Vous êtes sur la page 1sur 11

Project: Proposed Two Story Residence Total Area: 159.955 sq.

m
Owner of Project: Engr. & Mrs. Andrew Delos Santos
Submitted by: ___ Magpantay, Janette D. 2009-00925-MN-0 Section: BSCE II-2
Name and Student No.
COST ESTIMATE
QTY UNIT MATERIALS LABOR TOTAL AMOUNT
DESCRIPTION UNIT AMOUNT UNIT AMOUNT
GENERAL REQUIREMENTS
PERMITS & LICENSES
MOBILIZATION & DEMOBILIZATION
TEMPORARY FACILITIES
WATER & POWER
SECURITY
Sub-total
CIVIL WORKS
EXCAVATION (including catch basin,
septic tank, etc. 40.01 cu.m. 230.00 9,202.30 69.00 2,760.69 11,962.99
BACKFILL (INCLUDING COMPACTION 14.13 cu.m. 900.00 12,717.00 270.00 3,815.10 16,532.10
EARTHFILL (INCLUDING COMPACTION 30.83 cu.m. 900.00 27,747.00 270.00 8,324.10 36,071.10
GRAVEL BEDDING (Ftg. & slab on grade) 7.21 cu.m. 8.00 57.68 2.40 17.30 74.98
Sub-total 49,723.98 14,917.19 64,641.17
STRUCTURAL WORKS
footings & columns
Cement 81.00 bags 208.00 16,848.00 62.40 5,054.40 21,902.40
Sand 6.00 cu.m. 450.00 2,700.00 135.00 810.00 3,510.00
Gravel 10.00 cu.m. 550.00 5,500.00 165.00 1,650.00 7,150.00
beams & girders
Cement 31.00 bags 208.00 6,448.00 62.40 1,934.40 8,382.40
Sand 4.00 cu.m. 450.00 1,800.00 135.00 540.00 2,340.00
Gravel 14.50 cu.m. 550.00 7,975.00 165.00 2,392.50 10,367.50
suspended slabs cu.m.
Cement 66.00 bags 208.00 13,728.00 62.40 4,118.40 17,846.40
Sand 3.50 cu.m. 450.00 1,575.00 135.00 472.50 2,047.50
Gravel 7.50 cu.m. 550.00 4,125.00 165.00 1,237.50 5,362.50
slab on fill
Cement 61.00 bags 208.00 12,688.00 62.40 3,806.40 16,494.40
Sand 3.50 cu.m. 450.00 1,575.00 135.00 472.50 2,047.50
Gravel 6.50 cu.m. 550.00 3,575.00 165.00 1,072.50 4,647.50
Others:
Stairs
Cement 32.00 bags 208.00 6,656.00 62.40 1,996.80 8,652.80
Sand 2.00 cu.m. 450.00 900.00 135.00 270.00 1,170.00
Gravel 3.50 cu.m. 550.00 1,925.00 165.00 577.50 2,502.50
septic tank (cover and footings)
Cement 32.00 bags 208.00 6,656.00 62.40 1,996.80 8,652.80
Sand 2.00 cu.m. 450.00 900.00 135.00 270.00 1,170.00
Gravel 3.50 cu.m. 550.00 1,925.00 165.00 577.50 2,502.50
Sub-total 97,499.00 29,249.70 126,748.70
REBAR WORKS
footings & columns
8mm dia x 6m 105 pcs 65.00 6,825.00 19.50 2,047.50 8,872.50
10mm dia x 6m 2 pcs 125.00 250.00 37.50 75.00 325.00
12mm dia x 6m 20 pcs 185.00 3,700.00 55.50 1,110.00 4,810.00
16mm dia x 6m 123 pcs 330.00 40,590.00 99.00 12,177.00 52,767.00
beams & girders
8mm dia x 6m 100.00 pcs 65.00 6,500.00 19.50 1,950.00 8,450.00
12mm dia x 6m 216.00 pcs 185.00 39,960.00 55.50 11,988.00 51,948.00
16mm dia x 6m 57.00 pcs 330.00 18,810.00 99.00 5,643.00 24,453.00
suspended slabs 10mm dia x 6m 142 pcs 125.00 17,750.00 37.50 5,325.00 23,075.00
slab on fill 10 mm dia x 6m 163 pcs 125.00 20,375.00 37.50 6,112.50 26,487.50
Stairs
8mm dia x 6m 16 pcs 65.00 1,040.00 19.50 312.00 1,352.00
10mm dia x 6m 3 pcs 125.00 375.00 37.50 112.50 487.50
CHB 10mm dia x 6m 161 pcs 125.00 20,125.00 37.50 6,037.50 26,162.50
GI wires ( No. 16) 176 kgs 70.00 12,320.00 21.00 3,696.00 16,016.00
Others:
septic tank 10mm dia x 6m 22 pcs 125.00 2,750.00 37.50 825.00 3,575.00
catch basin 8mm dia x 6m 16 pcs 65.00 1,040.00 19.50 312.00 1,352.00
wall footing
8mm dia x 6m 36 pcs 65.00 2,340.00 19.50 702.00 3,042.00
10mm dia x 6m 56 pcs 125.00 7,000.00 37.50 2,100.00 9,100.00
Sub-total 201,750.00 60,525.00 262,275.00
FORMWORKS
Footings and Grade Beams
4' x 8' Plywood 6 pcs 540.00 3,240.00 162.00 972.00 4,212.00
2" x 2" Lumber 179 bd.f 40.00 7,160.00 12.00 2,148.00 9,308.00
Ground pedestal/slab sidings(Grd. Flr)
4' x 8' Plywood 28 pcs 540.00 15,120.00 162.00 4,536.00 19,656.00
2" x 2" Lumber 831 bd.f 40.00 33,240.00 12.00 9,972.00 43,212.00
Columns- Ftg to 2nd flr.
4' x 8' Plywood 25 pcs 540.00 13,500.00 162.00 4,050.00 17,550.00
2" x 2" Lumber 734 bd.f 40.00 29,360.00 12.00 8,808.00 38,168.00
Columns- 2nd to roof beam
4' x 8' Plywood 20 pcs 540.00 10,800.00 162.00 3,240.00 14,040.00
2" x 2" Lumber 594 bd.f 40.00 23,760.00 12.00 7,128.00 30,888.00
2nd flr beams
4' x 8' Plywood 23 pcs 540.00 12,420.00 162.00 3,726.00 16,146.00
2" x 2" Lumber 577 bd.f 40.00 23,080.00 12.00 6,924.00 30,004.00
roof beams
4' x 8' Plywood 16 pcs 540.00 8,640.00 162.00 2,592.00 11,232.00
2" x 2" Lumber 326 bd.f 40.00 13,040.00 12.00 3,912.00 16,952.00
2nd flr slab
4' x 8' Plywood 28 pcs 540.00 15,120.00 162.00 4,536.00 19,656.00
2" x 2" Lumber 831 bd.f 40.00 33,240.00 12.00 9,972.00 43,212.00
Sub-total 241,720.00 72,516.00 314,236.00
MASONRY WORKS
6" Thk. CHB 2,637 pcs 12.50 32,962.50 3.75 9,888.75 42,851.25
4" Thk. CHB 1,156 pcs 11.00 12,716.00 3.30 3,814.80 16,530.80
Cement Plastering
Cement (40kg/bag) 87 bags 208.00 18,096.00 62.40 5,428.80 23,524.80
Sand 2 cu.m. 450.00 900.00 135.00 270.00 1,170.00
Mortar Cement
Cement (40kg/bag) 252 bags 208.00 52,416.00 62.40 15,724.80 68,140.80
Sand 21 cu.m. 450.00 9,450.00 135.00 2,835.00 12,285.00
CHB wall footings
Cement 30 bags 208.00 6,240.00 62.40 1,872.00 8,112.00
Sand 2 cu.m. 450.00 675.00 135.00 202.50 877.50
Gravel 3 cu.m. 550.00 1,650.00 165.00 495.00 2,145.00
Sub-total 135,105.50 40,531.65 175,637.15
ROOFING WORKS
GI Corrugated Long span prepainted roof,

