Académique Documents
Professionnel Documents
Culture Documents
INTRODUCTION
construction, alteration and repair. According to Memon et al. (2014), the GDP
growth of the construction sector has recorded a growth of 22.2% in the second
infrastructure, utility and oil and gas projects, making construction industry as
one of the key industries in Malaysia. Such projects are like Seremban Gemas
Double Track, the Second Penang Bridge and Melaka Regasification Terminal.
al. (2010) mentioned that one of the many major problems faced by construction
projects is the issue of variation order, occurring during the construction phase.
of any work; the alteration of the kind or standard of materials or goods; the
1
removal from site of work, materials or goods that were formerly in accordance
with the contract, but which now have been changed and change in the
circumstances in which the work is carried out such as; access and use of site;
limitation of working space; limitation of working hours and changes made to the
sequencing of work. Variation also means any addition, deletion, or any other
revision to project goals and scope of work, whether they increase or decrease
Variation orders are the changes that are inevitable in any construction
project (Shahin et al., 2016) and it will affect the project performance itself. It
becomes more impossible to avoid for the project which are larger in size and
created, it gives several negative effects to both the client and the contractor. As
significant implications on cost, time and quality of construction. Not only that, it
also affects health, safety and professional relations (Halwatura & Ranasinghe,
even though there are many attempts and strategies have been done at the pre
contract stage, for instance by doing a modern planning, using overall checklist
and other solutions, the variations in construction projects are still not easy to
Despite all those negative implication that variation order may bring to
any disruptions associated in the construction site, to fulfill the demand, current
2
policies and laws, improving as well as other related causes that required by the
difficulty in the projects. Meanwhile, detrimental variations are those that reduce
owner value or have a negative influence on a project. So, project team should
the earliest stage possible, since the problem can be identified and beneficial
3
1.2 AIM
for civil engineering works and to provide understanding of what are the causes
1.3 OBJECTIVES
To achieve the aim and as a guide for this research, the specific objectives are
performance.
one of the major setbacks for construction projects, and that includes for civil
engineering projects. There are many factors that contribute to the changes and
the effects of such are also varied depending on its causes. A study by
Halwatura and Ranasinghe (2013) identified that poor estimation is the main
4
Variations and changes are expected in any construction projects.
contractual disputes and claims, and time overruns were found to be the top
Kenya. Sharifah Suzanna (2009) also found that variation orders issued during
When a variation order is created, it does not only bring several effects to
both contractor and client, but also to other construction project’s stakeholders.
They are the project’s stakeholders such as architects, quantity surveyors and
stakeholders about variation order specifically for civil engineering works, the
I. It is only focusing on the variation order for civil engineering works from
stakeholders’ perspectives,
II. The respondents involved were only the architects, quantity surveyors,
5
1.6 RESEARCH METHOLOGY
from various sources. It involved three main stages starting from collecting the
data, analysis the data, conclusion and recommendation related to the topic.
i. Phase One
form a base of this research. The source of data obtained is from the
be defined in this phase. Besides, analysis from the case study and
6
The process of research methodology can be summarized as Figure 1.1 below.
LITERATURE REVIEW
Gather information from article, journal, web site,
PHASE 1 conference reports and journals
DATA COLLECTION
From Case study and Questionnaire survey
PHASE 2
FINDINGS
CONCLUSION AND RECOMMENDATION
PHASE 3
Chapter 1: Introduction
scope of study, issues or problems statements and methodology that had been
distinguished the need and objective of this dissertation. It reveals clearly the
7
scope of study and the methodology that been used for collecting the relevant
This chapter explains how author carried out the research from the beginning
until the analysis. This chapter also acts as the guideline in achieving the
In this chapter. There are the findings gained from the research which are
carried out in early stage from a set of questionnaire which will be distributed to
8
Chapter 5: Conclusion and Recommendation
The last chapter will describe the conclusion the covered the whole research
that had been done. It also stated the best recommendation for the future used
CHAPTER 2
VARIATION ORDER
9
2.1 INTRODUCTION
process and parties involve in variation order procedure and the general
overview on civil engineering works. Next, this chapter will review on the
variation orders. Other than that, the effects of variation order, the proactive
measures to reduce variation order and last but not least the contractual
2.2.1 Definition
similar with Nurul Shuhada (2017) which defines variation as the change,
10
other contract documents, as well as a change in cost, which is based on
materials or goods to be used in the work, and the removal of any work,
materials or goods that are from site which are not accordance in the
contract. (Uyun, 2007). On the other hand, Oloo et al. (2014) describes
the work or an adjustment in the contract sum or even the contract time.
