Académique Documents
Professionnel Documents
Culture Documents
Headline sponsors:
BAR
ARRETT
STE
EEL
L LIMITED
Silver sponsors: Hadley Group, Building Products Division | Jack Tighe Ltd
Bronze sponsors: BAPP Group of Companies | Barnshaw Section Benders Ltd | Hempel |
Joseph Ash Galvanizing | Kaltenbach Limited | Kloeckner Metals UK | Sherwin-Williams |
Tension Control Bolts Ltd | Voortman Steel Machinery
As at September 2016
www.steelforlife.org
Steel continues to be the most popular frame material and this year’s
entries reflect the increasingly high standards that are being achieved,
not only in design and all aspects of fabrication, but also in the short
programmes and accuracy on site.
THE JUDGES
R B Barrett MA(Cantab)
Representing the Steelwork Contracting industry
Architect: Populous
PROJECT TEAM
When the London Olympic Stadium was football matches, an automated system of 4,700 tonnes which is nearly six times the
designed it was with an ethos of ‘embracing retractable seating was included in the new weight of its predecessor.
the temporary’ in the knowledge that, post- design, with all four sides of the lower
Games, its function would change and, as a bowl able to move over the running track In order to preserve some of the Olympic
result, the structure would need to change when in football mode. To meet UEFA Stadium’s identity, the iconic triangular
too. Such foresight paid dividends when it rules, the roof needed extending to fully lighting tower design that used to stand
was announced that the stadium would cover the retractable seating. over the old roof has been inverted and
become the new home of West Ham United they now appear to hang underneath the
football club at the beginning of the Work began on the project to transform new larger roof.
2016/17 season. the venue in late 2013. The new structure
included 8km of steel cables weighing 930 Early works involved the deconstruction of
One of the main stipulations for the future tonnes, 112 steel rafters, 2,308 purlins, 422 the old roof and the strengthening of the
use of the stadium was that it would retain struts, 9,900 roof panels and 14 light existing structure, foundations, V-columns
its running track. To prevent this from paddles each weighing 43 tonnes, with the and the perimeter compression truss.
adversely affecting the atmosphere at whole structure weighing in at around
Strengthening of the existing structure was Not least, the oval shape of the stadium 4D programming using BIM modelling was
one of the major challenges. Due to the and the movement and tolerance the key to delivering this successful project
additional weight of the new roof, it was requirements only gave the opportunity for to a very high profile deadline, which was
necessary to replace and/or strengthen the single pieces to be replicated twice, which originally the 2015 Rugby World Cup
existing V-columns and significant meant that half of the stadium structure taking place in September 2015. However,
strengthening works were carried out to was fabricated with unique members. this was brought forward even more to fit
the existing compression truss. in the Sainsbury’s Anniversary Games
Following the V-column and compression which took place in July 2015. This meant
For the compression truss strengthening truss strengthening work, to maintain that all major construction had to be
work alone the amount of hierarchical equilibrium until the oval was fully formed complete by May 2015.
complex calculations involved the the erectors worked in two teams at
steelwork contractor developing his own opposite ends of the stadium working in a The new structure now has a lifespan of
in-house software to process over 10,000 clockwise rotation constructing the back over 60 years and is set to become the new
calculations - a task that would have been roof first, then the front roof complete with national competition centre for UK
impossible using traditional methods. the lighting paddles and walkways. Athletics, and in 2017 will host the IAAF
World Athletics Championships and IPC
The ambitious new cantilevered roof now To ensure the correct distribution of forces World Championships. The stadium has
stands as the world’s largest with every seat through the cable support structure to the already hosted five games of the 2015
in the stadium now covered by the new roof. compression truss, the front and back roof Rugby World Cup and motor racing’s
are completely independent of each other. 2015 Race of Champions.
