DATE STARTED : JUNE 3, 2018

ORIGINAL COMPLETION DATE : OCTOBER 30, 2018


ORIGINAL CONTRACT DURATION : 150 CALENDAR DAYS
IMPROVEMENT/ CONSTRUCTION OF DRAINAGE ALONG JCT.JP. CABAGUIO AVE., VILLAMO
CONTRACTOR : RELY CONSTRUCTION & SUPPLY
ORIGINAL CONTRACT AMOUNT : P 16, 325, 389.43
ITEM NO DESCRIPTION OF WORK UNIT QUANTITY UNIT PRICE AMOUNT REL. WT. 1st Quarter
ACCOMPLISHMENT
37 CD
PRESENT % PREVIOUS % QTY TOTAL % 2.80%
PART B. OTHER GENERAL REQUIREMENTS -
B-5 Project Billboard/ Signboard EACH 2.00 3,988.50 7,977.00 0.049 0.0 2.00 0.0
B-7 Occupational safety and Health Program MO 5.00 23,120.53 115,602.65 0.708 0.1 1.00 0.1
B-8 Traffic Management MO 5.00 102,756.19 513,780.95 3.147 0.6 1.00 0.6
B-9 Mobilization/ Demobilization LS 1.00 138,794.14 138,794.14 0.850 - - -
B.4(1) Construction Survey and Staking KM 0.53 20,971.88 11,073.15 0.068 0.0 0.265 0.0
PART C. EARTHWORKS
101(2) Removal OF Actual Structures/ Obstruction ( Conc. MH) EACH 4.00 19,899.57 79,598.28 0.488 - - -
101(3)B1 Removal of Actual Structures/ Obstruction (0.15m Thk. PCCP) SQ.M. 1,408.00 75.07 105,698.56 0.647 - -
101(3)B2 Removal of Actual Structures/ Obstruction (0.20m Thk. PCCP Unreinforced) SQ.M. 1,020.00 141.90 144,738.00 0.887 - -
101(4)A3 Removal of Actual Structures/ Obstruction (910mm dia RCPC) LN.M. 315.00 686.97 216,395.55 1.326 - -
101(6) Removal of Structures and Obstruction ( Stone Masonry) CU.M. 40.50 412.08 16,689.24 0.102 - -
102(2) Surplus Common excavation CU.M. 408.00 174.57 71,224.56 0.436 - - -
103(3) Foundation Fill CU.M. 12.21 1,100.00 13,431.00 0.082 - -
103(6)A Pipe Culvert and Drain Excavation CU.M. 2,015.61 283.12 570,659.50 3.496 - -
105(1)A Subgrade Preparation SQ.M. 2,428.00 18.65 45,282.20 0.277 - -
803(1)A Structure Excavation Common Soil CU.M. 153.92 279.87 43,077.59 0.264 - - -
PART D. SUB-BASE & BASE COURSE
200(1) Aggregate Subbase Course CU.M. 981.20 792.40 777,502.88 4.763 - -
PART E. SURFACE COURCE -
311(1)c3 Portland Cement Concrete Pavement ( Unreinforced 230mm THK. 3 Days) SQ.M. 2,428.00 1,538.27 3,734,919.56 22.878 - -
311(1)e3 Portland Cement Concrete Pavement ( Unreinforced 280mm THK. 3 Days) SQ.M. 50.25 1,866.11 93,772.03 0.574 - -
PART I-B BANK AND SLOPE PROTECTION WORKS
505(2)a Grouted Riprap ( Class "A") CU.M. 31.76 2,731.25 86,744.50 0.531 - -
PART I-C DRAINAGE WORKS
1718(1) Pipe Culverts (1220mm dia) LN.M. 261.60 11,707.22 5,104,347.92 18.760 - -
Materials 174.40 12.506 5.7 80.00 5.7
1718(1) Pipe Culverts ( 1520mm dia) LN.M. 19.20 15,373.97 491,967.04 1.808 - -
Materials 12.80 1.206 0.0 0.40 0.0
1720(1)5 Manhole 1220mm dia EACH 16.80 67,927.04 1,630,248.96 6.990 - -
Materials 7.20 2.996 1.2 2.88 1.2
1720(1)a6 Manhole 1520mm dia EACH 8.00 67,927.04 543,416.32 3.329 - -
PART H. MISCELLANEOUS STRUCTURE
600(1) Concrete Curb Cast in Place LN.M. 528.00 621.16 327,972.48 2.009 - -
600(3) Concrete Gutter Cast in Place SQ.M. 528.00 536.42 283,229.76 1.735 - -
601(1) Sidewalk SQ.M. 1,584.00 730.58 1,157,238.72 7.089 - -
16,325,382.54 100.00 7.8 0.00 7.8
ORIGINAL 2.800
MONTHLY PROGRESS
ACTUAL 7.827
ORIGINAL 2.800
CUMULATIVE PROGRESS
ACTUAL 7.827
SLIPPAGE 5.027
TIME ELAPSED (%) 24.67%
2.800 24.400