2005)
scope, execution time or cost of work while Memon et al. (2014) define
that variation order is the deviation experienced in any project from base
identifies the change in price and time and describes the nature of the
work involved.
11
Variation, according to Oladapo (2007), is any change to the
basis on which the contract was signed. Variation involves not only
the conditions of the contract but also changes to the working conditions
themselves. Variations are only the changes made within a contract but
1994). It may be issued at any time before the practical completion date.
and the extra works. It is including the changes to the method of work,
The word ‘formal’ implies legal binding as such all variations should be in
mandatory form, clients usually have their own forms and procedures
12
2.2.2 Classification of Variation Order
having beneficial variation order in the project, it will optimize the client’s
costs. Beneficial changes do not only give a fast and proactive effect, but
they also enable to give the platform and environment for managers to
variation order as the one that negatively impacts the client's value or
13
Mohammad et al. (2010) mentioned that changes in a
reviews.
14
i. Identity of initiator
15
ii. Nature of variation
at any cost.
16
Besides that, Sim (2007) also mentioned that there are three
i. Additions
of works.
ii. Omissions
iii. Hybrid
17
2.2.3 General Process and Parties Involve in Variation Order
18
from the funding sources (Client), the contractual
19
v. Application to the Employer
order.
20
Negotiation, Facilitation, contemporary record keeping
facilities that affect the life of human beings. It is closely linked to the
design the structure in such a way that it can effectively support itself
along with resisting loads. The stability of the design will act as the
ventures meant for civil building and engineering. The technology used in
our daily lives has all been designed on the basis of civil design and
among structures, the earth and water, with applications ranging from
21
building or public-works project may require extensive planning, civil
airports.
iv. Devise systems for the control and efficient flow of traffic.
v. Plan and build river navigation and flood control projects.
vi. Provide plants and systems for water supply and sewage and
refuse disposal.
sub-disciplines that are intimately associated with each other. These are
22
This discipline involves the design of structures that
design and analysis should first define the loads acting on the
bridges.
23
2.2.4.4 Water Resources Engineering
environmental science.
(Arain & Pheng, 2005). Although no one can assure that variation order can be
and minimized if their origin and causes are clearly determined (Enshassi et al,
to the construction projects. Some factors are foreseeable, others are not
variation orders in construction project, both on the private and public projects.
24
Memon et al. (2014) have listed numbers of causes of variation orders.
The causes are the change of schedule, change in scope, Client’s financial
among contract documents and many others. Based on a research carried out
by Kaming et al. (1997), they also added that the major factors influencing cost
overrun for high-rise projects in Indonesia were the increase of material cost due
While in the case of time overrun, the most important factors that caused delays
resource shortage.
A study that is conducted by Arain and Pheng (2006) have identified four
orders.
2.3.1 Agents
2.3.1.1 Client
25
is made up of a heterogeneous group of individuals and
26
i. Change of scope
v. Replacement of materials
are two types of Clients exist. One is the Clients who have
professional team.
27
difficult to determine the exact requirements of the client.
maintenance cost.
2.3.1.2 Consultant
i. Change in design
v. Design complexity
28
vii. Lack of consultant's knowledge of available
29
lead to variation orders; issued to ensure compliance with
2.3.1.3 Contractor
30
v. Defective workmanship
his knowledge in the field will work better and fit the
31
Consultant’s decision. All has to be done relatively quickly
project’s productivity.
