge water from the augmented plant should be colourless and can be
reused within the work.
5. OTHER REQUIREMENTS
Workmanship and materials shall be of good commercial quality suitable for the
purpose intended and in accordance with the highest standards and practices
for equipment of the class covered by the specification.
c Lubrication
d Safety
These items shall include not only those usually furnished with elements of
machinery , but also the additional covers , guards, stairways, ladders , platforms,
handrails, alarms, etc which are necessary for safe operation of the plant.
e Layout Requirement
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION:
TCE.GP/9506A/130 0 B10
CO C 27 MISCELLANEOUS SERVICES
Chapter 15
Sheet 1of 1
15.1 PAINTING
All plant and equipment shall be painted conforming to relevant clauses as per
paining practice of TSL.
15.2 SPARES
The Contractor shall supply the spares required for commissioning of the
equipment & for its smooth and efficient operation up to successful
commissioning. These items shall be based on the Contractor’s experience in
commissioning similar plants in the past. The list of commissioning spares
shall be delivered along with the main equipment at site. The Contractor shall
supply all commissioning spares which will be required for successful erection,
testing & commissioning of the complete system without any commercial
implication. The Contractor shall be responsible for having the required items
at site in sufficient quantities to take care of the commissioning requirement.
Contractor shall indicate Insurance Spares, as required for smooth and trouble
free operation of Effluent Treatment Plant, with their Bid.
The Contractor shall include adequate sets of the special tools and tackles for
normal operation and maintenance of the equipment with less manpower in
their scope of supply.
.
15.2.5 Consumables and Operating Supplies
The Bid shall include brand names and tentative quantities of all consumable
materials such as lubricants, flushing oil, fills etc., required during start-up,
commissioning, initial filling and yearly requirements for normal operation. The
successful Bidder shall supply such materials required for initial filling and
during start-up & commissioning.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION:
TCE.GP/9506A/130 0 B11
CO C 27 TERMINAL POINTS
Chapter 16
Sheet 1of 1
16.1 Electrical Power: Electrical Power source will be identified by the owner
Duplicate full capacity feeders shall be made available at the MCC by
Purchaser.
Service water tap off shall be provided at a suitable location at the ETP
boundary by the Purchaser.
Drinking water tap off shall be provided at a suitable location at the ETP
boundary by the Purchaser. Drinking water at pressure 1.5-2.0 kg/cm2(g) and
1.2 m below the ground level.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION:
TCE.GP/9506A/130 0 B12
CO C 27 DRAWINGS & DOCUMENTS
Chapter 17
Sheet 1of 3
Different drawings & documents during bid stage & after award of contract for
Effluent Treatment Plant of ETP shall be conforming to relevant clauses of
TCE & TSL.
17.1 Mechanical Drawings and documents to be furnished along with the BID
The following documents shall be furnished by bidder along with bid (Mandatory).
17.2 Electrical Drawing and documents to be furnished along with the BID
a) Process and instrumentation (P&I) diagrams indicating all local and remote
measurements, alarm and interlock functions, using ISA symbols and using suitable
tag numbers against each instrumentation equipment.
b) List of measurements, alarms and interlock, along with BOQ and brief specification
of each instrumentation item indicating make, model series, scale range, quantity,
application and tag number (as per P& I diagrams).
c) Detailed technical literature of the instruments offered.
d) List of commissioning spares with details.
e) List of two years operation and maintenance spares with details and
unit rates.
c) Finalized list of measurements, alarms & interlocks, along with BOQ and
specification of each instrumentation item indicating make, model number, scale
range, quantity, application and tag number (as per P&I diagram).
i) Installation diagrams.
ii) Manufacturer’s test, calibration and guarantee certificates for all instruments.
*Note –The above drawing/documents are indicative only not exhaustive. Bidder
may submit additional drawings/documents if the same are required to complete the
bid in all respect.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION:
TCE.GP/9506A/130 0 B13
CO C 27 PROJECT SCHEDULE
Chapter 18
Sheet 1of 1
18.1 The Successful Bidder shall submit the following along with the offer
considering completion of the entire work (design, engineering, supply,
erection, testing and commissioning) within Twelve (12) months from the date
of LOI or Order whichever is earlier.
18.1.2 The major milestones for the project are to be highlighted in the schedule.
18.2 The successful bidder shall submit an overall erection plan for the plant and
equipment under his scope of supply along with the tender. The plan shall
include the following:
i. Requirement of construction water
ii. Requirement of construction power
iii. Requirement of construction and storage area
iv. Off-site/On-site organisation chart for the execution of the project.
18.3 The successful bidder shall submit the following before finalization of Contract:
i. Deployment of construction man power
ii. The erection techniques to be employed
iii. Details of deployment of equipment and machinery, tools & tackles,
etc, required for structural fabrication, structural and equipment erection.
iv. In case simultaneous erection work is carried out along with civil and
structural works, the movement of men, machine and materials at
site shall be planned suitably.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION:
TCE.GP/9506A/130 0 B14
CO C 27 PROGRESS MONITORING
Chapter 19
Sheet 1of 1
19.2 The Purchaser/ Consultant shall also have the right to:
i. Invite the Contractor for monthly / fortnightly meetings to review the progress
of each activity.
ii. Depute Purchaser’s authorized representatives for ascertaining/ expediting
progress at successful bidder’s works.
iii. Suggest remedial actions to bridge-up time gap between planned
progress & observed progress.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION:
TCE.GP/9506A/130 0 B15
CO C 27 OTHER FACILITIES AT SITE
Chapter 20
Sheet 1of 1
The SUCCESSFUL BIDDER shall make his own arrangement for all his
communication needs such as telephone, telex, etc. at his Site Office. The
TSL-TSL/MECON/PURCHASER will assist the SUCCESSFUL BIDDER in
getting the above facilities, in case he finds difficulty.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION:
TCE.GP/9506A/130 0 B16
CO C 27 SUCCESSFUL BIDDER’S COORDINATION WITH
PURCHASER Chapter 21
Sheet 1of 1
21.1 In cases where the performance of the erection work by the SUCCESSFUL
BIDDER affects the operation of the system facilities of the TSL/TCE such
erection work of the SUCCESSFUL BIDDER shall be scheduled to be
performed only in the manner stipulated by the TSL/TCE and the same
shall be acceptable at all times to the TSL/TCE may impose such
restrictions on the facilities provided to the SUCCESSFUL BIDDER such
as electricity, water, etc. as he may think fit in the interest of the TSL/TCE
and the SUCCESSFUL BIDDER shall strictly adhere to such restrictions
and co-operate with the TSL/TCE. It will be the responsibility of the
SUCCESSFUL BIDDER to provide all necessary temporary
instrumentation and other measuring devices required during startup and
operation of the equipment systems which are erected by him. The
SUCCESSFUL BIDDER shall also be responsible for flushing and initial
filling of all the oil and lubricants required for the equipment furnished and
erected by him, so as to make such equipment ready for operation. The
SUCCESSFUL BIDDER shall be responsible for supplying such flushing oil
and other lubricants unless otherwise specified elsewhere in these
documents.