0
DATE STARTED : JUN
ORIGINAL COMPLETION DATE : OCTO
UIO AVE., VILLAMOR STREET, DACUDAO DAVAO CITY ORIGINAL CONTRACT DURATION : 150 CA
CONTRACTOR : REL
150 Calendar Days ORIGINAL CONTRACT AMOUNT : P 16,
2nd Quarter 3rd Quarter 4th Quarter ITEM NO
37 CD 38 CD 38 CD
24.40% 67.20% 100.00%
PART B. OTHER GENERAL REQUIREMENTS
B-5
90 B-7
B-8
B-9
B.4(1)
PART C. EARTHWORKS
101(2)
80 101(3)B1
101(3)B2
101(4)A3
101(6)
102(2)
103(3)
70 103(6)A
105(1)A
Row 61 803(1)A
PART D. SUB-BASE & BASE COURSE
200(1)
60 PART E. SURFACE COURCE
311(1)c3
311(1)e3
PART I-B BANK AND SLOPE PROTECTION WO
505(2)a
PART I-C DRAINAGE WORKS
1718(1)

1718(1)

40 1720(1)5

Row 65 1720(1)a6
PART H. MISCELLANEOUS STRUCTURE
600(1)
600(3)
601(1)
0
21.600 42.800 32.800

24.400 67.200 100.000

49.33% 74.67% 100.00%


67.200 100.00

7.83
TED : JUNE 3, 2018
COMPLETION DATE : OCTOBER 30, 2018
CONTRACT DURATION : 150 CALENDAR DAYS
IMPROVEMENT/ CONSTRUCTION OF DRAINAGE ALONG JCT.JP. C
OR : RELY CONSTRUCTION & SUPPLY
CONTRACT AMOUNT : P 16, 325, 389.43
DESCRIPTION OF WORK UNIT QUANTITY UNIT PRICE AMOUNT REL. WT.
ACCOMPLISHMENT

PRESENT % PREVIOUS % QTY TOTAL %


HER GENERAL REQUIREMENTS -
Project Billboard/ Signboard EACH 2.00 3,988.50 7,977.00 0.049 0.049 2.00 0.049
Occupational safety and Health Program MO 5.00 23,120.53 115,602.65 0.708 0.142 1.00 0.142
Traffic Management MO 5.00 102,756.19 513,780.95 3.147 0.629 1.00 0.629
Mobilization/ Demobilization LS 1.00 138,794.14 138,794.14 0.850 - - -
Construction Survey and Staking KM 0.53 20,971.88 11,073.15 0.068 0.034 0.265 0.034
RTHWORKS
Removal OF Actual Structures/ Obstruction ( Conc. MH) EACH 4.00 19,899.57 79,598.28 0.488 - - -
Removal of Actual Structures/ Obstruction (0.15m Thk. PCCP) SQ.M. 1,408.00 75.07 105,698.56 0.647 - -
Removal of Actual Structures/ Obstruction (0.20m Thk. PCCP Unreinforced) SQ.M. 1,020.00 141.90 144,738.00 0.887 - -
Removal of Actual Structures/ Obstruction (910mm dia RCPC) LN.M. 315.00 686.97 216,395.55 1.326 - -
Removal of Structures and Obstruction ( Stone Masonry) CU.M. 40.50 412.08 16,689.24 0.102 - -
Surplus Common excavation CU.M. 408.00 174.57 71,224.56 0.436 - - -
Foundation Fill CU.M. 12.21 1,100.00 13,431.00 0.082 - -
Pipe Culvert and Drain Excavation CU.M. 2,015.61 283.12 570,659.50 3.496 - -
Subgrade Preparation SQ.M. 2,428.00 18.65 45,282.20 0.277 - -
Structure Excavation Common Soil CU.M. 153.92 279.87 43,077.59 0.264 - - -
B-BASE & BASE COURSE
Aggregate Subbase Course CU.M. 981.20 792.40 777,502.88 4.763 - -
RFACE COURCE -
Portland Cement Concrete Pavement ( Unreinforced 230mm THK. 3 Days) SQ.M. 2,428.00 1,538.27 3,734,919.56 22.878 - -
Portland Cement Concrete Pavement ( Unreinforced 280mm THK. 3 Days) SQ.M. 50.25 1,866.11 93,772.03 0.574 - -
ANK AND SLOPE PROTECTION WORKS
Grouted Riprap ( Class "A") CU.M. 31.76 2,731.25 86,744.50 0.531 - -
RAINAGE WORKS
Pipe Culverts (1220mm dia) LN.M. 261.60 11,707.22 5,104,347.92 18.760 - -
Materials 174.40 12.506 5.737 80.00 5.737
Pipe Culverts ( 1520mm dia) LN.M. 19.20 15,373.97 491,967.04 1.808 - -
Materials 12.80 1.206 0.038 0.40 0.038
Manhole 1220mm dia EACH 16.80 67,927.04 1,630,248.96 6.990 - -
Materials 7.20 2.996 1.198 2.88 1.198
Manhole 1520mm dia EACH 8.00 67,927.04 543,416.32 3.329 - -
SCELLANEOUS STRUCTURE
Concrete Curb Cast in Place LN.M. 528.00 621.16 327,972.48 2.009 - -
Concrete Gutter Cast in Place SQ.M. 528.00 536.42 283,229.76 1.735 - -
Sidewalk SQ.M. 1,584.00 730.58 1,157,238.72 7.089 - -
16,325,382.54 100.00 7.83 0.00 7.83
ORIGINAL
MONTHLY PROGRESS
ACTUAL
ORIGINAL
CUMULATIVE PROGRESS
ACTUAL
SLIPPAGE
TIME ELAPSED (%)
CTION OF DRAINAGE ALONG JCT.JP. CABAGUIO AVE., VILLAMOR STREET, DACUDAO DAVAO CITY