32'' x 8' (0.81m x 2.70m) 74 pcs 390.00 28,860.00 117.00 8,658.00 37,518.00
CEE Purlins (2" x 3" x 6m) 24 pcs 750.00 18,000.00 225.00 5,400.00 23,400.00
Faschia Board (1" x 12" x 6m) 7 pcs 1,100.00 7,700.00 330.00 2,310.00 10,010.00
Flashing 2 pcs 470.00 940.00 141.00 282.00 1,222.00
Gutters (2.35m long) 18 pcs 270.00 4,860.00 81.00 1,458.00 6,318.00
Trusses
2" x 2" x 6' lumber 45 pcs 70.00 3,150.00 21.00 945.00 4,095.00
2" x 2" x 16' lumber 7 pcs 190.00 1,330.00 57.00 399.00 1,729.00
2" x 2" x 20' lumber 14 pcs 240.00 3,360.00 72.00 1,008.00 4,368.00
Others
Bolts 98 pcs 34.00 3,332.00 10.20 999.60 4,331.60
Nails 2 kgs 70.00 140.00 21.00 42.00 182.00
Sub-total 71,672.00 21,501.60 93,173.60
ARCHITECTURAL FINISHING WORKS
FLOOR FINISHES
Kitchen (60x60 Cer Tiles) 30 pcs 87.00 2,610.00 26.10 783.00 3,393.00
T & B (25x25 Glazed Tiles) 79 pcs 50.00 3,950.00 15.00 1,185.00 5,135.00
Maid's room (30x30 Cer tiles) 107 pcs 34.00 3,638.00 10.20 1,091.40 4,729.40
Dining room (60x60 Cer Tiles) 36 pcs 87.00 3,132.00 26.10 939.60 4,071.60
Living room (45x45 Granite Tiles) 92 pcs 470.00 43,240.00 141.00 12,972.00 56,212.00
Boy's room (45x45 Mosaic Tiles) 72 pcs 95.00 6,840.00 28.50 2,052.00 8,892.00
Girl's room (45x45 Mosaic Tiles) 72 pcs 95.00 6,840.00 28.50 2,052.00 8,892.00
Family Hall (60x60 Cer Tiles) 19 pcs 87.00 1,653.00 26.10 495.90 2,148.90
T & B (25x25 Glazed Tiles) 64 pcs 50.00 3,200.00 15.00 960.00 4,160.00
Study room (45x45 Cer Tiles) 32 pcs 47.00 1,504.00 14.10 451.20 1,955.20
Masters bedroom (45x45 Mosaic Tiles) 93 pcs 95.00 8,835.00 28.50 2,650.50 11,485.50
Hallway (60x60 Cer Tiles) 14 pcs 87.00 1,218.00 26.10 365.40 1,583.40
Balcony (pebble wash out)
Cement (40kg/bag) 1.5 bags 220.00 330.00 66.00 99.00 429.00
Pebbles (16L/can) 7 cans 1,000.00 7,000.00 300.00 2,100.00 9,100.00
Carport (pebble wash out)
Cement (40kg/bag) 4.5 bags 220.00 990.00 66.00 297.00 1,287.00
Pebbles (16L/can) 18 cans 1,000.00 18,000.00 300.00 5,400.00 23,400.00
Sub-total 112,980.00 33,894.00 146,874.00
WALL FINISHES
Kitchen (painted)
Masonry sealer 5 liters 105.00 525.00 31.50 157.50 682.50
Quick drying enamel 4 liters 140.00 560.00 42.00 168.00 728.00
Maid's room (painted)
Masonry sealer 6 liters 105.00 630.00 31.50 189.00 819.00
Quick drying enamel 4 liters 140.00 560.00 42.00 168.00 728.00
Stairwell (painted)
Masonry sealer 1 liters 105.00 105.00 31.50 31.50 136.50
Quick drying enamel 1 liters 140.00 140.00 42.00 42.00 182.00
Storage (painted)
Masonry sealer 3 liters 105.00 315.00 31.50 94.50 409.50
Quick drying enamel 2 liters 140.00 280.00 42.00 84.00 364.00
Dining room (painted)
Masonry sealer 6 liters 105.00 630.00 31.50 189.00 819.00
Quick drying enamel 5 liters 140.00 700.00 42.00 210.00 910.00
Living room (painted)
Masonry sealer 8 liters 105.00 840.00 31.50 252.00 1,092.00
Quick drying enamel 6 liters 140.00 840.00 42.00 252.00 1,092.00
Boy's room (painted)
Masonry sealer 5 liters 105.00 525.00 31.50 157.50 682.50
Quick drying enamel 4 liters 140.00 560.00 42.00 168.00 728.00
Girl's room (painted)
Masonry sealer 6 liters 105.00 630.00 31.50 189.00 819.00
Quick drying enamel 4 liters 140.00 560.00 42.00 168.00 728.00
Family Hall (painted)
Masonry sealer 6 liters 105.00 630.00 31.50 189.00 819.00
Quick drying enamel 4 liters 140.00 560.00 42.00 168.00 728.00