21.2 The successful bidder at all times shall work in coordination with the
TSL/TCE and offer them all reasonable facilities to become familiar with
the erection, operation and maintenance of the equipment.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION:
TCE.GP/9506A/130 0 B17
CO C 27 SECURITY
Chapter 22
Sheet 1of 1
22.0 Security
The SUCCESSFUL BIDDER shall have total responsibility for all equipment and
materials in his custody stored, loose, semi-assembled and/or erected by him at
'Site'. The SUCCESSFUL BIDDER shall make suitable round the clock security
arrangements including employment of security personnel to ensure the protection of
all materials, equipment and 'Works' from theft, fire, pilferage and any other damages
and loss. All materials of the SUCCESSFUL BIDDER shall enter and leave the
project 'Site' only with the written permission of the TSL/TCE in the prescribed
manner. In case of inadequate security, TSL/TCE reserves the right to deploy
necessary security at site. All expenses incurred by TSL/TCE on account of this will
be charged to the SUCCESSFUL BIDDER.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION:
TCE.GP/9506A/130 0 B18
CO C 27 PROTECTION OF PROPERTY AND SUCCESSFUL
BIDDER'S LIABILITY Chapter 23
Sheet 1of 1
23.1 The Successful bidder shall be responsible for any damage resulting from his
operations. He shall also be responsible for protection of all persons
including members of public and employees of the TSL/TCE and the
employees of other Contractors and SUB-CONTRACTORS and all public and
private property including structures, buildings, other plants and equipment and
utilities either above or below the ground.
23.2 The Contractor will ensure provision of necessary safety equipment such as
barriers, sign-boards, warning lights and alarms, etc. to provide adequate
protection to persons and property. The successful bidder shall be
responsible to give notice to TSL/TCE of public or private property and utilities
when such property and utilities are likely to get damaged or injured during the
performance of his ‘Works’ and shall make all necessary arrangements with
such PURCHASERs, related to removal and/or replacement or protection of
such property and utilities.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: C1
TCE.GP/9506A/130 0
CO C 27 EXISTING PLANT PROCESS DESCRIPTION Chapter 24
Sheet 1of 4
24.2 Design characteristics of the inlet and outlet water from Existing Coke Oven ETP
Parameters ETP Inlet Value ETP Outlet Value(as
per plant design )
Source Outlet of Coke Oven Coke Oven Coke Oven
Pre Treatment plant, ETP
Benzol Plant
Volume m3 /hr 125 125
TSS in ppm 480 < 100
Oil & Grease 50 < 10
TDS in ppm 3200 2100
pH 8-10 7-9
COD in ppm 4000 250
BOD in ppm 2400 < 30
Ammonia as NH3 in ppm 150 50
Cyanide as CN in ppm 28 0.20
Thiocyanate in ppm 650 150
Phenol in ppm 400 1
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: C1
TCE.GP/9506A/130 0
CO C 27 EXISTING PLANT PROCESS DESCRIPTION Chapter 24
Sheet 2of 4
24.3 Operating characteristics of the inlet and outlet of water from Existing Coke Oven ETP
Parameters ETP Inlet Value ETP Outlet
Value(*as per
SGS analysis)
Source Coke Oven Pre Coke Oven
Treatment plant,LD1 Coke Oven ETP
Volume m3/ hr 75 75
TSS in ppm 46-52 70-90
Oil & Grease * 4.8-6.4 2-5
TDS in ppm 3720-3808 70-90
pH 7.8 7-9
COD in ppm 2116-2356 160
BOD in ppm 1050-1150 < 30
Ammonia as NH3 in ppm 117.6-132.11 15-20
Cyanide as CN in ppm 4.8-5.6 0.18-0.20
Thiocyanate in ppm 365-475.5 -
Phenol in ppm 310-331 <1
Equalization tanks:
The B.O.D. plant is designed to handle a pre-treated liquor flow upto 125 m 3/hr.
Generally the inlet stream to this plant varies in terms of quality and quantity. For
improved efficiency and reliability in control processes, this plant is being
operated at or near uniform conditions. Two equalization tanks, homogenize the
liquor in quality and quantity, before sending it for biological treatment. The
volume of each tank is 1680 m 3 and detention time per tank is more than 13.4
hrs. The pretreated excess liquor, along with other effluents, is taken into one of
these equalization tanks. When one tank is full, the flow is diverted to the other
tank. Once a tank is one third filled, air blowing is started through aeration grids
provided at the bottom at the rate of 0.9 m 3 air/m3 of water. This air causes
mixing of liquors for quite a long time, thus preparing a homogenous feed to the actual
biological treatment operation. Two blowers are provided for for blowing air.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: C1
TCE.GP/9506A/130 0
CO C 27 EXISTING PLANT PROCESS DESCRIPTION Chapter 24
Sheet 3of 4
Flash Mixer:
The liquor, after equalization, is pumped to the flash mixer by two pumps for this
purpose. The volume of flash mixer is about 1.44 m 3, where liquor is mixed with diluted
sheet mill liquor. This mixing is facilitated by a motor driven agitator. The sheet mill
liquor, which contains ferrous sulphate, supplies Fe++ ions for coagulation. These ions,
being positive, get attached to the negatively charged suspended solids in the liquor,
thus neutralizing their charge. Due to this, the suspended particles start coagulating,
forming bigger particles which will easily settle, with adequate residence time. Coagulant
dosage is 2 ml/ l of liquor and the detention time in the flash mixer is 30 seconds.
Clarifloculator:
Distribution chamber:
The waste water after primary treatment enters the distribution chamber, from where it is
equally divided into the four aeration tanks through 225 OD HDPE pipe, with the help of
V- notch weires.
From this stage, the main biological treatment of waste water liquor starts .In the removal of
carbonaceous BOD, the coagulation of non - settleable colloidal solids and the stabilization
of organic matter are accomplished biologically using variety of microorganisms, i.e. bacteria.
The microorganism converts the colloidal and dissolved carbonaceous organic matter into
various gases and into cell tissues. As these cell tissues have a specific gravity slightly
greater than water, the resulting tissues can be removed from the treated liquid by gravity
settling.