32
2.3.2 Problems Encountered When Managing Variation Orders
the architect requiring the contractor to alter the works in any of these
to charge the Client with higher rates for the variation items. This will
construction projects. That is why there is a high chance that there might
be disputes between the Client and the Contractor regarding time and
cost.
33
metropolitan, the problems encountered when negotiating variation
variation order. She has classified the problems into seven categories
that have been identified and three main reasons among them are the
2.3.2.1 Quality
34
Therefore, this shows that the existence of
2.3.2.2 Time
much longer when the works are difficult and need of high
countries.
35
distracted in managing the changes in his work schedule
2.3.2.3 Cost
location to another.
36
Not enough with that, contractors have to consider
the supplier, costs of the operator and fuel and also the
37
2.4 Effects of Variation Order
achieve to its maximum if the work invariably flows smoothly within time limits
uncommon that projects can perform precisely to their original schedule due to
Oyewobi et al. (2015) contended that effective project performance and delivery
can only be achieved when factors which have potentially negative effects on
possibly eliminated. There are obvious evidences from various literatures that
increase in the project cost (Arain & Pheng, 2005). Many of authors have
38
of terrace housing projects, Mohammad et al. (2017) have identified that
the changes of work have caused the project cost to increase by 14%
from the original cost. Charoenngam et al. (2003) have reported that his
research have shown that average cost escalation was 7% of the original
project cost with an average time extension of 30% than the originally
project cost.
and demolition. Oladapo (2007) also stated that projects in Nigeria are
construction cost exhibits the most significant impact with the severity
Ndihokubwayo and Haupt (2008) added that the more the variation
39
orders, the more they will impact on the overall construction delivery
cost. Their study concluded that variation order can give some cost
fees; iii) cost of resources that were used to carry out the
cash flow; ii) loss of productivity; iii) cost for redesign and
40
2.4.2 Time overruns
reasons for project time overruns. For example, a study of delays and
housing projects contended that the leading effect of the changes is the
construction.
41
and it was identified that time overruns was the third most important
construction phase. This will adversely affect the project and may cause
compensate for the losses from variations by cutting corners (Manzoor &
variables such for example lump sum, contractors may cut corners on
compensate for the losses as they are not optimistic at about cost
there are variations occurred. She then added that if there are too many
fear of the possibility for changes. This will result in a poor and little
and Low (2006) stated that poor relations and disputes among
al. (2010) that studied the effects of change orders on public construction
projects in Oman and found that disputes is one of the most ranked
that the effects of change orders are difficult to quantify, which often lead
43
2.5 Proactive Measures to Reduce Variation Order from
Academic Literature
the contract duration, total direct and indirect cost, or both. With so many
a project without changes to the plans or the construction process itself. Every
problems has its own solutions. Although variations and changes are said to be
authors, there are several common control procedures that can be applied to
44
that the Client is the main source of the variation orders in construction
study by Halwatura and Ranasinghe (2013), it was also stated that the
variation orders.
According to Hanif et al. (2016), in order to cater the problem, errors and
project.
as their study stated that the most familiar effect of variations which is
45
increase in project cost could be minimized through successful project
management.
to variations too (Oloo et al., 2014). Oyewobi et al. (2016) said that
the increase in project cost that was stem from variation order. Halwatura
stage, which is in the pretender period. Not only that, works should
one of the most effective ways to reduce the influence of change orders
which enables the digital sharing of reports images, and data among
46
consultants involved in the construction of which must be implemented to
(2013), they concluded that the Sri Lankan context should pay more
2005).
clear as possible as to what work is being done during the project and
who is doing it. Every aspect of project work should be covered for both
Client's and contractor's point of view who are the points of contract
(2010), the authors suggested that the project owner should provide a
47
Oloo et al. (2014) have concluded based on their findings that in order to
whether the project is viable and to help identify feasible options. It tells
conditions necessary for design Oloo et al. (2014). Pitroda (2015) also
added that Client should carry out proper feasibility study and survey
before the design stage. Mohammad et al. (2017) in their study have
suggested for improvement that the client must provide the requirements
feasibility study.