150 Calendar Days


1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
37 CD 37 CD 38 CD 38 CD SEPT OCT NOV DEC JAN
2.80% 24.40% 67.20% 100.00% 181/279 212/279 242/279 273/279 279/279

2.800 21.600 42.800 32.800 11.984 11.061 9.700 9.531 1.050


7.827
2.800 24.400 67.200 100.000 #REF! #REF! #REF! #REF! #REF!
7.827
5.027
24.67% 49.33% 74.67% 100.00% 64.875% 75.986% 86.738% 97.849% 100.000%
Contract ID No. : 18LC-0104
Contract Title : Construction of Drainage Canal at Upper La Filipina
Location : Tagum City, Davao del Norte

WEEKLY PROGRESS RE
PROJECT DATA : PROJECT STATUS :

Contract Amount : 47,530,183.04 Scheduled Accomplishment to Da


Revised Contract Amount : Previous Accomplishment
Contract Started : August 2, 2018 Actual Accomplishment to date
Contract Duration : 184 c.d. TOTAL PROGRESS ACCOMPLIS
Contract Expiration : February 2, 2019 Slippage to Date, +/-
Revised Contract Duration : Contract time Elapsed
Revised Expiry Date : Percent Time Elapsed

PROJECT STATUS UPDAT


PREVIOUS
PERIODI
REL. PROGRESS
ACCOM
WT. ACCOMPLISHMENT
ITEM DESCRIPTION Unit Qty PROG REL.
(%) QTY RESS WT. QTY
% (%)

PART B: Other General Requirements

B.5 Project Billboard /Signboard each 4.00 0.040

B.7(1) Occupational Safety and Health Program mo 4.00 0.144

B.7(1) Traffic Management mo 4.00 0.103

B.9 Mobilization and Demobilization ls 1.00 0.031

B.4(1) Construction Survey & Staking km 2.04 0.082

PART C: Earthworks

101(1) Removal of Structures and Obstruction (including ls 1.00 0.207

102(1) Unsuitable Excavation cu.m. 16,518.00 9.608

103(1)a Structure Excavation cu.m. 3,406.00 2.015


103(3) Foundation Fill cu.m. 10.00 0.021

103(6)a Pipe Culvert and Drain Excavation cu.m. 11.36 0.006

104(2)a Embankment (from Borrow) cu.m. 9,851.00 12.342

PART D: Subbase and Base Course

200(1) Aggregate Subbase Course cu.m. 944.00 1.229

PART G: Drainage and Slope Protection Structures

404(1)a Reinforcing Steel Grade 40 kg 54,913.00 7.669

405(1)a3 Structural Concrete Class A cu.m. 589.87 7.983

500(1)b1 Pipe Culvert, 610mm dia. (24" dia.) ln.m. 21.00 0.164

505(1)b7 Pipe Culverts, 1830mm dia(72" dia.) ln.m. 348.00 12.809

502(1)g Manhole (1830mm dia. RCPC) each 21.00 6.770

510(1) Bed Course Granular Material cu.m. 1,736.04 3.369 33.77 2% 0.066 -

510(2) Concrete (Slope Protection) cu.m. 2,280.68 35.407 25.33 1% 0.393 -

TOTAL 100.00 0.459

ISSUES / PROBLEMS ENCOUNTERED:

Reported by: Verified by:


Signature Signature
Name Jayson T. Raymundo Name
Title Resident Engineer/Project Supervisor Title
Date Date
61 Report Date : March 2, 2019
Week No. : 1
Period Covered : February 4-9, 2019

GRESS REPORT

mplishment to Date : 100.00 %


: 0.46 %
shment to date : 0.00 %
ESS ACCOMPLISHMENT : 0.46 %
: -99.54 %
: 182.00 c.d.
: 100.00 %

TATUS UPDATE
CUMULATIVE
PERIODIC PROGRESS
PROGRESS
ACCOMPLISHMENT
ACCOMPLISHMENT
REL. PROG REMARKS
PROGR REL.
WT. QTY RESS
ESS % WT. (%)
(%) %
0.00% - 33.77 2% 0.066 On going
0.00% - 25.33 1% 0.393 On going

- 0.459
SLIPPAGE, +/- -99.54

ACTIONS TAKEN/RECOMMENDATIONS:

Noted by:
Signature
Name
Title
Date
Contract ID No.
Contract Title :
Location :

MONTHLY PROGRESS REPO


PROJECT DATA : PROJECT STATUS :

Contract Amount : Scheduled Accomplishment to Date


Revised Contract Amoun : Previous Accomplishment
Contract Started : Actual Accomplishment to date
Contract Duration : TOTAL PROGRESS ACCOMPLISHMEN
Contract Expiration : Slippage to Date, +/-
Revised Contract Durati : Contract time Elapsed
Revised Expiry Date : Percent Time Elapsed

PROJECT STATUS UPDATE


PREVIOUS PERIODIC
REL. PROGRESS PROGRES
WT. ACCOMPLISHMENT ACCOMPLISH
ITEM DESCRIPTION Unit Qty PROG REL. PROG
(%) QTY RESS WT. QTY RESS
% (%) %
ISSUES / PROBLEMS ENCOUNTERED: ACT

Reported by: Verified by:


Signature Signature
Name Name
Title Resident Engineer/Project Supervisor Title
Date Date
Report Date :
Week No. :
Period Covered :

GRESS REPORT

: %
: %
: %
SS ACCOMPLISHMENT : %
: %
: c.d.
: %

ATUS UPDATE
PERIODIC CUMULATIVE
PROGRESS PROGRESS
ACCOMPLISHMENT ACCOMPLISHMENT
REL. PROG REL. REMARKS
WT. QTY RESS WT.
(%) % (%)
SLIPPAGE, +/- 0.00

ACTIONS TAKEN/RECOMMENDATIONS:

Noted by:
Signature
Name
Title
Date
Km.7 Tigatto Road, Buhangin, Davao City

PROJECT TARGET REPORT


PROJECT STATUS:
Accomplishment to Date : Period : February 1-28, 2019 PROJECT COST:
Required as per PERT CPM : 100.00 Project ID No. : 18LC-0104 Budget to Date :
Period Accomplishment : Project Code Name : La Filipina Drainage Canal Actual Budget : 47,530,183.04

CUMULATIVE PROGRESS
CUMMULATIVE ACCOMPLISHMENT
SCHEDULED TARGET
ACCOMPLISHMENT TO DATE
ITEM NO. ACTIVITY DESCRIPTION UNIT REMARKS
QUANTITY NET WT. QUANTITY NET WT. QUANTITY NET WT. QUANTITY NET WT.
(PERT-CPM) Wee
% % % %
PART B: Other General Requirements 4 5 6
B.5 Project Billboard /Signboard each 4.00 0.040 - - Completed
B.7(1) Occupational Safety and Health Program mo 4.00 0.144 - - Completed
B.7(1) Traffic Management mo 4.00 0.103 - - Completed
B.9 Mobilization and Demobilization ls 1.00 0.031 - -
B.4(1) Construction Survey & Staking km 2.04 0.082 1.04 0.042