The conversion of organic matter into gaseous end products and tissues can be
accomplished aerobically (in presence of air), anaerobic ally (in absence of air) or
facultatively using suspended growth or attached system.
In the B.O.D. plant , aerobic is being conversion ,where a part of organic matter
(Phenol) is converted to end product to obtain energy and parts(cyanide, ammonia,
thiocyanates) for the synthesis of new cells and hence the growth. In the aeration tank,
both these operation occur simultaneously.
The first stage aeration tank consists of 4 separate tanks with volume of 1800 M 3 each
(dimension -16.5m x33.0 m x 3.3 m) .Two surface aerators are , provided in each of the
tanks for supplying oxygen. For the metabolism, oxygen provision is 2.0 kg /kg of BOD.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: C1
TCE.GP/9506A/130 0
CO C 27 EXISTING PLANT PROCESS DESCRIPTION Chapter 24
Sheet 4of 4
From the first stage aeration tank, the mixed liquor continuously overflows into the first
stage clarifier by gravity through 400 OD HDPE pipes .Later the solids are separated
from liquor by settling. The first stage clarifier is a cylindrical tank of dimension 16 m dia.
X 3.0 m .The mixed liquor enters at the bottom of clarifier .An agitator running at low
rpm , for gentle settling of solids is provided. The settled solids are either recycled back
through the distribution chamber into the aeration tank or are removed to the thickener.
Three sludge pumps for handling sludge transportation between the units are provided.
Thickener:
Primary solids from the clarifloculator and excess biological solids from the secondary
clarifiers are pumped to the thickener for concentrating the solid content in the sludge.
Thickener is a cylindrical tank of dimension 6.5m*2.5m.The solids collected at the
bottom are taken to sludge drying beds. Here the solids which remain on the surface of
the beds are removed when they are dried and the liquid which percolates through the
media is disposed.
Coagulant Solution:
Concentration of ferrous sulphate = 10 %
Dosage = 4 – 5 ltr/min
Concentration = 4 % v/v
Dosage = 1 ltr/min
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: C1
TCE.GP/9506A/130 0
CO C 27 EXISTING PLANT PROCESS DESCRIPTION Chapter 24
Sheet 5of 4
Concentration = 15 % v/v
Dosage = 1 ltr/min.
40 0 C. So, cooling should be done properly after the pretreatment, such that the
operations of B.O.D. don’t get hampered. A high temperature may cause
destruction of the living organisms.
(c) PH level: At high pH levels (>10), the micro organisms are adversely affected.
To have a favorable biological degradation, the pH should lie between 7.5 to 10
under aerobic conditions.
(d) Aerator Performance: The performance of the aeration tanks will suffer when
the aerators are malfunctioning or inoperative. The aerators must supply
adequate amount of O2 from the atmosphere to the system.
(e) Nutrient (H3PO4 solution): For the propagation of the microorganisms, nutrients
like nitrogen and phosphorus are essential. Laboratory analysis has to be
carried out to ensure the presence of these elements in the desires quantity.
Proper dosing of H3PO4 solutions should be ensured.
(f) Mixed liquor colour: Healthy sludge shows a light brown colour. A dark
blackish colour may indicate anaerobic condition by low oxygen. This situation
may require a check of influent flow to the aeration tank.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: D1
TCE.GP/9506A/130 0
CO C 27 DATA SHEET A Chapter 25
Sheet 1of 3
25.2 Design characteristics of the inlet and outlet water from Existing Coke Oven ETP
Parameters ETP Inlet Value ETP Outlet Value(as
per plant design )
Source Outlet of Coke Oven Coke Oven Coke Oven
Pre Treatment plant, ETP
Benzol Plant
Volume m3 /hr 125 125
TSS in ppm 480 < 100
Oil & Grease 50 < 10
TDS in ppm 3200 2100
pH 8-10 7-9
COD in ppm 4000 250
BOD in ppm 2400 < 30
Ammonia as NH3 in ppm 150 50
Cyanide as CN in ppm 28 0.20
Thiocyanate in ppm 650 150
Phenol in ppm 400 1
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: D1
TCE.GP/9506A/130 0
CO C 27 DATA SHEET A Chapter 25
Sheet 2of 3
25.3 Operating characteristics of the inlet and outlet of water from Existing Coke Oven ETP
Parameters ETP Inlet Value ETP Outlet
Value(*as per
SGS analysis)
Source Coke Oven Pre Coke Oven
Treatment plant,LD1 Coke Oven ETP
Volume m3/ hr 75 75
TSS in ppm 46-52 70-90
Oil & Grease * 4.8-6.4 2-5
TDS in ppm 3720-3808 70-90
pH 7.8 7-9
COD in ppm 2116-2356 160
BOD in ppm 1050-1150 < 30
Ammonia as NH3 in ppm 117.6-132.11 15-20
Cyanide as CN in ppm 4.8-5.6 0.18-0.20
Thiocyanate in ppm 365-475.5 -
Phenol in ppm 310-331 <1
Concentration = 4 % v/v
Dosage = 1 ltr/min
Concentration = 15 % v/v
Dosage = 1 ltr/min.
40 0 C. So, cooling should be done properly after the pretreatment, such that the
operations of B.O.D. don’t get hampered. A high temperature may cause
destruction of the living organisms.
(c) PH level: At high pH levels (>10), the micro organisms are adversely affected.
To have a favorable biological degradation, the pH should lie between 7.5 to 10
under aerobic conditions.
(d) Aerator Performance: The performance of the aeration tanks will suffer when
the aerators are malfunctioning or inoperative. The aerators must supply
adequate amount of O2 from the atmosphere to the system.
(e) Nutrient (H3PO4 solution): For the propagation of the microorganisms, nutrients
like nitrogen and phosphorus are essential. Laboratory analysis has to be
carried out to ensure the presence of these elements in the desires quantity.
Proper dosing of H3PO4 solutions should be ensured.
(f) Mixed liquor colour: Healthy sludge shows a light brown colour. A dark
blackish colour may indicate anaerobic condition by low oxygen. This situation
may require a check of influent flow to the aeration tank.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: D2
TCE.GP/9506A/130 0
CO C 27 DATA SHEET B Chapter 26
Sheet 1of 11
EQUALIZATION TANK
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: D2
TCE.GP/9506A/130 0
CO C 27 DATA SHEET B Chapter 26
Sheet 2of 11
FLASH MIXER
9 Rotational speed of
impeller
10 Velocity gradient
11 Detail of drives
12 Rated power of motor KW
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: D2
TCE.GP/9506A/130 0
CO C 27 DATA SHEET B Chapter 26
Sheet 3of 11
CLARIFLOCCULATOR
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: D2
TCE.GP/9506A/130 0
CO C 27 DATA SHEET B Chapter 26
Sheet 5of 11
6 Diameter m
7 Average Depth m
8 Volume m3
9 HRT@ average flow hr
10 HRT@ design flow hr
NOTES TO BIDDER SIGNATURE OF
BIDDER
5. DATA SPECIFIED IN DATA SHEET-A HAS NOT BEEN
REPRODUCED IN DATA SHEET-B. IN CASE OF DEPARTURE
FROM DATA SHEET-A, BIDDER SHALL BRING OUT THE SAME
IN THE SCHEDULE OF DEVIATIONS, FAILING WHICH IT SHALL
BE CONSTRUCTED THAT BIDDER COMPLIES WITH THE
REQUIREMENTS STIPULATED IN DATA SHEET-A.