The 14 new lighting paddles are positioned However, for the installation of the lighting
beneath the new roof. Each lighting paddle paddles, the front roof had to be The stadium has also been upgraded to a
houses up to 41 lamps, many of which are temporarily tied to the back roof to ensure 54,000 all-seater UEFA category 4 football
the original lamps that shone over the that the lighting paddles did not overturn stadium, which is the highest category of
stadium during the London 2012 games. until the full ring stiffness of a complete football stadium possible in the world.
Four 600 tonne capacity cranes operated in oval was achieved.
tandem to lift the lighting paddles and the
other roof members into position.
© Cadw 2016
Harlech Castle is one of the finest surviving Both horizontal and vertical alignments To ensure that the bridge was future-proof
13th Century castles in Britain - it is a were constrained by the need to connect provision was made for services to be run
Grade I Listed Building, a Scheduled straight through the Castle’s gatehouse, in a duct under the bridge deck, allowing
Ancient Monument and also part of a whilst maintaining a suitable gradient the creation of a new venue within the
World Heritage Site. For many years access acceptable to those with impaired mobility. castle where events and performances can
to the Castle had been via a series of timber be hosted.
steps, with no provision for those with To minimise the impact of the views of the
impaired mobility. With the opening of a distant mountains of Snowdonia, the Throughout the design process there was
new visitor centre nearby, the vision was to profile of the bridge was reduced by continuous dialogue between the project
connect this to the Castle via a new tapering the bottom chords of the trusses team using 3D BIM CAD modelling to
‘floating’ bridge, and eliminating any diagonal bracing, thus explain design proposals and ensure the
avoiding a potentially more cluttered design developments were acceptable. The
Due to the sensitive nature of the site, the appearance. The visual lightness of the first key area for development was the truss
aesthetics have been a particularly bridge is significantly improved by the and deck configuration. The original
important consideration. Various concepts selection of a stainless steel mesh infill to proposal had fin plates welded to the back
were explored to satisfy the constraints of the parapets. The deck is 2m wide in of the CHS Vierendeel truss bracing
functionality, alignment, heritage and visual general, however it widens up to 3m above elements, which then became the tee web in
impacts before finally opting for the ‘S’- the middle support to provide an area the handrail upright. This arrangement
shaped low profile Vierendeel truss design. where people can enjoy the views. posed some fabrication challenges and raised
the possibility of weld distortion in the fin Bridge sections were set up in bespoke jigs Steel erection required meticulous planning
plate attached to the CHS. An alternative to control weld distortion and maintain and attention to detail to ensure a smooth
solution was adopted whereby SHS bracing their geometry during welding. and safe installation process, however the
was used and the handrail fabricated tee unique historic nature of the site put even
upright orientation was reversed. The face of The bridge is lit with a bespoke integrated more responsibility onto the erection team.
the SHS Vierendeel bracing then aligned LED lighting system that delivers bright Following offsite matching of the deck
with the flange of the tee to the balustrade white task lighting to the walkway, but has units the fit-up on site was perfect and the
which was tapered to give an elegant the added benefit of having a number of three main spans were installed without
transition to the handrail, whilst the bracing colour-changing effects that can be accessed any significant problems. With the bridge
also gives improved structural capacity for special events. sections in place, the careful co-ordination
particularly at the joint with the CHS chords of the fitting of the timber deck, parapets,
for a given section width. The bridge is finished with a timber deck and lighting and services allowed the bridge to
handrail for which FSC certified Ekki be completed in good time ready for its
To maximise headroom clearances under hardwood was selected, this requires no opening for the year’s summer visitors.
the bridge, and to give a more efficient preservative treatment and little maintenance.
structural solution at the supporting The deck boards feature anti-slip inserts and The new footbridge has been very well
columns, the depth of the truss profile was seamlessly follow the curves of the bridge. received and welcomed as an attractive
modified and the bottom chord form was addition to the historic site, whilst
achieved from a combination of curved and The biggest challenge to the installation team dramatically enhancing the visitors’
straight sections of tube. was the limited footprint of the site and the experience.
restricted access through Harlech. These
The bridge's dynamic performance required challenges were overcome with the careful
careful consideration in the design. The selection of the multi-wheel steer mobile
columns needed to be very stiff in the crane and rear wheel steer transport trailers.