PART C: Earthworks
Removal of Structures and Obstructions
101(1) (including Restorations-wooden house) ls 1.00 0.207 1.00 0.104 Issues with RROW 0.05

102(1) Unsuitable Excavation cu.m. 16,518.00 9.608 2,482.00 1.444 On going


103(1)a Structure Excavation cu.m. 3,406.00 2.015 - - Completed
103(3) Foundation Fill cu.m. 10.00 0.021 0.96 0.002 On going 0.00
103(6)a Pipe Culvert and Drain Excavation cu.m. 11.36 0.006 - - Completed
104(2)a Embankment (from Borrow) cu.m. 9,851.00 12.342 - -
PART D: Subbase and Base Course

200(1) Aggregate Subbase Course cu.m. 944.00 1.229 - -


PART G: Drainage and Slope Protection Structures

404(1)a Reinforcing Steel Grade 40 kg 54,913.00 7.669 13,462.81 1.880 0.47


405(1)a3 Structural Concrete Class A cu.m. 589.87 7.983 129.54 1.752

500(1)b1 Pipe Culvert, 610mm dia. (24" dia.) ln.m. 21.00 0.164 21.00 0.164

505(1)b7 Pipe Culverts, 1830mm dia(72" dia.) ln.m. 348.00 12.809 29.00 1.068 0.53
502(1)g Manhole (1830mm dia. RCPC) each 21.00 6.770 2.00 0.645 On going 0.64
510(1) Bed Course Granular Material cu.m. 1,736.04 3.369 619.01 1.200 On going 0.30
510(2) Concrete (Slope Protection) cu.m. 2,280.68 35.407 520.47 8.079 On going

TOTAL 100.00 16.38 Total 2.00


Total
Month of February

Week 1 Week 2 Week 3 Week 4

7 8 9 11 12 13 14 15 16 18 19 20 21 22 23 25 26 27 28 1 2

0.04

0.052 0.052

0.722 0.722

0.002
0.470 0.470 0.470 0.470
0.584 0.584 0.584
0.082 0.082
0.534 0.534
0.645
0.300 0.300 0.300 0.300
2.693 2.693 2.693

2.003 4.634 4.892 4.852


16.38
Page No.:

Km.7 Tigatto Road, Buhangin, Davao City

PROJECT ACCOMPLISHMENT REPORT


PROJECT STATUS:
Accomplishment to Date : 34.05 Period : January 1-31, 2019 PROJECT COST:
Required as per PERT CPM : 100.00 Project ID No. : 18LC-0104 Budget to Date :
Period Accomplishment : 9.92 Project Code Name : La Filipina Drainage Canal Actual Budget : 47,530,183.04

CUMULATIVE PROGRESS
CUMMULATIVE ACCOMPLISHMENT TO
SCHEDULED TARGET
ACCOMPLISHMENT DATE
ITEM NO. ACTIVITY DESCRIPTION UNIT REMARKS
QUANTITY NET WT. QUANTITY NET WT. QUANTITY NET WT. QUANTITY NET WT.
(PERT-CPM) % % % %
PART B: Other General Requirements

B.5 Project Billboard /Signboard each 4.00 0.040 4.00 0.040 - - Completed

B.7(1) Occupational Safety and Health Program mo 4.00 0.144 4.00 0.144 2.00 0.072 Completed

B.7(1) Traffic Management mo 4.00 0.103 4.00 0.103 2.00 0.052 Completed

B.9 Mobilization and Demobilization ls 1.00 0.031 0.50 0.016 - -

B.4(1) Construction Survey & Staking km 2.04 0.082 1.00 0.040 - -

PART C: Earthworks
Removal of Structures and Obstructions
101(1) (including Restorations-wooden house) ls 1.00 0.207 0.50 0.104 - - Issue with RROW

102(1) Unsuitable Excavation cu.m. 16,518.00 9.608 9,072.01 5.277 1273.00 0.740 On going

103(1)a Structure Excavation cu.m. 3,406.00 2.015 3,405.65 2.015 - - Completed

103(3) Foundation Fill cu.m. 10.00 0.021 9.04 0.019 7.62 0.016 On going

103(6)a Pipe Culvert and Drain Excavation cu.m. 11.36 0.006 11.36 0.006 - - Completed

104(2)a Embankment (from Borrow) cu.m. 9,851.00 12.342 3,122.02 3.911 - -


PART D: Subbase and Base Course

200(1) Aggregate Subbase Course cu.m. 944.00 1.229 - - - -

PART G: Drainage and Slope Protection Structures

404(1)a Reinforcing Steel Grade 40 kg 54,913.00 7.669 17,890.26 2.499 5,788.51 0.808