48
2.6 Contractual Provisions Relative to Variation Order
Variation orders usually happen to most projects and are very common
with large projects. The Client or the consultants for like the architect, project
submission and approval of a variation order, it usually helps to alter the original
contract so that the variation order is now part of the contract. The contractual
to the project, the procedures to make a change set forth in the contract
between the owner and the contractor must be consistent with the variation
order process set forth in the contract between the contractor and his
can also affect unintended consequences (Hao et al., 2008). The contractor
must therefore take this matter seriously when contracting not only with the
the clause most often relied on by contractors and subcontractors when looking
for extra cost recovery, and also becomes one of the root of project conflicts at
49
all times. Thus Jayalath (2012) concluded that, it is important for contractors to
understand what was specified in the standard variation order clause and what it
encompasses. This section will generally focus on the main two commonly used
Contract Forms by construction contracts which are P.W.D 203A revision 1/2010
and P.A.M Contract 2006 (With Quantities). Both of these Standard Form of
respectively.
mentioned that the standard form is usually used in conjunction with the
contract conditions and is clarified briefly under Clause 24.0 and Clause
variation orders, the process of variation orders, and how the parties
50
Clause 24.1 of Form of Contract P.W.D 203A notes that if there
are any works involving a variation, S.O must issue a variation order.
to the work. (Nurul Shuhada, 2017). The variation instructed by the S.O
shall not made void to the original contract between the Government and
the Contractor. Nurul Shuhada (2017) added that the main idea of this
condition is that to ensure that the variation order made does not allow
the Contractor to treat the contract as at end. Also, the claim paid should
also comply with the term of the contract as stated in the clause 25 of the
the specific duration for the Contractor to carry out the Variation Order's
variation by S.O.
outlines the meanings and interpretation of the variation and this Clause
goods to be used for the works. It must also include the removal off the
except if the work, materials or goods are not following the conditions in
the contract. She added that the S.O should advice only to omit any work
51
the contract, which are the responsibility of the Contractor, cannot be
Contractor.
made under Clause 24.0 to carry out his work as outlined in Clause
S.O on the basis of the provision specified in the contract form after the
duty to measure and value the variations carried out by the Contractor or
and the S.O as long as the contract sum is not affected. That being so, in
and rules such as Bill of Quantities’ rate, fair adjustment rate, agreed rate
52
Based on any required regulations of variation used, after having
the Contract Sum and will be adjusted accordingly. It also allowed the
clearly stated in the Clause 25.3 of the P.W.D 203A Form of Contract.
under the Clause 11.0 until the Clause 11.9. These clauses provide a
brief explanation of the roles and obligations of each party involved in the
work of the variation order before, during and after the works of the
earlier. Nurul Shuhada (2017) stated that there are a total of five broad
area of variation term in this contract form for the purposes of the
53
203A Contract Form, both are almost the same. Provided that, there are
Clause 11.1(d), mentioned that variation shall also be taken into account
when there is any changes to the provision of the contract in the situation
of any particular part of the site and also the execution and completion of
project. The instructed variation order will not vitiate the Client's original
contract with the Contractor. Moreover, the clause also enhances the
contractor's right not to delay the execution of the works of the variation
carry out all instructed variations with due diligence and expedition
that the variation order still can be issued even if the Contractor is in
issued. She even added that any variation order issued after the
54
express clause in the contract authorizing that variation order to be
Authority and Service Provider. All of these conditions have all been
Over and above that, there are also clauses spell out in P.A.M
site information and/or site measurements that are carried out at the site
(Nurul Shuhada, 2017). However, Quantity Surveyor does not have any
valuing the specific works involved while the quantity surveyor remains
2.7 Summary
all parties involved in the construction project. The effectiveness and severity of
the variation works in construction projects often depends on how the parties
involved are able to manage them. This is also including when the parties have
project.
CHAPTER 3
RESEARCH METHODOLOGY
3.1 INTRODUCTION
This chapter outlines the methods of study and describes the tools and
investigated what data will be collected using what methods and how this
reach the objectives and scope of the study. This chapter will be discussing
56
comprehensively about the research procedures involved throughout the study.