Study room (45x45 Granite Tiles)
Masonry sealer 4 liters 105.00 420.00 31.50 126.00 546.00
Quick drying enamel 3 liters 140.00 420.00 42.00 126.00 546.00
Master's Bedroom
Masonry sealer 6 liters 105.00 630.00 31.50 189.00 819.00
Quick drying enamel 5 liters 140.00 700.00 42.00 210.00 910.00
Hallway
Masonry sealer 4 liters 105.00 420.00 31.50 126.00 546.00
Quick drying enamel 3 liters 140.00 420.00 42.00 126.00 546.00
Exterior walls (painted)
Masonry sealer 35 liters 105.00 3,675.00 31.50 1,102.50 4,777.50
Quick drying enamel 27 liters 140.00 3,780.00 42.00 1,134.00 4,914.00
Others:
Tileworks @ T & B(8"x12") 832 pcs 14.00 11,648.00 4.20 3,494.40 15,142.40
Sub-total 31,703.00 9,510.90 41,213.90
CEILING FINISHES
METAL FURRINGS WITH I/2" THK GYPSUM BOARD
Kitchen 2' x 2' Plywood 29 pcs 70.00 2,030.00 21.00 609.00 2,639.00
T&B 2' x 2' Plywood 12 pcs 70.00 840.00 21.00 252.00 1,092.00
Maid's room 2' x 2' Plywood 27 pcs 70.00 1,890.00 21.00 567.00 2,457.00
Dining Room 2' x 2' Plywood 36 pcs 70.00 2,520.00 21.00 756.00 3,276.00
Stairwell 2' x 2' Plywood 23 pcs 70.00 1,610.00 21.00 483.00 2,093.00
Storage 2' x 2' Plywood 7 pcs 70.00 490.00 21.00 147.00 637.00
Living room 2' x 2' Plywood 52 pcs 70.00 3,640.00 21.00 1,092.00 4,732.00
Carport 2' x 2' Plywood 56 pcs 70.00 3,920.00 21.00 1,176.00 5,096.00
Boy's room 2' x 2' Plywood 80 pcs 70.00 5,600.00 21.00 1,680.00 7,280.00
Girl's room 2' x 2' Plywood 80 pcs 70.00 5,600.00 21.00 1,680.00 7,280.00
Family hall 2' x 2' Plywood 45 pcs 70.00 3,150.00 21.00 945.00 4,095.00
T&B 2' x 2' Plywood 9 pcs 70.00 630.00 21.00 189.00 819.00
Study room 2' x 2' Plywood 18 pcs 70.00 1,260.00 21.00 378.00 1,638.00
Master's bedroom 2' x 2' Plywood 54 pcs 70.00 3,780.00 21.00 1,134.00 4,914.00
Hallway 2' x 2' Plywood 14 pcs 70.00 980.00 21.00 294.00 1,274.00
Others: 0.00 0.00 0.00 0.00
Wood Primer 27 liters 105.00 2,835.00 31.50 850.50 3,685.50
Quick drying enamel 24 liters 140.00 3,360.00 42.00 1,008.00 4,368.00
Sub-total 44,135.00 13,240.50 57,375.50
TOILET FIXTURES
Common T & B (lav., w.c., sho.) 2 set 2,400.00 4,800.00 720.00 1,440.00 6,240.00
Laundry sink 1 set 1,400.00 1,400.00 420.00 420.00 1,820.00
Stainless Kitchen sinks with mixers 1 set 1,240.00 1,240.00 372.00 372.00 1,612.00
Sub-total 7,440.00 2,232.00 9,672.00
DOORS AND WINDOWS
D1 (0.9 x 2.10 Panel door) 1 set 4,980.00 4,980.00 1,494.00 1,494.00 6,474.00
D2 (0.65 x 2.10 Panel door, typical) 3 set 3,450.00 10,350.00 1,035.00 3,105.00 13,455.00
D3 (1.5 x 2.10 Alum. Sliding Door) 1 set 12,790.00 12,790.00 3,837.00 3,837.00 16,627.00
D4 (0.75 x 2.10 PVC door) 4 set 1,940.00 7,760.00 582.00 2,328.00 10,088.00
D5 (0.6 x 2.10 PVC door) 2 set 1,780.00 3,560.00 534.00 1,068.00 4,628.00
W1 (1.5 x 1.2 Alum. Sliding window) 1 set 3,900.00 3,900.00 1,170.00 1,170.00 5,070.00
W2(1.2 x 1.2 Alum. Sliding window) 3 set 2,700.00 8,100.00 810.00 2,430.00 10,530.00
W3(1.5 x 1.2 Alum. Sliding window, typical) 8 set 2,300.00 18,400.00 690.00 5,520.00 23,920.00
W4(0.6 x 0.5 Alum. Sliding window) 2 set 1,100.00 2,200.00 330.00 660.00 2,860.00
W5(2.4 x 1.2 Alum. Sliding window) 1 set 4,300.00 4,300.00 1,290.00 1,290.00 5,590.00
W6(1.5 x 0.9 Alum. Sliding window) 1 set 1,900.00 1,900.00 570.00 570.00 2,470.00
W7 (1.2 x 2.4 Fixed steel window) 1 set 1,400.00 1,400.00 420.00 420.00 1,820.00