6. THIS DATA SHEET SHALL BE FILLED UP COMPLETELY AND A
COPY SHALL BE ENCLOSED WITH EACH COPY OF THE BID.
1 Quantity Nos.
2 Compartments Nos.
2 Design Flow Rate m3/hr.
3 Average Daily Flow m3/day
4 Peaking Factor
5 BOD Design Load Kg/day
6 F/M
7 MLSS Concentration Mg/l
8 Aeration Volume m3
Required
9 HRT@ average flow hr
10 HRT@ design flow hr
11 Tank Size
Length m
Width m
Depth m
18 Weight of assembly ton
19 GA drawing submitted
NOTES TO BIDDER SIGNATURE OF
BIDDER
7. DATA SPECIFIED IN DATA SHEET-A HAS NOT BEEN
REPRODUCED IN DATA SHEET-B. IN CASE OF DEPARTURE
FROM DATA SHEET-A, BIDDER SHALL BRING OUT THE SAME
IN THE SCHEDULE OF DEVIATIONS, FAILING WHICH IT SHALL
BE CONSTRUCTED THAT BIDDER COMPLIES WITH THE
REQUIREMENTS STIPULATED IN DATA SHEET-A.
8. THIS DATA SHEET SHALL BE FILLED UP COMPLETELY AND A
COPY SHALL BE ENCLOSED WITH EACH COPY OF THE BID.
1 Quantity Nos.
2 Sludge Volume Index g/mL
3 Sludge Volume Load m3/ m2/day
4 Surface Area Required m2
5 Overflow Rate m / m2/day
3
6 Diameter m
7 Average Depth m
8 Volume m3
9 HRT@ average flow hr
10 HRT@ design flow hr
NOTES TO BIDDER SIGNATURE OF
BIDDER
9. DATA SPECIFIED IN DATA SHEET-A HAS NOT BEEN
REPRODUCED IN DATA SHEET-B. IN CASE OF DEPARTURE
FROM DATA SHEET-A, BIDDER SHALL BRING OUT THE SAME
IN THE SCHEDULE OF DEVIATIONS, FAILING WHICH IT SHALL
BE CONSTRUCTED THAT BIDDER COMPLIES WITH THE
REQUIREMENTS STIPULATED IN DATA SHEET-A.
10. THIS DATA SHEET SHALL BE FILLED UP COMPLETELY AND A
COPY SHALL BE ENCLOSED WITH EACH COPY OF THE BID.
CHLORINATION SYSTEM
8 Dimension of sludge
drying bed
Length m3
Width hr
Depth
NOTES TO BIDDER SIGNATURE OF
BIDDER
13. DATA SPECIFIED IN DATA SHEET-A HAS NOT BEEN
REPRODUCED IN DATA SHEET-B. IN CASE OF DEPARTURE
FROM DATA SHEET-A, BIDDER SHALL BRING OUT THE SAME
IN THE SCHEDULE OF DEVIATIONS, FAILING WHICH IT SHALL
BE CONSTRUCTED THAT BIDDER COMPLIES WITH THE
REQUIREMENTS STIPULATED IN DATA SHEET-A.
14. THIS DATA SHEET SHALL BE FILLED UP COMPLETELY AND A
COPY SHALL BE ENCLOSED WITH EACH COPY OF THE BID.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: D2
TCE.GP/9506A/130 0
CO C 27 DATA SHEET B Chapter 26
Sheet 10of 11
4 Dimension of tank
5 Material of construction Kg/day
& thickness
6 Propeller/agitator
7 b Shaft Mg/l
8 c Fixing bracket m3
9 Drive details hr
10 Rated kW of drive hr
NOTES TO BIDDER SIGNATURE OF
BIDDER
17. DATA SPECIFIED IN DATA SHEET-A HAS NOT BEEN
REPRODUCED IN DATA SHEET-B. IN CASE OF DEPARTURE
FROM DATA SHEET-A, BIDDER SHALL BRING OUT THE SAME
IN THE SCHEDULE OF DEVIATIONS, FAILING WHICH IT SHALL
BE CONSTRUCTED THAT BIDDER COMPLIES WITH THE
REQUIREMENTS STIPULATED IN DATA SHEET-A.
18. THIS DATA SHEET SHALL BE FILLED UP COMPLETELY AND A
COPY SHALL BE ENCLOSED WITH EACH COPY OF THE BID.
ISSUE
ISSUE ISSUE
R0
R0 R0
SPEC NO: TATA Consulting Engineers Limited SECTION: D3
TCE.GP/9506A/130 0
CO C 27 PERFORMANCE GUARANTEE Chapter 27
Sheet 1of 1
After completion of erection, cold tests and hot trial runs and fulfillment of
performance of individual equipment and systems, the integrated system
performance guarantee tests shall be conducted by the Contractor to establish the
rated out-put, quality of treated effluent and power consumption of the Effluent
Treatment Plant.
Details of the performance tests, test procedures and test schedules for the
demonstration of the performance guarantee shall be submitted to the Purchaser
and shall be mutually agreed upon.
Should the performance values fall below acceptable level, the unit/sub-unit/
equipment shall be rejected by the Purchaser and the Contractor shall be liable, at
the option of the Purchaser, either to replace the unit/sub-unit/equipment or to pay
compensation in addition to the liquidated damage as per the contract or as may
be agreed upon.
i. The discharge effluent from the augmented ETP should satisfy the permissible
standards of central pollution control board for all the concerned pollutant
parameters.
ii. Energy consumed as measured at motor control centre of the ETP shall not
exceed the values quoted during the tender stage.
iii.No negative tolerance shall be permissible on capacity and quality of the
treated effluent from the ETP. Further, no positive tolerance shall be
permissible for power consumption of the plant.
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E1
TCE.GP/9506A/130 0
CO C 27 SHOP INSPECTION AND TESTS Chapter 27
Sheet 1of 9
27.1 SCOPE
This specification covers the requirements for Shop Inspection and Tests to
be carried out by the PURCHASER/ CONSULTANT /INSPECTION
AGENCY.