The chapter will also address the research process in depth from how the data
clear which type of data is needed to analyze the problem and what type of
analysis is most appropriate for analyzing the data (Walliman, 2005). The
order for civil engineering projects, the causes of the variation order and its
be used to achieve the goals of the study. Therefore, every measure taken must
be appropriate and relevant to this topic of study. Fellows & Liu (1997) stated
that the methods of collecting data give an impact upon the analyses which may
Throughout this study two methods were performed to collect accurate and
57
from Jabatan Kerja Raya (JKR) Melaka and have involved in civil
engineering projects.
that the researcher would like to ask to the respondents and record their
generated.
and viewpoint.
topics related to the subject. Two distinct literature studies were adopted
59
variation order for civil engineering works, causes and the
from websites.
60
3.3 RESEARCH INSTRUMENT
containing several questions which are divided into numbers of sections were
the organization, his work experience and also what kind of projects the
respondents involved.
61
In this section, the questions asked on the respondents’
occurred.
the questions, the respondents need to state other effects which can
contribute to variation orders other than what have been listed in the
62
previous question. The respondents also need to give their suggestions
projects.
Engineers and Quantity Surveyors, who are from Jabatan Kerja Raya (JKR)
This is because they may have more experience in the project management and
The data will be analyzed by using Statistical Package for Social Science
software. The following methods are the statistical methods that have been used
63
In analyzing the data, the following assumed values have been
order for civil engineering works and also ways to minimize it.
order for civil engineering works and also ways to minimize it, the
The types, causes, effects and solution of variation order for civil
MS = ∑ (f x s)
N
64
REFERENCES
Al-Hadhrami, S.M. (2011) Analysis of Impact of Variation Request in the Construction
Industry of Oman, Unpublished Thesis (Master), Heriot-Watt University
Alnuaimi, A. S., Taha, R. A., Al Mohsin, M., & Al-Harthi, A. S. (2009). Causes, effects,
benefits, and remedies of change orders on public construction projects in Oman.
Journal of Construction Engineering and Management, 136(5), 615-622.
Arain, F. M., & Pheng, L. S. (2006). Developers' views of potential causes of variation
orders for institutional buildings in Singapore. Architectural Science Review, 49(1), 59-
74.
Awad, M. (2001). Analysis and management of change orders for combined sewer flow
construction projects. Unpublished Dissertation, Wayne State University.
Burati Jr, J. L., Farrington, J. J., & Ledbetter, W. B. (1992). Causes of quality deviations
in design and construction. Journal of construction engineering and management,
118(1), 34-49.
Chan, A. P., & Yeong, C. M. (1995). A comparison of strategies for reducing variations.
Construction management and Economics, 13(6), 467-473.
65
Choudhury, I. & Sanampudi, V. (2008). Effects of Construction Cost and Change Orders
on Construction Time for Industrial and Commercial Projects in India. Building Abroad,
Montreal, Canada.
Dickson, O. D., Gerryshom, M., & Wanyona, G. (2015). Variations in civil engineering
construction projects in Kenya: Causes and effects. International Journal of Engineering
Research and Technology, 4, 1124-1129.
Enshassi, A., Arain, F., & Al‐Raee, S. (2010). Causes of variation orders in construction
projects in the Gaza Strip. Journal of Civil Engineering and Management, 16(4), 540-
551.
Fellows, R. F., & Liu, A. M. (2015). Research methods for construction. John Wiley &
Sons.
Hanif, H., Khurshid, M. B., Lindhard, S. M., & Aslam, Z. (2016). Impact of variation
orders on time and cost in mega hydropower projects of Pakistan. Journal of
Construction in Developing Countries, 21(2), 37.
Hanna, A. S., Camlic, R., Peterson, P. A., & Nordheim, E. V. (2002). Quantitative
definition of projects impacted by change orders. Journal of Construction Engineering
and Management, 128(1), 57-64.
Hao, Q., Neelamkavil, J., & Shen, W. (2008). Managing changes in construction.