transverse direction so an elliptical section
was used which, when partly filled with
concrete, achieved the required result. This
choice also had the added architectural
JUDGES’ COMMENT
benefit of the elliptical column being less
obtrusive on elevation, whilst approximately
In a very sensitive setting this elegant bridge provides level access to the historic
matching the profile of the truss chord.
castle, whilst minimising its visual impact. The detailing and fabrication of the
Before work started on site the existing curved deck are exemplary. The erection was effected with a high degree of
façade was digitally scanned and the 3D precision despite the limited site and extremely difficult access.
survey was incorporated into the design
model to ensure the critical dimensional The modern shapes of the bridge create a beautiful counterpoint to the ancient
interface between the Castle entrance and castle it serves.
the bridge was achieved.
AWARD
Architect: dn-a
PROJECT TEAM
Located in the heart of Reading town with the provision of four additional steel- five-storey extension between levels 11
centre, the existing Thames Tower concrete framed office floors to increase the nett to 16, it was necessary to strengthen the
office block has been given a new lease of usable internal areas. This also provided columns and floors of the existing
life with an enlarged footprint at each floor huge ‘value-engineering’ savings to the concrete-framed structure. This was
level in conjunction with a five-storey steel- scheme as the basic core of the structure achieved by the following:
framed extension above level 11. was maintained and no amendments or
enhancements of the existing concrete i. The supply and installation of 15mm
The original scheme concept was to foundations were necessary. thick stiffening plates to the full width
demolish the existing concrete-framed of the concrete columns between levels
structure and replace it with a new 25- The refurbishment works included 6 and 11. The columns were initially
storey high tower, which would have stripping the building back to its structural ultrasonically scanned to avoid clashes
necessitated the requirement for new frame and the removal of the existing with the steel reinforcing bars.
supporting/up-rated concrete foundations. concrete cladding panels to all elevations, Following the bespoke fabrication of
which were then replaced with a new each of the 282no individual stiffening
However, through an innovative design terracotta tiling system to complement the plates, these were fixed to the columns
proposal, the core of the existing structure local town centre surroundings. by means of 14no resin anchor bolts
was maintained and developed using a and subsequently bonded to the
series of strengthening works throughout In order to accommodate the increased concrete face across the full plate area
the height of the concrete frame, along dead and imposed loads from the new using a special ‘fast-curing’ resin.
ii. These were further complemented The four corners of the building were also This was sequentially constructed by
by fabricated ‘cruciform’ stiffening altered to create a now perfectly square means of the primary steel frame, followed
brackets at the column heads, in order structure, which has further increased each by the metal deck flooring and associated
to adequately disperse the upper of the tower’s existing commercial concrete topping at each level. Following
load transfer. floorplates. This was achieved by the adequate curing of the concrete deck at
installing a new steel column to each of each level, the next level was subsequently
An intermediate mezzanine steel-decked the building’s corners with secondary infill constructed, up to level 15.
floor was also supplied and incorporated framing. These triangular corner infills
at level 01, using cellular beams to provide were then subsequently metal-decked and The steelwork for the new floors up to
a lightweight steel solution with maximum concreted throughout the full height of the level 16 was completed in December 2015.
integrated space for M&E equipment. building. This has increased the tower’s
floor space from 13,600m2 to
The above strengthening works, along with approximately 17,000m2 of offices and
further stiffening plates and brackets at 740m2 of restaurant/café space.
level 11, also facilitated the use of a roof- JUDGES’ COMMENT
mounted tower crane for the installation of The new upper steelwork extension is
the new upper five-storey extension. The connected to the existing concrete columns
tower crane was installed approximately at the newly created level 11 and corner This is a thorough and rigorous project
halfway through the steel site programme. infill sections. Predominantly based which has been carried out with ingenuity
Initially all of the internal steel members around a 6.3m x 5.8m internal grid to and skill. With both painstaking analysis
for the strengthening works had to be match the existing columns below, each and inventive thought, a substantial but
hoisted through the existing internal lift floor is formed with a series of cellular unloved city-centre concrete building has
cores and ‘hand-balled’ into position. beams that accommodate services and
been enlarged upwards and horizontally by
support a metal deck flooring system.
the creative use of steelwork.