27.2 GENERAL
27.2.2 For supply of systems, the VENDOR/CONTRACTOR shall, at the start of the
PURCHASE ORDER/CONTRACT, furnish a total list of items in his scope of
work. This list, giving a brief description of the item, quantity, names of
probable SUB-VENDORS/SUB-CONTRACTORS, and a blank column for
agency for final approval of drawings and documents, shall be submitted for
approval by PURCHASER/CONSULTANT. The blank column shall be filled
by PURCHASER/CONSULTANT. The list shall be submitted within two
weeks from the date of Letter of Intent.
27.2.3 For systems and major items such as pressure and load bearing items,
machineries etc., the VENDOR/CONTRACTOR shall furnish quality plan
giving details of checks and tests to be conducted by them on material,
process, subassembly and assembly. These shall include requirements as
prescribed in the applicable specifications, codes and statutory
requirements. The quality plan shall be reviewed by the PURCHASER/
CONSULTANT and the stages to be witnessed and verified shall be
indicated by the PURCHASER/ CONSULTANT in the approved quality plan.
pay for the time and expenses for the infructuous visit of the PURCHASER/
CONSULTANT.
27.2.5 In all cases where inspection and tests are required whether at the premises
or works of the VENDOR/CONTRACTOR or of any SUB-VENDOR
/SUBCONTRACTOR or at laboratory, the VENDOR/CONTRACTOR, except
where otherwise specified, shall provide free of charge all facilities such as
labor, materials, electricity, fuel, water, stores, test bed, apparatus and
instruments, laboratory tests etc. as may be required by the PURCHASER/
CONSULTANT to carry out effectively such tests of the equipment in
accordance with the PURCHASE ORDER/CONTRACT and shall give
CONSULTANT facilities to the PURCHASER / CONSULTANT to accomplish
testing.
27.2.6 The PURCHASER/ENGINEER shall at all working hours have access to all
parts of the VENDOR’s/CONTRACTOR's and his SUB- VENDOR’s /
SUBCONTRACTOR's factory where the items of the plant are being
prepared, for carrying out inspection activities as deemed necessary. A set
of the relevant latest approved drawings with approval marking of the
PURCHASER / CONSULTANT and drawings for proprietary items shall be
made available by the VENDOR/CONTRACTOR to the PURCHASER /
CONSULTANT, for reference during inspection.
27.2.8 The PURCHASER/ENGINEER shall have the right to inspect any machinery,
material, structures, equipment or workmanship furnished or used by the
VENDOR/CONTRACTOR and may reject any which is defective or
unsuitable for the use and purpose intended, or which is not in accordance
with the intent of the PURCHASE ORDER/CONTRACT. The VENDOR/
CONTRACTOR, upon demand by the PURCHASER/ CONSULTANT, shall
remedy or replace at the VENDOR’s/ CONTRACTOR's expense such
defective or unsuitable items of the plant, or the PURCHASER /
CONSULTANT may, at the expense of the VENDOR/CONTRACTOR,
remedy or replace such defective or unsuitable items of the Plant.
27.2.9 All principal mill test reports, the VENDOR/CONTRACTOR inspection and
tests reports, test certificates and test curves shall be supplied for all
inspection and tests carried out including other records such as stress
relieving charts, radiographic charts and other non-destructive testing
records in accordance with the provisions of the PURCHASE
ORDER/CONTRACT, duly certified by the main VENDOR/CONTRACTOR.
The PURCHASER / CONSULTANT shall reserve the right to call for
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E1
TCE.GP/9506A/130 0
CO C 27 SHOP INSPECTION AND TESTS Chapter 27
Sheet 3of 9
certificates of origin and test certificates for all raw material and equipment at
any stage of manufacture.
27.2.10 The PURCHASER/ CONSULTANT shall within fifteen (15) days from the
date of inspection as defined herein give notice in writing to the VENDOR /
CONTRACTOR of any non-conformance pertaining to all or any equipment
and workmanship which in his opinion is not in accordance with the
PURCHASE ORDER/CONTRACT. The VENDOR/CONTRACTOR shall
give due consideration to such objections and shall either make the
modificationsthat may be necessary to meet the said objections or shall
confirm in writing to the PURCHASER/ CONSULTANT giving reasons
therein that no modifications are necessary to comply with the PURCHASE
ORDER/CONTRACT.
27.2.11 When the factory tests and documentation have been satisfactorily
completed at the VENDOR’s/CONTRACTOR's or SUB-
VENDOR's/CONTRACTOR's works, the PURCHASER/ CONSULTANT
shall issue acceptance note or shipping release note or a certificate to this
effect within fifteen (15) days after completion, but if the tests are not
witnessed by the PURCHASER/ CONSULTANT, the certificate or
comments thereof shall be issued within fifteen (15) days of the receipt of
the VENDOR’s/CONTRACTOR's test certificate by the PURCHASER/
CONSULTANT. Failure of the PURCHASER/ CONSULTANT to take such
an action shall not prevent the VENDOR/ CONTRACTOR from proceeding
with the work. The completion of these tests or the issue of the certificates
shall not bind the PURCHASER/ CONSULTANT to accept the equipment,
should it, on further tests after erection, be found not to comply with the
PURCHASE ORDER/CONTRACT.
27.2.12 None of the plant and the equipment to be furnished or used in connection
with the PURCHASE ORDER/CONTRACT shall be dispatched until shop
Inspection, satisfactory to the PURCHASER/ CONSULTANT has been
made. However, such shop inspection and/or certification shall not relieve
the VENDOR / CONTRACTOR of his responsibility for furnishing the plant
and the equipment conforming to the requirements of the PURCHASE
ORDER/ CONTRACT nor prejudice any claim, right or privilege which the
PURCHASER / CONSULTANT may have because of the use of defective
or unsatisfactory items. Should the PURCHASER/ CONSULTANT waive
the right to inspect any item, such waiver shall not relieve the VENDOR /
CONTRACTOR in any way from his obligation under the PURCHASE
ORDER/CONTRACT. In the event of the PURCHASER’s/ CONSULTANT 's
inspection revealing poor quality of goods, the PURCHASER/
CONSULTANT shall be at liberty to specify additional inspection
procedures, if required, to ascertain the VENDOR / CONTRACTOR's
compliance with the equipment specifications.
27.3.1 In order to facilitate the inspection of bought-out materials and plant, the
VENDOR / CONTRACTOR shall submit for approval, three (3) copies of all
suborders and sub-contracts placed by him as soon as these are issued.