Sub-total 79,640.00 23,892.00 103,532.00
DOORS AND WINDOWS HARDWARES AND ACCESSORIES
Locksets and Handles 11 set 450.00 7,200.00 250.00 4,000.00 11,200.00
Sub-total 7,200.00 4,000.00 11,200.00
ELECTRICAL WORKS
Electrical & PVC Conduits
15mm dia 113 m. 75.00 8,475.00 22.50 2,542.50 11,017.50
20mm dia 93 m. 100.00 9,300.00 30.00 2,790.00 12,090.00
Electrical Wires
3.5sq.mm (TW wires) 226 m. 54.00 12,204.00 16.20 3,661.20 15,865.20
8.0sqmm (TW wires) 186 m. 75.00 13,950.00 22.50 4,185.00 18,135.00
Panel Board (14 branches) 1 pc. 2,400.00 2,400.00 720.00 720.00 3,120.00
Chandelier 1 pcs 5,450.00 5,450.00 1,635.00 1,635.00 7,085.00
Incandescent bulb 11 pcs 180.00 1,980.00 54.00 594.00 2,574.00
Flourescent bulb 9 pcs. 240.00 2,160.00 72.00 648.00 2,808.00
pinlight 11 pcs. 120.00 1,320.00 36.00 396.00 1,716.00
duplex outlet 19 pcs. 120.00 2,280.00 36.00 684.00 2,964.00
electrical range outlet 1 pcs 140.00 140.00 42.00 42.00 182.00
refrigerator outlet 1 pcs 140.00 140.00 42.00 42.00 182.00
booster pump 1 pcs. 790.00 790.00 237.00 237.00 1,027.00
aircon outlet 1 pcs. 140.00 140.00 42.00 42.00 182.00
lighting fixtures 21 pcs. 130.00 2,730.00 39.00 819.00 3,549.00
single pole switch 7 pcs. 75.00 525.00 22.50 157.50 682.50
duplex switch 9 pcs. 125.00 1,125.00 37.50 337.50 1,462.50
triplex switch 2 pcs. 150.00 300.00 45.00 90.00 390.00
Sub-total 65,409.00 19,622.70 85,031.70
SANITARY AND PLUMBING WORKS
Floor drain 5 pcs 60.00 300.00 18.00 90.00 390.00
Control valve 4 pcs 140.00 560.00 42.00 168.00 728.00
uPVC Pipes: drainage pipes (4" dia uPVC) 32 m. 65.00 2,080.00 19.50 624.00 2,704.00
water lines (3/4" dia uPVC) 29 m. 55.00 1,595.00 16.50 478.50 2,073.50
VSTR (2" dia uPVC) 21 m. 45.00 945.00 13.50 283.50 1,228.50
House bibb 2 pcs 75.00 150.00 22.50 45.00 195.00
1/4 Bend ebow 1 pcs 75.00 75.00 22.50 22.50 97.50
Angle valve 3 pcs 90.00 270.00 27.00 81.00 351.00
Reducer tee 2 pcs 80.00 160.00 24.00 48.00 208.00
Reducing coupling 2 pcs 85.00 170.00 25.50 51.00 221.00
Sub-total 6,305.00 1,891.50 8,196.50
WATERPROOFING
Balcony 6.5 sm 700.00 4,550.00 210.00 1,365.00 5,915.00
T&B 3 sm 700.00 2,100.00 210.00 630.00 2,730.00
Firewall 54.5 sm 700.00 38,150.00 210.00 11,445.00 49,595.00
Sub-total 44,800.00 13,440.00 58,240.00
GRAND TOTAL (Direct materials and labor) 1,197,082.48 360,964.74 1,558,047.22
10% Overhead and Mark up 155,804.72
12% Contractor's Profit 186,965.67
3% Contingencies 46,741.42
GRAND TOTAL 1,947,559.03
Total Area = 159.955 sq.m. Cost /sm: 12,175.00
QTY UNIT MATERIALS LABOR
DESCRIPTION UNIT AMOUNT UNIT AMOUNT
STAIRS
C - 100 x 50 x 2.5 stringer 3.00 pcs. 1,270.00 3,810.00 381.00 1,143.00
C - 150 x 65 x 6 stringer 1.00 pc. 2,960.00 2,960.00 888.00 888.00
C - 150 x 75 x 3 stringer 1.00 pc. 1,270.00 1,270.00 381.00 381.00
L- 50 x 50 x 3 3.00 pcs. 1,250.00 3,750.00 375.00 1,125.00
Wood planks (50 x 275mm) 4.00 pcs. 746.00 2,984.00 223.80 895.20
Screw with wood fillers 70.00 pcs. 16.00 1,120.00 4.80 336.00
Ficem Board (6mm thk.) 9.00 pcs. 620.00 5,580.00 186.00 1,674.00
Gusset Plate (6mm thk.) 4.00 pcs. 270.00 1,080.00 81.00 324.00
Base Plate (150 x 150 x 6mm) 4.00 pcs. 370.00 1,480.00 111.00 444.00
12-dia x 200mm A325 bolts 32.00 pcs. 47.00 1,504.00 14.10 451.20
stiff plate 34.00 pcs. 72.00 2,448.00 21.60 734.40