The structure’s original design had the
perimeter columns protruding beyond the The use of composite cellular beams has
main floor areas, along with splayed 45 kept the steel weight to an absolute The project was technically and logistically
degree corners throughout its full height. minimum, thus limiting the additional challenging, but teamwork and a
dead load on the existing structure below, committed client have achieved a solution
As part of the building refurbishment, and and ultimately allowing M&E services to which is exemplary in its calm elegance.
to maximise the internal floor areas, the be distributed within the structural depth
new design introduced a series of of the new steel members at all levels.
additional perimeter support beams which
were connected to the external edge of the Due to limited storage space on site,
existing concrete columns. Metal decking vehicular restrictions on member lengths
and associated concrete floor infills then and the need to minimise the weight of
created an increase to the building mechanical plant on the roof structures,
footprint up to the exterior face of the it was necessary to construct the upper
perimeter columns. extension on a floor-by-floor basis.
AWARD
Architect: Populous
PROJECT TEAM
The South Stand expansion increased the running around the whole circumference The stability cores were formed of steel
capacity of the stadium during the 2014/15 of the roof; therefore any modification to vertical brace planes with the inclusion of
football season, adding 6,000 new seats the roof could not affect this, even in outrigger bracing to add efficiency and,
through a third tier on the terraces and areas where roof rafters were removed. although a solution normally adopted on
1,500 additional seats around the pitch. Protection of the existing cable was vital tall buildings, this approach proved
An architecturally sympathetic extension of as there was no repair procedure in place, effective for the project. A design and
an existing catenary ringed structure was and damage would result in replacement costing study of the original stays, which
needed, which did not compromise the and potentially the closure of the stadium were formed of cable, revealed that bars
integrity or capacity of the structure and for two years. could be introduced for the new stays.
ensured that the existing stadium remained These had marginally more erection work
operational during works. Extensive design optimisation exercises associated with them, but overall were a
were undertaken, particularly for the steel more efficient solution. Combined 3D
The design was technically complex as the roof and the stability cores. A whole series modelling allowed the integration of all
existing roof involved a cable net structure of geometric studies evaluated the effects services within the structural envelope,
with a tension ring, from which steel roof of different stay and mast angles, including the late addition of increased
rafters hung. The structural integrity of concluding with a solution to satisfy both sports lighting requirements in accordance
the existing tension ring relies on it minimum material requirements and cost. with new regulations.
MEWP platform, intermediate roof
propping, tie bar installation lifting beams
to include remote release features and
hidden bolted splices in the rafters. The
availability of a CTL 1600 crane, the largest
crane of its type in the country, significantly
influenced the lifting methodology as it
permitted much larger lifts, speeded up
construction and reduced the need for
working at height splicing components.
JUDGES’ COMMENT
Structural Engineer: s h e d
Steelwork Contractor: S H Structures Ltd
Main Contractor: Lindum Group Ltd
Client: The Lincolnshire Bomber Command Memorial Trust
© Nicholas Worley
The striking roof canopy provides all- bolted together on site. However, in order The structure was initially painted offsite
weather protection for the 204m² sky to give a seamless appearance to the with a final decorative site applied coat
court. The tubular steel and fritted ETFE structure, it was vital that none of the required to achieve the perfect finish.
canopy frames views out in two directions bolted splice connections were visible. This was quite a challenge at the top of a
over central London, wraps up and over 16-storey building and required the use of
the garden and extends four storeys down The roof grid joints are fully welded specialist MEWPs and rope access
the face of the southwest façade in a connections formed with the help of CNC technicians. The final finish was a faultless
diagrid to assist solar shading. ‘cods-mouth’ type complex laser cuts to light metallic sheen to complement the
the ends of each CHS branch stub simple elegant nature of the structure.
