BSCE 2Z
ACTIVITY 7
COMP 212
ESTIMATE
CHB Length 4.85 m
Height 1.9 m
Area = Length x Height 9.215 sq m
Quantity = Area x 12.5 115.1875 pcs
= ROUNDUP(quantity,0) 116 pcs
SUMMARY
CHB 5" = total number of CHB 116 pcs
Cement = total number of Cement 17 bags
Sand = total number of Sand 11 cu m
Instruction:
Create a similar excel program calculating Number of CHB,
CEMENT and SAND for mortar and plaster. USE THIS AS A BASIS.
TO BE SUBMITTED and PRESENTED NEXT MEETING.
Save your work as “CE212 _SECTION_ACT7E8_LASTNAME-
FIRSTNAME-MI.xlsx”
DRAWING:
MASONRY WORKS
QUANTITY OF CEMENT & SAND FOR CHB MORTAR /m 2
BAGS CEMENT MIXTURE
CHB (mm) NO/m2 SAND (m3)
A B C D
100 (4") 12.5 0.792 0.522 0.394 0.328 0.0435
125 (5") 12.5 1.526 1.018 0.763 0.633 0.0844
150 (6") 12.5 2.26 1.5 1.125 0.938 0.125
QUANTITY OF CEMENT & SAND FOR PLASTER / m 2 AREA
CEMENT ON BAGS / THICKNESS OF PLASTER
MIX. CLASS
8mm 12 mm 16mm 20 mm 25mm
AA 0.144 0.216 0.288 0.36 0.45
A 0.096 0.144 0.192 0.24 0.3
B 0.072 0.108 0.144 0.18 0.225
C 0.06 0.09 0.12 0.15 0.188
D 0.008 0.012 0.015 0.02 0.025
SAND 0.008 0.012 0.016 0.02 0.025