ROOFINGS
LC - 140 x 43 x 14 x 2 4.00 pcs. 540.00 2,160.00 162.00 648.00
LC - 140 x 43 x 12 x 1.5 4.00 pcs. 320.00 1,280.00 96.00 384.00
L- 38 x 38 x 38 1.00 pc. 220.00 220.00 66.00 66.00
Roof tiles (0.31 x 0.31) 1,257.00 pcs. 61.00 76,677.00 18.30 23,003.10
JEA Span 45 Hat Type Purlins 82.00 pcs. 270.00 22,140.00 81.00 6,642.00
Steel Plate 26.00 pcs. 84.00 2,184.00 25.20 655.20
Stiff Plate 20.00 pcs. 72.00 1,440.00 21.60 432.00
Pedestal Plate 6.00 pcs. 87.00 522.00 26.10 156.60
Gusset Plate 12.00 pcs. 270.00 3,240.00 81.00 972.00
Ceiling Boards (4' x 10') 18.00 pcs. 342.00 6,156.00 102.60 1,846.80
Lumber (2" x 2" x 12') 71.00 pcs. 175.00 12,425.00 52.50 3,727.50
Hip Rolls (2.10) 28.00 pcs. 242.00 6,776.00 72.60 2,032.80
Nails 6.50 kilos 54.00 351.00 16.20 105.30
eaves 30.00 m. 84.00 2,520.00 25.20 756.00