The structure consists of a continuous member. Joints in the steel diagrid were
CHS diagrid frame that is supported on achieved using hidden ‘hand-cup’ type
eight tree columns which cantilever up splices where bolted connections are
from the main building’s 16th floor formed within the tubes themselves.
steelwork. Additional struts extend from JUDGES’ COMMENT
the ends of the cantilevered main building The column branching nodes were formed
steelwork that act to restrain the clad from a series of fin plates welded around
sidewalls. Further supports are provided a central stub which, in turn, were slotted The diagonal-framed steelwork and
off the façade for the open mesh apron. into CHS elements that form the ETFE canopy is a most effective
The geometry of the structure is complex – branches. The final nodes were then clad feature distinguishing this office
the asymmetry of the support positions, in multi-curved nylon shrouds produced building in a densely packed city.
that are set out based on the main building using 3D printing. Challenging technical constraints were
grid below, results in eight different tree effectively resolved to provide a most
columns and the roof diagrid is subtly Trial erection offsite allowed the complex desirable and popular roof garden.
pitched in four directions to generate falls. erection methodology to be verified
and refined. Additionally, this provides an often-
Due to the number of site and structural ignored fifth elevation of the building,
constraints, the only feasible option was The canopy was fixed to the façade of the as seen from the surrounding
to fabricate and deliver the structure in primary structure using architectural townscape heights.
individual pieces to be assembled and stainless steel pin connections and brackets.
COMMENDATION
Architect: AECOM
PROJECT TEAM
JUDGES’ COMMENT
‘The Diamond’ is a new Undergraduate engineering laboratories. The glazed such, specific MEWPs had to be selected
Engineering Facility for The University of apertures between the higher levels allow which had a big reach but were sufficiently
Sheffield providing specialist engineering both the roof lights and daylight to flood lightweight so as not to cause load
laboratories, lecture theatres, flexible into the open-plan study spaces below, capacity issues on certain platforms.
seminar rooms, open-plan learning and whilst also creating acoustic separation.
social spaces, a library and café. Numerous protection systems were
A large proportion of the structure below specified to cater for the multitude of
The building’s design is both conceptual roof level was neither on grid nor environmental and aesthetic requirements.
and practical, as well as being sympathetic orthogonal in set-out, but the adaptable Finishes provided included galvanized,
to the existing architecture of the area. Its and slender nature of steel construction zinc phosphate and multi-coloured
name derives from its unique exterior lent itself to the unusual design. systems to achieve those requirements
façade of interconnected diamonds in whilst minimising future maintenance.
anodised aluminium that are fitted to the The connections to the façade panels were
exterior glass cladding. formed using offsite shop-welded Construction work began in July 2013
propriety studs which reduced costs and the building was successfully
With a BREEAM ‘Excellent’ rating the significantly and saved weeks of additional completed in time for the beginning of the
structure is environmentally efficient. The construction time. 2015 autumn semester.
positioning of windows maximises the
inflow of natural light into the The city centre site produced several
laboratories, and aids ventilation without challenges and restricted access so timings JUDGES’ COMMENT
the sole reliance on air conditioning. The for deliveries were paramount. The steel was
windows are designed to control solar gain lotted in approximately 5-10 tonne lots to
within the building, with larger openings arrive and be erected in numbered sequence A testament to the success of this
to the north façade and smaller panels on for safety, practicality due to limited on-site imaginatively designed university
the south side, as well as the inclusion of storage and stability during construction. building is how well it is used by the
well-positioned opaque panels. The programme also had to consider students. Exposed steelwork elements,
minimising the disruption to the students. including an immaculate spiral
The ground floor has three access points staircase, contribute to the
to the central atrium with full-height The façades had to be accessed partly from architectural language of the interior.
glazing on the north and south edges the ground and partly from the structure
giving internal views into the specialist which resulted in numerous challenges. As This well-crafted building with its
excellent internal environment is
bound to inspire all who use it.