Copies of any drawings referred to in the sub-order or sub-contracts shall
also be submitted, unless agreed otherwise by the
PURCHASER/CONSULTANT.
27.3.2 The sub-orders, sub-contracts and drawings referred to above shall include
all components which are subjected to electrical and mechanical pressure or
stress when the plant is in operation, and also auxiliaries and spares which
are to be directly dispatched to site from the SUB-VENDOR’s
/SUBCONTRACTOR's works.
27.3.5 Sub-ordering and sub-contracting for major items such as pressure and load
bearing items, machinery etc. can be done only with the approval of the
PURCHASER/ENGINEER.
27.5.0 WELDING
27.5.1 All welding involved in construction and fabrication of the plant and items
covered under the PURCHASE ORDER/CONTRACT shall be carried out in
accordance with specifications and applicable codes.
27.7.1 GENERAL
The tests at works shall include electrical, mechanical and hydraulic tests in
accordance with the appropriate clauses of Statutory Regulation, relevant
codes and standards and approved drawings and specifications and in
addition any test called for by the PURCHASER/ CONSULTANT to ensure
that the plant being supplied fulfils the requirements of the specifications.
The VENDOR/CONTRACTOR shall carry out all the shop tests and
inspections specified under individual items of the equipment in Section-D of
the enquiry document, in addition to those normally required as per codes
and standards.For items not covered by any code or specifically mentioned
in the specifications, the tests are to be agreed with by the PURCHASER/
CONSULTANT. If considered necessary by the PURCHASER/
CONSULTANT, multi-part assemblies shall be fully erected and tested in the
works prior to packing and dispatch to the site.
All test certificates must be endorsed with sufficient information to identify the
material or the equipment to which the certificates refer, and must carry at
the top right hand corner the identification of the PURCHASER/
CONSULTANT and the PURCHASE ORDER/CONTRACT.
27.7.3 CALIBRATION
All instruments used for critical measurement such as pressure gauges for
leak tests, instruments for measuring performance parameters; instruments
for precision dimension measurements shall have valid calibration
certificates traceable to national standards. This means that the calibrating
agency engaged by the VENDOR/CONTRACTOR shall use instruments
which are in turn calibrated by Government approved agencies and such
information shall be recorded in the calibration certificate issued by the
calibrating agency by giving the certificate number, date and date of validity
of the certificate given by the Government approved agency.
27.8.1 Cold test shall include, inter alia, completion, erection, checking of
alignments, rotation and vibration, checking of insulation, checking of cabling
interconnection, input /output connection check, calibration of instruments,
pressure testing of pipelines, idle or over-load tests.
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E1
TCE.GP/9506A/130 0
CO C 27 SHOP INSPECTION AND TESTS Chapter 27
Sheet 7of 9
27.8.2 Income of refurbishing work, improvisation required to carry out cold test is
included in Contractor’s scope.
27.8.3 The cold test shall be performed on all plant and equipments and
items,covered under the contract /order.
27.8.4 After completion of ICT, the PURCHASER will issue ICT certificate to the
contractor.
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E1
TCE.GP/9506A/130 0
CO C 27 SHOP INSPECTION AND TESTS Chapter 27
Sheet 8of 9
To,
Tata Steel Limited,
Attn: Mr/Ms
PROJECT MANAGER
Dear Sir/Madam,
Items detailed below are ready for inspection. Please arrange inspection and
confirm the date.
1. PURCHASER
2. PROJECT
5. SUB-VENDOR/SUB-CONTRACTOR
We confirm that the items have been fully inspected and tested by us. All stages of
inspection as per approved quality plan have been carried out by us and all material
test certificates, quality control records and test reports and valid calibration reports
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E1
TCE.GP/9506A/130 0
CO C 27 SHOP INSPECTION AND TESTS Chapter 27
Sheet 9of 9
of measuring and testing instruments with traceability to national level are ready with
us.
Yours faithfully,
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E2
TCE.GP/9506A/130 0
CO C 27 DRAWINGS, ENGINEERING DOCUMENTS AND Chapter 28
INSTRUCTION MANUALS Sheet 1of 7
28.1.0 SCOPE
(c) Project Title including (if applicable) number of units and unit numbers
(j) Drawings and documents shall be duly signed in ‘checked’ and ‘approved’
columns.
(m) All relevant notes to the drawings and documents. All notes necessary
for understanding and execution of work shown on a drawing or
document shall be presented on the same drawing or document.
(q) All titles, noting, markings and writings on the drawing shall be in English.
(c) Drawings and documents which are for information and records only
(Category FI)
28.2.3.2 The category of each drawing and document shall be decided by the
PURCHASER/CONSULTANT.
28.2.5.2 Drawings and documents shall be fully legible and drawn in ink and all
writing shall be clearly printed or stenciled.
28.2.5.4 Drawings and their title blocks shall be properly drawn, prepared and
printed to the approval of the PURCHASER/CONSULTANT.
(f) Reference drawings and documents along with their revision numbers
28.2.8.1 Drawings and documents shall be submitted without delay in line with the
agreed schedule as per para 28.2.4 above. Number of copies submitted to
the PURCHASER/CONSULTANT shall be as per the distribution schedule
in Section-F of the enquiry document.
28.2.8.2 The sequence of submission of drawings and documents shall be such that
all information or data is available for reviewing each drawing and
document when it is received.
28.2.8.4 Drawings and documents submitted out of sequence will be returned to the
CONTRACTOR without review for re-submission as per the sequence of
drawing and document submission.
28.2.13.1 For all revisions of the drawings and documents, the VENDOR /
CONTRACTOR shall ensure that all revisions are clearly encircled with
revision numbers marked on the drawings and documents.
28.2.14 Any manufacturing and fabrication work carried out prior to the approval of
the drawings and documents shall be at the VENDOR’s/CONTRACTOR's
own risk and expenses.
28.2.16 REPRODUCIBLES
28.2.16.3 In case the drawings and documents are prepared using drafting
software, original floppy or compact disc shall be submitted. In addition
drawings and documents on Kilburn reproducible tracings film or
equivalent shall be submitted as called for in the enquiry document.
28.4.2 If, after the commissioning and initial operation of the plant, the instruction
manuals require any modification / additions / changes, the same shall be
incorporated and the updated final instruction manuals shall be submitted
in the form of one (1) reproducible original and number of copies shall be as
per Section-F of the enquiry document.
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E3
TCE.GP/9506A/130 0
CO C 27 PACKING, MARKING AND TRANSPORT Chapter 29
INSTRUCTIONS FOR EQUIPMENT Sheet 1of 5
29.1.0 PACKING
29.1.1 All equipment and material shall be protected for ocean shipment, inland
transport, and storage at the site, according to applicable Indian Standards
(IS) and to the instructions given in this specification.