166,077.00 49,823.10
TOTAL AMOUNT

4,953.00
3,848.00
1,651.00
4,875.00
3,879.20
1,456.00
7,254.00
1,404.00
1,924.00
1,955.20
3,182.40

2,808.00
1,664.00
286.00
99,680.10
28,782.00
2,839.20
1,872.00
678.60
4,212.00
8,002.80
16,152.50
8,808.80
456.30
3,276.00

215,900.10
PROJECT A
PLUMBING
NO. OF DAYS DAY ACTIVITIES MANPOW
2 1 to 2 INSTALLATION OF PLUMBING SANITARY AND WATER LINES 3
1 3 INSTALLATION OF PLUMBING FIXTURES 2

SCHEDULE OF MATERIALS
WEEK 1 PLUMBING SANITARY AND WATER LINES PVC PIPES, PLUMBING FIXTURES

EQUIPMENT SCHEDULE
WEEK 1
WEEK 2
WEEK 3
MANPOWER
plumbers
plumbers 2 helpers
PROJECT B
PLUMBING
NO. OF DAYS DAY ACTIVITIES MANPOW
10 INSTALLATION OF PLUMBING SANITARY AND WATER LINES 8
12 INSTALLATION OF PLUMBING FIXTURES 6

SCHEDULE OF MATERIALS
WEEK 1 PLUMBING SANITARY AND WATER LINES PVC PIPES, PLUMBING FIXTURES

EQUIPMENT SCHEDULE
WEEK 1
WEEK 2
WEEK 3
MANPOWER
plumbers
plumbers 6 helpers