COMMENDATION
JUDGES’ COMMENT
The Leeds Station Southern Entrance (LSSE) The shallow 600mm steel transfer deck elements from barges located in the river up
has created a landmark structure to relieve carries the superstructure loads back to into the arches to tight tolerances.
congestion to the existing northern concrete piers aligned with the existing
entrance, future-proof ticket gate line viaduct piers within the river. This was Tight tolerances were also needed for the
capacity and encourage growth in the south quickly erected above the river without the primary structure, which directly supports
of the city by improving pedestrian access. need for temporary works and provides the the cladding in lieu of a secondary support
required clearance above the 1:200 year + zone. The width of the building is also
Located in a prominent yet challenging 20% climate change flood level. constrained to accommodate two lifts, four
environment, straddling the River Aire and a escalators and a stair within a width of only
busy railway, the concept design envisaged Steel construction provided the flexibility to 12.5m. This resulted in a 25mm allowable
an architectural curved form, utilising glass span the new ticket concourse above the erection tolerance across the building width.
and gold shingles to create a signature electrified railway via 25m trusses with the
building of the highest aesthetic quality. concourse floorplate slung beneath, and Leeds station now boasts an iconic
modularisation facilitated construction gateway, reducing journey times to the
The project team rationalised the above the railway in 10-hour possessions Southbank by up to 10 minutes for the
architectural surface into a steel diagrid without disruption to train services. Such estimated 20,000 people that will use the
structure, comprising repetitive RHS arches offsite fabrication brought health and safety new entrance each day.
of known radii, connected out of plane by benefits in terms of minimising work above
SHS diagonal members. This efficient a river, adjacent to an operational railway
solution reduced the number of radii used and in a congested city centre.
to form each arch by a third whilst
JUDGES’ COMMENT
achieving the original geometry +/-10mm. At river deck level, access bridges and 50%
The framing solution also reduced the of the river deck concourse have been
This new gateway to the station provides a
structural zone from 700mm to 400mm, erected within the confined space of the
route from the fast-growing south side of Leeds,
freeing up internal space, and shared existing Victorian viaduct arches. This
relieving pressure on the busy north entrance.
vertical load to a transfer deck whilst required the adoption of innovative
The structure interfaces with the existing
providing an inherently stable structure. construction techniques and the fabrication
Victorian viaduct, station roof and concourses
of bespoke lifting frames to hoist structural
being directly over the River Aire.
JUDGES’ COMMENT
PROJECT TEAM
Structural Engineer: MLM Consulting Engineers Ltd
Steelwork Contractor: Severfield
Main Contractor: Interserve & Babcock Wilcox Volund
Client: Viridor Waste Management
NATIONAL FINALIST
PROJECT TEAM
Structural Engineer: Parmarbrook
Steelwork Contractor: William Haley Engineering Ltd
Main Contractor: Willmott Dixon Construction Ltd
Client: North West Cambridge Development,
University of Cambridge
JUDGES’ COMMENT
The Cluster Building is a circular, single storey
steel frame with lightweight roof. Its outer
radius is 46m and its inner radius is 24.5m. This innovatory school will form the focus
of a new community on the outskirts of
The Inner Canopy is a circular glazed steel the city. Circular in plan and arranged
This is a new school that encompasses canopy 2.7m wide. around a central garden courtyard, the
classrooms, group rooms, performing arts and simple elegant steel frame achieves long-
multi-purpose halls, dining hall, library, storage By using steel an open-plan arrangement span lightweight construction despite the
facilities, kitchen, WC and changing rooms. encompassing long spans with minimum depth foundation and programme constraints.
was achieved, providing internal flexibility and
The Communal Block, approximately 35m x future adaptability in terms of layout and wall
The steelwork framing contributed to
26m on plan, comprises a steel frame with partitioning. The weight of the superstructure
precast hollow core slabs at first floor and was also kept to a minimum which minimised a notable completion in two years
roof level. the size and depth of foundations. from inception.
