PROJECT : VICTORIA DE MORATO

SUBJECT: PYLON

MATERIAL COST
ITEM DESCRIPTION QTY. UNIT
UNIT COST

DIV.3 REINFORCED CONCRETE


Concrete (6,000 psi) (Pedestal) 0.12 cu.m 5,267.00
Formwork (Pedestal) 1.00 sq.m 440.00

SUB-TOTAL:

DIV.5 METAL WORKS


A. Pedestal (Pylon)
TS1- 200mm x 200mm x 10mm thk - 1.0 pc. 527.77 kgs. 88.53
WF1 - 12mm thk 582.16 kgs. 49.91
WF1 - 10mm thk 343.83 kgs. 49.91
12mm dia. Ties 12.34 kgs. 33.50
16mm dia. Round Bar Ladder 23.56 kgs. 33.50
20mm dia. Vertical Bar 19.76 kgs. 33.50
12mm thk (A36) Stiffener Plate 4.24 kgs. 49.91
20m thk (A36) Base Plate 28.26 kgs. 49.91
25mm thk (A36) Steel Plate 47.10 kgs. 49.91
20mm dia. (A325) Chemical Bolt 16.00 pcs 420.00
25mm dia. (A325) Anchor Bolt 8.00 pcs 563.00
Punching of Plate using magnetic drill-20mm thk 16.00 holes
Punching of Plate using magnetic drill-25mm thk 8.00 holes
Hauling of Materials 1,589.02 kgs.

B. Signages
38mm x 38mm x 5mm thk - 195.88 m 528.88 kgs. 28.09
50mm x 50mm x 6mm thk - 7.0m 32.71 kgs. 41.31

SUB-TOTAL:

GRAND TOTAL :
MATERIAL COST LABOR COST
DIRECT COST
COST UNIT COST COST

632.04 290.00 34.80 666.84


440.00 200.00 200.00 640.00

1,072.04 234.80 1,306.84

46,723.48 12.50 6,597.13 53,320.60


29,055.61 12.50 7,277.00 36,332.61
17,160.56 12.50 4,297.88 21,458.43
413.39 3.50 43.19 456.58
789.26 3.50 82.46 871.72
661.96 3.50 69.16 731.12
211.57 12.50 52.99 264.56
1,410.46 12.50 353.25 1,763.71
2,350.76 12.50 588.75 2,939.51
6,720.00 287.50 4,600.00 11,320.00
4,504.00 359.38 2,875.04 7,379.04
383.75 6,140.00 6,140.00
479.69 3,837.52 3,837.52
0.20 317.80 317.80

14,856.24 12.50 6,611.00 21,467.24


1,351.33 12.50 408.90 1,760.23

126,208.61 44,152.06 170,360.67

127,280.65 44,386.86 171,667.51