29.1.4 Any material found short upon opening the intact packing cases shall be
supplied by the VENDOR/CONTRACTOR at no extra cost to the
PURCHASER.
29.1.6 All packing cover and packing material shall become the property of the
PURCHASER.
29.1.8 For ocean transport, containers shall be used as far as possible. Dimensions
of packages and kind of packaging must be chosen to fully utilise the size of
containers.
29.1.9 All equipment shall be protected for the entire period of despatch, storage
and erection, against corrosion, incidental damage due to vermin, sunlight,
rain, high temperature, humid atmosphere, rough handling in transit and
storage in open including possible delays in transit. Material and equipment
shipped across the sea shall be packed to withstand without damage, the
effects of saline atmosphere. All machined and plated parts shall be
protected with anti-rust grease. Precautions shall be taken to protect shafts
and journals where they rest on wooden or other supports likely to contain
moisture. At such points, wrappings impregnated with anti-rust composition
or vapour phase inhibitors shall be used. These shall have sufficient
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E3
TCE.GP/9506A/130 0
CO C 27 PACKING, MARKING AND TRANSPORT Chapter 29
INSTRUCTIONS FOR EQUIPMENT Sheet 2of 5
29.1.10 All openings in the equipment shall be tightly covered, plugged or capped to
prevent foreign material from entering into the equipment.
29.1.11 The contents of the packages shall be sealed in thick polythene sheets.
The inside walls of the packages shall be lined with waterproof material to
protect the equipment from damage due to dust and moisture.
29.1.12 Adequate provision of skids or pallets shall be made to keep the packages
above the ground drain water. Crates and other large containers should
have drain holes in the bottom to prevent collection of water within the
packing. This is especially important where the cargo itself is subjected to
condensation (cargo sweat).
29.1.14 All cases shall be provided with suitable cut-outs, closed by bolted wooden
planks to facilitate inspection by custom authorities. Waterproof transparent
papers shall be provided at the cut-out locations to prevent water ingress
into the casing through the cut-out.
29.1.15 The contents of the package shall be punched on non-corrosive metal plate
and nailed to the package on a prominently visible place. If the number of
items in the package is too many, a typed list in transparent waterproof bag
shall be kept inside a galvanised sheet steel pocket nailed on to the outside
of package at prominently visible location. Copies of the packing list, in
triplicate, shall be forwarded to the PURCHASER prior to despatch. All
items of material shall be clearly marked for easy identification against the
packing list.
29.1.16 Fragile materials shall be securely braced within the package or otherwise
amply fastened and packed to prevent shifting or rattling. Soft non-
hygroscopic packaging materials shall be placed between the hard packing
materials and the fragile equipment. Articles, which do not completely fill the
selected package/container, must be cushioned, braced, fastened or
blocked to prevent damage to the article itself or destruction of the package.
Inner bracing or blocking must be such that the content's weight is
distributed over interior surfaces rather than concentrated at one or two
points.
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E3
TCE.GP/9506A/130 0
CO C 27 PACKING, MARKING AND TRANSPORT Chapter 29
INSTRUCTIONS FOR EQUIPMENT Sheet 3of 5
29.1.18 All flanges, etc., which are prone to scratching shall be provided with either
metal or wooden or plastic blanks bolted in place. Metal blanks should have
a minimum thickness of 3 mm and wooden blanks should be made from two
layers of wood, each of 10 mm thickness, nailed together with the grain of
each layer located at right angles to one another.
29.1.19 Loose material, e.g. bolts, nuts, etc. shall be packed and sealed in
polythene bags with proper tagging and packed in cases.
29.1.20 All spare parts shall be packed and treated for long storage conditions at
site.
29.2.0 MARKING
29.2.1 All packages shall be clearly, legibly and durably marked with uniform block
letters (preferably with waterproof paint) on at least three sides with:
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E3
TCE.GP/9506A/130 0
CO C 27 PACKING, MARKING AND TRANSPORT Chapter 29
INSTRUCTIONS FOR EQUIPMENT Sheet 4of 5
29.3.0 TRANSPORT
29.3.2 Depending upon the equipment and the mode of transport the VENDOR/
CONTRACTOR may propose to deliver the equipment in container or as
Break Bulk i.e. in components or sub-assembly form.
29.3.6 Immediately after the shipment has been effected, the shipping documents,
comprising Bill of Lading, Freight Invoice, FOB/FAS/FOR/FOT/FAT/FAR
Invoice, Packing List, Certificate of Origin, Letter to Insurers and Certificates
of Inspection shall be issued by the VENDOR/CONTRACTOR in
accordance with the instructions of the PURCHASER/CONSULTANT.
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E3
TCE.GP/9506A/130 0
CO C 27 PACKING, MARKING AND TRANSPORT Chapter 29
INSTRUCTIONS FOR EQUIPMENT Sheet 5of 5
These documents shall reach the PURCHASER before the arrival of ship.
Responsibility for delays, loss or damages of shipping documents shall rest
with the VENDOR/ CONTRACTOR.
29.4.1 Transformers rated 2000 kVA and less shall be shipped filled with oil.
Transformers rated above 2000 kVA shall be shipped without oil but with
the tank filled with nitrogen or equivalent inert gas. A gas cylinder with
suitable reducer connection and pressure gauge shall be supplied. These
accessories shall become the property of the PURCHASER. The required
quantity of oil shall be supplied separately in non-returnable drums.
29.4.2 Switchgear cubicles and instrument control panels shall be packed and
shipped in separate and convenient sections. All withdraw able equipment
like circuit breakers and circuit breaker arc-chutes shall be packed and
shipped separately. All relays and panel-mounted instruments shall be
packed and shipped separately with their operating mechanisms
temporarily arrested from movement during transport.
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E4
TCE.GP/9506A/130 0
CO C 27 SPARES AND MAINTENANCE TOOLS AND TACKLES Chapter 30
Sheet 1of 2
30.1.0 GENERAL
30.1.1 All spares and maintenance tools and tackles shall be designed to enable
maintenance to be carried out in the least time and at the least cost and
support resources without affecting the performance and safety aspects.
30.1.2 For all major equipment including pumps, fans, drives, heat exchangers and
large valves etc., appropriate structural steel members shall be provided for
mounting various handling devices which are necessary for the dismantling
and re-assembly of the equipment components during maintenance.
30.1.3 All the spares and maintenance tools and tackles supplied shall be new and
unused.
30.2.0 SPARES
The BIDDER shall include the following two (2) categories of spares in his
scope of supply.
30.2.4 All spares supplied shall be strictly inter-changeable with the parts for which
these are intended to be replacements. The spares shall be treated and
packed for long term storage under the climatic conditions prevailing at the
site e.g. small items shall be packed in sealed transparent plastic bags with
desiccators packs as necessary.
30.2.5 Each spare shall be clearly marked or labelled on the outside of its packing
with its description and purpose. When more than one spare is packed in a
single case, a general description of the contents shall be shown on the
outside of such case and a detailed list enclosed. All cases, containers and
other packages shall be suitably marked and numbered for the purposes of
identification.
30.3.1 The BIDDER shall indicate and include in his scope of supply all the
necessary tools, tackles, appliances and lifting devices for the effective
maintenance and servicing of the equipment and its components. The
BIDDER shall list themaintenance tools and tackles offered by him in
TCE.M4-982 ‘Schedule of Maintenance Tools and Tackles’. The BIDDER
shall also include and supply the minimum maintenance tools and tackles, as
called for in section C and D of the Enquiry Document. PURCHASER
reserves the right to exclude any of the aboveitems from the
VENDOR's/CONTRACTOR's scope of supply and effect priceadjustments on
the basis of the unit prices quoted. The dispatch of tools, tackles, appliances
and lifting devices shall be synchronized with the dispatch of the related
equipment.
30.3.2 Each tool and tackle shall be clearly marked with its size and purpose. Each
set of tools and tackles shall be suitably arranged in fitted boxes of mild steel
construction,the number of boxes being determined in relation to the layout
of the plant in question. The taps, stocks and dies shall be kept in approved
mild steel boxes with compartments for individual items. If the weight of any
box and its contents is such that it cannot be conveniently carried, it shall be
supplied on steerable rubber tires wheels.
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TATA Consulting Engineers Limited SECTION: E4
TCE.GP/9506A/130 0
CO C 27 SPARES AND MAINTENANCE TOOLS AND TACKLES Chapter 30
Sheet 3of 2
30.3.3 Each tool box shall be provided with a lock and two keys and shall be
painted navy blue and clearly marked, in white letters, with the name of
the equipment, plant or system.
30.3.4 The tools and tackles with the appropriate boxes, are to be handed over to
the PURCHASER at the time of issue of the taking-over certificate.
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC NO: TCE.M4- TATA Consulting Engineers Limited SECTION:F1
SCHEDULE OF GENERAL PERTICULARS Chapter 31
Sheet 1of 2
ISSUE
ISSUE
R0R0 ISSUE
R0
SPEC
TCE CONSULTING ENGINEERS LIMITED
NO. SECTION: F2 Chapter 32
SHEET 1 OF 2
TCE.GP/9506 SCHEDULE OF PRICES
A/130 0 CO C
27
GENERAL NOTES
1. This schedule shall be read in conjunction with the enclosed specification and drawing. BIDDER is deemed to have examined the technical and general conditions of Contract and to
have acquainted himself with the site conditions and the details of the work to be done and the manner in which the work is to be executed at site.
2. The price shall include cost of all materials, labour, tools, equipment and all requirements, temporary works and contingencies whether referred to or not in the specification for the
satisfactory and proper completion of the job.
3. BIDDER shall quote his rates against items of work listed which may be required to be executed by him as a variation from the price quoted and for works which may not fall under the
price.
4. The rates quoted shall be reasonable and shall compare favourably with estimated rates. Therefore all the rates quoted under these schedules will be scrutinised item by item with the
estimated rates and CONTRACTOR shall abide by negotiated rates.
5. Rates and prices shall be written in ink and shall be entered both in figures and words. Where there is a discrepancy between the rates quoted in figures and words, the rates in words
shall prevail. Where there is a discrepancy between the rates and amount, the former shall govern for the correct amount.
6. The unit rates quoted shall include for minor details of construction which are obviously and fairly intended and which may not have been referred to in this document but are essential for
the satisfactory completion of the work.
7. The rates shall include cost of dewatering wherever necessary and the OWNER will entertain no claim for payment on this account.
ISSUE
R0 ISSUE
R0
SPEC
TCE CONSULTING ENGINEERS LIMITED
NO. SECTION: F2 Chapter 32
SHEET 2 OF 2
TCE.GP/9506 SCHEDULE OF PRICES
A/130 0 CO C
27
Ex-
Sr. works Excise
No Brief Description Qty. Unit Price duty Edu cess Sales tax Freight & ins. Unit Price Total Price
Rs. Rs. Rs. Rs. Rs. Rs.
1
2.0 Supply of Electrical Equipments lot
1
6.0 Construction lot
7.0 Commissioning
ISSUE
R0 ISSUE
R0
SPEC NO: TCE.M4- TATA Consulting Engineers Limited SECTION:F3
998
SCHEDULE OF DEVIATIONS FROM GENERAL Chapter 33
CONDITIONS Sheet 1of 1
All deviations from the Technical Specification shall be filled in by the BIDDER clause by clause in
this schedule.
The BIDDER hereby certifies that the above mentioned are the only
deviations from the Technical Specifications for this enquiry. The BIDDER
further confirms that in the event any other data and information presented in
the BIDDER’s proposal and accompanying documents including drawings,
catalogues, etc., are at variance with the specific requirements laid out in the
Technical Specifications, then the latter shall govern and will be binding on
the BIDDER for the quoted price.
NAME ___________________
DESIGNATION ___________________
COMPANY ___________________
ADDRESS ___________________
DATE ___________________
ISSUE
R0 ISSUE
R0
SPEC NO: TCE.M4- TATA Consulting Engineers Limited SECTION:F4
998
SCHEDULE OF DEVIATIONS FROM TECHNICAL Chapter 34
SPECIFICATIONS Sheet 1of 1
All deviations from the Commercial Conditions of the specification shall be filled in by the BIDDER
clause by clause in this schedule.
The BIDDER hereby certifies that the above mentioned are the only
deviations from the Owner’s Commercial Conditions of Specification. The
BIDDER further confirms that in the event any other data and information
presented in the BIDDER’s proposal and accompanying documents are at
variance with the specific requirements laid out in the Owner’s Commercial
Conditions of Contract, then the latter shall govern and will be binding on the
BIDDER for the quoted price.
NAME ___________________
DESIGNATION ___________________
COMPANY ___________________
ADDRESS ___________________
DATE ___________________
The BIDDER shall indicate below a list of similar jobs executed by him, to whom a
reference may be made by the PURCHASER.
ISSUE
R0 ISSUE
R0
SPEC NO: TCE.M4- TATA Consulting Engineers Limited SECTION:F5
998
Chapter 35
SCHEDULE OF BIDDERS EXPERIENCE Sheet 1of 1
ISSUE
R0 ISSUE
R0