NATIONAL FINALIST
Sports Hall and Sixth Form Centre,
Channing School, London
PROJECT TEAM
Architect: BuckleyGrayYeoman
Structural Engineer: Heyne Tillett Steel
Steelwork Contractor: TSI Structures Ltd
Client: Channing School
JUDGES’ COMMENT
This project enhances sports facilities at a
Height restrictions for the sports hall roof, steelwork was in place and connections fully well-established girls’ school and is on a
from both above and below, led to a creative tightened, central roof props were lowered constricted site in an historic urban
double-pitched solution with no central gradually in unison. context. The latter has led to brick and tile
support using four sloped steel trusses which cladding, but with an intellectually elegant
span 34m along the length of the building. Stability has been provided by portal action to steel frame with carefully detailed and
the perimeter columns and braced bays at articulated connections.
With only a 30 degree pitch, large horizontal gable ends.
forces from the roof attempting to spread are
The standard of the finished work is
resisted by a series of exposed Macalloy ties The upper floor of the sixth form centre is a
between perimeter columns and the central clear span steel frame also tied with exposed very high.
valley chords of the trusses. Once all roof triangulated Macalloy cables.
NATIONAL FINALIST
PROJECT TEAM
Structural Engineer: AKT II
Steelwork Contractor: Severfield
Main Contractor: Mace
Client: CIT Developments LLP
JUDGES’ COMMENT
The re-use of a redundant concrete office
The transformation of this 1970s office scheme Within the tower the loadings from an block for upmarket residential
into a landmark structure was made possible additional 11 storeys of residential accommodation, with extension upwards and
through the use of innovative design solutions accommodation are carried through the horizontally, led to enormous structural
that are reliant on the use of structural steel. extended core rather than the external complexity. The merits of steelwork enable a
columns, which had limited additional
great increase in the number of storeys, in
The existing podium floorplates have been capacity. This was possible by hanging the
extended with two new floors added, whilst the new structure off the central core utilising a spite of the foundation constraints.
podium building’s cores have been strategically combination of a tension bar system and
relocated, opening out office space, promoting cantilevering steelwork in conjunction with The team worked well together to meet the
the ingress of natural light and encouraging a lightweight concrete floor slabs. tight programme and satisfy the planners and
collaborative working environment. The use of the client.
a steel structure helped to minimise the loading
onto existing foundations.
NATIONAL FINALIST
Architect: WilkinsonEyre
PROJECT TEAM
JUDGES’ COMMENT
Long approach ramps required complicated
The structure is a steel hybrid box girder/half- Visually, the gently curved, sculpted exterior curved and twisted box spine beams leading
through trough. This efficient structural form form is deliberately understated with a simple to the main span. The elegant main span is
gives both excellent torsional rigidity and uncluttered exterior. Internal steel stiffeners formed of a cleverly shaped box section with
allows the bridge to have a low overall define a series of gradually morphing skeletal upstand edge beams and neatly detailed post
structural depth. ‘ribs’. These regularly spaced ‘ribs’, required to and mesh safety barriers providing a visually
stiffen the cross section, constantly change shallow profile.
The structure tapers over its length, with shape as one travels across the bridge.
greatest depth at mid-span and minimal depth
The bridge provides a much needed safe
at each end. This form provides the structural The main bridge was installed within an 8-
depth where it is needed the most in the simply hour night-time closure, with ramps and stairs pedestrian and cycle link across the busy
supported span. being erected on subsequent nights to minimise A27 road.
disruption to the travelling public.