Institute for Research in Construction, National Research Council Canada.
Ibbs, C. W., Wong, C. K., & Kwak, Y. H. (2001). Project change management system.
Journal of management in engineering, 17(3), 159-165.
Ismail, A., Pourrostam, T., Soleymanzadeh, A., & Ghouyounchizad, M. (2012). Factors
causing variation orders and their effects in roadway construction projects. Research
Journal of Applied Sciences, Engineering and Technology, 4(23), 4969-4972.
Jawad, R., Abdulkader, R., & Ali, A. A. (2009). Variation orders in construction projects.
Journal of Engineering and Applied Sciences, 4(3), 170-176.
66
Jayalath, C. (2012). Understanding the Generality of Variation Clauses and the Variety
of Broad Interpretation that Exists under FIDIC Based Contract Modalities in Gulf.
Retrieved 17 October 2019, from http://www.cmguide.org/archives/3215
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing
construction time and cost overruns on high-rise projects in Indonesia. Construction
Management & Economics, 15(1), 83-94.
Karimidorabati, S., Haas, C. T., & Gray, J. (2016). Evaluation of automation levels for
construction change management. Engineering, Construction and Architectural
Management, 23(5), 554-570.
Koushki, P. A., Al‐Rashid, K., & Kartam, N. (2005). Delays and cost increases in the
construction of private residential projects in Kuwait. Construction Management and
Economics, 23(3), 285-294.
Manzoor Arain, F., & Sui Pheng, L. (2005). The potential effects of variation orders on
institutional building projects. Facilities, 23(11/12), 496-510.
Memon, A. H., Rahman, I. A., & Hasan, M. F. A. (2014). Significant causes and effects
of variation orders in construction projects. Research Journal of Applied Sciences,
Engineering and Technology, 7(21), 4494-4502.
Mohammad, N., Ani, A. C., Rakmat, R. A. O. K., & Yusof, M. A. (2010). Investigation on
the causes of variation orders in the construction of building project–a study in the state
of Selangor, Malaysia. Journal of Building Performance, 1(1).
Mohammad, N., Ani, A. I. C., & Rakmat, R. A. O. (2017). Causes and effects of variation
orders in the construction of terrace housing projects: A case study in the State of
Selangor, Malaysia. International Journal of Supply Chain Management, 6(1), 226-232.
Motawa, I. A., Anumba, C. J., Lee, S., & Peña-Mora, F. (2007). An integrated system for
change management in construction. Automation in construction, 16(3), 368-377.
Muhammad, N. Z., Keyvanfar, A., Majid, M. Z. A., Shafaghat, A., Magana, A. M., &
Dankaka, N. S. (2015). Causes Of Variation Order In Building And Civil Engineering
Projectsin Nigeria. Jurnal Teknologi, 77(16).
67
Ndihokubwayo, R. (2009). Variation orders on construction projects: value-adding or
waste?.
Ndihokubwayo, R., & Haupt, T. C. (2008). Uncovering the origins of variation orders.
Neupane, A. (2017, January 24). Variation Orders: Importance and Procedures for
Nepalese Construction Industry. Retrieved October 13, 2019, from
https://www.linkedin.com/pulse/variation-orders-importance-procedures-nepalese-
industry-neupane.
68
Understand Building Construction. (n.d.). Civil Construction. [online] Available at:
http://www.understandconstruction.com/civil-construction.html [Accessed 16 Oct. 2019].
Uyun, N. M. Y. (2007). Variation Control Affecting Construction Works for Lembaga
Kemajuan Tanah Persekutuan (Felda)”, Thesis, University Technologi Malaysia.
Walliman, N. (2005). Your research project: a step-by-step guide for the first-time
researcher. Sage.
Xavier, G., (1994) Variation in the Construction Industry. Malayan Law Journal Articles,
3 (1)
Zakaria, Z., & binti Ismail, S. (2013). An overview of comparison between construction
contracts in Malaysia: The roles and responsibilities of contract administrator in
achieving final account closing success.
69
70