405(1)a3 Structural Concrete Class A cu.m. 589.87 7.983 114.86 1.555 43.88 0.584

500(1)b1 Pipe Culvert, 610mm dia. (24" dia.) ln.m. 21.00 0.164 - - - -

505(1)b7 Pipe Culverts, 1830mm dia(72" dia.) ln.m. 348.00 12.809 319.00 11.742 55.00 2.024

502(1)g Manhole (1830mm dia. RCPC) each 21.00 6.770 19.00 6.125 16.00 5.158 On going

510(1) Bed Course Granular Material cu.m. 1,736.04 3.369 33.77 0.066 33.77 0.066 On going

510(2) Concrete (Slope Protection) cu.m. 2,280.68 35.407 25.33 0.393 25.33 0.393 On going

TOTAL 100.00 34.06 9.91


Verified Correct by:
Project Inspector / Assistant Chief Engineer
Prepared by:
Jayson T. Raymundo Approved by:
Project / Resident Engineer Chief Engineer
FEBRUARY MARCH APRIL
ITEM DESCRIPTION

Feb 18- Feb 25 Mar 18- Mar 25-


Feb 4-10 Feb 11-17 Mar 4-10 Mar 11-17 Apr 1-7 Apr 8-14 Apr 15-21 Apr 22-28
24 -mar 3 24 31

PART B: Other General Requirements

B.5 Project Billboard /Signboard

B.7(1) Occupational Safety and Health Program

B.7(1) Traffic Management

B.9 Mobilization and Demobilization

B.4(1) Construction Survey & Staking 0.040


PART C: Earthworks

101(1) Removal of Structures and Obstruction (including Restoration-wooden house) 0.052 0.052
102(1) Unsuitable Excavation 0.722 0.722 0.722 0.722 0.722 0.722
103(1)a Structure Excavation

103(3) Foundation Fill 0.002


103(6)a Pipe Culvert and Drain Excavation

104(2)a Embankment (from Borrow) 0.937 0.937 0.937 0.937 0.937 0.937 0.937 0.937
PART D: Subbase and Base Course

200(1) Aggregate Subbase Course 0.176 0.176 0.176 0.176 0.176


PART G: Drainage and Slope Protection Structures

404(1)a Reinforcing Steel Grade 40 0.470 0.470 0.470 0.470 0.470 0.470 0.470 0.470 0.470 0.470 0.470
405(1)a3 Structural Concrete, Class A 0.584 0.584 0.584 0.584 0.584 0.584 0.584 0.584 0.584 0.584 0.584
500(1)b1 Pipe Culvert, 610mm dia. (24" dia.) 0.082 0.082
505(1)b7 Pipe Culverts, 1830mm dia(72" dia.) 0.534 0.534
502(1)g Manhole (1830mm dia. RCPC) 0.645
510(1) Bed Course Granular Material 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.300
510(2) Concrete (Slope Protection) 2.693 2.693 2.693 2.693 2.693 2.693 2.693 2.693 2.693 2.693 2.693 2.693

4.696 4.634 4.892 4.852 5.707 5.707 5.707 5.882 5.160 5.160 5.160 4.390

Target Monthly Progress 19.07 23.00 19.87

Target Commulative Progress 19.07 42.08 61.95


APRIL MAY

Apr 29- May 13-


May 6-12
May 5 19

0.016

0.937
0.176 0.176

2.693

3.806 0.176 0.016

4.00

65.94
HEAVY EQUIPMENT UTILIZATION SCHEDULE

MONTH OF : October
PROJECT : Construction of Drainage Canal, Upper La Filipina
LOCATION : Tagum City, Davao del Norte

WEEK 1 WEEK 2 WEEK 3 WEEK 4 WORK ACTIVITY


EQUIPMENT
DATE: Oct 1-7 DATE: Oct 8-14 DATE: Oct 15-21 DATE: Oct 22-31
1. BACKHOE 2 2 2 2 For Excavation of Drainage Slope Protection
2. DUMP TRUCK 1 1 1 1 For Hauling of Embankment
3. BULLDOZER
4. ROADROLLER
5. TRANSIT MIXER 2 2 2 2 For Concrete Pouring of Slope Protection
6. ROAD GRADER
7. WATER TRUCK
8. WATER PUMP

Prepared by: Renzo Ray Olivar