NATIONAL FINALIST
Strabane Pedestrian and Cycle Bridge,
Co Tyrone
PROJECT TEAM
Structural Engineer: AECOM
Steelwork Contractor: S H Structures Ltd
Main Contractor: Fox Contracts
Client: Derry City and Strabane District Council
© Peter French The designed profile of the pylon legs was JUDGES’ COMMENT
parabolic. This shape was approximated
during fabrication by three constant radii, with This bridge provides a key link between the
This landmark cable-stayed bridge crossing the a discrepancy in geometry of less than 10mm, town centre and the residential and sports
River Mourne provides a crucial missing link making fabrication of the pylon more efficient areas to the south. The cable-stayed bridge
for pedestrians and cyclists between the and cost-effective. Offsite fabrication produced
cleverly cantilevers from the south side,
residential areas and schools south of the river a polished, precision-fabricated structure with
and Strabane centre to the north. the desired aesthetic qualities, as well as minimising the impact of foundations on the
minimising site activities. north end with its busy roads and critical
A key feature of the inclined and curved main infrastructure services.
pylon is a wishbone-shaped pair of Vierendeel The installation of the mast required two large
trusses that stiffen the top of the arch in this mobile cranes to safely carry out a critical and A striking steelwork project.
zone of highly focussed loading. complex tandem lift.
NATIONAL FINALIST
Information Age Gallery,
The Science Museum, London
JUDGES’ COMMENT
The key structural element in the new The deck comprises a simple curved box ‘spine This imaginative design which achieves
Information Age Gallery is a raised elliptical beam’ with regularly spaced cantilevering ‘ribs’ its supports from existing columns has
walkway which runs throughout the gallery at either side, which was well equipped to been carefully detailed, assembled and
and bridges the spaces in between six handle torsion generated by the plan curves installed into a highly constrained
interactive ‘story boxed’ zones. and eccentric column supports. existing gallery space.
Primary support is provided via these steel- The walkway was delivered as a series of 6.2m The merits of steelwork and the close
framed ‘story boxes’ and additional long cassettes with the cantilevering ‘arms and
collaboration between the designers,
intermediate supports off existing columns, glass balustrade supporting edge members pre-
with seemingly invisible connections giving the welded to the ‘spine’ offsite. These were lifted contractors and an informed client have
illusion of the walkway piercing into position using spider cranes and all contributed to success.
uninterruptedly through the pods. connected via full strength butt welds.
NATIONAL FINALIST
PROJECT TEAM
Architects Ltd
Structural Engineer: Hydrock
Steelwork Contractor: Weldrite Structures Ltd
Main Contractor: Willmott Dixon Construction Ltd
Client: Bournemouth Borough Council
The ‘leaf’ structures provide a visitor Structure is provided only where necessary. JUDGES’ COMMENT
information centre and a shelter in the centre Not only does the structure taper down from
of Pier Approach on Bournemouth’s seafront. root to tip, but the steel plate sections within
Two cantilevered leaf-form canopies focus
each box-girder cantilever and reduce in
Two identical structural forms were conceived - thickness. This saves material and mass, attention on the pier approach. One provides
one open to provide shelter and performance resulting in a highly efficient construction. welcome shade to the public whilst the other
space, the other enclosed by an elegant glass In addition, a discrete cantilever prop was has been enclosed for a tourist office.
structure to create an information centre. added to the kiosk in order to further reduce
Structurally a leaf is a natural cantilever, with a the work required by the cantilever and its The steelwork is neatly made and provides
singular ‘stalk’ (cantilever box-girder column) foundations. models for further regeneration of
supporting the ‘veins’ (cantilever beams) which Bournemouth’s seafront.
reach out to support the surface (roof).
The Structural Steel Design Awards Scheme
Any member of the design team may submit an entry using the
appropriate form. The declaration of compliance with the award
requirements must be completed by the entrant. CLOSING DATE FOR ENTRIES
Entrants should ensure that all parties of the design team have
been informed of the entry.
Friday 24th February 2017
Sponsored by The British Constructional Steelwork Association Ltd and Steel for Life.
2017 ENTRY FORM
PLEASE COMPLETE ALL SECTIONS BELOW IN FULL ARCHITECT
(including email addresses): Company Name: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
..................................................................... .....................................................................
..................................................................... Email: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Contact: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Tel: . . . . . . . . . . . . . . . . . . . . .
Email: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .